Page 1: 2 /Broadway Station Meeting · > During previous phases of the project, the community requested Metro consider ways to expedite and shorten the overall work schedule. > In order to

www.metro.net/regionalconnector 1

2nd/Broadway Station Meeting June 3, 2013

Page 2: 2 /Broadway Station Meeting · > During previous phases of the project, the community requested Metro consider ways to expedite and shorten the overall work schedule. > In order to

www.metro.net/regionalconnector 2

Tonight’s Speakers

Olga Arroyo, Metro Construction Relations Manager

Dan Comorre, P.E., Metro Director of Construction Management

Page 3: 2 /Broadway Station Meeting · > During previous phases of the project, the community requested Metro consider ways to expedite and shorten the overall work schedule. > In order to

www.metro.net/regionalconnector 3 3

Agenda

> Project Overview and Update

> Extended Work Hours Requests

> Next Steps

> How to Contact Us

Page 4: 2 /Broadway Station Meeting · > During previous phases of the project, the community requested Metro consider ways to expedite and shorten the overall work schedule. > In order to

www.metro.net/regionalconnector 4

Project Overview > $1.366 billion underground Light

Rail Transit System

> Connects Metro Gold Line to Metro Blue and Expo Lines

> 1.9-miles

> 3 Underground Stations • 1St/Central • 2nd/Broadway • 2nd/Hope

> 2020 Anticipated Opening Date

4

Page 5: 2 /Broadway Station Meeting · > During previous phases of the project, the community requested Metro consider ways to expedite and shorten the overall work schedule. > In order to

www.metro.net/regionalconnector 5

Procurement Effort

> Current: RFP was issued in Jan. 2013 to Metro Pre-Qualified Firms • Firms invited to participate in a Pre-Qualification process (SOQ) • Pre-Qualified firms invited to submit proposals (RFP)

> Proposals Due: July 2013

> Award Contract and Provide NTP: End of 2013

> Design/Build Activities Begin: Mid 2014

Page 6: 2 /Broadway Station Meeting · > During previous phases of the project, the community requested Metro consider ways to expedite and shorten the overall work schedule. > In order to

www.metro.net/regionalconnector 6

Ongoing Activities 3rd Party Utility Relocation

> Intersection work Saturday and Sunday only > Continue through early summer 2013 > Time Warner Cable (TWC) > AT&T / TCG > Level 3

Subsequent Relocations > So Cal Gas (SCG)

Page 7: 2 /Broadway Station Meeting · > During previous phases of the project, the community requested Metro consider ways to expedite and shorten the overall work schedule. > In order to

www.metro.net/regionalconnector 7

Information on Metro’s Request for an Extended

Work Hours

Page 8: 2 /Broadway Station Meeting · > During previous phases of the project, the community requested Metro consider ways to expedite and shorten the overall work schedule. > In order to

www.metro.net/regionalconnector 8

Summary of Work Hours Daytime Allowable Hours Extended Hours

Monday through Friday: 7am - 9pm

Monday through Friday: 9pm - 7am of the following day

Saturday: 8am - 6pm

Saturday: Before 8am & after 6pm

No Sunday work All day Sunday

Peak Traffic Hour Restricts construction from 6am – 9am and from 3:30pm – 7pm, Monday through Friday.

Holiday Moratorium Restricts construction from before Thanksgiving to after New Year’s Day holidays.

Page 9: 2 /Broadway Station Meeting · > During previous phases of the project, the community requested Metro consider ways to expedite and shorten the overall work schedule. > In order to

www.metro.net/regionalconnector 9

Restricted Construction Work Hours 12A 6A 7A 9A Noon 3:30P 7P 9P 12A

City of Los Angeles Permitted Work Hours

Peak Hour Exemption Permit

Extended Hours Exemption Permit

Page 10: 2 /Broadway Station Meeting · > During previous phases of the project, the community requested Metro consider ways to expedite and shorten the overall work schedule. > In order to

www.metro.net/regionalconnector 10

Getting to “Work” Applications for Construction Activity

Holiday Moratorium Exemption

Peak Hour Exemption

Night Time Exemption

City Decision

Permit for exemptions and extended hours work Secure approved Traffic Control Plans, Contractor to secure materials and equipment

Construction Work in the Street

Page 11: 2 /Broadway Station Meeting · > During previous phases of the project, the community requested Metro consider ways to expedite and shorten the overall work schedule. > In order to

www.metro.net/regionalconnector 11

Request Background > During previous phases of the project, the community requested

Metro consider ways to expedite and shorten the overall work schedule.

> In order to work extended work hours (shortening the overall construction duration of work), Metro must request permission from the City.

> Continued approval of extended work hours is conditional on performance, and is based on community feedback.

> Notices will be distributed to the community detailing expected and approved work activity.

Page 12: 2 /Broadway Station Meeting · > During previous phases of the project, the community requested Metro consider ways to expedite and shorten the overall work schedule. > In order to

www.metro.net/regionalconnector 12

Conceptual Construction Sequencing

Page 13: 2 /Broadway Station Meeting · > During previous phases of the project, the community requested Metro consider ways to expedite and shorten the overall work schedule. > In order to

www.metro.net/regionalconnector 13

Conceptual Construction Sequencing

Page 14: 2 /Broadway Station Meeting · > During previous phases of the project, the community requested Metro consider ways to expedite and shorten the overall work schedule. > In order to

www.metro.net/regionalconnector 14

Solider Pile Installation

Street is open to traffic

Page 15: 2 /Broadway Station Meeting · > During previous phases of the project, the community requested Metro consider ways to expedite and shorten the overall work schedule. > In order to

www.metro.net/regionalconnector 15

Pile & Deck Installation

Page 16: 2 /Broadway Station Meeting · > During previous phases of the project, the community requested Metro consider ways to expedite and shorten the overall work schedule. > In order to

www.metro.net/regionalconnector 16

Deck Installation

> Construction of Deck support system in place during Metro Gold Line Project

Page 17: 2 /Broadway Station Meeting · > During previous phases of the project, the community requested Metro consider ways to expedite and shorten the overall work schedule. > In order to

www.metro.net/regionalconnector 17

Deck Installation

> Temporary Deck maintains mobility of traffic while construction activities take place below it

Page 18: 2 /Broadway Station Meeting · > During previous phases of the project, the community requested Metro consider ways to expedite and shorten the overall work schedule. > In order to

www.metro.net/regionalconnector 18

Steady State

Page 19: 2 /Broadway Station Meeting · > During previous phases of the project, the community requested Metro consider ways to expedite and shorten the overall work schedule. > In order to

www.metro.net/regionalconnector 19

Cut and Cover Excavation below street surface Existing utilities and support

systems are visible.

Page 20: 2 /Broadway Station Meeting · > During previous phases of the project, the community requested Metro consider ways to expedite and shorten the overall work schedule. > In order to

www.metro.net/regionalconnector 20

Tunneling Equipment

Page 21: 2 /Broadway Station Meeting · > During previous phases of the project, the community requested Metro consider ways to expedite and shorten the overall work schedule. > In order to

www.metro.net/regionalconnector 22

Next Steps

> City Council, LAPD, and LADOT appreciates feedback from the community

> Consider submitting feedback in response to the presentation

> LAPD Officers may contact you

> Questions or comments can be directed to Metro Construction Relations

Page 22: 2 /Broadway Station Meeting · > During previous phases of the project, the community requested Metro consider ways to expedite and shorten the overall work schedule. > In order to

www.metro.net/regionalconnector 23

Community Outreach and Notification

> Advance look-ahead of activities provided at Regional Community Leadership Council Committee (RCLCC) Station Area and community meetings

> Presentation on activities in advance of work starting at Station Area Committee Meetings

> Notification to stakeholders one week in advance of work starting

> Construction updates on project website, Facebook and Twitter

Page 23: 2 /Broadway Station Meeting · > During previous phases of the project, the community requested Metro consider ways to expedite and shorten the overall work schedule. > In order to