1.ea engineering change notice 2 1 hi. ecn/67531/metadc... · through its primary fuses. this...
TRANSCRIPT
-
1 . E a 66 1456 hi. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
ECN 2 ENGINEERING CHANGE NOTICE Pwa 1 Of ~
ECN Category (mark one) Supplemental 0 S . A . K r i e g , CSB, S8-06 , 376-0931 Direct Revision IXI
3. Originatofs Name, Organization, MSIN, and Telephone No. 4. USQ Required? 5. Date
[XIYes 0 No 06/28/2000
V5Q fnokiy 6. CS@ 400- /Os'/ ) e s i g n v e r i f i c a t i o n by i n d e p e n d e n t review p e r EN 6-02
0 6. Project Title/No.NVork Order No. 7. Eldg./Sys./Fac. No. 0 CSB S u b p r o j e c t Change ECN Temporary
Standby 9. Document Numbers Changed by this ECN (includes I O . Related ECN No@). Supersedure 0 sheet no. and rev.)
212H
CancelNoid 0 SNF-6151, Rev. 0 N/A
4a. Justification (mark one)
Criteria Change 0
Environmental 0
As-Found 0 Facilitate Const. 0
Design Improvement
Facility Deactivation 0
Const. Error/Omission 0 Design Error/Omission 0
5. Distribution (include name .A. K r i e q ,
8. Approval Designator
Q , S 11. Related PO No.
N/A
740-0a Date
d .n&~.~ t~ f 6 4 q& m e
14b. Justification Details C h a p t e r s o m i t t e d i n r e v i s i o n 1 of doucment .
MSIN, and no. of copies) 58-06 (1) I
I RELEASE STAMP
2a. Modification Work
Yes (fill out Elk. 12b)
[XI No (NA Elks. 12b, 1 2c. 12d)
, . D . B a z i n e t , 58-06 (1) 1.M. B lack , R3-86 ( 1 ) . S . Moss, R3-11 (1)
1.M. S e r r a n o , 52-44 ( 2 ) ' S B P r o j e c t F i l e s , S8-06 (0) e n t r a l F i l e s , B1-07 ( 2 )
12b. Work Package No. 12c. Modification Work Completed 12d Restored lo Ori inal Condition (Temp.
N/A N/A N/A
or Standby ECds only)
Design AuthorityICo Engineer Signature & Design AuthoritylCo Engineer Signature 8 Jete &e
A-7900-01 3-2 (10/97) A - 7 W O t S1
-
Page 2 of 2 ENGINEERING CHANGE NOTICE
5 . Design Verification 17. Cost Impact Required ENGINEERING CONSTRUCTION
[XI Yes Additional $ N/A Additional 0 $ N/A 0 No Savings 0 $ Savings 0 $
- SDDIDD
Functional Design Criteria
Operating Specification
Criticality Specification
Conceptual Design Report
Equipment Spec.
Const. Spec.
Procurement Spec.
Vendor Information
OM Manual
FSARISAR
Safety Equipment List
Radiation Work Permit
Environmental Impact Statement
Environmental Report
1. ECN (use no. from p g ~ 1)
661456
18. Schedule Impact (days)
Improvement 0 N/A Delay 0
0 SeismiciStress Analysis 0 StresdDesign Report 0 Interface Control Drawing 0 Calibration Procedure 0 Installation Procedure 0 Maintenance Procedure 0 Engineering Procedure 0 Operating Instruction 0 Operating Procedure 0 Operational Safety Requirement 0 IEFD Drawing 0 Cell Arrangement Drawing
Essential Material Specification
0 Fat. Proc. Samp. Schedule 0 Inspection Plan
0 Tank Calibration Manual 0 Health Physics Procedure 0 Spares Multiple Unit Listing 0 Test ProceduredSpecification 0 Component Index 0 ASME Coded Item 0 Human Factor Consideration 0 Computer Soltware 0 Electric Circuit Schedule 0 ICRS Procedure 0 Process Control ManuallPlan 0 Process Flow Chad 0 Purchase Requisition 0 Tickler File 0 NONE
Environmental Permit 0 Inventory Adjustment Request 0 organuation has been notified of other affected documents listed below.
3. Other Affected Documents: (NOTE: Documents listed below will not be revised by this ECN.) Signatures below indicate that the signing
Document NumberlRevision Document NumberlRevision Document NumberlRevision
1. Approvals Signature Date
Design Authority S . A . K r - w - A - a L 4
Cog. Eng. D . M . Black ;% n7. Cog. Mgr. G.D. B a z i n r t 4 L; .zfi i'p
7- -- QA
-
SNF-6151 Revision 1
ECN 661456
Spent Nuclear Fuel Project Canister Storage Building System Design Descriptions
S. A. Krieg Fluor Hanford
Date Published
July 2000
Prepared for the U.S. Department of Energy Assistant Secretary for Environmental Management Project Hanford Management Contractor for the U S Department of Energy under Contract DE-AC06-96RL13200
P.O. Box 1000 Richland. Washington
Fluor H andord
Release Stamp
I. . I
Release Stamp
Approved for public release; further dissemination unl imited
-
SN F-6151 Revision 1
Spent Nuclear Fuel Project Canister Storage Building System Design Descriptions
Prepared for the U.S. Department of Energy Assistant Secretary for Environmental Management
Project Hanford Management Contractor for the U S Department of Energy under Contract DE-AC06-96RL13200
Fluor Hanf ord P.O. Box 1000 Richland, Washington
Approved for public release; further dissemination unlimited
-
or Service by trade name, trademark. manufacturer, or othewise, does not necessarily constitute or imply its endorsement, recommendation, or favoring by the United States Government or any agency thereof or its contractors or gubcontractors. .
This report has been reproduced from the best available copy. Available in paper copy and microfiche.
Available electronically at hllp:l lw.doe.govlbridge. Available for a processing fee to the U.S. Department of Energy and its contractors, in paper, from: U . S . Department of Energy Office of Scientific and Technical Information P.O. Box 52 Oak Ridae. TN 37831-0062 phone 865-575-8401 fax 865-576-5728 email reports@adonis osti gov(423) 576-8401
Available for sale to the public. in paper, from: U.S. Department of Commerce National Technical Information Service 5285 Port Royal Road Springfield, VA 22151 phone: 800-553-6847 fax: 703-605-6900 email: orders@ ntis.fedworld.gov Online ordering: http:llwww.ntis.govlordering.htm
Total Pages: 2 9
http://ntis.fedworld.govhttp:llwww.ntis.govlordering.htm
-
DE&S HANFORD, INC. SNF Canister Storage Building Contract TVW-SVV-370252
SNF-6151, Rev. 1 FLUOR DANIEL, INC. Government Services Operating Company
FDI Contract 80460210
SPENT NUCLEAR FUEL
SYSTEM DESIGN DESCRIPTIONS
CANISTER STORAGE BUILDING
-
..
DE&S HANFORD. INC . SNF Canister Storage Building Contract TVW-SVV-370252
~
I . 0
2.0
3.0
4.0
5.0
SNF.6151. Rev . 1 FLUOR DANIEL. INC . Government Services Operating Company
FDI Contract 80460210
TABLE OF CONTENTS
ELECTRICAL DISTRIBUTION SYSTEM DESCRIPTION (SYSIEM #1 AND #18) . . . 1.1 I . 2
I . 3 I . 4 I . 5 I . 6
INST 2 . I 2.2 2.3 2.4 2.5 2.6
Function . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Figure I : Site Plan Configuration . . . . Requirements . . . .
References . . . . . . Safct y . . . . . . . . . .
Opcmtion . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . .
. . . .
. . . .
UMENT/SERVICE A1 .. SYSTEM --SCRIP Function . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Operation . . . . . . . . . . . . . . . . . . . . . . . . . . . . Configuration . . . . . . . . . . . . . . . . . . . . . . . . . Requirements . . . . . . . . . . . . . . . . . . . . . . . . .
References Safety . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
ION (S
. . . .
. . . .
. . . .
. . . .
. . . .
. . . .
STEM +
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
I . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
FIRE PROTECTION SYSTEM DESCRIPTION (SYSTEM #3) . . . . . . . . . . . . . . . . . . . . . 3.1 Function . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.2 Operation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3.4 Requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3.6 References . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3.3 Configuration . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3.5 Safety . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
LIQUID WASTE COLLECTION SYSTEM DESCRIPTION (SYSTEM #4) . . . . . . . . . . . 4.1 Function . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4.2 Operation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4.3 Configuration . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4.4 Requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.6 References . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4.5 Safety . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
C:OMMUNICATIONS SYSTEM DESCRIPTION (SYSTEM # 5 ) . . . . . . . . . . . . . . . . . . . . 5.1 Function . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5.2 Operation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5.3 Configuration . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5.4 Requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5.5 Safety . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
.
. . .
. . .
. . .
. . .
. . .
. . .
. . .
. . .
. . .
. . .
. . .
. . .
. . .
. . .
. . .
. . .
. . .
. . .
. .
. .
. .
. .
. .
. .
. .
. .
. .
. .
___
. 1
. 7
. 7
. 8
. 8 I I 15 16
21 21 22 23 24 28 29
34 34 34 35 35 38 39
4 1 42 42 43 43 44 45
48 48 48 49 40
. 50 5.6 References . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . SI
-
. . .
DE&S HANFORD. INC . SNF Canister Storage Building Contract TVW-SVV-370252
SNF.6151. Rev . 1 FLUOR DANIEL. INC . Government Services Operating Company
FDI Contract 80460210
6.0
7.0
8.0
9.0
10.0
11.0
HEATING. VENTILATING AND AIR CONDITIONING SYSTEM DESCRIPTION
6.1 Function . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 53 6.2 Operation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 53 6.3 Configuration . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 54 6.4 Requircmcnts . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . SS 6.5 Safety . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 57 6.6 Refcrcnces . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . S~~
SANITARY WATER SYSTEM DESCRIPTION (SYSTEM #8) . . . . . . . . . . . . . . . . . . . . . . . 66 7.1 Function . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 66 7.2 Operation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 66 7.3 Configuration . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 66 7.4 Requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 67 7.5 Safety . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 67 7.6 References . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 69
(SYSTEMS#6AND#7) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . S~
BACKUP POWER SYSTEM DESCRIPTION (SYSTEM #9) . . . . . . . . . . . . . . . . . . . . . . . . . 71
HEALTH PROTECTION SYSTEM DESCRIPTION (SYSTEM # I O AND #I I ) . . . . . . . . . . . 73 9.1 Function . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 73 9.2 Operation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 73 9.3 Configuration . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 73 9.4 Requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 78 9.5 Safety . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 90 9.6 References . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 92
TRANSPORTATION CASK RECEIVING SYSTEM DESCRIPTION (SYSTEM #12) . . . . . 98 10.1 Function . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 98 10.2 Operation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 98 10.3 Configuration . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 105 10.4 Requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 106 10.5 Safety . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 118 10.6 References . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 121
TRANSPORTATION CASK SERVICING SYSTEM DESCRIPTION (SYSTEM #13) . . . . 127 11.1 Function . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 127 11.2 Operation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 127 11.3 Configuration . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 131 11.4 Requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 132 11.5 Safety . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 139 11.6 References . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1 4 ~
-
SNF.6151. Rev . 1 FLUOR DANIEL. INC . DE&S HANFORD. INC . SNF Canister Storage Building Contract TVW-SVV-370252
~
12.0
13.0
14.0
15.0
16.0
17.0
Government Services Operating Company FDI Contract 80460210
OVERPACK STORAGE TUBE VENT AND PURGE SYSTEM DESCRIPTION (SYSTEM #14) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 149 12.1 Function . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 149 12.2 Operation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 149 12.3 Configuration . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 157 12.4 Requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 158 12.5 Safety . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1 6 ~ 12.6 References . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 166
MCO HANDLING MACHINE SYSTEM DESCRIPTION (SYSTEM #IS) . . . . . . . . . . . . . . 170
VAULT COOLING SYSTEM DESCRIPTION (SYSTEM #l6) . . . . . . . . . . . . . . . . . . . . . . . 172 14.1 Function . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 172 14.2 Operation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 172 14.3 Configuration . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 172 14.4 Requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1 7 ~ 14.5 Safety . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 173 14.6 References . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 175
SECURITY SYSTEM DESCRIPTION (SYSTEM #17) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 179 15.1 Function . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 179 15.2 Operation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 179 15.3 Configuration . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 180 15.4 Requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 180 I Safety . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 181 15.6 References . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 182
ROLL-UP DOORS SYSTEM DESCRIPTION (SYSTEM #19) . . . . . . . . . . . . . . . . . . . . . . . 185 16.1 Function . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 185 16.2 Operation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 185 16.3 Configuration . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 188 16.4 Requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 189 16.5 Safety . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 193 16.6 References . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 194
FIRE WATER PUMP HOUSE SYSTEM DESCRIPTION (SYSTEM #20) . . . . . . . . . . . . . . 198 17.1 Function . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 198 17.2 Operation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 198 17.3 Configuration . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 199 17.4 Requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 199 17.5 Safety . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 202 17.6 References . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 203
-
DE&S HANFORD. INC . SNF Canister Storage Building Contract TVW-SVV-370252
SNF.6151. Rev . 1 FLUOR DANIEL. INC . Government Services Operating Company
FDI Contract 80460210
18.0 DISTRIBUTED CONTROL SYSTEM DESCRIPTION (SYSTEM #21) . . . . . . . . . . . . . . . . 206 18.1 Function . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 206
18.3 Configuration . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 208 18.4 Requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 208 18. S Safety . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2 0 ~ 18.6 References . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ~ 1 0
18.2 Opcration . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 207
19.0 MCO SAMPLINWWELD SYSTEM DESCRIPTION (SYSTEM #22 AND #23) . . . . . . . . . 213 19.1 Function . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 213 19.2 Operation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 213 19.3 Configuration . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ~ 2 2 19.4 Requircmcnts . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 223 19.5 Safety . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 226 19.6 References . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2 3 ~
-
DE&S HANFORD, INC. SNF-6151, Rev. 1 FLUOR DANIEL, INC. Government Services Operating Company
FDI Contract 80460210 SNF Canister Storage Building Contract TVW-SVV-370252
SPENT NUCLEAR FUEL CANISTER STORAGE BUILDING
ELECTRICAL DISTRIBUTION (System #1 AND #18)
SYSTEM DESIGN DESCRIPTIONS
-
DE&S HANFORD, INC. SNF Canister Storage Building Contract TVW-SVV-370252
SNF-6151, Rev. 1 FLUOR DANIEL, INC. Government Services Operating Company
FDI Contract 80460210
1.0 ELEC'I'RICAL DIS'L'KIHU'I'ION SYSTEM DESCRIPTION (SYSTEM #1 ANI) #18)
1.1 Function
1.1.1 Thc Norinal Electrical Distribution system i s dcsigncd to provide thi.cc phase ( 3 0 ) power from the 13.8 kV ovcrhcad power line (operated hy the Electrical Utilitics Group) for normal operation of the SNF CSB.
1.2 Operation
1.2. I Electrical power from the 13.8 kV overhead util i ty circuit C8-L7 fceds through fused Cutout Switch DD-32.101 on Utility Polc E-2773. Thc cutouts provide electrical isolation during planned maintcnancc activities or circuit overloads. Primary Metcring equipment for the Hanford Electrical Utilities kilowatt hour meter is also located on this pole. Power from the Cutout Switch is routed underground to the primary terminals of k i d Mounted Transformer XT-32- 102
Thc oil-filled Pad MountedTransforrner XT-32-10'.? i s cncrgized by 13.8 k V through its primary fuses. This transformer steps 13.8 kV down to 480Y/277 volts. Lightning arrcsters arc locatcd in the transfoi-mcr, primary cabinct. These arresters are dcsigned to protect the CSB huilding from voltngc surges on the acrial lines. The transformer secondary provides powcr to the lltility Mctcring Cabinet UC-32.201.
1.2.2
1.2.3 Utility Mctcring Cabinet UC-32-201 houses a 1200 ampere, 3 0 main circuit hreaker, which is the building service disconncct. This cii-cuit brcaker provides ground-fault protection as required by the National Elcctrical Code - I993 (NEC).
I .2.4 Low Voltage Switchgear cahinet SG-32-202, located in Electrical Equipment Room (03 I ) , is consti-uctcd to house eight 3 0 circuit hrcakcrs. Foui- o f these cubicles house circuit breakers to provide normal elcctrical power and oveI- current protection to four motnr control centers in the SNF CSB; two of the remaining four cubicles arc designated as spares (W11600 AF Cii-cuit Breakers) and the other two cubicles as spaces.
Motor Control Centers, MC-33-207 and MC-33-208 are encrgized hy the Normal Electrical Power System from Indoor Switchgcar SG-32-202. Thcsc two Motor Control Centers were originally designed to be supplied by cither the NED fced source or backup generators. Changes to the facility have climinatcd thc connections to backup generators.
I .2.5
-
DE&S HANFORD, INC. SNF Canister Storage Building Contract TVW-SVV-370252
SNF-6151, Rev. 1 FLUOR DANIEL, INC. Government Services Operating Company
FDI Contract 80460210
1.2.6 Two Motor Control Centers, MC-32-209 and MC-32-2 10, distrihute Noi-mal Elcctrical power to lighting circuits, motors, hcatcrs, power supplics and distribution transformers. MC-32-209 and MC-32-210 Lire energized by thc Normal Electt-ical Power System n-om Indoor Switchgear Ciihinet SG-32-202
. Figure 1: Sitc Plan
1.2.7 There are ninc Distribution Panels in the CSB: A, B, C, D, F, G, 11, J and K; Panel A is cnergized by MC-32-209, Panels B, D and J arc energized by MC-32-210, Panel H is energized by MC-33-207, Pancl G is energized by MC-33-208, Panels C and Fare energizcd hy the Uninterruptiblc Power Supply and Pancl K is supplied by Pancl J . Thesc panels and their molded case circuit breakers distributc clectrical power at 480Y/277 and 208Y1120 volts throughout the SNF CSB.
Uninterruptible Power Supply UP-33.213 has three power sources: Normal Power is supplied from MC-33-207, Battery Backup power is supplied from Battery BA-33-301, and Alternate Power is supplied from MC-33-210. If normal powcr i s lost, backup powcr from the UPS battery will utomatically supply power to the UPS for a limited time. Alternatc Power ti-om MC-33-210 is also selcctable with Maintenance Bypuss Switchcs located on the CJPS.
1.2.8
1.3 Configuration
1.3.1 Three-phase power from the 13.8kV overhead supply line i s co~ipled to a Cutout Switch located on util i ty pole E-2773, northeast of the SNF CSB Pad Mounted Transformer XT-32.102. Power leads connected 10 the bottom ol'thc Cutout Switch are routcd through underground conduit to the primary circuit of XT-32- 102. Srr Drtiwirig.s 11-2-1227.3.7 .shrc,l 3, 11-2-1227.36 s h ~ c ~ t s 3 & 4, ( I f i d Figure I : S i t e Pltiri
-
DE&S HANFORD, INC. SNF Canister Storage Building Contract TVW-SVV-370252
SNF-6151, Rev. 1 FLUOR DANIEL, INC. Government Services Operating Company
FDI Contract 80460210
1.3.2
1.3.3
1.3.4
1 .33
1.3.6
Pad Mounted Transformer XT-32- 102 and IJtility Metering C;ihinet IJC-32-201 arc mounted on a concrete pad locatcd outside the northeast corner of the SNF CSB. The transformer primary circuit contains priimiry fuses; the secondary circuit is routed underground to the Util i ty Metering Cabinet. S w f> t -uwir ig .v 11-2- 122733 s l ~ v t 3, Electriccil Cctitistc.r S to i -oge S l t lg Owrctll Oire Lirw Dingrtrrti and H-2- I22736 sheet 4, Ekctric(rl C'cuii,s/cr Stonr,cy ll/tl,y. Sit(, [Jridcrgrorriicl P o w r & Grouridirig Plori.
Utility Metering Cabinet UC-32-201 houscs 3 0 circuit breaker (18-32-202 . Electric uti l i ty metering is performed by the primary metering method. The secondary side of the potcntial transformer that is mounted on Pole E-2773 is routed through a I-inch conduit to a Meter and Field Data Acquisition System (FDAS) Logger in the CSB Electrical Equipment Room. This cii-cuit breaker CB-32-202, provides power to the Low Voltage Switchgear cabinet through underground conduit routed between the Util i ty Metering Cabinet and the SNF CSB Electrical Equipment Room (03 I ) . S w L1rrrwirig.s 11-2-122733 s h r r t 3, Electriccil Ccinistrr Storrrgr Bldg Ovc.rdl Orie I,iw Diqqruiri trritl 11-2- 122736 s h e e t 4, Electricti1 Cnr7istc,r Stortrge Bl&. Si/(! lJritl~,rsqroiirid t'oit,(,r & Groiiridiii,y Plrlrl.
Low Voltage Switchgear cabinet SG-32-202 is located in the SNF CSB Electrical Equipment Room (03 I ) . Four of the eight cubicles in the switchgear cabinet are currently utilized to distribute power to four Motor Control Centers (MCCs). The remaining four cubicles contain two spares (W/I600 AF Circuit Breakers) and two spaces for future expansion. See Drcrwir7,y 11-2-1227.?3 s l ier t 3, Electriccrl Ccrriistc~r Storqqe RkIg Oiwdl Oi7r Lirie f l iqrmri .
There are four individual MCCs, three are located in the Electrical Equipment Room (031) and one located in the UPS Room (020) of the SNF CSB. Each one is energized from a circuit breaker located in the Low Voltagc Switchgear Cabinet. Two Motor Control Centers, MC-33-207 and MC-33-208, originally had more than one power source; they are now energized only by Normal Electrical power from SG-32-202. Backup power supplied hy the Emergency Diesel Generators EG- IA (for MC-33-207) or EG-1B (for MC-33-208) through their respective Automatic Transfcr Switches TS-33-205 or TS-33-206 has heen eliminated from the design. The two remaining MCCs, MC-33.209 and MC-33-210, are also energized only from the Normal Electi-icnl Distribution system.
There is one Unintet-ruptible Power Supply, designated UP-33-2 13, to supplement the NED system. It is located in the UPS Room (020). UPS Back-up Battery cabinet BA-33-301, located in the CAEM Room 016. Normal UPS operation utilizes power from MC-33-207; i f normal power is lost, then the UPS backup battery wi l l automatically supply power for a short period of time.
-
DE&S HANFORD, INC. SNF Canister Storage Building Contract TVW-SVV-370252
Panel LX-32-2 I S (A)
DA-32-302 (B)
* DA-33-303 0 * DA-33-304 (F)
DA-32-216 (D)
XT-33-2 19 (G)
XT-33-219 (H)
DA-33-307 (J)
DA-33-307 ( K )
SNF-6151, Rev. 1 FLUOR DANIEL, INC. Government Services Operating Company
FDI Contract 80460210
Source Drawing (Loads) Drawing (One-Line) MC-32-209 H-2-122733 sh I
MC-32-210 H-2-122733 sh 2
MC-32-210
MC-33-207
**BA-33-301
kl-2- 122744, sh 1 H-2-122734 sh I
MC-32-2 I0 H-2-122733 sh 2
MC-33-207 H-2-122733 sh 5
MC-33-207 H-2-122733 sh 4
MC-32-209 F1-2- 122744, sh 2 El-2-122733 sh 1
DA-33-307 (J )
1.3.7 There are nine Distribution Pancls. designated A, B, C, D, F, G, H, J and K. K e f : Dnrrtir~~q H-2-122744, . vh . s - f & 2 fot - load schcdules.
A. Thc Distribution Panels ai-e located in the rollowing areas:
Pnncls A, B & D ai-e locatcd on the West wall of the Elccrt-ical Equipment Room 03 I .
Panel G and H are located on thc South wall of thc Electrical Equipment Room 03 1 .
Panels C & F arc located in UPS Room 020. Fecdcrs to Panels C & F may be connected to either MC-33-207 or MC-33-210 by closing the appropriate circuit breakcr on UPS-33-2 13. In the evcnt of a loss of power to the MCC supplying these pancls, the UPS Battcrics wi l l continue supplying these pancls for a short pcriod of time.
Panel J and Suh-Panel K arc located in the south end ofthe CSB to Supply thc Sample/Wcld Station.
B. The Distribution Panels arc fed from thc following sources:
-
DE&S HANFORD, INC. SNF Canister Storage Building Contract TVW-SVV-370252
NED OPERATIONAL REQUIREMENTS
SNF-6151, Rev. 1 FLUOR DANIEL, INC. Government Services Operating Company
FDI Contract 80460210
VALUE
1.4 Requirements
Outdoor temperalurc range - Electrical E ~ L I I ~ .
Indoor - general
1.4. I I l r s i g i i Rec/rrirei,ic,iit.s: The NED System is supplied by the 13.8 k V distribution system at the Hanford site. The nominal systems supplied to the SNF CSB x c :
Building distribution - 480Y/277 V, 30, 60 Hz.
Lighting - 480Y/277 V, 30,60 Hz.
Convenience outlets and UPS - 208Y/l20 V, 3 0 , 6 0 Hz,
115°F to -27°F
104°F to 55°F
11 Indoor - Electrical Equip Rooms I lO4"Fto 55°F 11 120°F Max Indoor - Design Base Accident
1.4.3 M~ii i r tc~r i t rr~c~e c r i i d Surveilltriicc~ Rcyiiir~,iiirrit.s:
Cutout Switch
A. The Cutout Switch will be inspected and maintained by the Hanford Electrical Utilities in accordance with a site standard schedule.
Pad Mounted Translormer
B. The Pad Mounted Transformer must be periodically inspected (by the Electrical Utilities Group) including the following, or anytime the exterior has been damaged i n accordance with C-16.720, 1.6.6; Pcid Mortrfird Trunsfhrnirr - Operution uiid M u i i i t m m i w Dcitci, Scnke ciiiti P r e p rut ioii :
Terminal Compartment Interior and All Operating Equipment for damage and leakage
Gauges, Controls, Drains, Plugs, Mountings, and Switches
-
DE&S HANFORD, INC. SNF Canister Storage Building Contract TVW-SVV-370252
SNF-6151, Rev. 1 FLUOR DANIEL, INC. Government Services Operating Company
FDI Contract 80460210
Utilitv Metering Cabinet
C. The Utility Metering Cahinet will be inspected and maint:iincd by the Hanford Electrical Utilities in accordance with a site standoi-d schedule
Low Voltage Switchgeai-
D. All Low Voltage Switchgear must be inspected and tested including the following, at least every 12 months of operation or, anytime after a fault condition in accordance with C-16330. 1.6.4; 480 Vtrc Low Voltu,p, Smi tchyt r r Oprrtriioii r i n d Muiriteriurrt~r Muriritrl; Appt,rrdi.t C. Scctiori 1. I . Ir~spwt io i i ciml Muiiiieiimce:
Visual Check
*
Interlocks
Operation (test for smooth operation)
Arc Chutes and Contacts
- Accessories
Anytime a brcakcr(s) is difficult to operate, or when the breaker is exposed to corrosive or caustic environment, the afl'ected disconncct switch(cs) may require lubrication in accordance with C-163.70, 1.6.4; 480 Vuc Low Voltuge Switclr,yeur Oporutioti tirid M U ~ I J ~ ~ ~ I I U I I ~ ~ ~ M m i i u l , Appcvitli.~ B. S ( 4 o r i I X , Mtiirituiriing the Swiichgrrir.
Inspections and tests for the following Low Voltage Switchgear components must he performed at least every 12 months or, anytime after ii fault condition in accordance with C-16330, 1.6.4; 480 Vtrc L o i t , Voltugo Sw~itcligecrr Operutiori u i i d Mti i i~trriuric~o Muiiirul, Appidi .x B. Sc,ctiori I X . Muiritciining the Switchgeur:
Breaker and Instrument Compartments
Breakers
Solid State Trip Units (secondary injection test only)
E.
F.
Brcaker Compartment Interiors
Bus Area
Instruments, Instrument Transfor-mcrs, and Relays
-
DE&S HANFORD, INC. SNF-6151, Rev. 1 FLUOR DANIEL, INC. Government Services Operating Company 9 FDI Contract 80460210 SNF Canister Storage Building Contract TVW-SVV-370252
Cablc and B L I S W ~ ~ Compartment
Overall Switchgear
Paint Refinishing
- Circuit Bi-caker Lifting Mechanism Motor Control Centers
G. All Motor Control Centers must bc inspected and tcstcd including the following, at least every 12 months of operation or, anytimc aftcr a fault condition in accordllnce with C-16482/C-l6482/3, 1.6.4, MCC /ri.srnictiori Mtrrl[itil, Opercrtiorr:
* Visual Check
Operation
Interlocks
Transformers
Ovcrload Relays and Fuses
Insulation
Latches and Mechanisms
Anytime a disconnect switch is difficult to operate, or when the switch is cxposed to corrosive or caustic environrncnt, the affccted disconncct switch may reyuirc lubrication i n accordance with C-16482/C-l64X-3B, 1.64 , MCC 11r.stri~tinrr Mtiriii(i1, Prmwtcrtivr Mniiitrricoic~e.
The following inspections and tests for the 480 V Motor Control Centers must bc performed at least every 12 months or, anytimc aftcr a fdul t condition in accordance with C-16482/C-1648-7B, 1.6.4, MC'C Imtnictiori Mtrnuul, Prtwntive Muiiztrncttice:
H.
1.
Doors and enclosure sides for evidence ofcxcess~ve hcat
Moisture or signs of dampness or drippings inside MCC
Integiity of bus splice connections
-
DE&S HANFORD, INC. SNF Canister Storage Building Contract TVW-SVV-370252
.
SNF-6151, Rev. 1 FLUOR DANIEL, INC. Government Services Operating Company
FDI Contract 80460210
Proper function and freedom of movement (no sticking or binding) of the disconnect handle operating mechanisms and dcfeater mechanisms
Bus stab connections lor wear and corrosion
Current carrying paits ( i t . , fuse clips, knifc hladcs of disconnccts, and line and load terminals) for discoloration, corrosion or othcr signs of ahnormalities
Contacts for excessive wear and diit accumulation
Loose connections on power and conti-ol circuit terminals
Coils for evidence of overheating (i,e., cracking, melting, or burnt insulation)
Damaged or burned out Pilot Lights
Damaged or blown Fuses
Power Distribution Panels
J . The Power Distribution Panels will be inspected and maintained hy the Hanford Electrical LJtilitics in accordance with a site standard schedule.
Uninterruptible Power Supply
K . The following Uninterruptiblc Power Supply parameters must be inspected and tested at least every 12 months of operation, or anytime after a fault condition, in accordance with C-16143, 1.6.6; I I I , s / ~ I / / ~ I ~ ~ ~ I ~ , Opcrtitiori ( i~ id MrlirIleric1rlc.e MrI l I l lNI . KOlltillL' M t l ; l l t ~ ~ l l ~ l l l c l ~ :
* Air Filter inspection and cleaning
Visual inspection for loose connections, overheated components, any abnormal setups or configurations
Voltage adjustments
The following parameters for the UPS Batteries must be read and recorded at least every 12 months or, anytime after an Equalizing Charge in accordance with C- 16/4.?, 1.6.8; I ~ ~ , s ~ d / ~ i / i o ~ i , OprrritiriR & Mtriritc~ririrm~ Murnrcrlfiw the Smliori UtrtfericJs, Chr~picr 10 - M ~ i ~ ~ f e n c t n c ~ :
Static Switch tested for proper transfer
L.
-
DE&S HANFORD, INC. SNF Canister Storage Building Contract TVW-SVV-370252
SNF-6151, Rev. 1 FLUOR DANIEL, INC. Government Services Operating Company
FDI Contract 80460210
Corrosion around battcrics and racks
Individual cell or unit voltages (Volts)
Ccll-to-cell connection rcsistancc (pohms)
Tcrminal connection rcsistnncc (pohms)
Connection rcsistancc
Ambient Tcmpcruturc in the immediate battcry cnvironmcnt
1.5 Safety
I .S. I Potcwtid Sqfi.ty IIuzirdy cirid Coricenis:
A. Electrical equipment should bc operated only by pcrsonnel adequatcly trained in thc use of the equipmcnt. For personncl safety, all clcctrical equipment should be assumed to he energized. Prior to performing any work on clcctrical equipment, ensure the equipment i s dc-cnergizcd fi-om all sources and the manufacturer's opcrating and maintenance instructions are followed. Propcr lockout and tagging procedurcs, as specificd in the applicable site administrative manual, must be followed a1 a11 timcs.
All electrical installations located in the proximity of or adjaccnt to Safety Class equipment is designed to not affect the integrity of that equipment under accidcnt conditions.
System protective devices are installed to minimizc damage to thc electrical system. The interrupting rating of electrical equipment has been selected to exceed the fault current available to the individual equipment by a minimum of 20 percent. In addition these devices have been sclccted and coordinated such that the interrupting device nearest the point of fault will open first and minimize disturbances to the rest of the system.
St@y Cla.s.s;fic,rctiori: The Normal Electrical Distribution Systcm is classificd as Gencral Servicc (GS), because it is not required to mitigate ;in accidcnt or to operate aftci- an accident, and provides a limited function in protccting thc facility worker from industrial and radiological hazards.
Under normal circumstances, the CSB receives electrical power from the Hanford Site transmission and distribution system via the 13.8 kV power pole near the north end of the building. The incoming voltagc is stcppcd down through a dedicated 480 volt (V) transformer. From the 480 V transformer power i s provided to four480 V Motor Control Centers (MCCs) located in the suppoit building of the CSB. All MCCs are classified as General Servicc (GS)
B.
C.
1.5.2
SI..\telll De.sl,q Ue.sl~rlprl~Jl,.r Page IS of236 Normnl Electrical Distrihution System: 06/06/00
-
DE&S HANFORD, INC. SNF Canister Storage Building Contract TVW-SVV-370252
DWG # D12976-I
D12976-2
H-2-12273 1 sheets 1&2
SNF-6151, Rev. 1 FLUOR DANIEL, INC. Government Services Operating Company
FDI Contract 80460210
DRAWING TITLE One line Diagram UPS 120 VDC Bus
Outline & Mounting Dimensions 20 KVA 3PH UPS
Electrical Canister Storage Bldg. Standard Drafting Symbols
Safety Class and Safety Significant (SS) str~icturcs, systems and components (SCCs) suppoi-tcd by electrical power are designed to he fail-to-safe (an electrical power failure leaves them in a position that docs not compromise safety).
Without electrical power, the capability of the CSB to contintic receiving, servicing and moving or MCOs to storage would he suspended. Suppoi-I activities, such as extended purging and re-incrting operations would he impossible.
~ ~ i ~ i ~ ~ ~ ~ i ~ ~ i ~ , ~ ~ t ~ ~ / Suf i ty The SNF CSB docs not have any connections to a chemical sewer or other means of direct disposal ol'h All hazardous wastes generated during inaintcnancc or other activities within the facility must be safely contained at the point of generation (ic, fluids drained into buckets, rags and other materials placed in plastic bags), and removed to some other facility having suitable means of safe hazardous material disposal available.
1.5.3 irdous chemical waste.
H-2- 122732 sheets 1-6
H-2-122733 sheets 1-5
1.6 References
Electrical Canister Storage Bldg. Standard Assemblies
Electrical Canister Storage Bldg. One Line Diagram MC-32-209
1.6. I Drawings relating to or rdeercnccd i n this document are:
H-2- 122734
H-2- I22735
H-2.122736 sheets 1-4
Electrical Canister Storage Bldg. One Line Diagram UP-33-213 (Uninterruptible Power Supply)
Electrical Canister Storage Bldg. Equipment Arrangement Plan
Electrical Canister Storage Bldg. Under Ground Conduit & Grounding Plan
11 H-2-122737 I Electrical Canister Storage Bldg. Pole Line Details H-2-122738 Electrical Canister Storage Bldg. Lightning Protection Plan sheets 1-2 I
S?srorr De.$I,yii Lk~.s
-
DE&S HANFORD, INC. SNF Canister Storage Building Contract TVW-SVV-370252
DWG # H-2-122740 sheets 1-5
H-2- 122741 sheets 1-5
SNF-6151, Rev. 1 FLUOR DANIEL, INC. Government Services Operating Company
FDI Contract 80460210
DRAWING TITLE Electrical Canister Storage Bldg. Above Ground Power Plan
Electrical Canistcr Storage Bldg. Above Ground Power Details
H-2-122742 sheets 1-4
H-2-122743
H-2-122744
H-2- 122745 sheets 1-4
Electrical Canister Storage Bldg. Lighting & Receptacle Plan
Electrical Canister Storage Bldg. LTG & RECP Sects & Dets
Electrical Canister Storage Bldg. Pancl Schedules
Electrical Canister Storage Bldg. Instrumentation Plan
11 H-2-122746 I Electrical Canister Storage Bldg. Instr Scctions & Details H-2-122747
- H-2-122748 sheets 1-4
Electrical Canister Storage Bldg. Comm & FA System Riser Diag
Electrical Canister Storage Bldg. Comm & Fire Alarm Plan
H-2- 122750 sheets 1-2
Electrical Canister Storage Bldg. Elementary Diagrams
96-05-04-01 SNF CSB System Safety C1;tssification Forms, 1997, II Electrical Supply DOC. # DOCUMENT TITLE
HNF-3553
11 HNF-PRO-704 I Hazard and Accident Analysis Process
Annex A, Canister Storage Building Final Safety Analysis Report, Section A2.8. I , Normal Electrical Power Distribution
I1 SNF-6154 I Design Basis Document, Section 5 , I~/cctr-ic~cd
HNF-3553
11 W-379-C-CSB-16122 I 15 kV Cable
Annex A, Canister Storage Building Final Safety Analysis Report, Section A2.8.3, Uninteimptihle Power System
1) W-379-C-CSB-I6143 1 Unintcrruptible Power Supply System 11 W-379-C-CSB-I6110 I Electrical Materials and Devices 11 W-379-C-CSB- 16320 I Pad Mounted Transformer
-
DE&S HANFORD, INC. SNF Canister Storage Building Contract TVW-SVV-370252
SNF-6151, Rev. 1 FLUOR DANIEL, INC. Government Services Operating Company
FDI Contract 80460210
DOC. #
W-379-C-CSB- 16330
W-379-C-CSB- 16482
W-379-C-CSB- 16482B
w-379-e-CSB- 1690s
W-379-C-CSB- I69OSB
W-379-C-CSB-1786 I
W-379-C-CSB- I786 I B
c-13200, 1.6.2
C-I61 IO, 1.6.1.W
C-16110, 1.6.1.2
C-161 I O , 1.6.4
C-16110, 1.6.4
C-161 10, 1.6.4
C-I61 10, 1.6.4
C-161 10. 1.6.4
C-161 10, 1.6.4
C-161 10, 1.6.6
C-161 I O , 1.6.7.A
C-16110, 1.6.7.1.C
C-16110. 1.6.7.1 .C
DOCUMENT TITLE
180 Volt Switchgear
Motor Control Ccntcrs
Motor Control Ccntcrs
Electrical Tcsting
Elcctrical Tcsting
Local Control Panels ~
Local Control Panels
Design for Low Voltage Switchgear SG-32-202 and Diesel Fucl Oil Storage Tank TK-001
Electrical Materials & Devices - Utili ty Mctcring Cahinct - Mctering Drawing - - Electrical Materials CG Devices - Load Break FIISC Links
Electrical Matcrials & Dcvices - Data Shcets for Translormcrs XT-32-214, XT-33-217, XI-32-2 18, XT-33-2 I9
Electrical Matcrials & Devices - Dry Type Transformers CG Mini Power Ccntcrs
Electrical Materials & Devices - Data Shccts for Enclosed Breakers
Elcctrical Materials & Dcviccs - Data Shccts foi Safcty Switches
Electrical Materials & Deviccs - Data Shccts for Switchbowds (Metering)
Electrical Materials & Devices - Data Shects for. Panclboards - DA-32-216, DA-31-302, DA-33-303, DA-33-304, LX-32-21 S , DA-33-30s
Dry Type General Purpose 'Transformers
Instructions for Panclhoard - Manufacturcr's Installation
Installation Instructions for Dry-Type Distribution Transformers
Transformer - Cooper/Elcctric Matcrials & Devices
Swreirr de si,^,^ ne.rcrip,io,r.v Page I 8 uf 236 Normal Electricid Dis~rihution System: 06/06/00
-
DE&S HANFORD, INC. SNF Canister Storage Building Contract TVW-SVV-370252
DOC. #
SNF-6151, Rev. 1 FLUOR DANIEL, INC.
DOCUMENT TITLE
Government Services Operating Company FDI Contract 80460210
C-161 10, 1.6.7.1.C
C-16143, 1.6.1
Utility Metering Cabinet - UMC - Installation Instructions Cutler-Hammer Switchhoard Dcsisn
Dcsign Drawings D 12076- I and D 12076-2 Kev. A for the Uninteriuptihle Power Supply
I( C-16143, 1.6.6 I Cyherex (UPS) 1nst;lllation O&M Manual C-16143, 1.6.8 Installation, Operating and Maintcnance Manual for II the Station Batteries
11 C-16143. 1.6.10 I UPS Factorv Accentance Test Data 11 C-16330, 1.6.4 480 Vac Low Voltage Switchgear Operation and Maintenance Manual
11 C- 16482, 1.6.1 I Design Drawings for MCCs -16482/C-164828, 1.6.1 1.6.1 - As-Builts, 1.6.3 -Spare Pal-ts List, 1.6.2 li” - 1.6.4 Materials Lists, I .6.4 O&M Manuals
-
DE&S HANFORD, INC. SNF-6151, Rev. 1 FLUOR DANIEL, INC. Government Services Operating Company
FDI Contract 80460210 SNF Canister Storage Building Contract TVW-SVV-370252
SPENT NUCLEAR FUEL CANISTER STORAGE BUILDING
INSTRUMENT/SERVICE AIR (System #2)
SYSTEM DESIGN DESCRIPTIONS
-
D E S HANFORD, INC. SNF Canister Storage Building Contract TVW-SVV-370252
SNF-6151, Rev. 1 FLUOR DANIEL, INC. Government Services Operating Company
FDI Contract 80460210
2.0 INSTKUMtiNT/SEKVICE AIK SYSTEM UtiSCKIPTION (SYSTEM #2)
2.1 Function
2. I . I Thc Instrument/Scrvicc Air (CAIIAISA) systcm is designcd to providc dry, oil- and particulatc-free compressed air to components and locations throughout the SNF CSB. The Instrument/Servicc Air system consists of the Comprcssed Air (CA) system, which supplics the Instnimcnt Air (IA) and Sei-vicc Air (SA) subsystems (see Figure I):
CA HEADER
IA DISTRIBUTION
> DISTRIBUTION
SA Figure 1 - Instrument/Service Air System Block Diagram
A. The compressed Air System (CA) supplies compressed air at 100 - 125 psig (typically supplied at 101 - I05 psig) for the two subsystems on a demand basis, and does not directly supply any end use.
The Instrument Air subsystem (IA) distributcs compressed air at 20 psig to HVAC and other cquipment (pneumatic actuators, control valves, dampcrs, instruments) throughout the SNF CSB.
The Service Air subsystem (SA) distributcs compressed air at 100 - I I O psig (typically supplied at IO1 - 105 p i g ) to the MHM Festoon, to the SamplindWeld Station, to the Cask Receiving Pit, and for general usc (air tools, etc.) to utility stations in the north end of the SNF CSB, near the cask receiving area.
B.
C.
S?.SIC.III Desi,yn Deso'iptioru I'agc 2 I of 236 InstrurnentiScrvice Air Systern:06/0(d00
-
D E W HANFORD, INC. SNF-6151, Rev. 1 FLUOR DANIEL, INC. Government Services Operating Company
FDI Contract 80460210 SNF Canister Storage Building Contract TVW-SVV-370252
2.2 Operation
2.2. I
2.2.2
2.2.3
2.2.4
2.2.5
2.2.6
2.2.1
The CA begins at the intakcs to two identical, two-stage, screw-type air compressors, CX-IA & CX-IB; the air compressors are located i n the Instrument Air Equipment Room (Room 0L5) of the SNF CSB.
The two-stage compressors are capable of pressurizing the air to 125 p i g . A 1st to 2nd stage Intercooler and an Aftercooler following the 2nd stage of the compressor reduce the temperature of the compressed ail- to s 120 "F. Two Moisture Separators internal to each compi-cssor remove entrained water droplets from the compressed air. The compressor lubrication system is designed to prevent the entry of oil particles into the air stream, thus delivering oil-free air.
The compressed air is routed through a particulate prefilter to remove remaining entrained water droplets and particulate matter, then enters the Air Dryer DR-I.
DR-I consists of two drying towers containing activated alumina desiccant (water-absorbing) material, with one tower operating in drying mode while the other tower is in regeneration mode. compressed air from the compressors passes through the active desiccant tower, where almost all of the water vapor contained in the air is adsorbed onto the desiccant. The dry, compressed air is routed through a particulate afterfilter to remove any entrained desiccant pxticles, then enters Air Receiver VX-I. Aftcr the air has been dried, i t is considered Service Air (SA).
VX-I is a large 340 ft' cylindrical vessel provided as air reservoir and surge volume for dampening pressure and volume lluctuations. Dry, oil- and particulate-free compressed air from VX-I enters the SA header, which supplies the 1A and SA systems at 100 - 125 p i g (typically supplied at 101 - 105 psig).
Service Air is routed through a 2 inch line from VX-I, which supplies Outlet Valves SA-V-30A and SA-V-30B inutil i ty Rooms 034 and 018, respectively. Additionally, the VX-I Service Air is distributed to two pressure regulators, PCV-250 and PCV-252 which typically deliver 101 - 105 psig Service Air. PCV-250 via SA-V-38, supplies Service Air to the Operations Area Cask LoadinlLoadout Area. PCV-252 supplies Service Air to the Service Station Pit, MCO Handling Machine Festoon, Sample/Weld Stations, and various distribution valves.
The Instrument Air System begins downstream of PCV-261 (set at 20 psig) and is supplied from PCV-250 Service Air. Instrument Air is supplied to HVAC dampers, PCV-I IS, and various outlet valves within the support building.
Sy.sf~m D e s i y , ~ Drscripfiom Page 22 o f 236 InstrumentIService Air System:06106/00
-
DE&S HANFORD, INC. SNF Canister Storage Building Contract TVW-SVV-370252
SNF-6151, Rev. 1 FLUOR DANIEL, INC. Government Services Operating Company
FDI Contract 80460210
2.3 Configuration
2.3. I Comprcsscd Air (CA) systcm:
A. The CA systcm interfaces with the following systems:
Thc Normal Electrical Distribution System (NED) providcs electrical power for compressor operation, via a dcdicated breaker and disconncct switch for cuch comprcssoi-
Thc Distributed Control System (DCS) providcs Gcncral Alarm annunciation for the Air Comprcssoi-s and thc Air Drycr
The CA system providcs compressed air to thc IA and SA sub-systcms.
All CA equipment is locatcd in thc Instrument Air Equipment Room ofthc SNF CSB.
2.3.2 Instrument Air (IA) suhsystcm:
8.
A. The IA subsystem interfaces with the following systcms:
The IA draws its compressed air from the SA at the SA headcr, downsti-cam of VX-I in thc Instrumcnt Air Equipment Room
Thc IA supplics cornpresscd air to HVAC and other cquipmcnt (c.g., pneumatic actuators, control valves, dampers, instrumcnts, ctc.).
The 1A supplies comprcssed air to instruments o n the Air Comprcssor local control panels.
B. IA piping and equipment is located throughout the SNF CSB
2.3.3 Servicc Air (SA) suhsystcm:
A. The SA subsystem interfaces with the following systems:
The SA rcceivcs compressed air from thc CA at the discharge of Aii Dryer DR-I in the Instrument Air Equipment Room (Room 015)
Thc SA supplies compresscd air to the IA subsystem from the SA header downstream of VX-I in the Instrumcnt Air Equipment Room
The SA supplies compresscd air to the MHM Festoon systcm to supply thc MHM.
-
DE&S HANFORD, INC. SNF Canister Storage Building Contract TVW-SVV-370252
Oil and Particulate content
SNF-6151, Rev. 1 FLUOR DANIEL, INC. Government Services Operating Company
FDI Contract 80460210
1 ppm
The SA supplies compressed air to utility stations throughout the northein end of the SNF CSB for use by air-driven tools and equipment
B. SA piping and cqiiipment is locatcd throughout thc SNF CSB.
2.4 Requirements
II Suspended particles I < 3.0 microns 11 II Dew point I -40 "F 11
CA Header pressure I 100- 125 psig I Air Cortiprc,ssor High Tmrprrtifurc, A/rrnt,.s must be responded to quickly, as the compressors may be damaged or destroyed by excessive temperatures during operation.
Air Dryer I f i g h Moisfurr and Fctilurc, fo SLvifclr Dryer alarms must be responded to quickly, as instrumentation and equipment using Instrument Air becomes unreliable and unpredictable when exposed to excess moisture in the Instrument Air stream.
S~~.sron De.sigii Descripriotrs Page 24 0 1 236 InstrumentlService Air Systcm:06106/00
-
r , * - I
-
DE&S HANFORD, INC. SNF Canister Storage Building Contract TVW-SVV-370252
SNF-6151, Rev. 1 FLUOR DANIEL, INC. Government Services Operating Company
FDI Contract 80460210
C. Mtiiiifriiciricc iiiicl Siii-willtiiici~ R(,c/i~irriiic,iil,v:
* Selected CA subsystem Pressure Indicators will be calihratcd yc~irly
Selected CA subsystem Temperature Indicators will he calibrated yearly
Air Dryer Moisture Indicator MI- I will bc checkcd freclucntly for indication of moisture and the indicating matei-ial replaced a s needed
Air Compressor Inlet Filter vacuum must be checked monthly, and the Inlet Filters replaced when required, based on monthly checks (see I-R APDD BOB-95 S; 4.4 "Standard Inlet Air Filter")
Air Compressor oil and oil filter is changed after the first IS0 hours of operation, and once per year (8,000 hours) thereafter (see I-R APDD 500B-95 8 4.6 "Oil and Oil Filter")
Air Compressor Drive Motor luhrication is performed cvcry thrcc months, and Air Compressor Fan Motor lubrication is performed once per year (see I-R APDD 590B-95 S; 4.10 "Motor Lubrication")
Air Dryer Dew Point Monitor must be checked and calibrated yearly
Air Dryer Solenoid and butterfly viilve diaphragms and seats are replaced yearly
When differential pressure exceeds 10 psi, Air Dryer Prefilter F-S and Afterfilter F-6 clements are replaced yearly
Air Compressor Condensate Strainers are inspected once per year (see I-R APDD 590B-95 S; 4.9 "Condensate Strainers")
The Dryer Prefilter drain valve and Dryer System Monitor Lights (on the Compu-Purge Controller panel) must be checked daily
Dryer Exhaust Mufflers, Dryer Filter AP indicators, and Dryer Purge Exhaust valves must be checked weekly
9
-
DE&S HANFORD, INC. SNF Canister Storage Building Contract TVW-SVV-370252
KE:OUIKE.MI.:N'r
SNF-6151, Rev. 1 FLUOR DANIEL, INC. Government Services Operating Company
FDI Contract 80460210
V A I ,U I<
Dryer Desiccant is inspected yearly for oil contamination and broken desiccant (see I-R Bulletin 342 Rev. 0, p. 9 for inspcction critcria and
nt replaccnient instruction).
Air Recciver VX-I is an ASME pressurc vessel which is inspected yearly. A bypass line is provided so the vcsscl can be opcncd for inspection without interruption of CA system operation.
Safcty (relief) valves PSV-246 (mounted on Drycr Inlet Shuttle valve CA-V-I I ) and PSV-249 (mounted on Air Rccciver VX-I ) must be tested and inspccted evei-y two yeat-s.
2.4.2 Instrument Air subsystem (IA):
A. I k v i K r z R~.c/"irf,rrirril.v: The IA requires dry, oil- and prticulatc-free compressed air at 20 psig and maximum temperature of 120 "F to reliably operate the equipment requiring instrument air. Compressed air mceting this rcquiremcnt is supplied by thc CA. I f Instrument Air contains exccss oil, moisture, or particulates, instruments and equipment that use Instrument Air may become fouled by the foreign rnatcri;il and begin acting eratically; some controls may begin acting randomly, and may fiiil in unsafe positions rather than the dcsigned safe positions.
Oprrcitioricd ~ i , ~ / i r i r ~ , r ~ i ~ , r t f . ~ : 1A operational requii-cments are given in the following table:
B.
Dew point I - 40 "F
If air pressure is lost, through failure of both compressors or othcr events, controls and cquiprncnt in the SNF CSB which use Instrumcnt Air are designed to fail in a safe position.
C, Muiritenaricr trrid Survvril/ar7cr Rrqi~irc,tiicrit,v:
1A subsystem Pressure Indicators PI-250 and PI-287 will he calibrated yearly.
IA subsystem pressure control valves PCV-250 and PCV-261 will bc calibrated yearly.
-
DE&S HANFORD, INC. SNF Canister Storage Building Contract TVW-SVV-370252
Dew point
SNF-6151, Rev. 1 FLUOR DANIEL, INC. Government Services Operating Company
FDI Contract 80460210
I - 40 "F
2.4.3 Service Air subsystem (SA):
A. Z~e.s i ,yr i Kepireiircvits: The SA requires dry, oil- and particulate-free compressed air at 90 - I 10 psig and maximum temperature of 120 "F to rcliably operate tools requiring compressed air. Compressed air meeting this requirement is typically supplied by the SA at 101 - 105 psig.
Opcr(itionti/ Krc/~circ,irieri/s: SA operational requirements we given in the following table:
B.
II 011 and ~ a r t i c u ~ a t e content I < I mm- II I1 Suspended particles I I 3.0 microns I1
2.5 Safety
2.5.1 Poteritid Sqfety Hu;cird.s c i i i d Coricerns
A. Hazards of the Instrument/Service Air system include rotating and remote-start equipment, high noise levels from venting iiii-, and possible high temperatures at some points in the system. Proper precautions, including proper use of Personal Protective Equipment appropriate to the hazard expected, should be taken.
I f the CA becomes inoperable due to a power failure or other event, the VX- I Air Receiver is sized to supply IS scfm to the CA header for 40 minutes at normal loads.
B.
C. Redundant air compressors are provided to improve plant availability in allowing for maintenance activities without disrupting normal operitions; redundancy is not required for plant snfety.
-
DE&S HANFORD, INC. SNF Canister Storage Building Contract TVW-SVV-370252
DWG #
SNF-6151, Rev. 1 FLUOR DANIEL, INC.
DRAWING TITLE
Government Services Operating Company FDI Contract 80460210
H-2-125 I60 Sheet I
H-2- I25 I60 Sheets 2 & 3
2.5.2
2.5.3
Piping OperatinglSupport Areas Compi-csscd Air/MCO Vac Plan
Piping OperatindSupport Areas Compressed Air/MCO Vac Plan, Sections & Details
.Sr/kiy Cltr.v.v$ctrtiori: The CA system, and the I A and SA subsystems of the Instrument/Servicc Air system arc classified a s General Service (GS) because they are not required to mitigate a n accident or to operate after ;in accident, and provides ii limited function in protecting the facility workci- from iiidusti-in1 and radiological hazards.
Loss of the Instrumcnt/Servicc Air System has no direct salety impact on any facility workers. A portable air supply can he brought i n t o the lacility if compressed air is required during an InstrumcntlSei-vice Air System l'ailurc. The point-of-connection will be via line CA-2"-SA-003-G at viilvc CA-V-30-B ( i n room 18) or CA-V-30-A (in room 34).
Uivirorir,irri/trl Saf;.y: The SNF CSB does not have any connections to a chemical sewer or other means of direct disposal of hazardous chemical waste. All hazardous wastes generated during maintenance oi- other activities within the facility must be safely contained at the point of generation ( i c , fluids drained into huckcts, rags and other materials placed in plastic hags), and removed to some other Facility having suitable means of safe hazat-dous material disposal
H-2- 125 163 Sheet 1
H-2-125 163 Sheet 2
2.6 References
Piping OpcratindSupport Areas compressed Air/MCO Vac Sections and Details
Piping Operating Area Section Compressed AirlMCOIVAC Sections & Details
2.6. I Drawings relating to or referenced in this document are:
H-2- 122733 Electrical Canister Storage Building One Line II Sheets I - 5 Diagram (MCC-32-209, MCC-32-2 IO) Electrical Canister Storage Building Panel I Schedules H-2- I22144 II
II H-2- 123392 1 P&ID Instrument/Servicc Air System
H-2- 125 161 Piping Operating/Support Areas compressed It Air/MCO Vac Plan
H-2- 125 163 Piping OperiitinglSupport Arcas Miscellaneous ll Sheet 3 Sections and Details
-
DE&S HANFORD, INC. SNF Canister Storage Building Contract TVW-SVV-370252
DWG # H-2-125 164
SNF-6151, Rev. 1 FLUOR DANIEL, INC.
DRAWING TITLE Piping Operating/Suppoil Arcas Compi-csscd Air/MCO Vent Sections and Details
Government Services Operating Company FDI Contract 80460210
DOCUMENT # DOCUMENT TITLE
S N F CSB System Safcty Classification Forms
HNF-3553 Annex A, Canistcr Storage Building Final Safcty Analysis Repoi-t, Section 2.8.5, "Instrument and Plant Air System"
Scction 96-05-04-02, Air Supply
SNF-6154
Ingersoll-Rand APDD 565A-94 (December 1994)
Design Basis Document, Section 2. Process Systems
lntellisys System Controller Opcrators Instruction Manual /Parts List
Ingcrsoll-Rand Kef 7904 I Intellisys System Controller
Ingersoll-Rand Sierra Team Work Instruction IOW1018 Rev. I
Ingersoll-Rand Drawing # 39848791 Rev. 4
Sheets I - 2
Ingcrsoll-Rand APDD 590-B-95 Sicid ' 5 0 - 100 1-loi-scpower All Units Operators (September 1995) I Instruction Manual
SIERRA 50-200 HP Production Test (Factory Acccptancc Test)
Plan. Foundation Standard Air Cooled
I
Ingersoll-Rand APDD 618A-95 I Sierra" SO - 100 Horscpowcr All Units Parts List (Scptembcr 1995) I Recommended Spares
Ingersoll-Rand Rcf 9300/930 I/ 9302/9304
Sicin" 50 - 100 HI' Air Cooled
IngersollLRand Rcf: 9000/900 I I 9002/9003
Sieira@ Oil-Frcc Rotary Screw
Ingersoll-Rand Docurncnts Cornprcssor Factory Acccptancc Test I Certifications
Transduccr, Pressurc I Ingcrsoll-Rand Drawing # 39538061 Rev. 5
-
,
DOCUMENT ##
Ingci-soll-Rand Drawing # 39541685 Rcv. 1
DE&S HANFORD, INC. SNF Canister Storage Building Contract TVW-SVV-370252
DOCUMENT TITLE Transducei-, Pressure (0 - 100 psig)
SNF-6151, Rev. 1 FLUOR DANIEL, INC. Government Services Operating Company
FDI Contract 80460210
Ingcrsoll-Rand Drawing # 39568092 Rev 3
Ingcrsoll-Rand Drawing # 30843677 Rev. S
Sensor, RTD - 2 5 NPT
Process and Instrumentation Diagram NLTS Air Cooled
Ingersoll-Rand Drawing # Transducer, Prcssurc 30541693 Rcv. I
Ingcrsoll-Rand Drawing # 39861901 Rev. S
Ingersoll-Rand Ref: 11501 Ingersoll-Rand Ref: I IS02 Ingcrsoll-Rand Ref: I IS03 Ingersoll-Rand Ref I1504
Ingersoll-Rand Ref: I1221 Ingcrsoll-Rand Ref: I I222 Ingcrsoll-Rand Ref: I1223 Ingcrsoll-Rand Ref: I1224 Incersoll-Rand Ref I1226
Schematic, Wiring Star Delta
Comprcssed Air Filters Data Sheets
Heatless Dryer b1RD Data Sheets
Ingcrsoll-Rand bulletin 342 Rev. D (9/96)
HRD Heatless Compresscd Air Dryers with Compu-Purge Conti-ol HRD Series Opcrator’s Instruction Manual
Roy E. Hanscn, Jr. Mfg. AF-783-B-lA
Roy E. Hanscn, Jr. Mfg. AF-783-B
Instrumcnt/Plant Air Receiver Vesscl Nameplate Mal-kings
Instrument/Plant Air Receiver Shop Drawing
W-379-C-CSB-176 I2 I Resistance Temperature Detectors
W-379-C-CSB- I3432
W-379-C-CSB-1506 1
W-379-C-CSB-IS 152
W-379-C-CSB- IS880
W-379-C-CSB- 16150
W-379-C-CSB- 17601
Instrument/Plant Air Rccciver
Piping Material, Fabrication, Erection, and Pressure Testing
Instrument/Plant Air Compressors
Instrument Air Dryer System
Motors - Induction for General Scrvice Temperature Transmitters - Electronic
W-379-C-CSB-17614B Thcrmocouples
-
DOCUMENT # DOCUMENT TITLE
II W-379-C-CSB- 17667 I Pressure Switches I1
W-379-C-CSB- 17626 W-379-C-CSB- 17626B
W-379-C-CSB-17663 W-379-C-CSB- 17663B
II W-379-C-CSB- 17670 I Solenoid valves II
Pressure Gauges
Pressure Keliel Valves
)I W-379-C-CSB-17682C I Current to Pneumatic Converters II
W-379-C-CSB- 1770.5 W-379-C-CSB- 1770SB
W-379-C-CSB- 17708 W-379-C-CSB-17708B
Instrument Piping Materials I W-379-C-CSB- I7703 11 W-379-C-CSB- 17703B Instrument Calibration and Checkout
Instrument Piping Pressure Testing
W-379-C-CSB- 17704 11 W-379-C-CSB-17704B General Instrumentation Installation and Testing
I (1 W-379-C-CSB-17864 I Instruments Furnished with Mechanical I W-379-C-CSB-1786 I Local Control Panels (1 W-379-C-CSB-17861B
W-379-C-CSB- 17864B 1 Equipment Canister Storagc Building
-
DE&S HANFORD, INC. SNF-6151, Rev. 1 FLUOR DANIEL, INC. Government Services Operating Company
FDI Contract 80460210 SNF Canister Storage Building Contract TVW-SVV-370252
SPENT NUCLEAR FUEL CANISTER STORAGE BUILDING
FIRE PROTECTION SYSTEM (System #3)
SYSTEM DESIGN DESCRIPTIONS
S?.striii U P . Y ~ , ~ I Z Uc,sc.,-iptio,r.s Page 33 01236 Fire Protection System: 06/06/00
-
DE&S HANFORD, INC. S N F Canister Storage Building Contract TVW-SVV-370252
SNF-6151, Rev. 1 FLUOR DANIEL, INC. Government Services Operating Company
FDI Contract 80460210
3.0 FlRE FKO'I'ECTION SYSTEM DISSCHlY'TlON (SYSTEM #3)
3.1 Function
3.1.1
3.1.2
3.1.3
The Fire Protection (FP) System is designed to supply raw water (RW) to the CSB Wet Pipe Spi-inkler System and fire hydrants.
The FP System has two main subsystems: Thc Fire Detection and Alarm (FD&A) Subsystem and the Fire Automatic Wet Pipe Sprinkler subsystem (AWPS). The FD&A subsystem is designed to detect excessive smoke and heat present in the CSB, and to notify personnel in the CSB Support Area and the Hanford Fire Department for the appropriate emerycncy i-csponse. Upon detection, the AWPS is designed to provide fire suppression for the CSB Suppoi-t Area and fire hydrants for manual fire fighting.
The raw water poition of the system also supplies fire water for the Fire Water Pump House Wet Pipe Sprinkler System and service water for wash-down and cleaning ofequipment, and for filling water trucks that are used for roadway dust suppi-cssion, when required.
3.2 Operation
3.2.1 The Fire Protection System consists of the Fire Water Supply (FWS) subsystem that supplies water to the Automatic Wet Pipe Sprinkler (AWPS) subsystem, and the Detection and Alarm subsystem that provides activation ofthc appropriate alarms and local sprinkler systems inside the support area of the CSB. The operating area deck does not contain any wet pipe sprinklers.
The FWS subsystem delivers raw water from the 12-inch fire water main outside the CSB to the AWPS subsystem. The FWS subsystem operates at ;I pressure near 125 psig and is designed to a capacity of 1,150 gpm at 98 p i g . Water from the FWS subsystem is provided on demand. The FWS subsystem consists of piping, valves, and fire hydrants. Post Indicating Valve (PIV) MV-FWX-31 I A isolates the 6-inch fire water line to the CSB from the IO-inch fire water line FWX-I0"-500-004-RF and from the 12-inch fire water main RWX-I2"-500-017-RF. As the water enters the building through a riser, i t flows through a backtlow preventer. The backflow prevcnter provides a positive drip-tight closure against the reverse flow caused by a CI-oss connection, and ensures that the water remains contained within the AWPS piping.
The AWPS subsystem receives water from the FWS subsystem for f i l e suppression. Heat from a fire activates nearby sprinkler heads, initiating water flow. Water within the AWPS subsystem then flows from thc FWS subsystem to the open sprinkler heads near the heat source.
3.2.2
3.2.3
Systeiii Desigii De.vcripria,is Page 34 of 236 l;irc Protection Syslem: 06/06/00
-
DE&S HANFORD, INC. SNF-6151, Rev. 1 FLUOR DANIEL, INC. Government Services Operating Company
FDI Contract 80460210 SNF Canister Storage Building Contract TVW-SVV-370252
3.2.4 The Detector and Alarm subsystem provides notification of fire to facility personnel and sends a radio signal to the IHanfoi-d Fire Department (HFD) to summon emergency aid. The Very Early Smoke Detection Alni-m (VESDAO) Detector System detects smoke particles in sampled ail- fi-om the upper portion of the operating area. The VESDA Detector System interfaces with the Fii-c Alarm Control Panel (FACP) initiating visible and audible alarms and notifying the HFD. The Heating, Ventilating and Air Conditioning (HVAC) duct smoke detectors interface with the HVAC control pancl (LP-HV-001) initiating shut down of several HVAC air handling units in addition to visible and audible alarms and notifying the HFD. Also, there are manual f i x alarm stations that activate the visible and audible alarins and notify the HFD if facility personnel detect a fire.
3.2.5 The FP System also has a backup water supply available via the Fire Water Pump HOLW (FWPH) System that supplies fire water anytime significant pressure fluctuations occur, raw water system pressure decays or the raw water supply is unavailable. See Sy.vtrrir De.si,yri Llescriptiorr Fire Writcr Putrip ( l o l r s r (FWPII ) Sy.s/errr (Syslc~nl 20).
3.3 Configuration
3.3. I The Fire Protection System interfaces with the following systems:
Electrical Distribution (System # I )
Self contained battery backup
The Electrical Distribution and Unintcrruptible Power Supply Systems provide power to the electrical equipment within the Fire Protection System. When the Detector and Alarm subsystem detects a fire in the ducts, the HVAC control panel (LP-HV-001) shuts down the associated HVAC equipment (i.e., AH-001, AH-002, and AH-003). The Fire Water Pump House System provides a backup source of water to thc FWS subsystem.
Heating. Ventilating and Air Conditioning (Systems #6 Rr #7) Fire Water Pump House (System #20)
3.3.2
3.4 Requirements
3.4.1 Fire Wuter Supply Siih-Sy.sreiti De.si,ytt R~,~/ i r i r~ , i t i~ , r i l , s :
A. The FWPH System distribution system incoiporates a Post Indicating Valve (PIV). Sprinkler risers are located at extei-ior walls. Outside control valves are located a minimum distance of40-feet from the FWPH and CSB buildings.
S\..stelll U'~.Sl~~ll Dc.s(~rlpriolr.s Page 35 o f 236 Fire Protection Syslrm: 06/06/00
-
DE&S HANFORD, INC. SNF Canister Storage Building Contract TVW-SVV-370252
PARAMETER Design Temperature
Design Pressure
SNF-6151, Rev. 1 FLUOR DANIEL, INC. Government Services Operating Company
FDI Contract 80460210
REQUIREMENT
100 " F (piping) / ~ 20 "F - 150 "F (valvc)
150 psig (piping) / 175 p i g (valvc)
System Flow II Design Lifc I 40 ycars II
I , 1 50 gpm E!) 98 psi
3.4.2
3.4.3
Sy.rroii l 7c .s I~~ t i De.s
-
DE&S HANFORD, INC. SNF-6151, Rev. 1 FLUOR DANIEL, INC. Government Services Operating Company
FDI Contract 80460210 SNF Canister Storage Building Contract TVW-SVV-370252
Normal Operating Pressure
Supeiyisory devices of critical functions (valve position switches, water level, temperature) in accordance with NFPA 72 Capability of indicating at least three separate conditions; a) fire alarm, b) a supervisory alarm, c) ii trouble signal indicating a fdult in either of the first two conditions. Indication of each condition is separate and distinct from the other two. By-pass test switches is provided to allow smokc detector testing operation of dampers or shut down W A C equipment.
B. Automatic Fire Detection Systems:
Smoke detectors arc installed in areas required by NFPA 72 or by fhe cognizant DOE fire protcction authority. Smoke detectors are photoelectric type and are installed i n accordance with NFPA 72.
C. Fire Barriers:
85 - 125 psig
Confinement systems. particularly the building shell and its associated ventilation system, arc designed with the capability of retaining the confinement function during a Design Basis Fire.
Fire resistance requirements are specified by the Fire Hazards Analysis. The Fire Hazards Analysis considers conditions that may exist during normal operations and under special conditions (e.g., during periods of renovation, modification, repair and maintenance, and end-of-life decontamination and decommissioning.). The fire-resistant rating is at least two hours under conditions of failure of any f i i c suppression system not designed as a safety class item. Penetration through any firewall ( i s . , wall separating the Support Area from the Operating Area, Support Area Deck and building exterior walls) incorporates, as a minimum, protection against Design Basis Fire exposurcs unless greater protection is required by other sections of these criteria (6430.lA para 01 10-90.0.6).
3.4.4 Oprrcrfioricrl Rec/itirc,r,rPrrts: FWPH Systcm operational 1-equirements are given in the following table:
Detectors and Alarms Fu I I-Ti me Operat ion
-
DE&S HANFORD, INC. SNF Canister Storage Building Contract TVW-SVV-370252
SNF-6151, Rev. 1 FLUOR DANIEL, INC. Government Services Operating Company
FDI Contract 80460210
3.4.5 Mtiiritrri(irict trr i t l Siirivi//mic'c Rcc/iiirrriic,rit.s:
N 0 7 F - Tcsting and inspcction for the Fire Protection System is pcrformcd by the Hanford Fire Department (HFD) in accordance with HNF'-I-'KO-.?.SI, Fire Protcc'fiori Syvtrtii 7 i , s / i i i , ~ / / i i s / ~ c , c ' / i o r i t i r id Mtiirlterlclrfc~c,.
A. Manual valves in the FWPH System must bc cxerciscd and lubricated at lcast annually.
N O 7 E - The surveillance for watcr lcaks threatening erosion around the CSB foundations should be formalizcd as a surveillance requirement bcforc CSB opcration begins.
B. An outdoor sui-vcillance for evidence of underground leaks (which may undcrmine thc CSB foundations) from the IO-inch and 12-inch underground Fit-c, Sanitary and Raw Watcr lincs located no t th and cast of the facility, and from the smallcr water lincs in the imrncdiatc area of the facility, must he pcrformed at lcast monthly; or, a flow totalizer must bc added to the system and regularly obscrved.
3.5 Safety
3.5. I P o t m i d St#ry Hazrirds czi id Coricrvris: Hazai-ds of the Firc Protcction Systcm include:
High pressure water High velocity water flow Wct electrical equipment aftcr initiation of sprinklcrs
Pipe failure could endanger facility personnel becausc of the high pressure watcr and high velocity watcr flow. Inadvcrtcnt opening of a spt-inkler hcad by mcchanical damage or a heat source other that a fire (e.&, electrical heatcr).
St&y Clcis.v(ficcltioii: The FP System is classified as General Service (GS), because i t is not required to mitigatc an accidcnt or to opcrate aftcr an accidcnt, and provides a limited function i n protecting the f x i l i t y workcr from industrial and radiological hazards. The 6-inch fire water supply entcrs the Northwest comer of the Support Building, supplying watcr to thc Support Building Automatic Wet Pipc Sprinkler System. Them are n o Safety Class (SC) or Safcty Significant (SS) functions associated with the supply portion of this systcm. Watcr leakage from thc FWPH System could ciiusc watci- accumulation and drainage problems. If the leakage was allowcd to remain unchcckcd, the prolonged soaking of the backfilled building perimeter could lead to the premature aging of thc below-grade concrete structure. Safc.ty Classification is based on the consequcnces of systcm failure.
3.S.2
-
DE&S HANFORD, INC. SNF Canister Storage Building Contract TVW-SVV-370252
DWG#
SNF-6151, Rev. 1 FLUOR DANIEL, INC. Government Services Operating Company si FDI Contract 80460210
DRAWING TITLE
NOTE - The surveillance for water leaks threatening erosion around the CSB foundations should be formalized ;IS a surveillance requirement before CSU operation begins.
3.5.3 The soil around underground RW and FWX lines must be checked monthly for evidencc of leakage, to avoid the risk of building foundation failure rcsulting from a washout following a break of the lines. This includes the 10-inch FWX- IO"-500-004-RF and 12-inch Fire, Sanitary and Raw Water lines to the noith and east of the facility, and the smaller underground lines in the immediate area of the facility.
~ ~ i ~ , ~ ~ [ ~ ~ i ~ ~ i [ , ~ i ~ f ~ / S&y: The SNF CSB does not have any connections to a chemical sewer or other means of direct disposal of hazardous chemical waste. All hazardous wastes generated during maintenance or other activities within the facility must he safely contained at thc point of generation (i.e., fluids drained into buckets, rags and other materials placed in plastic bags), and removed to some other facility having suitable means of safe hazardous material disposal available, in accordance w i t h "State Waste Discharge Permit Number ST-4508, as amended" Hanford Site.
3.5.4
H-2- I22747
H-2- 122748
H-2-125160 sheet I
H-2-125160 sheet 2
H-2.125163 sheet 3
3.6 References
Electrical Canister Storage Building Communication and Fire Alarm System Riser Diagram
Electrical Canister Storage Building Communication and Fire Alarm Plan
Piping OpcratindSupport Areas Compi~esseil Air/MCO Vac Plan
Piping Operating/Support Areas Compressed Air/MCO Vac Plan, Sections & Details
Piping Operating/Support Areas Misccllaneous Sections and Details
3.6.1 Drawings relating to or referenced in this document are:
Civil Water Lines Sections & Details I H-2- I I7077 sheets I - 3 II H-2-121500 I Control Systems CSB Fire Protection Schematic
-
DE&S HANFORD, INC. SNF Canister Storage Building Contract TVW-SVV-370252
DWG #
H-2-127156 sheet I
SNF-6151, Rev. 1 FLUOR DANIEL, INC. Government Services Operating Company
FDI Contract 80460210
DRAWING TITLE
Piping Operations Suppoil Area Fire Protection Fcatum Floor Plan
~~~
H-2- I27 IS6 sheet 2
Piping Operations Area Fire Protection Features Floor Plan
DOC. # HNF-PRO-35 I
HNF-PRO-372
HNF%D-SNF-FHA-OO:! Final Fire Hazard Analysis for the Canistei- Storage Building
DOCUMENT TITLE Fire Protection Systcm Testing/lnspection and Maintenance
Hanford Fire Department
HNF-3553
SNF-6154 I Design Basis Document, Section 2, Process Systems
Annex A, Canister Stoi-age Building Final Safety Analysis Repoit, Section A2.7. I , Fire Protection Features
SNF-6154 I Dcsien Basis Document, Section 11. Fire Protection
NIA
N/A Crcighton Engineering: Hydraulic Calculations tor SNF Canister Storage Building
Westinghouse Hanford Company HWVP Raw Water and Fire Water Systcm Operation & Maintcnancc Manual, Volumes: I - 3
NFPA 72, 1906
ST-4508
W-379-C-CSB- I550 1
W-379-C-CSB- 1506 I
I
NFPA 25, 1998 1 Inspection, Testing and Maintenance of Water Based
National Fire Protection Code
Hanford Site State Waste Discharge Permit
Automatic Wet Pipe Sprinkler Systcm
Piping Material, Fabrication, Erection and Pressui-e Testing (Carbon Steel, Iron and Nonmetallic)
1 Fire Protection Systems
W-379-C-CSB-17697 1 Smoke and Heat Detectors W-379-C-CSB-2220 1 Excavation And Backfill
-
DE&S HANFORD, INC. SNF-6151, Rev. 1 FLUOR DANIEL, INC. Government Services Operating Company
FDI Contract 80460210 SNF Canister Storage Building Contract TVW-SVV-370252
SPENT NUCLEAR FUEL CANISTER STORAGE BUILDING
LIQUID WASTE COLLECTION (System #4)
SYSTEM DESIGN DESCRIPTIONS
-
DE&S HANFORD, INC. SNF Canister Storage Building Contract TVW-SVV-370252
SNF-6151, Rev. 1 FLUOR DANIEL, INC. Government Services Operating Company
FDI Contract 80460210
4.0 LIQUID WASTE COI,I,ECTION SYSIEM DESCRIPTION (SYSTEM #4)
4.1 Function
The Liquid Waste Collection System (LWC) includes two sumps, SU-I and S11-2. S1J-l is designcd to collect water condcnsate from the HVAC Air Handling Unit cooling coils, and provide for transfer of the condensatc to Dcpurtnient of Transportation (DOT)-certified containers for disposal. SU-2 is dcsigned to collect water fi-om the compressed air systems and is usually drained by cvapoi-ation, and does not require pumping. Thc LWC is not to be considcred ii floor drain or fire suppression water catc hmcnt.
4.2 Operation
4.2.1 condensate that gathers on the cooling coils of thc HVAC air handling units in the HVAC Equipment room of the SNF CSB drips into drip pans, then drdins to Liquid Collection Sump SU-I. A maximum condensate generation rate of approximately I gallon per hour for 8 hours pcr day is expected, based on assumed HVAC operating time and maximum humidity levels.
When the water levcl in sump SU-I reachcs 50%) (12 inches, 55 gallons) as sensed by Level Sensor LSH- I IO, DCS Alarm L A N I I9 is activated.
After Alarm LAH- I19 activation, an operator positions a container meeting DOT transpoilation requirements (as found in 49CFR171 & 49CFR172) next to Pump P-4, which is mounted near the sump and connccred to the Service Air (SA) system with block valves, an air filter, and it regulator. Thc operator connects the supplied suction hose to P-4 and a discharge hose to the Dynamic Surgc Suppressor (also known as a pulsation damper) mounted downstream of P-4. [The suction hose is already positioned in the sump, since the grating cannot be removed] and the operator then places the discharge hose into the container. When SA is valved in to the pump motor through the regulator, the pump transfers water from the sump to the container. This process continues until the pump is unable to lower the level any farther or thc container is f u l l , and Alarm LAH-I 19 has cleared.
4.2.2
4.2.3
4.2.4 The contents of the full container are sampled and tested foi- radiological and chemical contamination. When the contents are released for disposal, the container may he transported to a facility at which the contents can be transfeired to the Treatment Effluent Disposal Facility (TEDF). Or, if the contcnts mcet the criteria Tor discharge under Washington State Waste Discharge Permit ST 4509 for cooling water and condensate, the condensate may be used, as a “best management practice” for lawn irrigation or dust abatement. SNF Opelations Managcment wi l l be responsible for determining disposition of container contents that 31% found to be in excess of TEDF and/or State Waste Permit rclcase limits.
-
DE&S HANFORD, INC. SNF Canister Storage Building Contract TVW-SVV-370252
Sump Construction
Sump volume
Pump design flow
SNF-6151, Rev. 1 FLUOR DANIEL, INC. Government Services Operating Compa