2 /broadway station meeting · > during previous phases of the project, the community requested...
TRANSCRIPT
www.metro.net/regionalconnector 1
2nd/Broadway Station Meeting June 3, 2013
www.metro.net/regionalconnector 2
Tonight’s Speakers
Olga Arroyo, Metro Construction Relations Manager
Dan Comorre, P.E., Metro Director of Construction Management
www.metro.net/regionalconnector 3 3
Agenda
> Project Overview and Update
> Extended Work Hours Requests
> Next Steps
> How to Contact Us
www.metro.net/regionalconnector 4
Project Overview > $1.366 billion underground Light
Rail Transit System
> Connects Metro Gold Line to Metro Blue and Expo Lines
> 1.9-miles
> 3 Underground Stations • 1St/Central • 2nd/Broadway • 2nd/Hope
> 2020 Anticipated Opening Date
4
www.metro.net/regionalconnector 5
Procurement Effort
> Current: RFP was issued in Jan. 2013 to Metro Pre-Qualified Firms • Firms invited to participate in a Pre-Qualification process (SOQ) • Pre-Qualified firms invited to submit proposals (RFP)
> Proposals Due: July 2013
> Award Contract and Provide NTP: End of 2013
> Design/Build Activities Begin: Mid 2014
www.metro.net/regionalconnector 6
Ongoing Activities 3rd Party Utility Relocation
> Intersection work Saturday and Sunday only > Continue through early summer 2013 > Time Warner Cable (TWC) > AT&T / TCG > Level 3
Subsequent Relocations > So Cal Gas (SCG)
www.metro.net/regionalconnector 7
Information on Metro’s Request for an Extended
Work Hours
www.metro.net/regionalconnector 8
Summary of Work Hours Daytime Allowable Hours Extended Hours
Monday through Friday: 7am - 9pm
Monday through Friday: 9pm - 7am of the following day
Saturday: 8am - 6pm
Saturday: Before 8am & after 6pm
No Sunday work All day Sunday
Peak Traffic Hour Restricts construction from 6am – 9am and from 3:30pm – 7pm, Monday through Friday.
Holiday Moratorium Restricts construction from before Thanksgiving to after New Year’s Day holidays.
www.metro.net/regionalconnector 9
Restricted Construction Work Hours 12A 6A 7A 9A Noon 3:30P 7P 9P 12A
City of Los Angeles Permitted Work Hours
Peak Hour Exemption Permit
Extended Hours Exemption Permit
www.metro.net/regionalconnector 10
Getting to “Work” Applications for Construction Activity
Holiday Moratorium Exemption
Peak Hour Exemption
Night Time Exemption
City Decision
Permit for exemptions and extended hours work Secure approved Traffic Control Plans, Contractor to secure materials and equipment
Construction Work in the Street
www.metro.net/regionalconnector 11
Request Background > During previous phases of the project, the community requested
Metro consider ways to expedite and shorten the overall work schedule.
> In order to work extended work hours (shortening the overall construction duration of work), Metro must request permission from the City.
> Continued approval of extended work hours is conditional on performance, and is based on community feedback.
> Notices will be distributed to the community detailing expected and approved work activity.
www.metro.net/regionalconnector 12
Conceptual Construction Sequencing
www.metro.net/regionalconnector 13
Conceptual Construction Sequencing
www.metro.net/regionalconnector 14
Solider Pile Installation
Street is open to traffic
www.metro.net/regionalconnector 15
Pile & Deck Installation
www.metro.net/regionalconnector 16
Deck Installation
> Construction of Deck support system in place during Metro Gold Line Project
www.metro.net/regionalconnector 17
Deck Installation
> Temporary Deck maintains mobility of traffic while construction activities take place below it
www.metro.net/regionalconnector 18
Steady State
www.metro.net/regionalconnector 19
Cut and Cover Excavation below street surface Existing utilities and support
systems are visible.
www.metro.net/regionalconnector 20
Tunneling Equipment
www.metro.net/regionalconnector 22
Next Steps
> City Council, LAPD, and LADOT appreciates feedback from the community
> Consider submitting feedback in response to the presentation
> LAPD Officers may contact you
> Questions or comments can be directed to Metro Construction Relations
www.metro.net/regionalconnector 23
Community Outreach and Notification
> Advance look-ahead of activities provided at Regional Community Leadership Council Committee (RCLCC) Station Area and community meetings
> Presentation on activities in advance of work starting at Station Area Committee Meetings
> Notification to stakeholders one week in advance of work starting
> Construction updates on project website, Facebook and Twitter
www.metro.net/regionalconnector 24
How to Contact Us
[email protected] Facebook.com/metroregionalconnector @metroconnector www.metro.net/regionalconnector Project Hotline: 213-922-7277