Planning and Deterministic scheduling
![Page 2: 2 planning](https://reader034.vdocuments.us/reader034/viewer/2022051610/549acdadb47959fc088b45e5/html5/thumbnails/2.jpg)
Motivation for Scheduling
• Reducing chances of delay• Recovering from Delay• Delays result from poor planning• Assigning responsibilities
![Page 3: 2 planning](https://reader034.vdocuments.us/reader034/viewer/2022051610/549acdadb47959fc088b45e5/html5/thumbnails/3.jpg)
Motivation for Scheduling
• Better utilization of resources• Identification of critical resources• Identify and Resolution of conflict ahead of time
![Page 4: 2 planning](https://reader034.vdocuments.us/reader034/viewer/2022051610/549acdadb47959fc088b45e5/html5/thumbnails/4.jpg)
Motivations for scheduling
• Formalization necessary but not sufficient for managing
![Page 5: 2 planning](https://reader034.vdocuments.us/reader034/viewer/2022051610/549acdadb47959fc088b45e5/html5/thumbnails/5.jpg)
Ubiquitous role of scheduling
Importance of schedule • Design (preliminary schedule)
• Establish finish, milestone times for choreographing activities Procurement time, subcontractor presence, tenant occupancy
• Importance for thinking through issues
• Identify critical path
![Page 6: 2 planning](https://reader034.vdocuments.us/reader034/viewer/2022051610/549acdadb47959fc088b45e5/html5/thumbnails/6.jpg)
Ubiquitous role of scheduling
Importance of schedule • Communication tool between parties
• Framework for monitoring
• Role in control - Assessing impacts of changes - Allows demonstration of indirect costs - Legal importance
![Page 7: 2 planning](https://reader034.vdocuments.us/reader034/viewer/2022051610/549acdadb47959fc088b45e5/html5/thumbnails/7.jpg)
Ubiquitous role of scheduling
Importance of schedule
• Link to resources - Payments - Resource usage
• Identify exposure to external forces (crowding, weather conditions )
![Page 8: 2 planning](https://reader034.vdocuments.us/reader034/viewer/2022051610/549acdadb47959fc088b45e5/html5/thumbnails/8.jpg)
Linkage to estimation
• Scheduling allows understanding of cash flow over time
• Given time value of money, scheduling critical to understanding present value of estimate
![Page 9: 2 planning](https://reader034.vdocuments.us/reader034/viewer/2022051610/549acdadb47959fc088b45e5/html5/thumbnails/9.jpg)
THE GANTT CHART
•Attributed to Henry Gantt – most popular PM tool (80%)
•Used to plan big shipbuilding projects (cargo ships WWI)
•Graphical way of showing task durations, project schedule
•Does not explicitly show relationships between tasks
•Limited use for project tracking•Easy to understand
![Page 10: 2 planning](https://reader034.vdocuments.us/reader034/viewer/2022051610/549acdadb47959fc088b45e5/html5/thumbnails/10.jpg)
A Gantt Chart of a Sample Project
![Page 11: 2 planning](https://reader034.vdocuments.us/reader034/viewer/2022051610/549acdadb47959fc088b45e5/html5/thumbnails/11.jpg)
Completion Today Calendar
![Page 12: 2 planning](https://reader034.vdocuments.us/reader034/viewer/2022051610/549acdadb47959fc088b45e5/html5/thumbnails/12.jpg)
Gantt: Sequential vs. phased
![Page 13: 2 planning](https://reader034.vdocuments.us/reader034/viewer/2022051610/549acdadb47959fc088b45e5/html5/thumbnails/13.jpg)
Hierarchy of Gantt Charts
![Page 14: 2 planning](https://reader034.vdocuments.us/reader034/viewer/2022051610/549acdadb47959fc088b45e5/html5/thumbnails/14.jpg)
CPM NETWORKS
![Page 15: 2 planning](https://reader034.vdocuments.us/reader034/viewer/2022051610/549acdadb47959fc088b45e5/html5/thumbnails/15.jpg)
History
• Late 1950s– Program Evaluation and Review Technique (PERT)
• U.S. Navy, Booz-Allen Hamilton, and Lockeheed Aircraft• Probabilistic activity durations
– Critical Path Method (CPM)• Dupont De Nemours Inc.• Deterministic activity durations
![Page 16: 2 planning](https://reader034.vdocuments.us/reader034/viewer/2022051610/549acdadb47959fc088b45e5/html5/thumbnails/16.jpg)
Gantt vs. CPM
![Page 17: 2 planning](https://reader034.vdocuments.us/reader034/viewer/2022051610/549acdadb47959fc088b45e5/html5/thumbnails/17.jpg)
The Language of PERT/CPM
• Activity– task or set of tasks– Have definable ending and beginning– use resources
• Event– state resulting from completion of one or more activities– consume no resources or time– predecessor activities must be completed
![Page 18: 2 planning](https://reader034.vdocuments.us/reader034/viewer/2022051610/549acdadb47959fc088b45e5/html5/thumbnails/18.jpg)
The Language of PERT/CPM continued
• Milestones– events that mark significant progress
• Network– diagram of nodes and arcs– used to illustrate technological relationships
• Path– series of connected activities between two events
![Page 19: 2 planning](https://reader034.vdocuments.us/reader034/viewer/2022051610/549acdadb47959fc088b45e5/html5/thumbnails/19.jpg)
The Language of PERT/CPM continued
• Dummy activity– An arrow representing merely a dependency of one activity
upon another.– It carries a zero time estimate
![Page 20: 2 planning](https://reader034.vdocuments.us/reader034/viewer/2022051610/549acdadb47959fc088b45e5/html5/thumbnails/20.jpg)
The Language of PERT/CPM concluded
• Critical Path– set of activities on a path that if delayed will delay completion
of project
• Critical Time– time required to complete all activities on the critical path
![Page 21: 2 planning](https://reader034.vdocuments.us/reader034/viewer/2022051610/549acdadb47959fc088b45e5/html5/thumbnails/21.jpg)
Building the Network
• AOA Network• AON Network
![Page 22: 2 planning](https://reader034.vdocuments.us/reader034/viewer/2022051610/549acdadb47959fc088b45e5/html5/thumbnails/22.jpg)
Sample Set of Project Activities and Precedences
Task Predecessor
a --
b --
c a
d b
e b
f c, d
g e
![Page 23: 2 planning](https://reader034.vdocuments.us/reader034/viewer/2022051610/549acdadb47959fc088b45e5/html5/thumbnails/23.jpg)
Stage 1 of a Sample AON Network
![Page 24: 2 planning](https://reader034.vdocuments.us/reader034/viewer/2022051610/549acdadb47959fc088b45e5/html5/thumbnails/24.jpg)
Stage 2 of a Sample AON Network
![Page 25: 2 planning](https://reader034.vdocuments.us/reader034/viewer/2022051610/549acdadb47959fc088b45e5/html5/thumbnails/25.jpg)
A Completed Sample AON Network
![Page 26: 2 planning](https://reader034.vdocuments.us/reader034/viewer/2022051610/549acdadb47959fc088b45e5/html5/thumbnails/26.jpg)
Stage 1 of a Sample AOA Network
![Page 27: 2 planning](https://reader034.vdocuments.us/reader034/viewer/2022051610/549acdadb47959fc088b45e5/html5/thumbnails/27.jpg)
Stage 2 of a Sample AOA Network
![Page 28: 2 planning](https://reader034.vdocuments.us/reader034/viewer/2022051610/549acdadb47959fc088b45e5/html5/thumbnails/28.jpg)
A Completed Sample AOA Network
![Page 29: 2 planning](https://reader034.vdocuments.us/reader034/viewer/2022051610/549acdadb47959fc088b45e5/html5/thumbnails/29.jpg)
A Completed Sample AOA Network Showing the Use of a Dummy Task
![Page 30: 2 planning](https://reader034.vdocuments.us/reader034/viewer/2022051610/549acdadb47959fc088b45e5/html5/thumbnails/30.jpg)
A Sample Problem for Finding the Critical Path and Critical Time
Activity Predecessor Duration
a -- 5 days
b -- 4
c a 3
d a 4
e a 6
f b, c 4
g d 5
h d, e 6
i f 6
j g, h 4
![Page 31: 2 planning](https://reader034.vdocuments.us/reader034/viewer/2022051610/549acdadb47959fc088b45e5/html5/thumbnails/31.jpg)
Stage 1 of a Sample Network
![Page 32: 2 planning](https://reader034.vdocuments.us/reader034/viewer/2022051610/549acdadb47959fc088b45e5/html5/thumbnails/32.jpg)
A Complete Network
![Page 33: 2 planning](https://reader034.vdocuments.us/reader034/viewer/2022051610/549acdadb47959fc088b45e5/html5/thumbnails/33.jpg)
Information Contents in an AON Node
![Page 34: 2 planning](https://reader034.vdocuments.us/reader034/viewer/2022051610/549acdadb47959fc088b45e5/html5/thumbnails/34.jpg)
The Critical Path and Time for Sample Project
![Page 35: 2 planning](https://reader034.vdocuments.us/reader034/viewer/2022051610/549acdadb47959fc088b45e5/html5/thumbnails/35.jpg)
Calculating Activity Slack
• Slack or FloatLST - EST = LFT - EFT = Slack
![Page 36: 2 planning](https://reader034.vdocuments.us/reader034/viewer/2022051610/549acdadb47959fc088b45e5/html5/thumbnails/36.jpg)
An MSP Version of PERT/CPM Network
![Page 37: 2 planning](https://reader034.vdocuments.us/reader034/viewer/2022051610/549acdadb47959fc088b45e5/html5/thumbnails/37.jpg)
A Gantt Chart of Sample Project Showing Critical Path, Path Connections, Slack, EST, LST, EFT, and LFT
![Page 38: 2 planning](https://reader034.vdocuments.us/reader034/viewer/2022051610/549acdadb47959fc088b45e5/html5/thumbnails/38.jpg)
A Gantt Chart of a Day Care Project Showing Expected Durations, Critical Path, Milestone, and Resource Requirements
![Page 39: 2 planning](https://reader034.vdocuments.us/reader034/viewer/2022051610/549acdadb47959fc088b45e5/html5/thumbnails/39.jpg)
A Progress Report on a Day Care Project Showing Actual Progress Versus Baseline
![Page 40: 2 planning](https://reader034.vdocuments.us/reader034/viewer/2022051610/549acdadb47959fc088b45e5/html5/thumbnails/40.jpg)
Exercise 1
Draw a AOA and AON diagrams for the project:
Task Prereq. Time A None 5 B None 6 C None 10 D A 3 E B 4
![Page 41: 2 planning](https://reader034.vdocuments.us/reader034/viewer/2022051610/549acdadb47959fc088b45e5/html5/thumbnails/41.jpg)
Exercise 2
Task Prereq. Time A None 4 B None 6 C None 3 D A, B 7 E B, C 8
Draw a AOA and AON diagrams for the project:
![Page 42: 2 planning](https://reader034.vdocuments.us/reader034/viewer/2022051610/549acdadb47959fc088b45e5/html5/thumbnails/42.jpg)
Exercise 3
Task Prereq.A NoneB NoneC NoneD AE A, BF A, B, C
Draw a AOA and AON diagrams for the project:
![Page 43: 2 planning](https://reader034.vdocuments.us/reader034/viewer/2022051610/549acdadb47959fc088b45e5/html5/thumbnails/43.jpg)
Exercise 4
Task Prereq.A NoneB NoneC AD BE A, B
Draw a AOA and AON diagrams for the project:
![Page 44: 2 planning](https://reader034.vdocuments.us/reader034/viewer/2022051610/549acdadb47959fc088b45e5/html5/thumbnails/44.jpg)
Exercise 5
Task Prereq. Time A None 4 B None 9 C None 5 D A, B 6 E B, C 4 F A, B, C 10
(Tricky!)
Draw a AOA and AON diagrams for the project:
![Page 45: 2 planning](https://reader034.vdocuments.us/reader034/viewer/2022051610/549acdadb47959fc088b45e5/html5/thumbnails/45.jpg)
Exercise 6
Task Prereq. Time A None 6 B None 4 C None 7 D A 5 E A 9 F C 2 G C 8 H B, E, F 4 I B, D, E, F 7 J B, E, F, G 3
Draw a AOA and AON diagrams for the project: