19th national award for excellence in cement... · boiler-55 tph, afbc, cvpl, turbine ... power...
TRANSCRIPT
ULTRATECH CEMENT LIMITED
(UNIT: REDDIPALAYAM CEMENT WORKS)
19th National Award for Excellence in Energy Management 2018: 29, 30 & 31 August 2018, Hyderabad
Team Members:
Mr. Praveen Kumar (HOD TS & WCM)
Mr. N Srinivasan ( SH TS)
1
Hirmi Cement Works
Jafrabad Cement Works
Magdalla Cement Works
Ratnagiri Cement Works
Andhra Pradesh Cement Works
Arrakonam Cement Works
Awarpur Cement Works
Jharsuguda Cement Works
West Bengal Cement Works
Bathinda Cement Works
Aditya Cement
Vikram Cement
Gujarat Cement Works
Kotputli Cement Works
Hotgi Cement Works
Rajashree Cement Works
Ginigera Cement Works
Panipat Cement WorksDadri Cement Works
Aligarh Cement Works
Location of Integrated Plants,
Grinding Units and Bulk Terminals
RWCW
Reddipalayam Cement Works
Integrated plant
Grinding unit
Bulk terminals
Mangalore Cement Unit
BSBT- Dodballapur
Shankarapally Bulk Terminal
Navi Mumbai Cement Unit
Cochin Bulk Terminal
Sewagram Cement
Works
Wanakbori Cement
Works
Patliputra Cement Works
Dankuni Cement Works
Jhajjar Cement Works
Magdalla Terminal
Units SymbolNumber of
Units
Integrated
Plants19
Grinding Units 25
Bulk Terminals 7
UltraTech Cement Ltd Overview
Area of spread (RDCW) RDCW Unit
Plant capacity 1.6 MTPA
Area of mines 188.62 Ha
Area of plant 125 Ha
Nearest air port Trichy
(75 km)
2
CEMENT – MANUFACTURING PROCESS
3
MILESTONES
▪ Preheater upgraded
from IV to V stage
▪ Cooler up gradation
▪ GCT vessel height increased
▪ Three cooler fans replaced with high
efficiency fans
▪ Modified Pre-heater twin cyclone Aero-
vane
▪ Clinker breaker Upgradation
▪ Kiln speed
increased from 3.2
to 5.5 RPM
▪ TA duct dia
increased from 2.1
M to 2.5 M
▪ Cooler grate area
increased from
52m2 to 72m2
▪ Kiln Inlet
modification
▪ Kiln feed bucket
elevator speed
increased from
1.5 to 1.7m/Sec
▪ New Plant
Commissioned
FY2016-17
Feb 2000
Apr 2002
Feb 2003
Jun 2004
Sep 2006
Apr 2012
3250 TPD
3150 TPD
3000 TPD
2800 TPD
2400 TPD
1800 TPD
3294 TPD
▪ By continuous
improvement &
optimization
4
▪ State of the art Cement Plant commissioned in the millennium year 2000
▪ 1st Unit in UTCL having Robo lab for total quality control from sampling to
analysis
▪ State of art testing laboratory for Alternative fuels
▪ Designed for using multiple fuels
▪ Pioneer in using alternate fuel with pre-processing system
▪ Pioneer in Using alternate raw material
▪ First Plant in the World to get CDM credit for use of Agro waste alternate fuel
▪ Packing facility with Centralized discharge from cement silo
▪ No fatal accident since last 16 years
UNIQUE FEATURES
5
6
SL NO. DESCRIPTION MAKE SIZEDESIGN
CAPACITYOPERATING CAPACITY
PHOTO
1Limestone Crusher
with Secondary crusher
L&T,
MMD APPM 1615,
MMD 500700 TPH 800 TPH
2 Raw Mill Loesche LM 35.4 180 TPH 230 TPH
3 Coal Mill Loesche LM 21.2 18 TPH 25 TPH
4 Kiln Fuller 3.75 M X 57 M 2400 TPD
3250 TPD
(5 – stage Pre-Heater)
Major process equipment
7
SL NO.
DESCRIPTION MAKE SIZEDESIGN
CAPACITYOPERATING CAPACITY
PHOTO
5 Cooler FLSCross Bar :
10X48 M, HRB3500 TPD 3300 TPD
6
Cement Mill
(Close circuiting
with V-
Separator)
KHD 3.8 Dia X 11.8 M 135 TPH 200 TPH
7
Electronic
Packer ENEXCO 12 Spouts 2 X 180 TPH 2 X 180 TPH
8
Thermal Power
Plant - 12.5 MW
DG - 6.25 MW (2 Nos)
Boiler- CVPL,
Turbine- BHEL
Boiler-55 TPH,
AFBC, CVPL,
Turbine – Triple
extraction cum condensing turbine
TPP
12.5 MW
DG
12.5 MW
TPP
13.5 MW
DG
12.5 MW
Major process equipment
MANAGEMENT SYSTEMS
ISO :18001 -Safety ISO :14001 EnvironmentISO : 9001 - Quality ISO :27001 ISMS ISO :50001 EnMS
8
Reduction in specific energy consumption
746715
733
724691 689
676658
641613
500
600
700
800
Kcal/kg equivalent Cement
Better
Total 3554 No's of EScerts credited for PAT cycle-1
22.92
18.16
13.00
10.94
9.62
9.60
8.34
18-19 Q1
17-18
16-17
15-16
14-15
13-14
12-13
AF
R S
ubstitu
tion %
TS
R
31.52
31.90
30.61
28.47
27.79
26.89
18-19 Q1
17-18
16-17
15-16
14-15
13-14
Fly
ash a
dditio
n in
PP
C
9
Action Plan to Achieve PAT cycle –II Target
Sr. No. Energy efficiency improvement measures
Investme
nt
Rupees in
Lacs
Date of
completion of
measure/ likely
completion
Energy Consumption
Annual Energy saving(TOE)
BeforeAfter
Measures
Electricity
(kWh)
Coal
Measures (Tonne)
1Pressure drop reduction in Preheater 4th stage
cyclone14 completed 1067 1016 583680
2Reduction of pressure drop through junction
box & duct modification at RM ESP32 Completed 176 166 109440
3Replace CFL lamps,HPSV lamps and Tube lights
with LED lamps10.6 Completed 8.39 4.94 40171
4Installation of Aerzen Turbo blower for Kiln coal
firing in place of existing Twin lobe blower 34.89 Completed 32 21 124032
5 Substitution of alternate fuel from 11 % to 15% 45 Completed 48621 48370 321
6 To enhance fly ash addition up to 30% 124 Completed 60639 60342 151614 364
7 Replacement of HVMP lamps with LED in TPP 3 Completed 138 119 224400
8 VFD for BF pump in TPP 25 Completed 175 161 163200
9 Overhauling of TG in TPP 70 Completed 25851 25753 196
10 Heat recovery from rotary kiln 100 Mar-19 33978 33880 196
Total 242186 241239
10
Specific Power Consumption – kWh/MT Clinker
Better
0.00
10.00
20.00
30.00
40.00
50.00
60.00
70.00
CII NationalBenchmark
2012-13 2013-14 2014-15 2015-16 2016-17 2017-18 2018-19 Q1
16.28
59.89 60.3263.43
59.86 58.30 58.5157.48
11
Specific Power Consumption – kWh/MT Cement
Better
50.0
60.0
70.0
80.0
CIINational
Benchmark
2012-13 2013-14 2014-15 2015-16 2016-17 2017-18 2018-19 Q1
65.0
71.8 72.0 71.1
66.763.9
64.3 63.5
12
13
Energy Performance Indicators Vs National Benchmarking
S.NO Section Electrical Energy Consumption (kWh/Mt)
CII Benchmark
FY 2015
Achieved
(FY15-16)
Achieved
(FY16-17)
Achieved
(FY17-18)
Achieved
(FY18-19) Q1
1 Single stage Crusher 0.70 0.78 0.75 0.78 0.88
2 Double stage crusher 0.65
3 Raw Mill - VRM 13.3 14.87 14.66 14.78 14.11
4 Raw Mill – Ball mill 16.5
3 Coal Mill 23.90 49.75 52.96 48.01 44.90
4 Pyro – 5th Stage 16.28 27.01 26.23 26.31 27.09
5 Pyro – 6th Stage 17.05 NA
6 Shut Down 0.69 0.46 0.69 0.19
7 Misc 3.91 3.43 3.43 3.26
8Up to Pyro (kWH/MT of
Clinker)38.43 59.86 58.30 58.51 57.48
14
S.NO Section Electrical Energy Consumption (kWh/Mt Cement)
CII Benchmark
FY 2015
Achieved
(FY15-16)
Achieved
(FY16-17)
Achieved
(FY17-18)
Achieved
(FY18-19) Q1
9Cement Mill- Ball mill with
HPRG23.75 22.84 22.92 23.00 22.34
10Cement Mill- Ball mill with
Close circuit27.16 - -
11 Packing Plant 0.65 0.70 0.66 0.72 0.62
12 Overall 69.13 66.72 63.91 64.31 63.49
S.NO Section Thermal Specific Energy (kcal/kg clinker)
CII Benchmark
FY 2015
Achieved
(FY15-16)
Achieved
(FY16-17)
Achieved
(FY17-18)
Achieved
(FY18-19) Q1
1Thermal SEC for 5 stage
Preheater707 735.43 734.86 735.35 734.67
Energy Performance Indicators Vs National Benchmarking
Energy saving proposals under implementation
15
Sl.No. Descriptions Status Target Date
Proposed
energy savings
(Lac kWh)
Expected
Monetary Gain
(Lacs/annum)
Investment
( Rs Lakh)
Payback
(Months)
1Refurbishment and overhauling of Raw Mill Fan (Impeller
change)In progress
30/10/2018
(S/D Req.)11.76 46 35.00 11
2To reduce pressure drop in Raw mill through nozzle ring/
armor ring modificationIn progress
30/10/2018
(With S/D)5.71 22.4 27.65 15
3 Reduce pressure drop across PH down comer duct In progress30/10/2018
(S/D Req.)4.73 18.54 50.00 33
4
Replacement of Cement Mill area Cooling tower pump
with EE 60 m3/hr., 60 meter head and 65% efficiency to
save energy.
In progress 30.09.2018 0.41 1.60 1.00 8
5 Arrest air ingress in Boiler APH outlet to ESP outlet Completed 15.06.2018 0.32 1.26 1.00 10
6Install Boiler blow down heat recovery system to recover
blow down water heatPlanned 30.10.2018 0.68 2.67 4.00 18
7
Revamp the insulation on the main steam pipeline from
boiler to turbine to bring down the temperature drop
below 5 Deg C.
Completed 15.06.2018216.3 MT Coal
saving/yr10.5 10.00 11.00
8 Maintain TG vacuum to improve TG heat rate In progress15.06.2018 (a)
30.09.2018 (b)
511 MT Coal
saving/yr24.8 40.00 19.00
Future Energy Saving Projects
Sl no Location & Equip Modification Suggested
Expected
Saving KW
1 PH Stage III Cyclone
Existing cyclone cap of 6300 mm size is to be replaced with 6900 mm size
without changing the original roof height. Minor modification will be done at
the outlet duct to match with the existing arrangement.
119
2 PH Stage V Cyclone
Existing cyclone roof will be lifted by 500 mm along with the similar
modification to the connecting duct. Inlet duct dimension will change from
4477 x 2545 to 4977 x 2545 ii) Existing immersion tube length is to be
increased.
64
3 Raw mill
Installation of New generation classifier (LSVS) along with inbuilt Vortex
rectifier in Raw Mill to reduce power consumption 194
4 Alternate Fuel AFR Pre processing & Feeding system capacity encasement to save fossil fuel7452Mkcl /Year
saving of Fossil fuel
16
Summary of Energy saving Initiatives ( FY 2015 to 2018)
Sl NoYear of
Implementation Number of projects Savings In Rs Million
Total Annual Energy
Savings TOE
1 2015-16 6 3.25 66.62
2 2016-17 10 9.51 382.46
3 2017-18 5 9.94 446.06
Total 21 22.70 895.14
17
Energy saving Initiatives
18
Year Title of Energy Saving projectAnnual Savings
Rs (Million)
Energy saving
(MTOE)
2015-16
❖ Installation of VFD in 1st RO HP pump 0.16 3.19
❖ Installation of VFD in TPP Drag Chain Feeder 0.02 0.41
❖ Optimization in coal unloading & operation of crushing 0.30 6.17
❖ Installation of Turbo Blower for PC firing 1.00 20.50
❖ Kiln Auxiliary power reduction 1.76 36.06
2016-17
❖ Use of TPP fly ash in the pre-calciner having high Calorific value 7.98 351
❖ Removal of Pre collector Cyclone in the Coal Mill Circuit during Bag house conversion 0.14 3.39
❖ Coal mill nozzle ring modification 0.09 2.30
❖ Installation of Raw Mill Reject Handing System 0.17 1.01
❖ Installation of Cement Mill Reject Handing System 0.13 0.44
❖ Power optimization of RM BH rotary air lock 0.01 0.33
❖ pressure drop reduction in Pyro circuit by modifying PH cyclone-04 & PH fan inlet box
modification0.17 4.22
❖ Raw mill fan inlet box modification to reduce pressure drop reduction 0.13 3.14
❖ Reduction of pressure drop through Junction box & duct modification 0.18 4.29
❖ HPMH & HPMV lamps replaced with LED lamps provided in plant areas, truckyard,coal
tippler, CCR building and Colony areas.0.51 12.34
Energy saving Initiatives
19
Year Title of Energy Saving projectAnnual Savings
Rs (Million)
Energy saving
(MTOE)
2017-18
❖ Air ingress reduction in Raw mill 0.18 3.87
❖ Overhauling of TG 2.45 274.5
❖ Power factor improvement 7.39 162.97
❖ Install energy efficient fan for Packing plant Bag filter fan 612BF2 0.05 1.20
❖ Install correct size Raw mill Bag house fan ( Fan impeller Tipping) 0.16 3.52
20
Installation of In-House fabricated secondary & tertiary shredder with accessories
Challenge➢ As the source and type of Alternate fuel is changing unpredictably
in vide range, So the requirement of universal shredder machine capable to process different types of alternate fuel was felt.
Approach➢ Secondary & Tertiary shredder In-House fabricated and installed in
line with the primary shredder
Investment: Rs.28.0 Lac Savings : Rs. 60 Lac
Benefits :➢ Availability of processed alternate fuel to achieve AFR substitution
up to 40% ➢ Increase in % TSR from 13 % to 18% . Now Consistently sustaining
above 22 % by TSR AFR Shredder
Improvement Project :-01
Increasing Alternate Fuel Consumption
Problem statement :High pressure drop in Preheater Cyclone No :04
Preamble: RDCW have 5 stage ILC Preheater system having pressure
drop around 722 mmwc across preheater with PH fan power of 12.04
kWh/ton clinker.
During upgradation first and second stages cyclones were upgraded to
new design, where as other three cyclones are old with pressure drop
of 120-130 mmwg pressure.
Action Taken : Detailed study conducted and modified the cyclone
inlet area and Diameter of cyclone for pressure drop reduction and
power saving
Benefit : PH fan power reduced by 40 Kwh
Replication potential : YES
Pressure drop reduction across Cyclone-04
Improvement Project :-02
21
Installation of Turbo blower for kiln coal firing
Improvement Project :-03
22
Problem statement: High power consumption & High Noise level
Background : Twin lobe blower was installed for kiln coal firing It is belt driven
system & water circulation for cooling is required continuously. It consumes 70 Kw
power at rated flow of 33000m³/hr @ 0.5 bar.
Based on the performance of Turbo blower installed for PC firing and consultation
with OEM It was decided to replicate the same for kiln firing.
Execution:
Installed the Godrej turbo blower in place twin lobe blower for Kiln firing. It is direct
driven system & air cooled cooling system. It consumed power of rated flow
3300m³/hr @ 0.5 bar is 35kw.
Benefit : Tangible : 35 Kw per hour
{Source of idea : Presentation of M/s Godrej & Boyce on Turbo Blower during
Green Cementech 2014 at Hyderabad on 15 th -16 th May 2014}
Turbo blower
Utilization of Renewable Energy
2051093
1844096
1592363
20291432192542
1000000
1200000
1400000
1600000
1800000
2000000
2200000
2400000
Wind Power (Units)
Installed Capacity (5*225) KW
144974
136527
138791
142949
136624
132000
134000
136000
138000
140000
142000
144000
146000
Solar Power (Units)
100 KW Solar Plant
23
Utilisation of waste material as fuel
24
Alternate fuelAlternate fuel Consumption (MT)
2015-16 2016-17 2017-18
AFCARBONPOWDER 1819 3618 2764
AFETPSLUDGE 130 57 147
AFFIBREWASTE 439.07 81 159
AFFOOTWEARSCRAP 517 483 473
AFFMCGWASTE 2305 1057 780
AFMSWRDF 999 2233.1
AFOILSLUDGE 13
AFOILYCOTTONWASTE 274.54 334 610
AFPAINTSLUDE 1602 1370 1566
AFPLASTICWASTE 6430 7979 10669
AFSPENTCARBON 69 52 35
AFWASTEFUELTYRES 640.86 712 1326
AFWOODENDUST 9.49 1465
AFPHWASTELIQUID 38 12
AFCHARCOAL 88
8.349.6 9.62
10.94
13.00
18.16
22.94
6
8
10
12
14
16
18
20
22
24
12-13 13-14 14-15 15-16 16-17 17-18 18-19 Q1
Alternate Fuel Substitution % TSR
➢ Capex of Rs. 2643 lakh. sanctioned for Alternate fuel pre handling
and feeding system to achieve AFR substitution ( mainly Industrial
waste & municipal waste ) by 40 % TSR. Expected Simple payback
2.5 years
RECOGNITION FOR AFR utilization
MOU made Between M/S. 'UltraTech cement Ltd (UTCL) & Municipal Corporation of Tiruchirappalli (TMC) For “Disposal of Plastic waste from Municipal Solid Waste (MSW) through Co – processing in Cement Kilns”
159
MOU made with following Municipalities for MSW Supply at plant site
S. No Municipalities1 ARIYALUR
2 JAYANKONDAM
3 PERAMBALUR
4 PUDUKKOTTAI
5 KUMBAKONAM
6 SRIRANGAM
7 MAYILADUTHURAI
8 CUDDALORE
9 CHIDHAMBARAM
10 PANRUTI
11 NELLIKKUPPAM
12 VIRUDHACHALAM
13 KARAIKUDI
14 TRICHY CITY CORPORATION
15 AVADI
16 POONAMALLE
17 THIRUVERKADU
18 THIRUVALLUR
19 Chengelpet
20 Madurantakam
21 Manapparai
Net CO2 Emissions
601
577
565556
541
500510520530540550560570580590600610
2013-2014 2014-15 2015-16 2016-17 2017-18
Kg CO2/MT Cementitious Material
The First Cement Company in the World to earnCarbon Credits by using alternate fuels and earned52 million selling credits to Europe already part ofthe Aditya Birla Group in 2007
26
Green Supply Chain
INITIATIVES
Green Supply Chain Policy rolled out
Reverse Logistics
Development new Material sources – Nearby area…Lead Reduction
ARC’s & AMC’s…..Supplier engagement
Procurement of Energy Savings Motors (IE-3) & appliances(5 Star
Rating electronic products & LEDs etc.)
Green Packaging :Developed Returnable Boxes (GI Box ) for
packaging in place of Carton Wooden Box (within the lead distance
of 100 Km
On-line payment system
Development of Supplier Portal (Emptoris.)
Vendor Managed Inventory (VMI)
Implemented sending soft order copies to all supply vendors instead
of hard copies.
Procuring of 75 GSM paper instead of 80 GSM
38
Awareness for vendors
39
By HOD (Mtrls.) on GSC Co2 emission Energy conservation Water conservation
Interaction with vendors
29
ENERGY MONITORING & REVIEW SYSTEMS
29
To measure, monitor, trend & compare power consumption of all major
systems/ sub systems/ auxiliaries for improving Sp. Energy Consumption
Energy monitoring System
❖ Online monitoring
❖ Report generation and archiving is possible
❖ PI system available in all PC and every engineer can monitor all
parameters.
❖ Daily Report on Utilization of Various Fuels.
❖ Useful for analysis of operational deviation
Energy Optimization
❖ EO system results in optimized and smooth operation of the plant and
very minimal operator intervention is required in plant operation.
Plant performance Review Mechanism
❖ Daily Power & Production variance review meeting {FH(T)+DH+SH}
❖ Monthly Plant performance review meeting {UH +FH+DH+SH}
❖ Monthly Communication meeting {UH +all employees}
30
Budget for Energy saving projects
Note : Capex for the Projects having energy saving potential is raised through UH at any point of time & energy savings projects are
given priority.
31
Plant Colony
Workers colony
Govt.School, Reddipalayam
Plant
Vallalar Middle School
Thelur Govt. High School Awareness Street Play
Awareness & Training
Energy & Water Conservation
▪ Creating awareness by celebrating Energy conservation Week
▪ In-house training conducting to all employees
▪ Awareness creating to all Colony residents
▪ Awareness creating to workmen's through pep talks
▪ Awareness through various competitions to Staff, Workmen, School
children and Colony residents
In-house training for employeesEmployee recognition
32
Awareness & Training
Energy & Water Conservation
Green Belt Development
39 % of total area covered with tree
plantations as against 33% of statutory
norms
Survival rate - 96%
33
Green Initiatives
On the eve of World Environment day a Green Walk along with “swachh bharat abhiyan” was organized at surrounding
areas to create awareness among villagers. The whole work force was divided in four groups headed by Function
heads and cleaned the common public places. A large number of villagers also joined Voluntarily to make the area
clean. Program was concluded with sibling plantation at plant and honoring the hygiene workers of municipality
34
Swachh bharat abhiyan outside of the plant & market
AWARDS & ACCOLADES
35
RDCW has been awarded the “ Green Co” - Gold
Certification by Confederation of Indian Industry in
accordance with the Green Company rating system.
This award recognize the significant contribution of
RDCW in the area of energy reduction, environment
and sustainability performance.
RDCW is among few companies in India and first in
our cement business to be certified under Green Co.
RDCW was measured on ten parameters and
environmental practices. The Green Co drivers for
excellence are- Energy Efficiency, Water
conservation, GHG emission, Waste management,
Material conservation, Recycling, Recyclability,
Green supply chain, Renewable Energy, Product
Stewardship and Life Cycle Assessment.
AWARDS & ACCOLADES
RDCW has been awarded “Most Innovative Project” for the Best Practices in Waste
Management by CII GreenCo Best Practices Award 2016.
36
State Government Safety Award Greentech Safety Award
AWARDS & ACCOLADES : Safety
❖First place for best safety practices “SAFECON 2015” by CII
❖State Level Safety Award from Tamil Nadu Government (1999,2000, 05, 06 & 08)
❖Safety Appreciation Award from NSC Tamilnadu Chapter 2003
❖Greentech Safety Award - Bronze in 2006 , Silver in 2007 & Silver in 2010.
❖Two First Prizes State Level Safety Award from Tamilnadu Government (2005 & 2006)
❖Global Cement Awards Lowest Injury Incidence Rate – First prize ($1000).(2006)
❖Golden Peacock Award GPOHSA 2009 & 2010 .
SAFECON 201537
❖“GreenCo Gold’’ certification by CII-Green Company Rating System – 2015
❖National Excellent Energy Efficient Unit Award by CII – (2009, 2010, 2011, 2013, 2014, 2015, 2017 & 2017)
❖National Energy Efficient Unit Award by CII (2004, 2006,2007, 2008 & 2012)
❖Global Cement Awards, Lowest Specific Energy consumption, raw meal & clinker grinding – 2006
❖NCCBM Best Electrical Energy Performance Award 2008-09
❖NCCBM Second Best Improvement in Thermal Energy Performance Award 2008-09
CII Energy Awards
AWARDS & ACCOLADES : Energy
38
❖ Green Manufacturing Excellence Award by Frost & Sullivan 2013,2014,2015,2016,2017
❖Tamil Nadu Pollution Control Board - Green Award 2012
❖ FIMI National Award in Environment -2014
❖ GreenTech Environment Excellence - Silver Award 2006 & 2009 & Gold -2012
❖ Global Cement Award Lowest specific CO2 emission - 2006
❖ Most Innovative Scheme for environmental impact abatement - 2006
❖ FICCI Environment Sustainability of Business Award 2006 – 2007
FIMI National AwardTNPCB GREEN AWARD Frost and Sullivan GMEAFrost & Sullivan Leader award
for Sustainability 4.0
AWARDS & ACCOLADES : Environment
39
Thank you
40