1b.promotion of energy conservation in indian thermal power

Upload: krishna-chaitanya

Post on 09-Apr-2018

218 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/7/2019 1B.Promotion of Energy Conservation in Indian Thermal Power

    1/35

    Energy Conservation Act and Energy AuditEnergy Conservation Act and Energy Audit

    ATAR SINGHATAR SINGH

    DEPUTY DIRECTOR, NPTIDEPUTY DIRECTOR, NPTI

  • 8/7/2019 1B.Promotion of Energy Conservation in Indian Thermal Power

    2/35

    India has an installed power generating capacity of 143,061 MW (as on

    March 31, 2008) of which the thermal power stations share is 91,906

    MW (64%).

    IntroductionIntroduction

  • 8/7/2019 1B.Promotion of Energy Conservation in Indian Thermal Power

    3/35

  • 8/7/2019 1B.Promotion of Energy Conservation in Indian Thermal Power

    4/35

    Energy consumption in India is low, though efficiency of use is reasonable

    Per capita energy consumption is 530 kgoe; world average is 1770 Energy intensity of Indian economy was 0.18 kgoe/$-GDP(PPP) in 2004;

    compared to 0.14 in Japan and 0.19 in the EU

    Energy demand is increasing due to rising incomes, acceleratedindustrialization, urbanization and population growth 2003-04 : 572 Mtoe

    2016-17 : 842-916 Mtoe 2026-27 : 1406-1561 Mtoe

    Meeting the increasing demand only through increases in supply may leadto: Reduced energy security due to volatility in availability and prices of

    imported fuels Adverse environmental impacts Strain on balance of payments

    Energy conservation and energy-efficiency are an essential part of nationalenergy strategy

    Energy Use in India

  • 8/7/2019 1B.Promotion of Energy Conservation in Indian Thermal Power

    5/35

    The contribution of energy generated by thermal stations was 559

    billion kWh, which is about 80% of electricity generated (704.5 billion

    kWh) in 2007-08.

    There has been significant improvement in the plant load factor of

    thermal stations, which improved from 52.4% in 1985-86 to 78.6 in

    2007-08, registering a remarkable improvement of 50 % during the

    period.

    Since the major power generation contribution is from thermal sector,

    an average increase of 1% in the thermal power plant efficiency would

    result in:

    a. Coal savings of approx. 11 million tons per annum for nation

    (approx) worth 200 Million Euro

    b. 3% CO2 reduction per annum (approx.13.5 million tons per annum)

    Indian Thermal Power StationsIndian Thermal Power Stations

  • 8/7/2019 1B.Promotion of Energy Conservation in Indian Thermal Power

    6/35

    ALL INDIA PLANT LOAD FACTOR (%) OFCOAL FIRED THERMAL POWER STATIONS

    57

    .1

    77

    .03

    78.61

    74

    .3

    53

    .2

    74

    .8

    72

    .772

    .2

    69

    .969

    67

    .3

    64

    .664

    .7

    64

    .4

    63

    60

    61

    55.3

    53

    .9

    56

    .5

    55

    56

    .5

    52

    .4

    48

    53

    58

    63

    68

    73

    78

    1985-86

    1986-87

    1987-88

    1988-89

    1989-90

    1990-91

    1991-92

    1992-93

    1993-94

    1994-95

    1995-96

    1996-97

    1997-98

    1998-99

    1999-2000

    2000-01

    2000-02

    2002-03

    2003-04

    2004-05

    2005-06

    2006-07

    2007-08

    YEARS

    PLF(%)

  • 8/7/2019 1B.Promotion of Energy Conservation in Indian Thermal Power

    7/35

    INDIAN SCENARIO: DESIGN HEAT RATEINDIAN SCENARIO: DESIGN HEAT RATE

    TRENDS*TRENDS*

    PERIOD STEAMPRESSURE&

    TEMPERATURE

    UNIT SIZE

    (MW)

    TURBINE

    Heat Rate

    (Kcal/kWh)

    Unit Heat Rate

    (Kcal/kWh)

    1951-60 60 kg/cm2, 482oC 30 57.5 2470

    1961-75 70 kg/cm2, 496oC to

    90 ata 538oC

    60 100 2370

    1961-75 130 ata 535/535oC 110 120 2170 2060 2552-2423

    1977-82 130 ata 535/535oC 210 (Russian) 2060 2423

    1983+ 150 ata 535/535oC 210(Siemens)

    2024 2335

    1984+ 170 ata 535/535oC 500 1950 (TDBFP) 2294

    1990+ 150 ata 535/535oC

    170 ata 538/538 oC

    210/ 250

    250/ 500

    1950 (MDBFP)

    1950 (TDBFP)

    2294

    2294

    *Above are best design values (design rates of individual unit varies based on

    reference ambient, coal quality, design and supply dates)

  • 8/7/2019 1B.Promotion of Energy Conservation in Indian Thermal Power

    8/35

    EFFECT OF CRITICAL PARAMETERS ONEFFECT OF CRITICAL PARAMETERS ON

    HEAT RATEHEAT RATE

    Variation Impact (kCal /kWh)

    200 MW Unit 500 MW Unit

    SH Spray 20 T/hr 0.30 0.81

    RH Spray 20 T/hr 12.00 4.76MS Pr. 10 kg 12.00 7.30

    MS Temp. 10oC 6.00 6.20

    RH Steam 10oC 6.00 5.55

    Load 10 MW 12.00 4.36

    Cond. Back Pr. 5 mm Hg 8.00 6.70

    FW Temp. 10oC 8.00 10

  • 8/7/2019 1B.Promotion of Energy Conservation in Indian Thermal Power

    9/35

    Power sector reforms

    Promotion of clean coal technologies,

    Energy Conservation Act 2001

    Electricity Act 2003

    National Electricity Policy, 2005

    Adoption of Super Critical Technology for 660/ 800 MW units for Ultramega Projects (4000 MW each) and

    Increased emphasis on environmental considerations

    Policy initiatives of Government of India to improve thePolicy initiatives of Government of India to improve the

    power sector efficiencypower sector efficiency

  • 8/7/2019 1B.Promotion of Energy Conservation in Indian Thermal Power

    10/35

    Emphasis on plant load factor instead of efficient generation.

    Degradation of equipment resulting in loss of capacity.

    Delayed overhauls (Seasonal Constraints)

    Financial constraints lead to inadequate maintenance

    Lack of awareness on efficiency related issues

    Inadequate monitoring system for parameters

    Barrier to Efficiency Improvement in Power Sector Barrier to Efficiency Improvement in Power Sector

    Indian ScenarioIndian Scenario

  • 8/7/2019 1B.Promotion of Energy Conservation in Indian Thermal Power

    11/35

    Enacted in October 2001Enacted in October 2001Become effective from 1st March 2002Become effective from 1st March 2002

    Bureau of Energy Efficiency (BEE) operationalized fromBureau of Energy Efficiency (BEE) operationalized from

    11stst March 2002.March 2002.

    MISSION OF BEEMISSION OF BEE

    Develop policy and strategies with a thrust on self regulationDevelop policy and strategies with a thrust on self regulationand market principles, within the overall framework of theand market principles, within the overall framework of the

    EC Act with the primary objective of reducing energy EC Act with the primary objective of reducing energy

    intensity of the Indian economy.intensity of the Indian economy.

  • 8/7/2019 1B.Promotion of Energy Conservation in Indian Thermal Power

    12/35

    DESIGNATED CONSUMERSDESIGNATED CONSUMERS( Energy Intensive Industries and other Establishments)( Energy Intensive Industries and other Establishments)

    (A programme to initially focus on energy policy issues of energy(A programme to initially focus on energy policy issues of energyefficiency improvement in organized sectors such as energy intensiveefficiency improvement in organized sectors such as energy intensiveindustries and commercial sector through establishment of energyindustries and commercial sector through establishment of energymanagement system, capacity building of energy professionals,management system, capacity building of energy professionals,implementation of energy audits, establishments of specific energyimplementation of energy audits, establishments of specific energyconsumption norms and support to consumers on providingconsumption norms and support to consumers on providinginformation on authentic energy data )information on authentic energy data )

    Schedule to EC Act provides list of 15 energy intensive industries and otherSchedule to EC Act provides list of 15 energy intensive industries and otherestablishments to be notified as designated consumers (DC). DCs toestablishments to be notified as designated consumers (DC). DCs to

    Appoint or designate energy managersAppoint or designate energy managers

    Get energy audits conducted by accredited energy auditorsGet energy audits conducted by accredited energy auditors

    Implement techno-economic viable recommendationsImplement techno-economic viable recommendations

    Comply with norms of specific energy consumption fixedComply with norms of specific energy consumption fixed

    Submit report on steps takenSubmit report on steps taken

  • 8/7/2019 1B.Promotion of Energy Conservation in Indian Thermal Power

    13/35

    1) Criteria for Notification for a Industry as Designated Consumer

    Thermal Power Stations- 30,000 metric tonne of oil equivalent (MTOE) per yearand above

    2) Fertilizer- 30,000 metric tonne of oil equivalent (MTOE) per year and above

    3) Cement- 30,000 metric tonne of oil equivalent (MTOE) per year and above

    4) Iron & Steel- 30,000 metric tonne of oil equivalent (MTOE) per year and above

    5) Chlor-Alkali- 12,000metric tonne of oil equivalent (MTOE) per year and above

    6) Aluminium- 7,500 metric tonne of oil equivalent (MTOE) per year and above

    7)Railways- One traction substation in each Zonal Railway , Production units andWorkshops of Indian Railways having total annual energy consumption of 30,000

    MTOE or more under Ministry of Railways

    8) Textile-3,000 metric tonne of oil equivalent (MTOE) per year and above

    9) Pulp & Paper-30,000 metric tonne of oil equivalent (MTOE) per year and above

  • 8/7/2019 1B.Promotion of Energy Conservation in Indian Thermal Power

    14/35

    The Ministry of Power, Government of India and GTZ (Deutsche

    Gesellschaft fr Technische Zusammenarbeit (GTZ) GmbH) signed an

    implementation agreement with respect to the Indo-German Energy

    Programme in 2006.

    The Indo German Energy Programme (IGEN) is performing researchwork and performance assessment in support of the implementation of

    the Energy Conservation Act 2001 in cooperation with the Ministry of

    Power and its statutory bodies Bureau of Energy Efficiency (BEE), and

    Central Electricity Authority (CEA).

    Under the IGEN agreement, CEA has been entrusted with the task of

    ensuring performance optimisation and efficiency of thermal power

    plants.

    The Indo German Energy Programme (IGEN)The Indo German Energy Programme (IGEN)

  • 8/7/2019 1B.Promotion of Energy Conservation in Indian Thermal Power

    15/35

    The overall aim of this measure under Indo Germany Energy

    programme is to support and prepare public and private power plant

    operators for performance reporting as well as implementation of

    financially attractive and technically viable improvements of power plant

    net heat rate under the provisions of the Energy Conservation Act.

    The project is being executed under two main sub-components:

    1. Mapping Studies of thermal power generating units

    2. Performance Optimisation of Thermal Power Stations

    The Indo German Energy Programme (IGEN)The Indo German Energy Programme (IGEN)

  • 8/7/2019 1B.Promotion of Energy Conservation in Indian Thermal Power

    16/35

    GTZ has provided support to CEA in creating a database of the older

    thermal power plants in India.

    The scope of the work primarily covers the mapping of the 85 thermal

    power generating units by using Ebsilon software.

    The mapping is done for two-condition design status and the actual

    operating status based on plant parameters gathered from different plant

    locations.

    Its primary purpose is to provide a baseline mapping for creating a

    databasewithin CEA and identify areas both short and long term, needing

    attention in order to improve energy efficiency.

    The baseline map would permit an objective method of setting targets

    and monitoring progress.

    Mapping Studies of Indian Thermal Power StationsMapping Studies of Indian Thermal Power Stations

    (Sub Component-I)(Sub Component-I)

  • 8/7/2019 1B.Promotion of Energy Conservation in Indian Thermal Power

    17/35

    Mapping studies of 65 Thermal power generating units of the 14 Indian

    States viz.

    Andhra Pradesh, Chhattisgarh, Gujarat, Haryana, Jharkhand,Karnataka, Madhya Pradesh, Maharashtra, Orissa, Punjab, Rajasthan,

    Tamil Nadu, Uttar Pradesh & West Bengal have been completed.

    The mapping studies carried out by using Ebsilon Software have

    brought out the deviations between design and operating parameters

    such as gross heat rate, turbine heat rate, boiler efficiency , specific

    coal consumption of the power generating units .

    MAPPING STUDIES - PROGRESS ACHIEVEDMAPPING STUDIES - PROGRESS ACHIEVED

  • 8/7/2019 1B.Promotion of Energy Conservation in Indian Thermal Power

    18/35

  • 8/7/2019 1B.Promotion of Energy Conservation in Indian Thermal Power

    19/35

    1. The mapped thermal generating units were characterized by a wide

    band of energy performance

    2. Few of them were very closed to their designed energy performance,

    but majority of them had deviated from their designed performance by

    a bigger margin

    3. Operating Gross Heat Rate was found to be varying from 2477 to 3084

    kCal/kWh against their design values of 2321 and 2444 kCal/kWh

    respectively, exhibiting deviation band width of 156 kCal/kWh (6.3%) to

    640 kCal/kWh (20.7%)

    Salient features of outcome of Mapping Studies ofSalient features of outcome of Mapping Studies of

    twenty-six nos. of 210 MW unitstwenty-six nos. of 210 MW units

  • 8/7/2019 1B.Promotion of Energy Conservation in Indian Thermal Power

    20/35

    4. For an average designed Gross Heat Rate of 2384 kCal/kWh for these

    26 units of 210 MW capacities, the heat rate has increased by an average

    value of 385 kCal /kWh, registering an average increase of 16% from theirdesign performance.

  • 8/7/2019 1B.Promotion of Energy Conservation in Indian Thermal Power

    21/35

    5. The mapping studies have proved that older units having better

    operation and maintenance practices can still demonstrate higher

    performance than comparatively younger units. 27 % of 210 MW power

    generating units, having age more than 25 years have shown better

    performance than 54 %of 210 MW units in the age group of 14-25 years

    Average Gross Heat Rate byage group (210 MW)

    (as observed through Mapping Studies)

  • 8/7/2019 1B.Promotion of Energy Conservation in Indian Thermal Power

    22/35

    6. The operating gross heat rate of turbines was found to be the major

    contributor in the deterioration in the energy performance of 210 MW

    units. The turbine gross heat rate varied from 2045 to 2407 kcal/kWh

    indicating a wide difference of 362 kCal/kWh in the operating

    performance of 210 MW turbine units, which is about 60% of the total

    deviation (607kCal/kWh) observed for 210 MW generating units.

    Turbine Heat Rate of 210 MW capacity units (kcal/kWh)

    (as observed through Mapping Studies)

    2407

    2045

    1900

    2000

    2100

    2200

    2300

    2400

    2500

    A G H t R t b T bi T

  • 8/7/2019 1B.Promotion of Energy Conservation in Indian Thermal Power

    23/35

    Average Gross Heat Rate by Turbine Type(210 MW)

    (as observed through Mapping Studies)

    12 units

    13 units

    One unit

    2,400

    2,450

    2,500

    2,550

    2,600

    2,650

    2,700

    2,750

    2,800

    2,850

    2,900

    kca

    l/kW

    h

    Total average 2,783 2,739 2,806

    Franco-Tosi KWU LMZ

  • 8/7/2019 1B.Promotion of Energy Conservation in Indian Thermal Power

    24/35

    Average Gross Heat Rate by Boiler Type (210 MW)(as observed through Mapping Studies)

    one unit

    21 units

    4 units

    2,400

    2,500

    2,600

    2,700

    2,800

    2,900

    3,000

    kca

    l/kWh

    Total average 2,906 2,745 2,783

    ABL BHEL Transelectro

  • 8/7/2019 1B.Promotion of Energy Conservation in Indian Thermal Power

    25/35

    Boiler Efficiency of 210 MW capacity units (%)

    (as observed through Mapping Studies)

    84.20

    77.25

    82.00

    74.00

    76.00

    78.00

    80.00

    82.00

    84.00

    86.00

  • 8/7/2019 1B.Promotion of Energy Conservation in Indian Thermal Power

    26/35

    Percentage of Auxiliary Consumption of 210MW capacity units (%)

    11.82

    8.07

    6.5

    7.5

    8.5

    9.5

    10.5

    11.5

    12.5

  • 8/7/2019 1B.Promotion of Energy Conservation in Indian Thermal Power

    27/35

    The overall aim of this measure is to support and prepare public and

    private power plant operators for performance reporting as well as

    implementation of financially attractive and technically viable

    improvements of power plant net heat rate under the provisions of theEnergy Conservation Act.

    This phase has been initiated with effect from 15th January, 2008 and is

    expected to be completed by 15th January, 2010. The following 5

    outputs are planned:

    Performance Optimisation of Thermal Power StationsPerformance Optimisation of Thermal Power Stations

    under IGEN Programmeunder IGEN Programme

    (Sub Component II)(Sub Component II)

  • 8/7/2019 1B.Promotion of Energy Conservation in Indian Thermal Power

    28/35

    1. Capacity building of power plant personnel and Technical assistance

    for conduct of high quality energy audits

    2. Technical assistance in the establishment of energy management

    system in the power plants

    3. Annual statistics of validated impact of energy conservation in power

    plants

    4. Familiarization and interchange of best practices with power plant

    operators in Germany or Europe

    5. Development of electronic data base to analyze the findings of all

    energy audit reports carried out in power plants and assessment of

    impacts with respect to energy conservation and efficiency.

    Performance Optimisation of Thermal Power StationsPerformance Optimisation of Thermal Power Stations

    under IGEN Programmeunder IGEN Programme

    (Sub Component II) Contd(Sub Component II) Contd

  • 8/7/2019 1B.Promotion of Energy Conservation in Indian Thermal Power

    29/35

    The following progress has been achieved in the past 6 months since theinitiation of the activities with effect from 15th January, 2008.

    Output 1

    Technical Assistance for Conduct of High Quality Energy Audits

    1. 1 Survey of best practices on power plant performance monitoring in

    Germany / Europe, data generation and its analysis, software and

    analytical tools used, on line as well as mobile measuring instruments,

    newest trend in power plant performance optimization, etc.

    -- (completed)

    PERFORMANCE OPTIMISATION OF THERMAL POWERPERFORMANCE OPTIMISATION OF THERMAL POWER

    STATIONS - PROGRESS ACHIVEDSTATIONS - PROGRESS ACHIVED

  • 8/7/2019 1B.Promotion of Energy Conservation in Indian Thermal Power

    30/35

    1.2. Organization of 20 workshops and 20 seminars to disseminate findings

    across India

    --- Workshops & Seminars across the country in progress.

    1.3 Development of standard procedure for energy auditing of power

    plants and its finalization

    --- Application of guidelines for energy auditing of thermal power

    plants manual prepared

    1.5 Undertake statistical analysis of 100 energy audit reports prepared by

    accredited energy auditors for assessment of their quality and findings

    ---- (Received 25 reports from power stations and evaluated for

    statistical analysis on the qualitative assessment such as areas

    covered, quality of reports, probing skills, report structure etc.)

    O t t 2

  • 8/7/2019 1B.Promotion of Energy Conservation in Indian Thermal Power

    31/35

    Output 2

    Technical Assistance in the Establishment of energy management system in

    the power plants

    2.1 Development of a model organizational structure for establishing Energy

    Management Cells, employing certified Energy Manager, based on the outcome

    of the survey of all public and private power plants

    --- in progress

    2.2 Discuss with public & private power plants owner findings in workshops and

    present a common most preffered energy conservation studies plan and delivery

    mechanism

    Miscellaneous:

    To promote energy efficiency improvement in the power plants, a new home page on

    "Power Plant Optimization" Component has been established w.e.f May, 2008 in

    www.energymanagertraining.com .

  • 8/7/2019 1B.Promotion of Energy Conservation in Indian Thermal Power

    32/35

  • 8/7/2019 1B.Promotion of Energy Conservation in Indian Thermal Power

    33/35

    The following outcomes are expected of the programme:

    a. Assistance in the improved efficiency of thermal power plants

    b. Establishment of mapped power plants data bank

    c. Establishment of Energy Efficiency cell at Power Plants

    d. Capacity building of the power plant professional on power plant

    optimization

    e. Standard Prescribed format for submitting Energy Audit Reports.

    Outcome Expected from IGENOutcome Expected from IGEN

  • 8/7/2019 1B.Promotion of Energy Conservation in Indian Thermal Power

    34/35

    CONCLUSIONSCONCLUSIONS

    The increasing preference for commercial energy has led to aThe increasing preference for commercial energy has led to asharp increase in the demand for electricity and fossil fuels.sharp increase in the demand for electricity and fossil fuels. Use of Fossil Fuels result in emission of huge quantity ofUse of Fossil Fuels result in emission of huge quantity of

    carbon dioxide causing serious environmental damages.carbon dioxide causing serious environmental damages. There is a considerable potential for reducing energyThere is a considerable potential for reducing energy

    consumption by adopting energy efficiency measures inconsumption by adopting energy efficiency measures inthermal power stations of our country.thermal power stations of our country.

    Energy efficiency will not only reduce the need to create newEnergy efficiency will not only reduce the need to create newcapacity requiring high investment, but also result incapacity requiring high investment, but also result insubstantial environmental benefitssubstantial environmental benefits..

    With the enactment of the Indian Energy Conservation Act,With the enactment of the Indian Energy Conservation Act,2001, an institutional framework is now available for2001, an institutional framework is now available forpromoting energy efficiency in all sectors of the economypromoting energy efficiency in all sectors of the economy

    Efficient use of energy and its conservation will succeed as aEfficient use of energy and its conservation will succeed as aprogram if there is a strong institutional set up in the countryprogram if there is a strong institutional set up in the countryand opinion leaders and captains of industry take lead inand opinion leaders and captains of industry take lead inimplementing the best practices supporting the conservationimplementing the best practices supporting the conservationprogrammeprogramme

  • 8/7/2019 1B.Promotion of Energy Conservation in Indian Thermal Power

    35/35