1981: refrigerated ammonia storage tanks insulation
TRANSCRIPT
ChicagoBridge& Iron
CompanyCBT-5393
REFRIGERATED AMMONIA STORAGE TANKSINSULATION SYSTEMS, DIKING AND PURGING
By: Jay M. ShahSupervising Design Engineer
Chicago Bridge & Iron CompanyOak Brook, Illinois 60521
For Presentation at The26th Symposium on Safety
In Ammonia Plant andRelated Facilities.Montreal, CanadaOctober 5-9,1981
R1FRIGERATID AMMOMA STORAGE TANKS
INSULATION SYSTEMS, DffilWG AND PUHGING
Bys Jay M. Shah
Supervising Design Engineer
Chicago Bridge & fron CompanyOak Brook, ülinois 60521
For Presentation at The26th Sympc«ium on SafetyIn Ammonia Plants andRelated Facilities.
Montrealj CanadaOctober 5-9, 1981
ABSTRACT
Various designs of refrigerated ammonia storage tanks and insulation systems that are
commonly used are presented. Some design considerations for secondary containmentsystems for ammonia facilities are provided. A procedure is given for placing an ammoniatank in service and also for taking a tank out of service for inspection, repairs ormodifications.
REFRIGERATED STORAGE TANKS
Large flat bottom tanks are designed for near atmospheric pressure, generally l to 2 psig
(6895 to 13790 pascal). Tank walls are cylindrical, roofs are either spherical or ellipsoidal
and bottoms are normally flat or slightly cone shaped. The tank rests upon some form ofload hearing insulation which transmits the weight of the contents to the foundation andground beneath the tank. Anchorage for flat bottom tanks must hold the shell down
against uplift forces from wind, earthquake and internal pressure acting under the roof.Anchorage must also permit the vessel to move radially in response to temperature
changes. A system of anchor bolts or straps attached to the tank shell embedded inconcrete is normally used. The weight of concrete must be greater than the uplift forces.
Ammonia tanks are generally designed in accordance with API Standard 620 Appendix R.This standard is prepared specifically for low temperature tanks suitable for the storagetemperature of ammonia at -27<>F (-33<>C) and even lower temperatures for the storage ofother refrigerated products. The material of construction is normally high manganese
carbon steel which retains its notch ductility at low temperature. These materials arelisted in API 620 Appendix R and include A537 and A516 Grades 60 and 70.
INSULATION SYSTEMS
Flat bottom tanks can be of two types, different primarily in the type of insulation system
used. A conventional doublé wall tank (essentially tank within a tank), Figure l, has the
insulation distributed in the annular space. Loose fill perlite is the primary insulationused in the shell and roof of a doublé wall tank. This insulation system requires a dryinterstitial gas to protect the insulation. The outer tank is usually designed for about 2
inches (50 mm) of water pressure. The outer tank normally is not designed for holdingliquid ammonia.
An economical modification to the conventional doublé wall insulation system is thesuspended deck insulation concept whieh CBI introduced in 1966. Figure 2 shows thisconcept* This insulation system eliminates the inner tank roof. The prineiple is similar tothe suspended ceiling in a building where insulation limits the heat transfer to or from thespace below.
A widely accepted and eeonomieal insulation system is a single wall tank with externalinsulation as shown in Figure 3. The vessel wall is insulated with rigid polyurethanefoamed-in-place between the shell and an aluminum jacket. The inside face of the
corrugated aluminum sheet is primed with a coating designed to enhance adhesion
between the jacket and the foam. The exterior surf ace is coated with an alkyd orpolyester enameL The suspended deck type insulation is also used for single wall tank
because it provides maintenance free inexpensive roof insulation. Externally appliedïnsulation on curved roof surfaces can be used but will require maintenance and issusceptible to damage from natura! phenomena sueh as high winds etc.
Single wall insulation can be repaired while the tank is in service. The damaged portion is
cut out, a new piece of aluminum vapor barrier is fastened in place, and new foam isexpanded into the patch area through a small filling hole. Block urethane patehes and
hand spray techniques may also be used.
Single wall insulation systems should be inspected at least once a year. Inspection and
maintenance for single wall insulation system consists of inspecting the jacket seams andthe jacket to foundation connection to assure that all fasteners are snug and the jointsclosed. Open areas should be recaulked and pulled tight.
DIKING SYSTEM
The American National Standard, "Safety Requirements for the Storage and Handling of
Anhydrous Ammonia", (ANSI K61.1-1972) stipulates that dikes or drainage be provided toprevent accidentally discharged liquid from spreading to uncontrolled areas.
Secondary containment should be provided to satisfy specific project needs for each
project. A seeondary containment system should be selected which will meet the needsfor limiting the hazards, but which also considers operator safety, plant operation andconvenience of inspection and maintenance. Design of the seeondary containment system
will be influenced by such characteristics of the site as its dimensions, topography, soil
conditions, ground water conditions and the use and occupation of adjacent and nearbyproperties and waterways.
The following four types of secondary containment systems are commonly used:
1. Remote impounding basins serving one or more tanks.
2. Earth dike or low wall impounding system surrounding one or more tanks.
3. Non-integrated, high wall impoundment around a single tank. The tank andcontainment systems are structurally independent.
4. Integrated high wall impoundment incorporated into a single tank. The tank andcontainment system are not structurally independent.
The remote impounding basin utilizes the natural topography augmented as necessary byexcavation and diking. Dikes, and channels around the tanks direct the flow to the
impounding basin with a minimum exposure to other tanks and surrounding facilities.
Earth diking surrounding one or more storage tanks is the most common type of secondary
containment system used (Figure 4). Dike heights usually range between three to twelvef eet. The clearance from dike to tank provides for access to the tank and space to locate
equipment near the tank. The floor of the impounding area is sloped or contoured todirect spilied product away from the tank to a sump or low area. The dikes are normally
eonstrueted of compacted earth but reinforced concrete can also be used or combinedwith earth.
Non-integrated high impounding walls structurally independent of the tank may be of low
temperature steel, reinforced concrete or prestressed concrete construction (Figure 5).With the wall close to the tank, it is important that the structural independance of tankand wall including independence of foundation support should be maintained. If pumps are
located outside the wall, the wall is penetrated by pump suction line and the pipe forms
part of the secondary liquid boundary. In such a case a remotely controlled shutoff valveshould be provided inside the dike and also outside the dike wall. Also a low dike
encompassing the pipe and the pump should be provided as well as other safety features to
minimize the potential hazards.
An integrated containment concept (Figure 6) has the appearance of doublé wallconstruction. Both inner and outer tank walls and bottoms are made of low temperaturematerials. The primary and secondary containments are supported by the samefoundation. Piping penetration through the primary and secondary containers is necessaryif pumps are located outside the tank. Foundation failure and pipe break are credible
events. To contain product spilied as a result of these events, a supplemental dikesurrounding the integrated containment system is desirable.
PROCEDURE TO PLACE AMMONIA TANK IN SERVICE
The suggested procedure described here is very generalized in nature. There are many
details and considerations which vary with each individual project and should beconsidered for placing ammonia tank in or out of service. The following procedure
assumes that the tank is at ambient temperature and contains air.
(1) Nitrogen Purge
Air and ammonia gas mixed in the ratio of 15.5 to 26.6 percent ammonia in air create aflammable mixture. The hazard of fire or explosion can be reduced in a tank being purged
with ammonia by decreasing the oxygen content to a safe concentration before admittingthe ammonia. The recommended purging end point is 12.5% oxygen by volume (this
includes a 20% saf ety factor) when nitrogen is used as a purging gas. (D
Nitrogen purge gas normally enters the tank at the bottom and flows up through the
suspended deck vents and into the vapor space in the dome. The purge gas is exhaustedthrough the relief vents and through the dome vents.
During intial purge the flow of N2 in the tank should be kept at a reduced rate tominimize the mixing. In actual practice displacement purge is difficult to achieve and
some mixing takes place. Experience indicates that nitrogen required to purge the
ammonia tank is about l i times the tank volume.
(2) Ammonia Purge
For the ammonia purge of the tank all venting should be done through a flare, if available,
otherwise exhaust gas should be vented at a safe location. Purging is normallyaceomplished by flowing ammonia vapor into the top of the storage tank. The warmammonia vapor being lighter than nitrogen, will form a pocket in the top of the tank. The
purge is intended to slowly piston the nitrogen out through the bottom nozzle and out tothe flare or vent stack. Since pistoning out nitrogen is quite effective, purging shouldcontinue until vapor composition in the tank is higher than 95% ammonia by volume.
(3) Tank Cooldown
Prior to establishing a high fill rate of cold ammonia liquid, the tank should be cooleddown gradually to avoid high thermal stresses. Admission of cold liquid to a tank bottom
may cause buckling of the bottom due to thermal stresses between the local area which iscooled and the remainder of the bottom. The local buckling could cause deformation orpossible damage to the bottom plates. It is recommended that the cooldown nozzle forammonia be located at the top and the location of the nozzle be such that severe local
cooling does not occur. The cool-down nozzle should be provided with spray ring or splashcap for uniform liquid distribution. The cooldown line should be used for liquid service
during initial cooldown only. Cooldown should be considered complete when liquid startsaccumulating at the bottom.
PROCEDÜEE TO REMOVE AMMONIA TANK OUT OF SERVICE
The following procedure assumes that the tank contains cold liquid ammonia.
(1) Liquid Removal
As mueh liquid ammonia as possible should be removed by pumping out of the
storage tank. It may not be possible to completely empty the contents of the tankby pumping. Residual ammonia liquid can be removed by injecting warm ammoniagas to vaporize the remaining liquid in the tank.
(2) Tank Warm-Up
Warm ammonia gas should be introdueed into the bottom of the tank through the
pump suction or other line. The purge gas and vaporized ammonia is dischargedfrom the top of the tank through the vapor withdrawal line to the flare or to theammonia refrigeration or processing plant. Caution must be exercised inintroducing the warm gas so that the tank design pressure is not exceeded andexcessive temperature differences are not created in the tank bottom. The warmgas flow should continue until the tank bottom temperature is above 32<>F (0<>C).
(3) Nitrogen Purge
Dry nitrogen gas should be introduced into the bottom of the tank through pumpsuction line and discharge the effluent from the top of tank through the vapor
withdrawal line to flare or a safe vent point. Nitrogen purge should continue untilthe ammonia concentration is bèlow 15%. The vent nozzle on the dome should be
opened and purging should be continued.
(4) Air Purge
After the nitrogen purge has been completed and tank shell temperature is abovethe dew point of air, fans should be connected to the pump suction nozzle and relief
valve nozzle. Make sur e that the tank is isolated from any ammonia source byphysically disconnecting all process piping. The roof vents should be open wide and
roof manhole should be open part way. The fans should be turned on to force airinto the tank. The exhaust gas from the tank should be monitored to determineconcentration of ammonia and nitrogen in the air being exhausted. When it isdetermined that it is safe to enter the tank, a pressurized air source should be
connected to the purge vent on dome of the roof. The air source should be able toprovide one air change per hour in the dome area to remove a possible build-up ofgas.
(5) Inspection
After the inspection and/or repair tank should be placed in service following the
procedure described in previous section.
BÏBLIOGRAPHY
(1) "Purging Principles and Practice", American Gas Association, 1975.
(2) D. M. Morrison and J. J. Aarts, "Refrigerated Storage Tank Retainment Walls",Presented at the Safety Symposium for Ammonia Plants, Portland, Orgeon, August
17-20, 1980.
(3) C. C. Hanke Jr., I. V. LaFave, and L. F. Litzinger, "Purging LNG Tanks into and outof Service Considerations and Experience". AG A Distribution Conference, May 6-8,1974.
(4) "Low Temperature Storage", CBI Bulletin No. 8400.
INNER KOOF
LOOSi F1LLPERLITE
INSUtATION
. RESiliENT3LANKET
fNNIR TANK
OUTEB TANK
ANCHOiAGl
CONCSETitlNGWALL
NDATIONLOAD BEARING
INSULAÏIONHEATING COILS
IN SANOOUTE1 STIEL
BO' iOTfOM
Figöre 1The Doublé Wall Wlth The
, Corswentional Inner Tank
SUSPËNDEDi NSU LATINGDECK
LOOSE F1LLPERLITEINSULATION
EARTHEM-ADiKE
SELF-SUPPORTINGTANK ROOF STA1R AMD PLATFORM
INNER STEELTANK "GOLD"
OUTER STEELTANK"WARM"
R ESI LI ENTBLANKET
INNER STEELBOTTOD"GOLD"
ANCHORAGE
CONCRETERINGWALL FOUNDATION
HEATtNG.COILS
LOAD BE AR INGINSULATION
OUTER STEELBOTTOIVS
Figyre 2Doublé Wali Tank Wlth Sospended losylatiog Deck
SUSPENDEDSNSULATiNGDECK
POLYURETHANEINSULATtONBONDED TO METALJACKET AND TANK WALL
METAL JACKET
ANCHORAGE
EARTHEN _\DiKE
SELFSUPPORTINGTANK ROOF
STA! R PLATFORMAND PIPING TOWER
STEELTANKGOLD"
CONCRETERING WALL FOUNDATION
HEATINGCOILS
LOAD BEARINGINSULATiON
STEEL BOTTOM"COLD"
Figure 3Single Wal! Tank
4
SELF-SUPPORTINGTANK ROOF
STAIR PLATFORMAND PSPING TOWER
SUSPENDEDSNSULATINGDECK
Al R SPACE
PRESTRESSEDCONCRETEDIKE
POLYURETHANEINSULATIONBONDED TO METALJACKET AND TANK WALL
METAL JACKET
ANCHORAGE
CONCRETERINGWALL FOUNDATION
STEEL TANK"GOLD"
__HEATINGCOILS
LOAD BE AR ING STEEL BOTTOfVtSNSULATION "COLD"
Figure 5Singie WaS! Tank With Concrete Dike
SUSPENDEDINSULATJNGDECK
POLYURETHANE SNSULATIONBONDED TO METAL JACKETAND TANK WALL
SELF-SUPPORTINGTANK ROOF
\
STASR PLATFORMAND PiPING TOWER
INNER STEELANK "COLD"
OUTER STEELTANK "COLD"
VAPOR SPACE
METAL JACKET
ANCHORAGEINNER STEELBOTTOM
CONCRETESEPARATION
SLAB
EARTHENJ CONCRETEDIKE RINGWALL FOUNDATION
HEATING.COILS
LOAD BEARSNGINSTALLATION
OUTER STEELBOTTOM "COLD"
Flgure 6Entegrated Low Temperature Tank