1khd626830de commissioning report etl600
TRANSCRIPT
We reserve all rights in this document and in the information contained therein. Reproduction,use or disclosure to third parties without express authority is strictly forbidden. © ABB Switzerland Ltd
Rev. ind: ..
Type des. Part no. Prep. R. Pauli / PSNEX 2006-02-14 Doc.kind No. of p.
Appr. H. Benninger / PSND 2007-02-14 Resp.dept. PSNEX
Title Commissioning Report ETL600 13+
Doc. no. Lang. Rev. ind. Page
ABB Switzerland Ltd en D C1 1KHD626830 FILE: 1KHD626830de Commissioning Report ETL600.doc; TEMPLATE: TECHN_DOC_STAND_P.dot R0; SKELETON: ; SAVEDATE: 2/15/2007 10:53:00 AM
COMMISSIONING REPORT
Powerline Carrier Equipment: Series ETL600
Project : ………………………….. ABB Order N° : ………………………….. Station : ………………………….. Link : ………………………….. Equipment N° : ………………………….. Frequency : TX = …………kHz RX = …………kHz Direction : …………………………..
Commissioning Report contains ETL600 System Test Report Pages C1 to C13 HMI600 Printout of Configuration Pages ............. HMI600 Printout of Status Pages .............
The tuning of the equipment is in accordance with the following instructions:
Programming and Testing of ETL600 1KHW001493-EN Compatibility Requirements for ETL600 1KHW001490-EN Tuning of ETL600 Rx RF Filter P4RX 1KHW001491-EN Tuning of ETL600 Tx RF Filter E5TX 1KHW001492-EN Input Voltage Change B5LC 1KHL015788-EN APLC Channel Equalization for ETL600 1KHW001494-EN Firmware Download for ETL600 1KHW001496-EN Technical Data ETL600 1KHW001498-EN
Doc. no. Lang. Rev. ind. Page
ABB Switzerland Ltd en D C2 1KHD626830
SAFETY INSTRUCTIONS
Please refer to chapter 2 of Instruction Manual 1KHW001489.
Designations and abbreviations used:
Designation Meaning
___________ Measured value
[ ... ] Programmed value
[ ] D Preferred setting (default)
[ X ] Test passed or jumper is set
[ ] Not tested or jumper is not set
B5LA Module type
BER Bit Error Ratio
Def. Default value
equ. Equipment
fLo Lower frequency, usually meant as low cut-off frequency
LED Light Emitting Diode found on the front panel
HMI600 User Interface Program for ETL600 running on a PC
N11, …, N71 Position in rack. Slot number N11, …, N71
Rx Receiver
Tx Transmitter
PC Personal Computer
X11, …, X71 Position in rack. Equivalent to N11, …, N71
(T.22/..1) Connector 1 of terminal block connected to board at rack position N22
REVISION
Rev. ind. Page (p.) Chapter (c.)
Description Date Dept./Init.
c Step C10.2 Replaced T22 by T71 2006-04-26 PTUKT/Be
d p. 1, p. 13 p. 1 C.14, C.15
Changed department designations Added lines for Link designation and HMI600 status printout Inserted tests of G.703.1 and LAN ports
2007-02-01 PSND/Be
Rev. ind. Commissioning Report ETL600 Equipment HE
Notes: .............................................................................................................................................................. .............................................................................................................................................................. .............................................................................................................................................................. Sign Commissioning Eng.: Sign Witness Eng.:
Doc. no. Lang. Rev. ind. Page
ABB Switzerland Ltd 1KHD626830 en D C3
Test No.
Test procedure
Test point
Permissible value
Units
Test result
C.1. General
C.1.1 Checking the line of communication Line attenuation dB [ ] Return loss Ar dB [ ]
C.1.2 Visual checks Proper wiring of protective earth P7LA, P7LC PE wired [ ] Proper wiring of protective earth Cubicle PE wired [ ] Proper wiring of power supply P7LA, P7LC polarity ok [ ]
upper ∗ lower Proper settings on power supply modules B5LA, B5LC jumpers & fuses ok
[ ] [ ] D If the positive pole (+) of the battery is
grounded, place an earth jumper to the positive pole (+) of the cubicle supply
Cubicle supply terminals [ ]
C.2. Power supply for channel rack P7LA
upper * lower
C.2.1 Battery supply 48V DC B5LA (BAT-0V) -46 to –56 V DC [ ] [ ] D
C.2.2 Mains supply 230V AC B5LC (UR-0V) -46 to –52 V DC [ ] [ ] D
C.2.3 Mains supply 115V AC B5LC (UR-0V) -46 to –52 V DC [ ] [ ] D
C.2.4 Ripple on 48V DC B5LA (BAT-0V) < 1 V rms [ ] [ ] D
C.2.5 Ripple on UR (Mains) B5LC (UR-0V) < 1 V rms [ ] [ ] D
∗ ‘upper’ und ‘lower’ stands for upper rack / lower rack and applies to 80 W equipment ETL680 only.
Rev. ind. Commissioning Report ETL600 Equipment HE
Notes: .............................................................................................................................................................. .............................................................................................................................................................. .............................................................................................................................................................. Sign Commissioning Eng.: Sign Witness Eng.:
Doc. no. Lang. Rev. ind. Page
ABB Switzerland Ltd 1KHD626830 en D C4
Test No.
Test procedure
Test point
Permissible value
Units
Test result
C.3. Upload configuration [ ]
C.4. Change configuration, if necessary [ ]
C.4.1 Reducing Output power, if necessary
Determine Ar min = minimal value of Ar as measured in C.1.1
Ar min= ___________
dB
Calculate output power reduction Ared: No reduction, if Ar min ≥ 12 dB: Ared = max(0, (3 - Ar min / 4 ))
Ared = ___________
dB
Decrease Max. power PEP by Ared HMI600: Configuration / System / Channel settings / Max. power (PEP)
[ ]
Store configuration to flash HMI600: Equipment / Store configuration to FLASH
[ ]
C.5. Transmitter
C.5.1 Adjust Tx RF level Dialog box: Adjust Tx RF level
Click Start or Set RF line monitor on RF hybrid or RF line (X175)
value indicated in dialog box
[ ]
C.5.2 Adjust Tx alarm level Dialog box: Adjust Tx alarm level
Click Activate Tx alarm level, set jumper CH and turn potentiometer R116 on P1LA till LED on it lights
LED to be ON
[ ]
Tx alarm indication: RF hybrid & - in case of 80W - combiner
LED to be ON [ ]
State of HW alarm relay after programmed delay.
Pins 2-3 of V9OT cable Closed [ ]
Turn potentiometer R116 on P1LA till LED on it goes off.
LED to be OFF [ ]
Tx alarm indication RF hybrid & - in case of 80W - combiner
LED to be OFF [ ]
State of HW alarm relay after programmed delay. Click OK.
Pins 2-3 of V9OT cable Open [ ]
Rev. ind. Commissioning Report ETL600 Equipment HE
Notes: .............................................................................................................................................................. .............................................................................................................................................................. .............................................................................................................................................................. Sign Commissioning Eng.: Sign Witness Eng.:
Doc. no. Lang. Rev. ind. Page
ABB Switzerland Ltd 1KHD626830 en D C5
Test No.
Test procedure
Test point
Permissible value
Units
Test result
C.6. Receiver
C.6.1 Adjust Rx RF level Menu: Equipment Commissioning and
maintenance, dialog box: Adjust Rx RF level
Follow the instructions in the dialog box Line attenuation Dialog box __________ dB Increase of receive level (due to parallel
PLC links) Dialog box
__________ dB
Adjustment performed [ ]
C.6.2 Connect RF cable and set alarm thresholds 1
Alarm thresholds set (Menu: Configuration / System / Alarm settings)
Dialog box [ ]
C.6.3 Check link alarms 1 Link alarm of the local equipment Alarm status of the local
equipment No local link alarm
[ ]
Link alarm of the remote equipment No remote link alarm
[ ]
C.6.4 Tune hybrid P3LE 2
RF Coaxial cable to be connected. Dialog box: Tune RF hybrid
Press 'Start measurement' & adjust the balancing network (Resistance with jumper RA/RB/RC/RD/RP and potentiometer R226, inductance with jumper LA – LN/LP and capacitance with jumpers CA to CL, CP)
Dialog box Till minimum is read by HMI.
[ ]
C.6.5 SNR pilot
Upload status data of local equipment Ch 1 Ch 2 Ch 3 SNR pilot HMI600 > 15 dB [ ] [ ] [ ]
C.7. Equalization
C.7.1 Measure frequency response
Ch 1 Ch 2 Ch 3
In menu Equipment / Commissioning and maintenance / Frequency response / APLC channel 1, APLC channel 2 or APLC channel 3
HMI600 [ ] [ ] [ ]
1 If the remote equipment is operational 2 The tuning is not necessary when the ETL600 is operated without Rx filter P4RX.
Rev. ind. Commissioning Report ETL600 Equipment HE
Notes: .............................................................................................................................................................. .............................................................................................................................................................. .............................................................................................................................................................. Sign Commissioning Eng.: Sign Witness Eng.:
Doc. no. Lang. Rev. ind. Page
ABB Switzerland Ltd 1KHD626830 en D C6
Test No.
Test procedure
Test point
Permissible value
Units
Test result
C.7.2 Select Equalizer
Ch 1 Ch 2 Ch 3
In menu Equipment / Commissioning and maintenance / Select equalizer / APLC channel 1, APLC channel 2 or APLC channel 3
HMI600 [ ] [ ] [ ]
C.8. R1BC, if present [ ]
Activate alarms as programmed on R1BC.
Corresponding N/C contacts on R1BC.
Closed [ ]
Deactivate alarms as programmed on R1BC.
Corresponding N/C contacts on R1BC.
Open [ ]
C.9. Configure Real time Clock (RTC)
C.9.1 Setting real time clock Menu: Equipment, Commissioning and
maintenance, Eventrecorder, Set clock
Download date/time to RTC Dialog box Actual time and date
[ ]
C.9.2 Test external real time clock synchronization, if available
Menu: Equipment, Commissioning and maintenance, Eventrecorder, Set clock
Download date/time to RTC Dialog box Wrong time Upload date/time from RTC Dialog box Correct time [ ]
Test No.
Test procedure
Test point
Permissible value
Units
Test result
C.10. NSD600 / G4AI, if present
C.10.1 NSD600 loop test TPE1 TPE2
Check Actual transmission time TLink
Menu: Equipment, Commissioning and maintenance, NSD600 send loop test
HMI600
< 2*T0
ms
_______
_______
Rev. ind. Commissioning Report ETL600 Equipment HE
Notes: .............................................................................................................................................................. .............................................................................................................................................................. .............................................................................................................................................................. Sign Commissioning Eng.: Sign Witness Eng.:
Doc. no. Lang. Rev. ind. Page
ABB Switzerland Ltd 1KHD626830 en D C7
Test No.
Test procedure
Test point
Permissible value
Units
Test result
C.10.2 Command transmission time Command A
Tx command A Rx command A
Terminal: (T71/1) – (T71/2) [ ](T…/...) – (T.../…) [ ](T71/9) – (T71/10) [ ](T…/...) – (T.../…) [ ]
Refer HMI600 Mean value
≤ T0
ms
TPE1
________
TPE2
________
Command B Tx command B Rx command B
Terminal: (T71/3) – (T71/4) [ ](T…/...) – (T.../…) [ ](T71/11) – (T71/12) [ ](T…/...) – (T.../…) [ ]
Refer HMI600 Mean value
≤ T0
ms
TPE1
________
TPE2
________
Command C Tx command C Rx command C
Terminal: (T71/5) – (T71/6) [ ](T…/...) – (T.../…) [ ](T71/13) – (T71/14) [ ](T…/...) – (T.../…) [ ]
Refer HMI600 Mean value
≤ T0
ms
TPE1
________
TPE2
________
Command D Tx command D Rx command D
Terminal: (T71/7) – (T71/8) [ ](T…/...) – (T.../…) [ ](T71/15) – (T71/16) [ ](T…/...) – (T.../…) [ ]
Refer HMI600 Mean value
≤ T0
ms
TPE1
________
TPE2
________
C.10.3 Reset counters
Menu: Equipment, Commissioning and maintenance, Eventrecorder, Reset counter, OK:
HMI600 All counters = 0 [ ]
C.11. Testing of O4LE
C.11.1 Service Phone. Mark if configured: N11 [ ]
N22 [ ]
N54 [ ]
Pick up the phones and talk. Service phone, at front panel
Talk is possible without feedback
N11 [ ]
N22 [ ]
N54 [ ]
C.11.2 Hot line direct phone Mark if configured: N11 [ ]
N22 [ ]
N54 [ ]
Pick up the phone, wait, pick up remote phone
Direct phone Talk is possible without feedback
N11 [ ]
N22 [ ]
N54 [ ]
Rev. ind. Commissioning Report ETL600 Equipment HE
Notes: .............................................................................................................................................................. .............................................................................................................................................................. .............................................................................................................................................................. Sign Commissioning Eng.: Sign Witness Eng.:
Doc. no. Lang. Rev. ind. Page
ABB Switzerland Ltd 1KHD626830 en D C8
Test No.
Test procedure
Test point
Permissible value
Units
Test result
C.11.3 Remote subscriber Mark if configured: N11 [ ]
N22 [ ]
N54 [ ]
Measure voltage at open loop condition
43 V … 52 V V DC N11: ___________
N22: ___________
N54: ___________ Pick up the phone, wait, pick up
remote phone
Talk is possible without feedback
N11 [ ]
N22 [ ]
N54 [ ]
C.11.4 Pax 2-wire Mark if configured: N11 [ ]
N22 [ ]
N54 [ ]
PAX-BLOCKING normal
Measure at terminal, telephony 6a-6b, 6b-7a
6a-6b is open 6b-7a is closed
N11 [ ]
N22 [ ]
N54 [ ]
PAX-BLOCKING blocked Interrupt local loop, wait about 30 sec.
Measure at terminal, telephony 6a-6b, 6b-7a
6a-6b is open 6b-7a is closed
N11 [ ]
N22 [ ]
N54 [ ]
C.11.5 Pax 4-wire Mark if configured: N11 [ ]
N22 [ ]
N54 [ ]
Test E-Wire: Close and open at Remote equ. at terminal, telephony 4a-4b
Terminal, telephony 3a-3b
E-Wire must toggle N11 [ ]
N22 [ ]
N54 [ ]
Measure Output level. Feed 800 Hz with configured input level of remote PAX (Default: -3.5 dBm). (Activate at terminal, telephony 4a-4b)
Feed into rem. equ. at terminal, telephony 1a-1b Measure at terminal, telephony 2a-2b
Configured Output level ±1 dB (Def.: -3.5 dBm)
dBm (600 Ω)
N11 [ ]
N22 [ ]
N54 [ ]
PAX-BLOCKING normal
Measure at terminal, telephony 6a-6b, 6b-7a
6a-6b is open 6b-7a is closed
N11 [ ]
N22 [ ]
N54 [ ]
PAX-BLOCKING blocked Interrupt local loop, wait about 30 sec.
Measure at terminal, telephony 6a-6b, 6b-7a
6a-6b is open 6b-7a is closed
N11 [ ]
N22 [ ]
N54 [ ]
Rev. ind. Commissioning Report ETL600 Equipment HE
Notes: .............................................................................................................................................................. .............................................................................................................................................................. .............................................................................................................................................................. Sign Commissioning Eng.: Sign Witness Eng.:
Doc. no. Lang. Rev. ind. Page
ABB Switzerland Ltd 1KHD626830 en D C9
Test No.
Test procedure
Test point
Permissible value
Units
Test result
C.11.6 Pax 4/2-wire Mark if configured: N11 [ ]
N22 [ ]
N54 [ ]
Test E-Wire: Close and open at terminal, telephony 4a-4b
Terminal, telephony 3a-3b
E-Wire must toggle N11 [ ]
N22 [ ]
N54 [ ]
Measure Output level at AF1. Feed 800 Hz with configured input level (Def.: -3.5 dBm). (Activate at terminal, telephony 4a-4b)
Feed into terminal, telephony 1a-1b Measure at terminal, telephony 2a-2b
Configured Output level ±1 dB (Def.: -3.5 dBm)
dBm (600 Ω)
N11 [ ]
N22 [ ]
N54 [ ]
Measure Output level at PAX2W. Feed 800 Hz with configured input level (Def.: -3.5 dBm). (Activate at terminal, telephony 4a-4b)
Feed into rem. equ. at terminal, telephony 1a-1b Measure at terminal, telephony 8a-8b
Configured Output level ±1 dB (Def.: -7.0 dBm)
dBm (600 Ω)
N11 [ ]
N22 [ ]
N54 [ ]
Test Local/Transit: Measure Output level at AF1. Feed 800 Hz with configured input level of PAX2W (Def: -0.0 dBm). Activate terminal, telephony 5a-4b and 4a-4b.
Feed into rem. equ. at terminal, telephony 8a-8bMeasure at terminal, telephony 8a-8b
Configured Output level ±1.5 dB (Def.: -7.0 dBm)
dBm (600 Ω)
N11 [ ]
N22 [ ]
N54 [ ]
PAX-BLOCKING normal
Measure at terminal, telephony 6a-6b, 6b-7a
6a-6b is open 6b-7a is closed
N11 [ ]
N22 [ ]
N54 [ ]
PAX-BLOCKING blocked Interrupt local loop, wait about 30 sec.
Measure at terminal, telephony 6a-6b, 6b-7a
6a-6b is open 6b-7a is closed
N11 [ ]
N22 [ ]
N54 [ ]
C.11.7 Transit mode for E&M wire Mark if configured: N11 [ ]
N22 [ ]
N54 [ ]
Test E-Wire: Close and open at Remote equ. at terminal, telephony 4a-4b
Terminal, telephony 3a-3b
E-Wire must toggle N11 [ ]
N22 [ ]
N54 [ ]
Rev. ind. Commissioning Report ETL600 Equipment HE
Notes: .............................................................................................................................................................. .............................................................................................................................................................. .............................................................................................................................................................. Sign Commissioning Eng.: Sign Witness Eng.:
Doc. no. Lang. Rev. ind. Page
ABB Switzerland Ltd 1KHD626830 en D C10
Test No.
Test procedure
Test point
Permissible value
Units
Test result
C.11.8 Testing the teleoperation ports
N11 N22 N34 N54 N65C.11.9 Teleoperation AF1, if not used for telephony
Mark if configured:
[ ] [ ] [ ] [ ] [ ]
Fed input level, [dBm], @ 800 Hz at AF1-IN
Expected Output level at AF1-OUT
Measured Output level at AF1-OUT
N11: ___________±1
N22: ___________±1
N34: ___________±1
N54: ___________±1
N65: ___________±1
Feed into terminal, telephony 1a-1b Measure at terminal, telephony 2a-2b Ext. Boost not active.
N11: _______±1
N22: _______±1
N34: _______±1
N54: _______±1
N65: _______±1
dBm (600 Ω)
N11: ___________
N22: ___________
N34: ___________
N54: ___________
N65: ___________
N11 N22 N34 N54 N65C.11.10 Teleoperation AF2 Mark if configured:
[ ] [ ] [ ] [ ] [ ]
Fed input level, [dBm], @ 800 Hz at AF2-IN of remote.
Expected Output level at AF2-OUT
Measured Output level at AF2-OUT
N11: ___________±1
N22: ___________±1
N34: ___________±1
N54: ___________±1
N65: ___________±1
Feed into rem. equ. at terminal, teleop. 3a-3bMeasure at terminal, teleop. 4a-4bext. Boost not active.
N11: _______±1
N22: _______±1
N34: _______±1
N54: _______±1
N65: _______±1
dBm (600 Ω)
N11: ___________
N22: ___________
N34: ___________
N54: ___________
N65: ___________
N11 N22 N34 N54 N65C.11.11 Teleoperation AF3 Mark if configured:
[ ] [ ] [ ] [ ] [ ]
Fed input level, [dBm], @ 800 Hz at AF3-IN of remote.
Expected Output level at AF3-OUT
Measured Output level at AF3-OUT
N11: ___________±1
N22: ___________±1
N34: ___________±1
N54: ___________±1
N65: ___________±1
Feed into rem. equ. at terminal, teleop. 5a-5bMeasure at terminal, teleop. 6a-6bext. Boost not active.
N11: _______±1
N22: _______±1
N34: _______±1
N54: _______±1
N65: _______±1
dBm (600 Ω)
N11: ___________
N22: ___________
N34: ___________
N54: ___________
N65: ___________
Rev. ind. Commissioning Report ETL600 Equipment HE
Notes: .............................................................................................................................................................. .............................................................................................................................................................. .............................................................................................................................................................. Sign Commissioning Eng.: Sign Witness Eng.:
Doc. no. Lang. Rev. ind. Page
ABB Switzerland Ltd 1KHD626830 en D C11
Test No.
Test procedure
Test point
Permissible value
Units
Test result
N11 N22 N34 N54 N65C.11.12 Teleoperation AF4 Mark if configured:
[ ] [ ] [ ] [ ] [ ]
Fed input level, [dBm], @ 800 Hz at AF4-IN of remote.
Expected Output level at AF4-OUT
Measured Output level at AF4-OUT
N11: ___________±1
N22: ___________±1
N34: ___________±1
N54: ___________±1
N65: ___________±1
Feed into rem. equ. at terminal, teleop. 7a-7bMeasure at terminal, teleop. 8a-8bext. Boost not active.
N11: _______±1
N22: _______±1
N34: _______±1
N54: _______±1
N65: _______±1
dBm (600 Ω)
N11: ___________
N22: ___________
N34: ___________
N54: ___________
N65: ___________
N11 N22 N54 C.11.13 Teleoperation AF4 used for ext. teleprotection
Mark if configured: [ ] [ ] [ ]
Test EXT-BOOST:
Activate at remote equ. at terminal, teleop. 9a-9b
Fed input level, [dBm], @ 800 Hz at AF4-IN
Feed into rem. equ. at terminal, teleop. 7a-7b
Expected Output level at AF4-OUT
Measured Output level at AF4-OUT
N11: ___________
N22: ___________
N54: ___________
Measure at terminal, teleop. 8a-8b
N11: _______±1
N22: _______±1
N54: _______±1
dBm (600 Ω)
N11: ___________
N22: ___________
N54: ___________
C.12. V.11 ports
C.12.1 V.11 Port 1 Front plate P4LT/P4LU
BER test V.11 PORT 1 BER ≤ 10-5
during ____ sec [ ]
C.12.2 V.11 Port 2 Front plate P4LT/P4LU
BER test V.11 PORT 2 BER ≤ 10-5
during ____ sec [ ]
C.13. V.24 ports
C.13.1 V.24 Port 1 Front plate P4LT/P4LU
BER test V.24 PORT 1 BER ≤ 10-5
during ____ sec [ ]
C.13.2 V.24 Port 2 Front plate P4LT/P4LU
BER test V.24 PORT 2 BER ≤ 10-5
during ____ sec [ ]
Rev. ind. Commissioning Report ETL600 Equipment HE
Notes: .............................................................................................................................................................. .............................................................................................................................................................. .............................................................................................................................................................. Sign Commissioning Eng.: Sign Witness Eng.:
Doc. no. Lang. Rev. ind. Page
ABB Switzerland Ltd 1KHD626830 en D C12
Test No.
Test procedure
Test point
Permissible value
Units
Test result
C.13.3 V.24 Port 3 Front plate P4LT/P4LU
BER test V.24 PORT 3 BER ≤ 10-5
during ____ sec [ ]
C.13.4 V.24 Port 4 Front plate P4LT/P4LU
BER test V.24 PORT 4 BER ≤ 10-5
during ____ sec [ ]
C.13.5 V.24 Port 5 Front plate P4LT/P4LU
BER test V.24 PORT 5 BER ≤ 10-5
during ____ sec [ ]
C.13.6 V.24 Port 6 Front plate P4LT/P4LU
BER test V.24 PORT 6 BER ≤ 10-5
during ____ sec [ ]
C.14. Testing of G.703.1 port
C.14.1 G.703.1 Port Front plate P4LT/P4LU
BER test G.703.1 PORT BER ≤ 10-5
during ____ sec [ ]
C.15. Testing of LAN port
C.15.1 LAN Port Front plate P4LT/P4LU
Test of throughput LAN PORT Throughput during _____ sec
_____
__________________
Percentage of errored frames LAN PORT % errored frames during _____ sec
%
_________
C.16. Manual reset [ ]
C.17. Documentation
If possible, take printout of Configuration data for reference.
[ ]
Save the 'et6' file on disk with Serial No. of ETL coded in the file name, e.g. ‘HE400327C.et6’.
[ ]
Rev. ind. Commissioning Report ETL600 Equipment HE
YES NO YES NO
Commissioning Approved: Exceptions Noted: Name of responsible
PSNP3
Signature & Date
Company ABB Switzerland Ltd Consultant Customer
Doc. no. Lang. Rev. ind. Page
ABB Switzerland Ltd 1KHD626830 en D C13
Pending Items List: Issue Description