    CP07-A-1A(South)-Waterfront Commercial InfrastructureWorks South

    Ref: XXXXXX 17th Sep 2013

    Page 1 of 4

    ANNEXURE A

    I. General Conditions

    1. Our offer is based on the construction duration of 22 monthsincluding mobilization.2. All staff numbers and positions mentioned in the "Organization Chart" are the result of

    a preliminary assessment and are not final and not necessarily available from the

    commencement of the project but will be progressively assigned to their duties as per

    the loaded schedule of works that will be submitted after Contract Award.

    Furthermore, the staff members need not be available for the full period. A more

    accurate Organization Chart and Staffing Histogram will be provided after contract

    award.

    3. Our offer is based on and allows for compliance with only those Governmental Laws inforce at the time of the tender. Any changes have to be considered, mutually agreed

    and compensated to us accordingly (including any new Taxation, or custom duties etc).4. Testing & Commissioning shall be completed upon the availability of permanent power,

    water etc.

    5. We assume that sufficient storage laydown areas shall be made available to us free ofcharge at Contract Award in order to ensure timely completion of the works.

    6. Our offer includes in the Preliminaries an amount to cover the requirement/services forthe Client/Engineer as stipulated by the tender documents.

    7. The Preliminaries include the following costs for Mobilization, Running Costs andDemobilization: -

    1. Salaries and Wages Salaries of Project/Site Managers, Supervisory and Administrative staff on site. Wages of Indirect Labour who help in general services e.g. loading/unloading,

    cleaning groups, safety labours, chainmen, banksmen, watchmen, office boys, etc.

    2. Temporary Site Installation for Contractor and Sub-contractor. Offices, stores, workshops, storage yard, laboratories, fences, scaffoldings, etc. Offices and other facilities/services for the Client/Engineer including their running

    costs as per the tender requirements.

    Labor Accommodation costs are included in the Unit Rates. Running cost of services for the above, e.g. Water, power, telephone, refreshment,

    entertainment, stationary, consumables and its maintenance.

    3. Temporary plant and equipment needed to perform the works (does not includeequipment used by the Sub-contractors for the scope of permanent works e.g.

    Earthwork, Structural steel, Road work, etc..) and small tools.

    4. Labour transport is included in unit rates.5. Financial and Bank charges including Insurance and Bank Guarantees etc.6. HSE Requirements and its running costs.7. QA/QC Requirements and its running costs.

  • 8/12/2019 2 Lusail Annexure - A

    2/4

    CP07-A-1A(South)-Waterfront Commercial InfrastructureWorks South

    Ref: XXXXXX 17th Sep 2013

    Page 2 of 4

    II. Conditions of Contract and Mitigation of Risk Elements

    Please see attached:-

    Schedule of Clarification Schedule of Qualification

    III. Technical

    1. Our offer excludes any works related supply erection commissioning of equipments likeTransformers, pumps etc in the substations or pumping station.

    2. Please refer attachment 1A for list of manufactures for MEP works.3. We have considered a warranty of 1 year for MEP equipments in our scope of works

    IV. Exclusions (Unless Specifically Measured in the Bill of Quantities or Covered with in the Provisional Sums)1. Our offer excludes relocation of any existing services.2. Our offer excludes any provision for crossing existing underground services.3. Our offer excludes Statutory Fees for Permanent connection (By Client)4. Our offer excludes Overtime for Consultants Inspectors.

    V. PRICE ESCALATION

    In view of the unstable conditions in the market our offer is based on the following current supplied at site

    rates for the materials listed below have been used for pricing:

    Concrete (Supplied to site excluding pump & temperature control)Concrete C30 OPC QAR 340/m

    Concrete C40 OPC+60%GGBS+5%MS QAR 390/m

    Concrete C50OPC+60%GGBS+5%MS QAR 400/m

    RebarsUncoated Deformed Reinforcingstraight bars (Turkey) as per BS 4449 QAR 3000/Ton

    Diesel QAR15.89/Gallon Copper US$ 7370/Ton

  • 8/12/2019 2 Lusail Annexure - A

    3/4

    CP07-A-1A(South)-Waterfront Commercial InfrastructureWorks South

    Ref: XXXXXX 17th Sep 2013

    Page 3 of 4

    ATTACHMENT1ALIST OF MAKESWe are attaching herewith list of suppliers which we propose to use for this project and is

    accordinglyincluded in the estimate.

    Air Conditioning

    1. Pipe Supports Weicco / Flamco / Equivalent2. Preinsulated Pipe Perma Pipe / EPPI / SPPI / Insa Foam / Equivalent3. Valves Crane / Hattersely / Flowcon / T&A / Econosto / Danfoss / Equivalent

    Electrical1. Electrical Switchgear (HV & LV) ABB / Schneider / Merlin Gerin / Siemens / Equivalent2. Transformer ABB / Tesar / Siemens / Federal / Equivalent3. Switches & sockets Crabtree / Clipsal / MK / Equivalent4. Single core wires Oman / Jeddah / Tekab / Ducab / Riyadh / Equivalent5. Armoured cables Oman / Jeddah / Saudi / Riyadh / Ducab / Equivalent6. Flexible cables Ducab / Saudi Cables / BICC / Equivalent7. Fire Proof Cable Ducab / Draka /Pirilli / Equivalent8. PVC conduits & Acc Decoduct / Clipsal / Multiplast9. GI Conduits & Acc Panasonic / Smartr / Marucchi / Equivalent10.GI back boxes Clipsal / Elektra / Bartan / Equivalent11. Isolators ABB / Moeller / Merlin Gerin / Equivalent12.Cable Tray, Trunking & Ladders PSI / EMI / Gerson / Lenric / Equivalent13.Cable lugs & Glands CMP / BICC / Equivalent14.Earthing / LP Furse / A.N.Wallis / Equivalent15.GI Trunking / Trays MK / EMI / PSI / Transdelta / Gerson / Equivalent16.Fire Alarm system Esser / Simplex / Gent / Notifier / Equivalent17.Light Fittings Philips / Thorn / Weef / Zumtobel / Disano / Idealux / Ruud /Sylvania / Alpha LED /

    oomlux / Emirates Lights /Thornlux / Equivalent

    Plumbing

    1. Valves Crane / Hattersley / Equivalent

  • 8/12/2019 2 Lusail Annexure - A

    4/4

    CP07-A-1A(South)-Waterfront Commercial InfrastructureWorks South

    Ref: XXXXXX 17th Sep 2013

    Page 4 of 4

    2. Rain Water Outlet Wade / Zurn / Equivalent3. UPVC Pipes Hepworth / Cosmoplast / National Plastic / Equivalent

    Fire Fighting System

    1. Fire Fighting System Naffco / Daffoos / Unisafe / Fire Link / Chubb / Equivalent