2 special bridges

20
Project Reference Cat alogue Bridge Design Services Special ridges

Upload: wpcheng

Post on 01-Jun-2018

213 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 2 Special Bridges

8/9/2019 2 Special Bridges

http://slidepdf.com/reader/full/2-special-bridges 1/19

Project Reference Catalogue

Bridge Design Services

Special ridges

Page 2: 2 Special Bridges

8/9/2019 2 Special Bridges

http://slidepdf.com/reader/full/2-special-bridges 2/19

King Khaled / King Abdullah Intersection Road Upgrade. 

Arriyadh Development Authority, Riyadh, Kingdom of Saudi Arabia. 

Client: Bernard Consulting Engineers, Austria / Saudi Arabia. 

Project: King Khaled / King Abdullah Intersection Road Up-grade Project, Riyadh, Saudi Arabia 

Services: Preliminary Design 

Detail Design 

Services period: 2014 

Background: 

With ever more increasing traffic congestion, the KingKhaled / King Abdullah which is one of the main inter-sections in the city of Riyadh, required a substantialupgrade in infrastructure to improve the flow of traffic.This design and construction method was chosen soas not have further substantial negative impact on traf-fic congestion during construction. 

The new overpass and flyover bridges are mostly con-structed using the cast in place method, however some

areas required a steel deck due to larger spans andnarrower deck depths required due to vertical clear-ance tolerance issues. 

Overpass B1: 49.2m+100m+49.2m = 198.4m totalbridge length / 10.5m deck width. 

Overpass B2:30m+35m+45.586m+45.586m+30m+30m+61m+30m+

30m+30m+30m+36.443m = 423.615m total bridgelength / 13.5m average deck width. 

Flyover F1: 30m+37.5m+37.5m.24.5m+35.5m+35m+35m+35m =270m total bridge length / 11m deck width. 

Flyover F2:30m+40m+40m+40m+30m+30m+30m+40m+40m+35m+45.581+45.586+30.118 = 476.285m total deckwidth / 11.2m average deck width. 

Existing Overpass Extension: 23.065m+23.065m =46.129m total bridge length / Bridge has been extend-

ed from 26.6m wide to 104.7m wide. 

Project Reference Catalogue

Bridge Design Services

Special ridges

Page 3: 2 Special Bridges

8/9/2019 2 Special Bridges

http://slidepdf.com/reader/full/2-special-bridges 3/19

The C903 Steel Deck Segmental Project is an extension of the existing main northand south freeway number 1.

Client:Evergreen Steel Construction, Taiwan. 

Project: The C903 Steel Deck Segmental Project is an exten-sion of the existing main north and south freeway num-ber 1.

Services: 

Steel Deck Segmental Erection Girder Design. 

Services period:2010-2013 

Background: 

The C903 Steel Deck Segmental Project is an extensionof the existing main north and south freeway number 1.The Extension of the freeway is located between Wuguand Yungmei, Taoyuan County, Taiwan.

The main erection gantry is 117m long and erected steeldeck segments with span lengths of 55m.

The standard deck steel segment dimensions consists ofa deck width of 18m and a prefabricated length of 14m.The deck segments have a depth of 4m. 

Project Reference Catalogue

Bridge Design Services

Special ridges

Page 4: 2 Special Bridges

8/9/2019 2 Special Bridges

http://slidepdf.com/reader/full/2-special-bridges 4/19

Linkou Power Plant Renewal Project, Taiwan Power Company, Linkou,New Taipei County, Taiwan. 

Client: Kung Shin Construction, Taiwan. 

Project: Linkou Power Plant Renewal Project, Taiwan Power Company, Linkou, New Taipei County, Taiwan. 

Services:Steel Roof Lifting Equipment Design & Climbing Formwork System Design. 

Services period: 

2012-2014 

Background: 

Linkou Power Plant Renewal Project, Taiwan Power Company, Linkou, New Taipei County, Taiwan. 

The project consist of 10 new coal storage silos that are to be constructed as part of Taipower ’s continuing up-grades to its power plants.

Each silo has an inside diameter of 46m.

The external concrete wall of the silos vary from 1.6m thick at the base to 0.6m at the top. The roof consists ofan inclined steel truss system lifted into position as one unit. The total height of each silo is 72m from ground

level to top of roof level. 

Project Reference Catalogue

Bridge Design Services

Special ridges

Page 5: 2 Special Bridges

8/9/2019 2 Special Bridges

http://slidepdf.com/reader/full/2-special-bridges 5/19

Ramstore Arch Bridge, Astana, Kazakhstan 

Client: Mega Yapi Construction and Trading Company, Turkish Repub-lic. 

Project: Ramstore Arch Bridge, Astana, Kazakhstan 

Services:Specialist Bridge Consultant, Construction Engineering. 

Services period: 

2009-

2010 

Background: The filling in of the Ishim River in Astana, Kazakhstan, for the construction of the Ramstore Bridge deck, allowedfor a simple and fast approach in constructing the deck support arch with minimal interruption to the deck con-struction. The Russian designed bridge consists of a four lane orthotropic steel deck of approximately 120 metrespan, supported by cables from a single skewed arch with a height of 60 metres and span of 180 metres. Thesteel box arch, with a weight of 600 tons is made up 19 segments ranging from 10 to 14 metres in length and ashort segment fixed to the foundation at each end. Samko Engineering of Turkey and Byelkamit of Kazakhstan,the steel contractors on the bridge, tasked Wiecon, a consultant from Taiwan, with providing a fast and inexpen-sive construction method for the archthe final two segments were positioned using a mobile crane while the archwas held in position by the gantry. On final segment installation the arch was welded at both foundation seg-ments. Deck construction was completed ahead of arch erection allowing stay cable works to commence imme-diately. Ramstore Bridge was completed at end of November 2008.

Project Reference Catalogue

Bridge Design Services

Special ridges

Page 6: 2 Special Bridges

8/9/2019 2 Special Bridges

http://slidepdf.com/reader/full/2-special-bridges 6/19

Project Reference Catalogue

Bridge Design Services

Special ridges

Riyadh – 

Kingdom of Saudi Arabia

King Abdul Aziz Flyover

Client:  Arriyadh Development Authority(ADA)Kingdom of Saudi Arabia. 

Project: King Abdul Aziz Flyover - Riyadh 

Services:

Preliminary and Detail 

Specialist bridge consultant 

Services period: 2009-2010 

Background:

The King Abdul Aziz Flyover has a total length of 375m and consists of two pre-stressed concrete approach bridges each of 140m length and a width of 26.2m.

The main bridge has a single span of 95m and consists of a steel orthotropic steeldeck of 26.2m width, supported by a steel arch and one central plane of cables. 

The substructure consists of spread footings and a series of reinforced concretepiers. 

Page 7: 2 Special Bridges

8/9/2019 2 Special Bridges

http://slidepdf.com/reader/full/2-special-bridges 7/19

Project Reference Catalogue

Bridge Design Services

Special ridges

Riyadh – 

Kingdom of Saudi Arabia

Exit 11 Bridge Project 

Background:

The Exit 11 bridge consists of a 9span curved bridge.

The bridge is supported by spreadfooting foundations and reinforced

concrete piers. 

The deck is a single cellprestressed concrete structurewith a deck width of 7.4m and adepth of 2,25m. 

The construction methodproposed for this bridge is aconventional span by spanmethod with cast in situ concrete. 

Client:  Arriyadh Development Authority(ADA)Kingdom of Saudi Arabia. 

Project: EXIT 11 

Services:

Preliminary and Detail 

Specialist bridge consultant 

Services period: 2010-2011 

Page 8: 2 Special Bridges

8/9/2019 2 Special Bridges

http://slidepdf.com/reader/full/2-special-bridges 8/19

Client - Miaoli City Government, Taiwan 

- Gen Yeh Engineering 

Project Miaoli Second Road Bridge, Taiwan. 

Services 

- Feasibility study

- Preliminary & detailed design

- Contractor's consultant- Project planning- Site supervision- Camber control calculation

Services period2004 - ongoing 

Background 

Miaoli Second Road Bridge crosses the main channel of the Houlong River and provides a fast access betweenthe City of Miaoli and Miaoli County.

With the close proximately of the HSR alignment it was determined that the bridge would have a landmark de-sign; hence the unique pylon butterfly arch shape. The intent being that the pylon would give the impression ofthe front end of a high speed train traveling at full speed. 

The bridge is 314.5 m in overall length and 23 m in width; and comprises of the precast box beam section 3.2 mdeep for the two approach spans of 45 m and 60 m; a structural steel box section main span of 170 m and 3.2m deep; and a 39.5 m long precast box beam section.

The 45 m high concrete butterfly arch is uniquely shaped and comprises of the single central anchor leg curvingup over the 60 m approach span, and then dividing into two back legs which span of the bridge approach.  

The bridge forms a sinuously curving 

structure which comprises of a cablesuspended deck close to the butterfly arch pylon; then with an underslung catenary cable and a V shaped strut

system over the 2/3 rds of the steel box span near the HSR alignment. 

Problems during the design were to: - arrive at a technical design solution 

for this unconventional arch bridge- ensure the bridge can withstand 

large earthquake forces- ensure the bridge would be stable

in typhoon conditions

Miaoli Second Road Bridge, 

Miaoli County, Taiwan 

Project Reference Catalogue

Bridge Design Services

Special ridges

Page 9: 2 Special Bridges

8/9/2019 2 Special Bridges

http://slidepdf.com/reader/full/2-special-bridges 9/19

Chenab Arch Bridge, Baramulla Link,

Indian Railway Network 

Background 

The 290 km extension of theIndian Railway network provides adirect connection from Delhi to

Srinagar in Kashmir.

Constructing the rail network inthis isolated region involvedsignificant engineering challengesincluding the 1,315 m long steelarch bridge which crossed theChenab River.

The bridge was 359 m above theriver bed and is the highest railstructure of its kind in the world.Chenab Bridge is located inSeismic Zone 5 and wind

velocities can be as high as 220km per hour. 

Chenab Bridge erection used26,000 tons of steel and was thelargest steel arch built in India.With a 480 m long and 130 m higharch span it was four times thespan range of existing archbridges in India.

The bridge has a two rib arch;made from large steel trusses;while the chords are sealed steelboxes, filled with concrete to assist

in controlling wind induced forces. 

Design services were provided fora set of traveller equipment, usedfor the erection of bridge steelsegments which form thesuperstructure piers, the arch spanand the typical bridge deck spansof 48 m. 

The traveller equipment used forthe erection of the steel segmentsbeing 34 m in length and 16 m inheight. 

Client Indian Railways. 

Project Detailed design of one set of traveller equip-ment used to erect the Chenab

 Arch Bridge steel segments to form the super-structure piers, arch andthe typical deck spans of 48 m.

 

Services 

The detailed design of the traveller equipmentused for the erection ofthe bridge .

 

Services period2005 - 2006 

Project Reference Catalogue

Bridge Design Services

Special ridges

Page 10: 2 Special Bridges

8/9/2019 2 Special Bridges

http://slidepdf.com/reader/full/2-special-bridges 10/19

ClientTHSRC; the Taiwan High Speed Rail Corporation;the BOT concessionaire company responsible forthe 345 km high speed rail project between Taipeiand Kaohsiung. 

Project Design Construct Lot C 250; Hochtief/ Ballast Nedam / Pan Asia; the HBP Joint Ven-

ture. 

Services 

- Feasibility study 

- Preliminary design- Detailed design 

- Contractors consultant - Equipment design 

Services period 

2001 - 2003 

Background 

Services were provided for the detail design and

the construction support for the 259.8 m long andeight spancomposite launched high speed rail bridge cross-ing the first north south freeway near Taichung.  

The composite launched bridge was part of theDesign Unit DU 11.01.

The launched concept was proposed as an alter-native for the tender design as it allowed for fasttrack construction without significant interruptionsto the traffic flow on the Second Freeway.

The composite concept called for an erectionmethod of launching the U shaped steel troughand then finally casting a concrete deck slab ontop using a movable form traveller. 

Services were provided to determine the methodof erection and for the design of the movable formtravellerto cast the HSR concrete deck slab. 

Taiwan High Speed Rail Project, Contract C 250,

Composite Launched Bridge, Design Unit 11.01 

Project Reference Catalogue

Bridge Design Services

Special ridges

Page 11: 2 Special Bridges

8/9/2019 2 Special Bridges

http://slidepdf.com/reader/full/2-special-bridges 11/19

ClientTHSRC; the Taiwan High Speed RailCorporation; the BOT concessionairecompany responsible for the 345 kmhigh speed rail project between Taipeiand Kaohsiung. 

Project Warren Truss Steel Bridges used for

very long span crossings on the highspeed rail alignment. 

Services 

Independent Checking Engineer andIndependent Site Engineer services. 

Services period1999 - 2007 

Taiwan High Speed Rail Project, 

Warren Truss Steel Bridges 

Project Reference Catalogue

Bridge Design Services

Special ridges

Page 12: 2 Special Bridges

8/9/2019 2 Special Bridges

http://slidepdf.com/reader/full/2-special-bridges 12/19

Taiwan High Speed Rail Project, Contract C 210,

Warren Truss Steel Bridge, Design Unit 08 

Background 

Service were provided to the OF joint venture for the preliminary anddetail design of the 1,800 ton

Warren truss steel bridge in DU 08to cross a busy highway in northernTaiwan.

The method of construction was topreassemble the rectangularshaped welded box sections andlaunch the bridge into position;however it was later decided to fullyerect the bridgein place on temporary supports. 

The bridge had a span of 65 m and

consisted of two parallel steeltrusses joined by cross beams; andutilized a composite concrete slabfor the high speed rail deck. 

The steel truss bridge design calledfor a rigorous investigation into thedynamic behaviour of the bridge tolimit the vertical acceleration, cantand end rotations.

To determine the magnitude of

these values for the high speed railsystema rolling stock analysis was carriedout on the bridge structural

elements.

The scope of services included: - superstructure design includingthe 

concrete slab below track level - dynamic analysis using thefinalised

substructure dimensions and the 

adjacent superstructure design 

- rolling stock analysis 

- pot bearing and shear keydesigns;

providing design forces,movements 

and any other relatedrequirements 

- expansion joints; providing thetruss

bridge movements 

- provision of 3D perspectives- calculations to assess both the

assembly and launching stagesof the steel truss bridge 

- provision of loadings as a design

input for the temporary bentsupport - provision of the constructionmethod

and drawings 

- design coordination with THSRC 

and other nominated consultants- interface coordination 

Client THSRC; the Taiwan High Speed Rail Corpora-tion; the BOT concessionaire company respon-sible for the 345 km high speed rail project be-tween Taipei and Kaohsiung. 

Project Design Construct Lot C 210; for the Obayashi/ Futsu; OF Joint Venture. Steel Truss Bridge,

Design Unit 08. 

Services 

- Feasibility study 

- Preliminary design 

- Detailed design 

- Contractors consultant 

Project Reference Catalogue

Bridge Design Services

Special ridges

Page 13: 2 Special Bridges

8/9/2019 2 Special Bridges

http://slidepdf.com/reader/full/2-special-bridges 13/19

Taiwan High Speed Rail Project, Contract C 250,

Warren Truss Steel Bridge, Design Unit 12.03 

Background 

Services were provided to the jointventure for the preliminary and de-tail design of the DU 12.03 Warren

truss steel bridge. 

The Warren truss steel bridge beinglocated just north of Taichung HSRStation; comprising of a 22 m high,welded steel box sections that wassite assembled using high strengthbolts. 

The DU 12.03 truss bridge hadspansarranged as 61 m + 70 m + 60 mand consisted of two parallel steeltrusses joined by cross beams with

a concrete 

composite slab base for the track. 

The steel truss bridge design calledfor a rigorous investigation into thedynamic behaviour of the bridge tolimit both vertical acceleration, cantand end rotation. 

To determine the magnitude of

these values for the high speed railsystema rolling stock analysis was carriedout on the bridge structural ele-

ments. 

The scope of services included: - superstructure design includingthe 

composite slab below track level - dynamic analysis using finalised

substructure dimensions and the 

adjacent superstructure design 

- rolling stock analysis 

- pot bearing and shear key de-signs;

providing design forces, move-ments 

and any other related require-ments 

- expansion joints; providing thetruss

bridge movements 

- provision of 3D perspectives - calculations to assess all the

assembly stages of the bridge 

- provision of loadings as a designinput for temporary bent supports 

- providing the construction methodand drawings 

- design coordination with THSRC 

and other nominated consultants

- interface coordination

 

Client THSRC; the Taiwan High SpeedRail Corporation; the BOT conces-sionaire company responsible forthe 345 km high speed rail project. 

Project Design Construct Lot C 250;Hochtief/ Ballast Nedam / Pan Asia; theHBP Joint Venture; Design Unit12.03. 

Services 

- Feasibility study 

- Preliminary design- Detailed design 

- Contractors consultant 

Project Reference Catalogue

Bridge Design Services

Special ridges

Page 14: 2 Special Bridges

8/9/2019 2 Special Bridges

http://slidepdf.com/reader/full/2-special-bridges 14/19

Taiwan High Speed Rail Project, Contract C 250,

Launched Bridges, Design Units 13.02 / .05 / .08 

Client Taiwan High Speed RailCorporation. 

Project Design & Construct Lot C 250; JVof Hochtief / Ballast Nedam / Pan

 Asia; Design Units 13.02, 13.05 &13.08. 

Services 

- Feasibility study 

- Preliminary design- Detailed design 

- Contractors consultant 

Services period : 2001 - 2003 

Background 

Service were provided for thedesign and erection of 3 of the HSRWarren truss bridges; just south ofTaichung Station. The 3 bridges

were for the main line rail south andnorth bound and the branch line toWurih Depot. The parallel bridgescross the North- South Freeway, the Fazi River andProvincial Highway #1. 

Each bridge comprised of twoparallel trusses joined by crossbeams; and were fabricated fromwelded steel box sections; and then

assembled using over 600,000 highstrength bolts. 

Each bridge consisting of 3continuous spans 150 + 120 + 140m; 441 m long, and the weight for allthree bridges was 24,000 tons. To avoid any road trafficdisturbances,

a sophisticated erection schemewas devised to preassemble thefirst two bridge spans; ontemporary supports in the center;and launch this bridge to the southabutment using a 108 m longlaunching nose beam. 

Then this bridge was movedsideways into its final position onthe west side. The erectionprocedure was repeated for thenext bridge truss, which waslaunched and then moved into its

final position on the east side. 

The third truss was then erectedand launched between the twopreviously erected bridges. Aconcrete slab was cast for the trackdeck after checking the final leveland alignment of each of the threebridges. 

The steel truss bridge design called

for a rigorous investigation into thedynamic behaviour of thesebridges;to limit the vertical acceleration,cant and end rotation.

 A rolling stock analysis was carriedout on the bridge structuralelements; and mechanical shear

keys added to each bridge to resistthe horizontal seismic forces.

Two pot bearings (per span pertruss); the largest ever to bemanufactured; now support thethree bridges. 

 A series of shock transmitting unitswere installed to ensure the uniformdistribution of the longitudinalseismic forces among thesupporting piers. 

Project Reference Catalogue

Bridge Design Services

Special ridges

Page 15: 2 Special Bridges

8/9/2019 2 Special Bridges

http://slidepdf.com/reader/full/2-special-bridges 15/19

Nanfang Au Steel Arch Bridge, Suao, Taiwan

Arch Bridge Design 

ClientMAA Engineers, Taiwan. 

Project Nanfang Au Cable Supported Steel Arch Bridgeacross Suao Harbour.

Services 

- Preliminary design 

- Detailed design 

- Camber calculations and bearing presets 

- Consultant during the construction 

Services period 

1995 – 1998 

Background 

The Nanfang Au Steel Arch Bridge is located on the east coast of Tai-wan spanning across the entrance of Suao Fishing Village and an 18 mheight clearance was required for the boats. The Arch bridge was builtto replace the original concrete bridge acrossthe harbour. 

The main bridge span was 140 m, with a 15 m wide deck and was de-signed as a steel orthotropic fully welded multi cell box construction. Thesteel arch is 27 m high at the center.

Both preliminary and detailed design services were provided; includingthe static analysis, cable optimization, seismic analysis as well as buck-ling analysis at the arch joint. 

Project Reference Catalogue

Bridge Design Services

Special ridges

Page 16: 2 Special Bridges

8/9/2019 2 Special Bridges

http://slidepdf.com/reader/full/2-special-bridges 16/19

ChoShei - Shi Pipe Support Bridge 

 Yun - Lin, Taiwan

Client China Petroleum Company. 

Project Pipe Support Bridge, Taiwan. 

Services 

-  Aesthetic evaluation 

-  Preliminary & detail design

-  Construction consultant

-  Consultant to United Geotech 

Services period1995 – 1996 

Background 

 A 70 m truss pipe bridge consistingof high grade galvanized steelpipes 2,200 m in length; was de-signed to carry the gas and gaso-line pipes of the client, China Petro-

leum acrossthe ChoShei - Shi River.

The design work was carried out inconjunction with United Geotechwho were responsible for the bridgealignment and soil investigation. 

The scope of work consisted of theaesthetic evaluation and prelimi-nary design at the proposal stage,

and the detail design including stat-ic, seismic and buckling analysis. 

Project Reference Catalogue

Bridge Design Services

Special ridges

Page 17: 2 Special Bridges

8/9/2019 2 Special Bridges

http://slidepdf.com/reader/full/2-special-bridges 17/19

Taipei – 

Ilan Expressway No. 5, Taiwan

Bridge Designs 

Client Sinotech Consulting Engineers. 

Project : Taipei – Ilan Expressway Detail Design 

Services Period : 1990 – 1993

Background 

 A total of 7,113 m of bridges were designed

including: 

- balanced cantilever- incrementally launching- advancing shoring- prestressed concrete arch- cast in place

Of 30 bridges the main ones were:- Shihding Interchange  66 m 

- Shihding Viaduct 809 m 

- Tanbian Bridge  480 m 

- Wutu Hsi Bridge 564 m 

- Pengshan Viaduct East 394 m 

- Pengshan Viaduct West 615 m 

- Pengshan East Bridge

 131 m

 

- Pengshan West Bridge  280 m 

- Pengshan Viaduct 2  231 m 

- Pinglin Viaduct East 1  538 m 

- Pinglin Viaduct West 1 290 m 

- Pinglin Viaduct East 2  650 m 

- Pinglin Viaduct West 2 628 m 

- Toucheng Viaduct East 721 m 

- Toucheng Viaduct West 716 m 

Project Reference Catalogue

Bridge Design Services

Special ridges

Page 18: 2 Special Bridges

8/9/2019 2 Special Bridges

http://slidepdf.com/reader/full/2-special-bridges 18/19

Taipei – 

Ilan Expressway No. 5, Taiwan

Ping Lin Interchange 

Client Sinotech Consulting Engineers,Taiwan. 

Project Ping Lin Interchange, Taiwan. 

Services 

Preliminary and detailed bridge

design consultant to Sinotech.Designs were provided for: - balanced cantilever  - incrementally launched 

- advancing shoring method 

- prestressed concrete arch 

- cast in place structures 

Services period 

1990 - 1993

BackgroundThe 30.8 kilometer Expressway is from the eastern suburbs of Taipei City to Ilan on the eastern coast line ofTaiwan. 

The Ping Lin Interchange serves the residents of the Ping Lin Tea Village and is located before the entranceto Snow Mountain Tunnel; which isalso the location of the Expressway Traffic Control Center. 

The Ping Lin Interchange structures were constructed by the full support method.  

The full support method for cast in place structures being the traditional method of bridge construction, that in-volves, supporting the formwork directly from the ground using a scaffolding system. 

Project Reference Catalogue

Bridge Design Services

Special ridges

Page 19: 2 Special Bridges

8/9/2019 2 Special Bridges

http://slidepdf.com/reader/full/2-special-bridges 19/19

Taiwan High Speed Rail Project, Contract C 250,

Cast inSitu, Design Unit 09.01 

Client THSRC; the Taiwan High SpeedRail Corporation; the BOTconcessionaire companyresponsible for the 345 km highspeed rail project between Taipeiand Kaohsiung. 

Project 

Design Construct Lot C250;Hochtief / Ballast Nedam / Pan Asia; the HBP Joint Venture; for C250 design and construction ofDesign Unit 09.01. 

Services 

-  Preliminary design-  Detailed design 

-  Contractors consultant -  Equipment design 

Services period 

2001 – 2003 

Background 

Services were provided for detaildesign and construction support forthe 3 span, prestressed concretehigh speed railway bridge inDesign Unit DU 09.01. 

The bridge alignment was locatednear Taichung and the prestressed

concrete box girders weredesigned to be cast insitu. 

The high speed rail elevated bridgedesign was carried out inaccordance with THSRC designspecifications for the project. 

The dynamic behaviour of thebridge under train loading waschecked by carrying out a rollingstock analysisin order to determine the vertical

acceleration characteristics of thestructure.

The analysis assured that the HSRelevated structure was well withinthe specifications requirement.

 As Taiwan is a highly seismic area,subject to severe earthquakes; the

elevated high speed rail structureneeded to be designed towithstand severe groundmovements. 

Project Reference Catalogue

Bridge Design Services

Special ridges