1981 1982 in visit/9_official... · 2008. 6. 18. · department of energy wave energy steering...
TRANSCRIPT
DEPARTMENT O F ENERGY
WAVE ENERGY S T E E R I N G COMMITTEE
U N I T E D KINGDOM WAVE ENERGY PROGRAMME
CONSULTANTS' 1981 A S S E S S M E N T
P R E L I M I N A R Y I N F O R M A T I O N
MARCH 1982
RENDEL PALMER & T R I T T O N C o n s u l t i n g E n g i n e e r s , 61 S o u t h w a r k S t r e e t , L o n d o n S E 1 1 S A
I n A s s o c i a t i o n w i t h : KENNEDY & DONKIN C o n s u l t i n g E n g i n e e r s , P r e m i e r H o u s e , W o k i n g , S u r r e y G U 2 1 1 S G
INDEX
1. Status of the Document
2. Some Preliminary Conclusions
3. Comparative charts and tables
Key Summary (Fig 1)
Energy Cost Make-Up Sheet (Fig 2)
Undiscounted Capital Cost 2GW Scheme (Fig 3)
Discounted Total Cost of Scheme per Metre of Structure (Fig 4)
Discounted Cost of Energy (p/kWh)(Fig 5)
Discounted Cost of Air Devices by Function per Metre Length (Fig 6)
Discounted Cost of Air Devices by Function for the 2GW Scheme (Fig 7)
Energy Costs of Air Devices by Function (Fig 8)
Device Capture Efficiencies in the 46 S.Uist Spectra (Fig 9)
Comparison of Device Capture Efficiency (Fig 10)
Comparison of Mean Annual Power Captured per Unit Length of Structure (Fig 11)
Comparison of Overall Station Efficiency (Fig 12)
Comparison of Mean Annual Power Landed per Unit Length of 2GW Station (Fig 13)
Relationship between Captured Power and Swept Volume (Fig 14)
Comparison of (Swept Volume) (Structural Volume) by Device (Fig 15)
comparison of (Mean Annual Power) (Cost of Anchoring the Device) (Fig It
Comparison of (Mean Annual Power) (Total Anchor Force Provided) (Fig 17)
Civil Construction Requirements for 2GW Installation (Fig 18)
4. Notes on Specific Topics
(i) Basis of Costing Civil Construction
(ii) Costing of Device Installation
(iii) Costing of M and E Plant and Transmission
(iv) The Framework of Cost Appraisal
(V) Assessment of Availability
(vi) Data Used in Productivity Assessment
(vii) Assessment of Productivity
5. Device Data Sheets & Notes
(i 1 Bristol Cylinder
(ii) Lancaster Flexible Bag
(iii) Oscillating Water Coluinns
a. NEL Bottom Standing Terminator
b. Vickers Terminator
c. Vickers Attenuator
d. Belfast
e. NEL Floating Terminator
f. NEL Floating Attenuator
(iv) Edinburgh Duck
(V 1 Lanches ter Clam
6. Where the Money has Gone
(A pull out illustration giving allocation of costs)
7. What is the Available Resource at South Uist?
1. S T A T U S O F DOCUMENT
AND
2 . SOME P R E L I M I N A R Y C O N C L U S I O N S
Data Base
STATUS OF THE DOCUMENT
At 30th November the information from Device Teams was
incomplete in many areas, and changing almost from
day to day. This was in part because lessons learned
from tank testing, or costing of designs were being
applied to produce revised designs very late in the
programme. In other cases late or incomplete testing
and designing simply had not produced the data needed.
Numbers produced for E.T.S.U. at that date were totally
unreliable and declared to be so by R.P.T.
In the case of some Teams, interaction with R.P.T. early
in December and the results of the first costing exercise
stimulated significant and urgent redesign to improve cost
effectiveness, so that up to the present date 3.2.82,
new data is still being presented to the Consultants,
and in the absence of calculations, this has had to be
validated by experience and extrapolation.
However, advantage has been taken by R.P.T. of the areas
of similarity between devices to fill in missing numbers,
and to correct obvious anomolies, so that the overall
picture is more reliable than would otherwise be the case.
During the period since November 1981 the opportunity has
also been taken to cross fertilise between devices and
to credit all devices of a type with any particularly
cost effective solution that can be of general benefit.
An important result of late design development has been that
for some devices (NEL, Bristol) the design offered for
assessment is different in some measure from the design
tested in the tank. Alternatively, for other devices,
time and resources have not allowed adequate testing.
In these instances the production of reliable productivity
data has been impossible, and important questions remain
to be answered in further testing.
Productivity is crucially dependent on the power flux in
the sea, and this is perhaps equally uncertain in deep
and shallow water. The main problem is the uncertainty
surrounding the directionality of the energy in the sea.
A short paper is included on this topic.(See Section 7).
There has not yet been enough data, or enough time for
analysis to produce the cost distributions which are the
ultimate requirement from the assessment. Fig. 3 uses
a star rating to identify broadly the security of data.
Compared to previous assessments, there is greater
certainty concerning the predicted costs of the civil
structure. Other very important areas, such as
availability were dealt with globally in previous years and
are now the subject of proper analysis, albeit from a weak
data base.
In summary, across all devices, the following broadly
applies. In rough order of certainty we would list
Civil Engineering Structure (well defined)
Transmission Costs (based on recent tenders)
*~oorings and gravity Anchors (unit pricing well defined)
M&E plant (incompletely specified undesigned, novel)
Installation of Bottom Mounted Devices (many uncertainties)
Productivity (many assumptions)
Availability
Maintenance
(no very helpful (experience for data (base
Interpretation from the data base
Overall the Consultants have the sense that they are
seeking to place firm numbers on to devices which are
in some cases still evolving by step changes. Combined
with the weakness of the data base itself, the result can
not be other than unsatisfactory, and there is the
strongest feeling that more time is needed to study and
analyse the data so recently presented.
This said, a number of trends can be discerned, and some
conclusions can be drawn which are unlikely to be
overturned by the six month's work which most teams still
have ahead of them.
2. SOME PRELIMINARY CONCLUSIONS
1. TWO devices are clearly internally uneconomic, or less
good than other similar devices and can be dismissed from
further consideration. These are :-
Belfast
N.E.L. floating attenuator
2. The Lanchester Clam has a combination of identifiable
good features which satisfactorily explain its present
position as the most economic air device, but closer
examination is needed to determine just how good it is - and if it could be made even better.
3. The relatively close grouping of the air devices in overall
economic terms conceals a key difference between them.
See Fig. 6 and Fig. 10. The fixed NEL Terminator
combines high cost of structure and installation with
high efficiency because of its fixed reference frame.
Conversely the compliant spine of the Clam confers low
structure cost and lower efficiency. The submerged
Vickers devices see less power and have to survive lower
forces.
A very careful comparative study and analysis of these
designs is required to determine where,in the spectrum of
compliance and productivity,lies the optimum pneumatic
device. This must precede any decisions to go forward
with or to reject specific pneumatic devices.
4. The very high forces attracted by fixed devices, and
the potential cost of locating them on a rocky bottom in
shallow water is a key factor in pushing up their cost.
Typically a breakwater is resisting 1 0 0 to 300 times the
force resisted by the compliant mooring of a floating
device of the same length.
5 . Pneumatic devices are predicted to have high availability
on the basis of current technology, (in contrast to
hydraulic power take offs).
6. Consideration of Fig. 8 shows the somewhat surprising
fact that it costs as much to get the power out of the
air,to Skye as it does to get the power out of the sea
into the air. Much more work has been done on the
latter, and instinctively one might expect that the
greatest scope for cost savings probably lies with the
M&E side .......
7 . ..... Transmission is seen to be an almost crippling on-cost to all schemes, There is a factor of almost five dividing
the conceptualcosting of Merz McLellan for a future
scheme and the hard contract price for a current project
in the English Channe1,which K&D have used for the #
Consultants assessment.
The key raw material of the copper is less than 2% of the
final cost of the cable as laid. This is an unusual
ratio, which seems to offer the prospect for a
possible technical breakthrough in the future.
8. The Duck is a device which is conceptually almost perfect
as a power absorber and converter, but requires a level
of reliability in hydraulic components one to two orders
above that allocated by YARD. Should this prove to be
achieveable, then the device could realise its target
availability, and the conceptual cost of power wduld
become a reality and the device would be a winner.
It is important to appreciate that the fine matching of the
power take off to the incident waves is made possible by
the hydraulics and is not available to other devices,
although 'latching' can give useful benefits to
pneumatics.
The Consultants believe that there is not evidence enough
to conclude at this time that the performance specified
by the Duck team will not be available in the future,
and a considered view must be taken of this device for
the medium to long term.
9. The Bristol Cylinder has not yet fulfilled the high
expectations which were engendered two years ago by its
elegant hydrodynamics. The high costs of installation
and power take-off have led to disappointing high cost
of power, even allowing for a degree of tuning and an
optimised cylinder design which have still to be proved
in tank testing.
It is interesting to note that this device is in fact
conceptually the non symmetrical,terminator,version of
the TI device which has been studied for TAG 1.
TI is a point absorber with power extracted from the
heave motion, but no power extracted from the surge.
The cylinder extracts from the surge also, thereby
doubling the theoretical efficiency . TI has been
costed out cheaper than the cylinder. A careful
comparison needs to be made to establish if there are
lessons to be learned that can improve the cylinder
significantly.
Answers to this question can probably be obtained
within the remainina period of the McAlpine Contract,
The potential benefits of tube pumps have already been
admitted to the current costing exercise.
3 . COMPARATIVE CHARTS & TABLES
n m m
D I S C O U N T E D C O S T O F ENERGY ( P I k W h )
\ \
- A N C A S T E R /// // X/)CJ j \ \ ; \ \\1 = L E X I B L E
EDINBURGH I U C K
l//" K x f l \l
3 A G
Y E L F L O A T I N G 4 T T E N U A T O R
/'////KN,\X%i<X):I\'\\' X\'\\\] \, '.
/ ,S'
N E L BTM. STDG. T E R M I NATOR
// ,,' / L i
NEL F L O A T I N G T E R M I N A T O R
V I C K E R S TERM1 N A T O R
A>. \
V I C K E R S ATTEN UATOR
~////'///i"xx>ch\\\l
K E Y TO F U N C T I O N S '
N E L B T M S T N D G TERM.
V 1 C K E R S A T T E N .
V l C K E R S T E R M .
P R O V I D E R E A C T 1 O N S U R F A C E
R E S I S T W A V E I N D U C E D F O R C E S
C O N T A I N A I R 1 W A T E R
C O N V E R T P O W E R
T R A N S M I T
S E L F A S T
L A N C H E S T E R C L A M
L A N C A S T E R F L E X I B L E B A G
N E L F L O A T I N G T E R M .
( P l kSn/h) C O S T OF A B S O R B I N G E N E R G Y I N T O A I R 1 C O S T OF E X T R A C T I N G E N E R G Y F R O M A I R ( P l k W h ) A ' I
* 8 6 4 2 0 2 4 6 8 10
Device Capture Factors in the L6 South Uist Spectra
LFB Clam.
J ~ - - - - - - - - - - - - - + L 6 8 10 12 1L
Te ( sec) Te (sec)
C Bristol Cyl inder.
Tile r c s r i l t s f r ~ l m 1-hc Clam and n r i s t o l (:y L i n d e r have hi?i.n f u r t h e r m o d i f i e d t o t n k e a c c o u n t o f chnngcs i n d e v i c e c r , n i i j i u r a t i o n i n ordc.r t o . l r r i v e a t t h e meal1 a n n u a l p r o d u c t i v i t y ( s e c s ~ c t i o i i s L ( v i ) , 4 ( v i i 1, 5 ( i ) and S(..,)).
4. Tiic ii~cari povcr c l c n s i t y r ~ s r d I ~ a s becn t h n t s p c c i f i c d i n t h e
f u l l s p c c t n ~ m s n i t . ih ly r r o n s f o r m e d t o t h e c o r r c c t d e p t h ( : : i ,ct ion h ( v i i ) ) , i n c l u t l i n g t h o s r i .omyonrnts nnL m o d c l l e d h y t h e wave t ;~r tk .
Figure 9 .
5 . I h r c l 1 a r a c t c r i . ; t i c d ~ m e n s i n n h , ~ s b e e n t a k e n as i l e v l c c l c n g c h f o r a l l e r r e p t t l i r V i c k c r s A t t e n c l a t o r w11c.r~ t h e , . . . 3 L . , . .
1 . . ffl 0
I I I I I
NEL FC TNG ATTEN
VICKERS 1 ATTEN
L F B
4
VIC KERS TERM
.h
LANCHESTER CLAM
N E L FLOATING TERM
N E L BTM STNDG TERM
EDINBURGH DUCK
BRlSTOL CYLl NDER
BELFAST DEVICE -
'M STNDG TERM i
l 1
I
U R G H D U C K
N.E.L. F l t g P Atten.
b L.F. B.
L a n c h e s t e r C l a m .
N.E.L. F l t g . Term,
B e l f a s t D e v i c e
V i c k e r s Term.
Bristol Cyl i nder
Vic kers Atten.
E d i n b u r g h Duck
N.E.L. Btm. stndg. Term.
I - C:,
COMPARISON OF S W E P T V O L U M E BY D E V I C E ( A T RATED POWER)
STRUCTURAL VOLUME
0 BELFAST N E L N E L B T M N E L
F i T N b S I N U G F L T N G -
A T T E N T E R M TERM
L F B V I C I E R S C L A M V I C K E R S D U C K B R I S T O L AT TEN TE HM
Comparison o f Mean Annual
Power per Ern Spent Anchoring
and I n s t a l l i n g t h e D e v i c e
F ig . 1 6
U (lJ W
5 ~ 3 . 0 - -c= ' U 0
"'& ' -4 -W 0 U
L - O 2.5- W ? - > a, a,' -J 07
m L L aJ 0
B-'= O 3 . 0 - n
4
C - m m - #
Cornoarison o f Mean A n n u a l P o w e r p e r Tonne o f A n c h o r a q e F o r c e P r o v i d e d
I J W I I
4.NOTES ON SPECIFIC TOPICS
4 . (i) BASIS OF COSTING OF CIVIL CONSTRUCTION
In view of the difficulties which had arisen in previous years, when
Device Teams costed independently and the Consultants attempted to rationalise
the results - with the inevitable conflicts which arose - for the present round of reporting it was decided that the Consultants would circulate a
\+?orking Paper setting out the approach for the Teams to adopt.
The Working Paper was prepared by a small committee which included
representatives of many of the Device Teams. This ensured that any special
points which the Teams wished to explore were adequately covered and helped
the results to gain general acceptance.
The Working Paper set out standard rates for the most important items
which could be anticipated in a Bill of Quantities and explained in great
detail how these rates were derived.
The detail included rates for labour, plant and materials with build-ups
of on-costs for such things as bonus, sick pay, site offices, overheads etc.
It gave productivity rates so that a Team could check the amount of labour
and plant assumed for a given operation. This Paper also set out (where
appropriate) the limits of applicability of rates. Thus, having the derivation
of the rates, Device Teams were in a position to develop their own rates should
it be felt that the standard rates were inapplicable. The intention was that
this would be the exception rather than the rule.
With this approach, problems of costing were limited to those associated
with the justification for the adoption of a special rate, and the assumptions
made in its derivation.
In order that everything was on a common basis, all rates etc. were
based on those applicable at Hunterston. For this purpose the area at
Hunterston was assumed to be infinitely large and with adequate water depth
at a convenient distance offshore. With this assumption a standard construction
facility, capable of an output of 200,000 cu m of concrete per annum, was
costed. The variable covered in the Working Paper related to the manner in
which the device was launched. Teams had the choice of ship lift, slipway or
flooded basin.
Although all construction facilities were to be norinally at Hunterston,
the intention was that the concept would represent a series of such facilities
at various suitable sites in Scotland. In the event, Teams developed single
larger facilities which indicated economies when compared with the use of
multiple standard facilities. While it is accepted that such an approach could
lead to some economy it could also lead to greater labour difficulties and
4/(i) 11
possible environmental problems. For these reasons, and in order to retain
uniformity of pricing throughout, the most likely costs quoted have in all
cases been based on the use of standard sized facilities but a suitably
weighted design tolerance has been postulated to allow for the possibility
of economies arising from use of large facilities.
THE COSTING OF DEVICE IXSTALLATION
Device installation is one of the most difficult aspects of Wave
Energy to cost. It involves the following:-
1. The development of a feasible overall method of installation.
2. The selection of appropriate marine craft.
3 . The assessment of the time necessary to carry out each marine
operation making up the overall installation method.
4. The assessment of the sea state in which each marine operation
can be undertaken.
5. The statistical likelihood of, and waiting period for the
occurrence of various sea states at the different water depths
in which the Teams propose to site their devices.
Although periodsof good weather can occur at any time of the
year, taken statistically over the lengthy period required for
installation of the devices necessary for a 2GW station, these
factors obviously vary with the season of the year.
6. The further limitations (where appropriate) due to daylight,
fog or current.
7. The costing of the marine craft involved.
In order to assist, the Consultants produced a Working Paper giving
the statistical parameters relevant to 5 and 6 above, and EASAMS gave
iriformation on the cost of a number of marine craft - i.e. those required for
maintenance. Costings for the remainder of the craft were obtained from other
sources.
The costing exercise had to deal with two essentially different types
of device: floating and bottom standing.
The former involve the prelaying of moorings and the hook-up of devices
thereto. Piles set in the rock sea bed were a preferred form of anchorage
and necessitated the use of large specialised craft costing upwards of
£40,000,000 apiece. Specialised clump anchors may prove to be a more economical
solution.
The installation of bottom standing devices involves the local preparation
of the sea bed, the careful lowering of the device and its final anchorage to
the sea bed - in most cases using rock ties. Once again large specialised craft
are involved; in this case faced with the added hazard of working in relatively
shallow water depths.
4/(ii)/l
The approach t o cos t ing lends i t s e l f t o t a b u l a r p re sen ta t ion s e t t i n g out
opera t ions , wave and l i g h t l i m i t a t i o n s , ope ra t iona l du ra t ions e t c . This l eads
t o an eva lua t ion of t h e t o t a l t ime f o r t h e complete i n s t a l l a t i o n procedure, t h e
number of devices which a p re sc r ibed f l e e t of v e s s e l s can i n s t a l i n a year and
hence the number of such f l e e t s (and t h e i r c o s t ) necessary t o enable a l l t h e
devices t o be i n s t a l l e d wi th in t h e time p re sc r ibed by the Device Teams.
COSTING OF M AND E PLANT AND TQANSMISSION -- Where tu rb ines and genera tors have been cos ted by the Teams, these
c o s t s have been checked and i f necessary ad jus t ed t o al low f o r i tems which
may have been omit ted.
I n t he case of t u rb ines and genera tors f o r devices which have no t had
a f u l l design and c o s t i n g e x e r c i s e c a r r i e d ou t by a manufacturer, cos t ing
formulae, based on t h r e e sources of information, have been developed by the
Consul tants t o p r i c e . Addi t iona l ly these formulae ensure t h a t t he p l a n t c o s t s
f o r d i f f e r e n t devices do c o r r e l a t e . I t must be emphasised t h a t t h i s cos t ing
method i s very approximate and of a pre l iminary na tu re and i s a p p l i a b l e f o r
u n i t s up t o lOMW only.
A i r Turbine
Three sources of information were considered t o provide a system t h a t
permit ted a c o r r e l a t i o n of a i r t u rb ine c o s t s .
It must be noted t h a t gene ra l ly because of the v a s t l y d i f f e r e n t
geometries and degrees of complexity i t i s thought a t t h i s s t a g e impossible
t o c o s t a i r t u rb ines genera l ly (Wells, Franc is and Axial flow) according t o
r a t i n g o r speed. The only parameter a v a i l a b l e becomes weight.
Three sources of information were considered t o permit very crude
cos t ings of t u rb ines on a common b a s i s .
1 ) Quote from Airex Ltd. f o r SEA C l a m t u rb ine . This quote was
f o r f45K f o r a s i n g l e s t a g e 3.5m 8 b lade Wells t u rb ine . f5K
was added by SEA t o al low f o r s p l a s h guard, s h a f t ba lanc ing
and module assembly. Estimated (SEA) u n i t weight i s 6.5T.
2 ) Quote from Sirocco f o r B e l f a s t Wells tu rb ine . This i s a
1.25111 2 plane opposed flow t u r b i n e (4 r o t o r s each of 6
b l ades ) . Weight 7.7T. The Sirocco quote was E80K f o r one of
a batch of 5 - quoted r educ t ion for mass product ion i s 20%
i . e . E64K per u n i t .
3) K & D have a tender p r i c e (1978) f o r a 2.3m 0 Franc i s t u rb ine .
This a t 1981 p r i c e s i s equ iva l en t t o a t o t a l of f600K. This
t u rb ine c o s t may be s p l i t i n t o two components:-
a ) t u r b i n e runner - 7T @ 18K/T - f125k
b) a l l o t h e r m a t e r i a l s - 77T @ ~ K / T - f475k
(The turbine runner is a 2.3m @ single multi-blade casting, fully
hand ground to profiles for hydro applications).
A rice reduction of 15% for bulk production brings the total cost to E500K.
The best approximation that can be made at the present time for
turbine costs is assumed to be:-
Wells and rotating parts of other turbines E 8000 /T
Casings, castings, machined housings f 60001T
Diffusers, cnnvolutes, ducting etc. E20001T
Where no weights or drawings are available axial flow turbines have
been priced on other device turbines and factored by the square of the
diameter ratio.
Generator
The costing formula for generators has been developed from three
sources of information:-
1) Clam figure from GEC for 'off the shelf' 1MW generator. This
figure was f43K - 45K for 1MW diesel driven machine. 45K is
the marinised version and has basically a higher insulation
rating and is Lloyds approved for marine use. This price is
for a constant speed machine in a 1.3 MW frame including
cooling fan, casing and mounting. This machine, rated at 1MW
is heat rated to 1.3 MW and is 50160 Hz, 1100 rpm, ex works T
tested and assembled (wt = 8 ).
2) Merz & Mclellan figure for the Duck - 1.2 MW + 3.3 kV switch
gear - 46K per unit.
3) K & D pricing figure for large 'one off' hydro generators. 1
This figure - £3.3 (MW/rpm)'m. is for essentially a constant
speed (but with up to 90% overspeed capability) machine and
includes excitation and both generator and turbine control,
casing, mounting, basic cooling and is F.O.B.
The formula is based on rating and speed. It includes a basic cost l
of £1.56 (MWIrpm) ' million, which figure includes casing immediate to the machine, testing and works assembly. An addition is made of 15% for
variable speed machines and rather over 5% for constant speed machines.
This is to cover excitation control, additional assembly on site, transport
and loading out. Finally an allowance of £6,000 per MW is made for cooling
sepa ra t ion .
The formula i s , therefore : -
I 6 f 1.56 (l4w/rpm) h 10 x 1.15 + (6,000 X MW)
Transmission
The t ransmiss ion scheme inc ludes two subsea c ros s ings , (from the
devices t o the Outer Hebrides and from the Hebrides ac ros s the Minch t o
Skye) p lus t ransmiss ion l i n e s and onshore i n s t a l l a t i o n s on the I s l ands
themselves.
For t ransmiss ion l i n e s , c i v i l works and p l a n t i n s t a l l a t i o n on the
I s l ands (o r platforms o f f sho re ) allowance has been made f o r cos t of
cons t ruc t ion inc rease due t o remoteness, d i f f i c u l t ground condi t ions , poor
access , h igher wages and more expensive t r a n s p o r t arrangements. This has
lead t o an inc rease of between 50 and 100%.
For major submarine cab le l ay ing o f f Outer Hebrides and ac ros s t he
Minch t o Skye, t he Consul tants have been guided by two r e c e n t and major
cab le c o n t r a c t s placed j o i n t l y wi th STK, Oslo, and P i r e l l i , Milan, by BC
Hydro f o r supp l i e s t o Vancouver I s l and . Appropriate supply and l a y r a t e s
have been derived from these a c t u a l and c u r r e n t con t r ac t s .
A coun te rpa r t check was made us ing c o s t of forthcoming channel DC
l i n k (CEGB). Derived c o s t suppor ts r a t e s used i n e s t ima te s . Of i n t e r e s t i s
the f a c t t h a t Consul tants1 r a t e f o r the cab le s t o Skye i s agreed by the Vickers
Team and appears gene ra l ly acceptab le t o LFB Team's Consul tants .
The r a t e s used f o r t he submarine cab le s a r e a s follows:-
400 kV Cables (Hebrides t o Skye) £1.75 m/km 3 phase
275 kV Cables from the devices t o t h e I s l a n d s -
E1.6m/km 3ph (1600mm2) + f l. 4m/km
D.C. S e r i e s Power Connections - 35kV fO.l5m/loop km (800mm2)
THE FRAMEWORK OF COST APPRAISAL
O u t l i n e o f Approach
The c o s t a p p r a i s a l o f t h e u n i t c o s t of energy ( i n pence/kWh) and o f t h e
2GW power s t a t i o n ( i n E M) were under taken i n a n e q u i v a l e n t manner t o
p r e v i o u s y e a r s ; b u t f o r t h i s r e p o r t a computer program h a s been used t o
a l l o w more d e t a i l e d a n a l y s e s t o be under taken r a p i d l y and e a s i l y .
Any a s p e c t o f t h e scheme c o s t s c a n be s p e c i f i e d s e p a r a t e l y , by g i v i n g a
c o s t r a t e , a q u a n t i t y , and r e f e r i n g t o a p r o f i l e o f e x p e n d i t u r e through
t ime. These s e p a r a t e i t ems cou ld b e , f o r example, t h e c o s t p e r d e v i c e f o r
i n s t a l l i n g machinery, t h e c o s t p e r v e s s e l f o r purchas ing a t u g , o r a lump
sum f o r p r o v i d i n g temporary moorings.
The program accummulates t h e p r o d u c t s o f c o s t r a t e , q u a n t i t y and
e x p e n d i t u r e p a t t e r n by y e a r i n t o a framework by y e a r , g i v e n codes f o r each
i t e m a l l o c a t i n g i t t o a c o s t c e n t r e , and a l l o c a t i n g i t t o e i t h e r scheme
c a p i t a l c o s t s o r power s t a t i o n maintenance.
The d e t a i l e d c o s t c e n t r e s , some 16, a r e i n f a c t used a t t h e l e s s d e t a i l e d
l e v e l shown i n F i g u r e s 2 and 3 .
The energy o u t p u t o f each scheme i s c a l c u l a t e d by a p p l y i n g t h e average
a n n u a l energy c a p t u r e d p e r d e v i c e , f a c t o r e d by t h e a v e r a g e power c h a i n
c o n v e r s i o n and t r a n s m i s s i o n e f f i c i e n c y and t h e average a v a i l a b i l i t y , t o a
p r o f i l e g i v i n g t h e number o f d e v i c e s on s t a t i o n i n each y e a r .
Uni t Cost o f Energy
To d e r i v e a n o v e r a l l ave rage u n i t c o s t , t h e v a r i o u s s t r e a m s o f c o s t s and
energy landed have t o be b rough t t o a common b a s i s . For t h e s imple scheme
assumed i n p r e v i o u s y e a r s , t h i s was done by a n n u a l i s i n g t h e t o t a l c a p i t a l
c o s t and add ing i t t o t h e (assumed c o n s t a n t ) y e a r l y maintenance c o s t and
a n n u a l ene rgy landed. For t h i s a s sessment round, because o f t h e v a r i a b l e
s t r e a m s o f a l l t h r e e components a r i s i n g from t h e more d e t a i l e d
assumpt ions adop ted , a d i f f e r e n t ( b u t ma themat ica l ly e q u i v a l e n t ) approach
was used.
A l l s t r eams o f c o s t s and energy were conver ted t o n e t p r e s e n t t o t a l s ,
u s i n g t h e s p e c i f i e d o p p o r t u n i t y c o s t o f c a p i t a l ( d i s c o u n t r a t e ) o f 5
p e r c e n t . The t o t a l accumulated c o s t s were t h e n d i v i d e d by t h e t o t a l
accumulated energy t o g i v e t h e pence p e r k i l o w a t t hour f i g u r e s g iven .
Array C a p i t a l Cos t s
These f i g u r e s a r e S imply t h e und i scoun ted t o t a l e x p e n d i t u r e i n c u r r e d a t
t h e t ime t h e f u l l energy i s deployed.
S e n s i t i t i v i t v T e s t s
S i n c e a l l d e v i c e s have b r o a d l y s i m i l a r p r o f i l e s o f e x p e n d i t u r e and energy
p r o d u c t i o n , changing t h e d i s c o u n t r a t e does n o t a l t e r t h e d e v i c e m e r i t
o r d e r .
Work i s c u r r e n t l y underway on t e s t i n g t h e e f f e c t o f a l t e r e d component l i f e
a s sumpt ions , p r i n c i p a l l y t h e examina t ion o f p ro long ing t h e l i f e o f t h e
c o n c r e t e s t r u c t u r e from 25 t o 50 y e a r s . T h i s produces improvements o f
between abou t 1 5 t o 20 p e r c e n t i n t h e u n i t c o s t s , w i t h d e v i c e s w i t h h i g h
c o n c r e t e c o n t e n t o b v i o u s l y producing t h e h i g h e r s a v i n g s . T h i s may narrow
t h e range of t h e o v e r a l l c o s t s o f power, b u t i s u n l i k e l y t o a l t e r t h e
m e r i t o r d e r .
Cos t , q u a n t i t y and energy t o l e r a n c e s have a l l been e s t i m a t e d f o r t h e
o r i g i n a l d a t a , and t h e i r a g g r e g a t e e f f e c t on t h e sp read o f p o s s i b l e
r e s u l t s has been t e s t e d by r e p e a t e d sampl ing from t h e p r o b a b l e range o f
each of t h e v a l u e s inc luded i n t h e d a t a . The r e s u l t s o f t h i s s e n s i t i v i t y
t e s t a r e be ing used t o g u i d e t h e emphasis o f f u r t h e r work, i n an e f f o r t t o
improve t h e p r e c i s i o n of t h e l e s s w e l l s p e c i f i e d d e v i c e s .
THE ASSESSMENT OF AVAILABILITY
The a v a i l a b i l i t y of t he va r ious devices has long been a s e n s i t i v e
s u b j e c t and u n t i l r e c e n t l y i t has not been p o s s i b l e t o cons ider i t i n a
coherent fash ion . The way has r e c e n t l y opened f o r a more l o g i c a l approach
wi th t h e r e c e i p t of information on f a i l u r e r a t e s now a v a i l a b l e from Yard. These
d a t a cover most of t he i tems of p l a n t used aboard the devices .
Based on the assumption t h a t p l a n t i s given adequate r o u t i n e maintenance,
Yard have suppl ied information on the frequency of f a i l u r e per year . I n
t h i s context i t w i l l be apprec ia ted t h a t a s the number of s i m i l a r p l a n t
elements ( say tu rb ines ) i s increased , so p ropor t iona te ly a r e the numbers of
f a i l u r e s per year .
Yard have a l s o prepared l o g i c diagrams s e t t i n g out t h e sequence and number
of p l a n t elements. This , i n conjunct ion wi th the f a i l u r e f requencies enables
an assessnlent t o be made of the percentages of each of t h e i tems of p l a n t which
( s t a t i s t i c a l l y ) have f a i l e d a f t e r o n e y e a r l s o p e r a t i o n . Hence the percentage l o s s
of power a t t he end of t he year can be der ived .
As t h e l o s s of power i s presumed t o vary l i n e a r l y , t h e average (percentage)
l o s s of power over t h e year i s h a l f t h a t occurr ing a t t h e end of the year . This
would be on the assumption t h a t r e p a i r teams v i s i t each device a t l e a s t once
a year . The percentage a v a i l a b i l i t y i s 100% l e s s t h i s average l o s s .
Should the inc idence of f a i l u r e a t t h e end of the yea r be excess ive ,
cons ide ra t ion has t o be given t o r e p a i r a t more f requent i n t e r v a l s .
To the l o s s of power due t o f a i l u r e of p l a n t must be added l o s s due t o t h e
f a i l u r e of t he t ransmiss ion system, leading t o t he o v e r a l l a v a i l a b i l i t y f a c t o r .
The Consul tants have found t h a t f o r most of t h e devices a s a t i s f a c t o r y
a v a i l a b i l i t y can be achieved on the b a s i s of Yard's f a i l u r e r a t e s associ.ated wi th
a reasonable frequency of r e p a i r v i s i t s .
I n t h e case of t h e Lancas te r F l e x i b l e Bag and the S.E.A. C l a m , t he
r e l i a b i l i t y of t h e f l e x i b l e membranes i s c r u c i a l . Yard have given a range of
f i g u r e s f o r f a i l u r e f o r t hese elements and by t ak ing a f i g u r e r a t h e r nea re r t h e
lower end of t he range, a s a t i s f a c t o r y r e l a t i o n s h i p between a v a i l a b i l i t y and
maintenance can be achieved.
I n t h e case of t h e Edinburgh Duck, a d i f f e r e n t approach had t o be adopted
a s t h e use of Yard's f a i l u r e r a t e s i n d i c a t e d t h a t t h e Duck would n o t be operable .
The assessment of f a i l u r e r a t e s i s a very d i f f i c u l t s u b j e c t - d a t a being
sca rce o r non-exis tent and o f t e n widely vary ing o r con t r ad ic to ry . Hence
Yard's f i g u r e s may be open t o adjustment. This i n f a c t was the ' d i f f e r e n t '
approach adopted by the Consul tants . A reasonable l e v e l of a v a i l a b i l i t y
and maintenance was assumed and the corresponding f a i l u r e r a t e s der ived.
This approach l ed t o a requirement t h a t t h e average f a i l u r e r a t e s t o be
achieved t o make the Duck adequately r e l i a b l e must be 1/50 of those s e t
ou t by Yard.
Yard's i n i t i a l assessment of f a i l u r e r a t e s f o r t he B r i s t o l Cylinder l ed
t o an unacceptably low a v a i l a b i l i t y . But Yard's i n i t i a l i n t e r p r e t a t i o n of
t h e Team's p re sen ta t ion was v e r y pes s imis t i c . Study of the r e s u l t s by
the Team showed f a i l u r e r a t e s could be s u b s t a n t i a l l y reduced a t n e g l i g i b l e
a d d i t i o n a l c o s t , such a s by providing redundancy i n s e a l s . Also f a i l u r e
of a rode does no t cause the extreme l o s s i n p roduc t iv i ty assumed by Yard.
Revised f a i l u r e r a t e s i nco rpora t ing these f a c t o r s have no t been received
by the Consul tants from Yard i n time f o r t h i s r e p o r t . Hence an est imated
a v a i l a b i l i t y f a c t o r of 80% has been used i n the p r o d u c t i v i t y assessment.
The a v a i l a b i l i t i e s der ived inc lude allowances f o r r e p a i r a s we l l a s
l o s s of power p r i o r t o r e p a i r . A longer r e p a i r downtime has been assumed
f o r f l o a t i n g devices due to the g r e a t e r d i f f i c u l t i e s of access . The
a v a i l a b i l i t i e s taken i n t o p r o d u c t i v i t y c a l c u l a t i o n s a r e 80% f o r the Duck
and the Cylinder , between 83 and 86% f o r t he f l o a t i n g devices and 87 - 91%
f o r the bottom s tanding devices .
4 ( v i ) NOTE ON DATA USED I N PRODUCTIVITY ASSESSMENT
. ,
1. The B r i s t o l Cy l inder h a s been t e s t e d i n t h e 46 s p e c t r a s e l e c t e d by
10s . The w a t e r dep th a t t h e in tended d e v i c e l o c a t i o n i s 42m, t h e
dep th a t which t h e s p e c t r a were measured, and t h e r e f o r e no f u r t h e r
t r a n s f o r m a t i o n f o r dep th was n e c e s s a r y .
The Team h a s s u p p l i e d d e t a i l e d r e s u l t s showing t h e c a p t u r e
measured i n t h e t ank and t h e c o r r e c t i o n s n e c e s s a r y t o a l l o w f o r
i m p e r f e c t i o n s i n t h e i r t e s t r i g and s p e c t r a l components n o t
reproduced a t Cadnam. F u r t h e r f a c t o r s have been p r e s e n t e d t o
a l l o w f o r t h e improved p r o d u c t i v i t y which t h e Team b e l i e v e w i l l be
ach ieved wi th a c y l i n d e r o f d i a m e t e r l a r g e r t h a n t h a t t e s t e d and
i n c o r p o r a t i n g v a r i a b l e s p r i n g i n g and damping. The Team h a s d a t a
t o s u p p o r t t h i s , b u t from r e g u l a r wave t e s t s o n l y . F u r t h e r t e s t s
by t h e Team i n t h e n e a r f u t u r e w i l l conf i rm o r c o n t r a d i c t t h e s e
c o r r e c t i o n s . For t h e p r e s e n t t h e C o n s u l t a n t s have a l lowed f o r a l l
e x c e p t t h o s e i n r e s p e c t o f wave components n o t r e p r o d u c i b l e i n t h e
t ank - t h e C o n s u l t a n t s n o t c u r r e n t l y n o t b e i n g i n agreement w i t h
t h e Team over t h e v a l i d i t y o f t h e s e f a c t o r s .
Power c h a i n e f f i c i e n c y c u r v e s have been s u p p l i e d by t h e
C o n s u l t a n t s excep t f o r t h e rode pumps, f o r which a s i n g l e v a l u e
f i g u r e o f 0.85, s u p p l i e d by t h e Team, h a s been used. K & D a r e i n
g e n e r a l agreement w i t h t h e Teams's M & E C o n s u l t a n t s o v e r
e f f i c i e n c y v a l u e s , f o r t u r b i n e s , g e n e r a t o r s and t r a n s m i s s i o n .
2. The Clam h a s been t e s t e d i n t h e 46 s p e c t r a s e l e c t e d by IOS
t r ans fo rmed t o a dep th o f 80m. However, due t o t h e l a r g e s c a l e
f o r t e s t i n g chosen by t h e Team (1 :55) , t h e Cadnam tank was n o t a b l e
t o g e n e r a t e 11 o f t h e h i g h e s t ene rgy s p e c t r a a t t h e s p e c i f i e d Hs.
The Team reduced t h e wave ampl i tude f o r t h e s e s p e c t r a and
e s t i m a t e d c a p t u r e assuming l i n e a r i t y , i . e . t h a t c a p t u r e e f f i c i e n c y
i s independent of wave h e i g h t . T h i s p rocedure , which i n c r e a s e s
t h e c a p t u r e from t h a t measured by 20%, i s c la imed by t h e Team t o b e
v a l i d b u t t h e C o n s u l t a n t s a r e s c e p t i c a l . I n t h e s h o r t term t h e
i n c r e a s e h a s been i n c l u d e d i n t h e C o n s u l t a n t s ' p r o d u c t i v i t y
a s s e s s m e n t , b u t more d a t a i s awai ted from t h e Team.
The Team have proposed f u r t h e r c o r r e c t i o n t o power c a p t u r e f i g u r e s
a l l o w i n g f o r l o s s e s , d i f f e r e n c e s i n geometry between t h e model and
t h e p r o t o t y p e , and c a p t u r e i n s e a s t a t e s o f power l e s s t h a n 10
kW/m. These have been i n c o r p o r a t e d i n t h i s r e p o r t , b u t a r e s u b j e c t
t o c o n f i r m a t i o n by mode1 t e s t s . These c o r r e c t i o n s g i v e a n
a d d i t i o n a l i n c r e a s e i n p r o d u c t i v i t y o f 37%, o f which 16% i s due t o
t h e bag l eng th b e i n g i n c o r r e c t l y modelled. Thus t h e t o t a l
i n c r e a s e i s p r o d u c t i v i t y a p p l i e d t o measured d a t a amounts t o 65%.
Cons tan t power c h a i n e f f i c i e n c y v a l u e s o n l y have been s u p p l i e d by
t h e Team and t h e r e f o r e t h e C o n s u l t a n t s have based t h e number o f
d e v i c e s i n a 2GW scheme a l s o on t h e Team's f i g u r e .
The Duck p r o d u c t i v i t y a ssessment h a s been made from t e s t s i n P-M
s e a s i n t h e narrow tank . Capture from t h e 46 s e l e c t e d s p e c t r a h a s
been e s t i m a t e d by t h e Team by assuming l i n e a r i t y o f performance
(wi th r e s p e c t t o t h e i n c i d e n t d i r e c t i o n o f waves and t h e i r
combina t ion) and i n t e r p o l a t i n g between narrow t a n k r e s u l t s . S t e p s
have been t aken towards s u b s t a n t i a t i n g t h e s e r e s u l t s by t e s t i n g a
s t r i n g o f s i x ducks i n t h e wide t a n k , b u t on a f i x e d s p i n e and i n
r e g u l a r , u n i d i r e c t i o n a l waves.
Power c h a i n e f f i c i e n c y d a t a and t h e number o f d e v i c e s have been
s u p p l i e d by t h e Team.
4 . The LFB h a s been t e s t e d i n t h e 46 s p e c t r a s e l e c t e d by IOS, b u t
t ransformed t o a dep th o f 75m. Capture r e s u l t s have been a d j u s t e d
by t h e Team t o a l l o w f o r l o s s e s i n t h e model. I n a d d i t i o n RPT have
i n c r e a s e d t h e p r o d u c t i v i t y r e s u l t s by 8% t o a l l o w f o r c a p t u r e i n
s e a s o f power l e s s t h a n 10 kw/m and t o remove t h e e f f e c t o f a n
unnecessa ry t u r b i n e c u t - i n v a l u e inc luded by t h e Team. The
t u r b i n e s w i l l c a p t u r e power i n low energy s e a s t a t e s , a l b e i t a t a
much lower e f f i c i e n c y t h a n a t i t s d e s i g n r a t i n g .
Power c h a i n e f f i c i e n c y c u r v e s have been s u p p l i e d by t h e Team and
t h e number o f d e v i c e s r e q u i r e d f o r a 2GW scheme agreed .
5. The NEL Breakwater h a s n o t been t e s t e d i n t h e 46 s e l e c t e d s p e c t r a .
R e s u l t s r e c e i v e d from t h e Team have comprised a s i n g l e t h e o r e t i c a l
monochromatic e f f i c i e n c y c u r v e , which is i n s u f f i c i e n t t o e n a b l e
t h e C o n s u l t a n t s t o make a thorough a s s e s s m e n t o f t h e hydrodynamic
pe r fo rmance o f t h e d e v i c e . Based on t h e i n f o r m a t i o n a v a i l a b l e ,
t h e C o n s u l t a n t s had t o make two a s s u m p t i o n s i n o r d e r t o a s s e s s t h e
d e v i c e pe r fo rmance i n t h e 4 6 s e l e c t e d s p e c t r a , i .e. t h a t
(i) t h e d e v i c e p e r f o r m a n c e i s i n d e p e n d e n t o f w a v e h e i g h t .
( i i ) t h e d e v i c e p r o d u c t i v i t y i n a mixed s e a c a n be o b t a i n e d by
a p p l y i n g a c o s i n e r u l e t o t h e 12 u n i d i r e c t i o n a l compone S F o f e a c h m u l t i d i r e c t i o n a l s p e c t r u m and s u b s e q u e n t
s u p e r p o s i t i o n .
The d e v i c e hydrodynamic e f f i c i e n c y t h u s o b t a i n e d h a s b e e n
i n c r e a s e d by 5% t o r e f l e c t t h e i n c r e a s e d d i r e c t i o n a l i t y o f t h e
s e a s , due t o r e f r a c t i o n , a s t h e waves p r o p a g a t e i n s h o r e . T h i s
i n c r e a s e h a s been n e c e s s a r y b e c a u s e t h e 4 6 s e l e c t e d s p e c t r a were
l i n e a r l y t r a n s f o r m e d t o t h e d e s i g n d e p t h o f 21m w i t h t h e
d i r e c t i o n a l d i s t r i b u t i o n o f e n e r g y k e p t c o n s t a n t .
From t h e power c h a i n e f f i c i e n c y c u r v e s p r o v i d e d by t h e Team, t h e
C o n s u l t a n t s ' e s t i m a t e o f t h e number o f d e v i c e s f o r t h e 2GW scheme
a g r e e s w i t h t h e number p roposed by t h e Team.
6 . The NEL F l o a t i n g T e r m i n a t o r h a s been t e s t e d i n t h e 46 s p e c t r a
s e l e c t e d by IOS a t a w a t e r d e p t h o f 42m, f o r which no
t r a n s f o r m a t i o n i s r e q u i r e d . S u b s e q u e n t l y t h e Team have d e c i d e d t o
r e s i t e t h e d e v i c e i n l O O m d e p t h , and i t h a s been assumed t h e
c a p t u r e e f f i c i e n c y r e m a i n s unchanged ( i . e . t h e pe r fo rmance o f t h e
d e v i c e i s l i n e a r ) even though t h e seas a r e more e n e r g e t i c a t t h i s
d e p t h . The Team h a s a p p l i e d no c o r r e c t i o n t o i t s r e s u l t s and
t h e r e f o r e r e g a r d s them a s c o n s e r v a t i v e .
C o n s t a n t power c h a i n e f f i c i e n c y v a l u e s have b e e n s u p p l i e d by t h e
Team, as h a s t h e number o f d e v i c e s r e q u i r e d f o r a 2GW scheme.
7. NEL F l o a t i n g A t t e n u a t o r
No e x p e r i m e n t a l d a t a were s u p p l i e d by t h e Development Team. Hence
t h e p r o d u c t i v i t y o f t h e d e v i c e had t o b e t a k e n a s t h a t quoted by
t h e Team. These r e s u l t s were based on narrow t a n k t e s t s i n
monochromatic s e a s u s i n g pre-1981 p rocedure . Not b e i n g suppor ted
by any e x p e r i m e n t a l r e s u l t s t h e C o n s u l t a n t s have r e s e r v a t i o n s a s
r e g a r d s t h e i r v a l i d i t y .
The C o n s u l t a n t s have a p p l i e d a d i f f e r e n t a v a i l a b i l i t y f a c t o r t o
t h a t quoted by t h e Team, i . e . 0.83 n o t 0.87.
The number o f d e v i c e s r e q u i r e d f o r a 2GW scheme h a s been t aken t o
be t h a t g i v e n by t h e Team - i n s u f f i c i e n t power p l a n t d a t a p reven ted
t h e C o n s u l t a n t s from making an independent e s t i m a t e o f t h e number.
8. The Vickers A t t e n u a t o r h a s been t e s t e d i n t h e 46 s e l e c t e d s p e c t r a
a d j u s t e d f o r r e f r a c t i o n by HRS f o r a dep th o f 25m. Values o f power
c a p t u r e i n t h e s p e c t r a were s u p p l i e d by t h e Team. The Team's d a t a
inc ludes a c o r r e c t i o n f o r d u c t f r i c t i o n l o s s e s , t h e c o r r e c t i o n
producing an i n c r e a s e i n p r o d u c t i v i t y o f around 10% o f t h e
o r i g i n a l v a l u e .
A combined power c h a i n e f f i c i e n c y c u r v e h a s been s u p p l i e d by t h e
Team, who have a l s o determined t h e number o f d e v i c e s r e q u i r e d f o r a
2GW scheme.
9 . The Vickers Termina to r h a s been t e s t e d i n t h e 46 s p e c t r a s e l e c t e d
by IOS t ransformed t o a dep th o f 25m. L i n e a r t r a n s f o r m a t i o n o f
s p e c t r a t o t h i s w a t e r dep th over t h e uneven seabed o f f t h e Hebr ides
i s n o t v a l i d ; t h e s p e c t r a should b e a d j u s t e d f o r r e f r a c t i o n u s i n g
t h e HRS program. The p r o d u c t i v i t y o f t h e d e v i c e i s l i k e l y t o have
been underes t ima ted by n o t t a k i n g accoun t o f r e f r a c t i o n . The Team
have s u p p l i e d v a l u e s f o r power c a p t u r e i n t h e s p e c t r a which they
have c o r r e c t e d f o r d u c t f r i c t i o n l o s s e s , t h e c o r r e c t i o n producing
a n i n c r e a s e i n p r o d u c t i v i t y o f around 30% o f t h e o r i g i n a l v a l u e .
Cons tan t v a l u e power c h a i n e f f i c i e n c i e s have been supp l i e d by t h e
Team, who have a l s o determined t h e number o f d e v i c e s r e q u i r e d f o r a
2GW scheme.
Cons tan t v a l u e power c h a i n e f f i c i e n c i e s have been s u p p l i e d by t h e
Team, who have a l s o determined t h e number o f d e v i c e s r e q u i r e d f o r a
2GW scheme.
10. B e l f a s t Device
P r o d u c t i v i t y a ssessment o f t h e d e v i c e i n i t s c u r r e n t l y proposed
form i s based on narrow t a n k t e s t i n g i n PM s p e c t r a . R e s u l t s have
been a d j u s t e d by t h e Team t o s i m u l a t e c a p t u r e i n t h e 46 South U i s t
s p e c t r a . There i s ev idence t o v e r i f y t h i s approach s i n c e
agreement was found between t e s t s on a n e a r l i e r d e v i c e
c o n f i g u r a t i o n i s b o t h PM s p e c t r a i n t h e narrow tank and t h e 46
s p e c t r a i n t h e wide t a n k a t Edinburgh.
The d e v i c e i s a p o i n t a b f s o r b e r and a s such i t i s impor tan t t o
s t u d y i t s behav iour i n a n a r r a y . However, o n l y a s o l i t a r y d e v i c e
was t e s t e d i n t h e t ank . P r o d u c t i v i t y of t h e p r e s e n t doub le row
a r r a y w i l l t h e r e f o r e be l e s s t h a n model t e s t s p r e d i c t owing t o a s
y e t u n q u a n t i f i a b l e s h i e l d i n g o f t h e second row.
A c o n s t a n t power c h a i n e f f i c i e n c y v a l u e was s u p p l i e d by t h e Team.
4 ( v i i ) ASSESSMENT 01: PKODLIC'TIV LTY
The p r o d u c t i v i t y assessment of t h e v a r i o u s t y p e s of d e v i c e i s based
on a s t e a d y s t a t e model u s i n g e x p e r i m e n t a l random, m u l t i d i r e c t i o n a l s e a
e f f i c i e n c y d a t a i n 46 s e a s t a t e s . These s p e c t r a have been s e l e c t e d by
I . O . S . , t o a l l o w t h e mean annua l p r o d u c t i v i t y of a l l d e v i c e s t o be e s t i m a t e d
i n a f a i r , c o n s i s t e n t and economical manner. T h e i r s e l e c t i o n was made from
a l a r g e r s e t of 399 s p e c t r a , s y n t h e s i s e d from d a t a c o l l e c t e d a t t h e o f f s h o r e
buoy i n 42m of wa te r o f f South U i s t . The 399 s p e c t r a a r e c o n s i d e r e d t o
r e p r e s e n t t h e mean annual s e a c l i m a t e .
P r i o r t o any t e s t s , t h e 46 s e l e c t e d s p e c t r a have t o b e t ransformed
t o t h e wa te r dep th a t which t h e v a r i o u s types of d e v i c e a r e t o be p laced .
Two methods of t r a n s f o r m a t i o n a r e used:
( i ) A l i n e a r i n t e r p o l a t i o n of t h e power l e v e l i g n o r i n g any
r e f r a c t i o n e f f e c t s . T h i s method i s presumed t o b e
s a t i s f a c t o r y f o r w a t e r d e p t h s g r e a t e r t h a n o r e q u a l t o 35m.
The r e c e n t recommendations by TAG 2 t o reduce t h e power i n
t h e s e a a t d e p t h s g r e a t e r t h a n 42m has been implemented by
assuming l i n e a r d e v i c e performance.
( i i ) A r e f r a c t i o n t r a n s f o r m a t i o n f o r wa te r d e p t h s between
35m and 25m.
R e f r a c t i o n e f f e c t s have been t h e s u b j e c t of a n e x t e n s i v e s t u d y by
t h e Hydrau l ics Research S t a t i o n , who under took t h e t a s k of t r ans forming t h e
46 s e l e c t e d s p e c t r a t o 25m of w a t e r . A t even s h a l l o w e r w a t e r dep ths o t h e r
f a c t o r s , such as wave b r e a k i n g , need t o b e invoked t o e x p l a i n t h e observed
power l o s s . The n a t u r e and i n t e r p r e t a t i o n of t h e s e e f f e c t s i s n o t y e t
f u l l y unders tood and they should be t h e s u b j e c t of an e x t e n s i v e r e s e a r c h
programme.
For t h e p r e s e n t , w i t h no f u r t h e r i n f o r m a t i o n , t h e C o n s u l t a n t s used
t h e i r l i n e a r t r a n s f o r m a t i o n method t o produce a n a v a i l a b l e wave c l i m a t e f o r
d e v i c e s a t w a t e r d e p t h s l e s s t h a n 25m. T h i s p l a c e s t h e sha l lower w a t e r
d e v i c e s a t a d i s a d v a n t a g e and a l lowances have t o be made t o t a k e t h i s a s p e c t
i n t o account .
The d e v i c e mean annual p r o d u c t i c i t y i s computed from t h e exper imenta l
random, mixed s e a s e f f i c i e n c y d a t a o b t a i n e d from tank t e s t s i n t h e 46
s e l e c t e d s p e c t r a ( t r ans formed t o t h e a p p r o p r i a t e d e p t h ) . The mean product-
i v i t y of t h e d e v i c e i n t h e s e s p e c t r a i s o b t a i n e d and subsequen t ly modif ied
t o g i v e t h e mean annual p r o d u c t i v i t y . The m o d i f i c a t i o n is n e c e s s a r y i n order
t o t a k e i n t o account t h e f a c t t h a t t h e 46 s p e c t r a (when f a c t o r e d by t h e i r
a p p r o p r i a t e we igh t ings and summed) r e p r e s e n t a d u r a t i o n of 2671399 of a y e a r .
Th i s amounts t o 76.52 of t h e mean annua l energy, t h e remain ing 23.5% a s s o c i a t e d
w i t h t h e 132 s p e c t r a excluded by t h e s e l e c t i o n p r o c e s s account f o r a s follow:;:-
The energy a s soc i a t ed with s p e c t r a whose Te va lue i s o u t s i d e the
range 7-12.9 sec. a r e ignored ( t o t a l energy l o s s 2.5%). Also ignored
a r e s p e c t r a with power l e s s than 10 kw/m. As wel l a s being only a
small percentage l o s s (2 ,4%) , t he power l e v e l i s so low t h a t f i xed
lo s ses w i th in the power cha in w i l l make the generated e l e c t r i c a l ou tput
neg l ig ib l e .
Four s p e c t r a a s soc i a t ed with h igh mean l e v e l s of power 0 3 0 0 kwjm)
were a l s o excluded by the s e l e c t i o n process , I n t h e sea s t a t e s
represented by these s p e c t r a , t h e r e w i l l occur peaks of power f a r g r e a t e r
than can be captured by devices , a cu tof f being imposed on power
captured by the r a t i n g of the p l an t . Hence the h igh mean power l e v e l s
w i l l probably n o t r e s u l t i n increased capture of energy. It i s t he re fo re
assumed t h a t the energy captured i n t hese spec t r a i s the same a s t h e
energy captured i n a s i m i l a r spectrum, bu t of reduced power l e v e l ,
contained i n the s e t of 46. Spectrum 388 has been chosen f o r t h i s
purpose.
F i n a l l y , 27 s p e c t r a were excluded because of unusual combination of
parameters, bu t otherwise ly ing wi th in the bounds of Power and Te of the 46
spec t r a . The energy a s soc i a t ed wi th t h e s e s p e c t r a amounts t o 10.1% of
the annual energy, and the device capture e f f i c i e n c y i n t hese s p e c t r a
i s taken a s the mean cap tu re e f f i c i e n c y f o r t he weighted s e t of 46.
The power cha in p roduc t iv i ty i s obtained by assuming t h a t f o r a given
s e a s t a t e the inpu t power t o the t u r b i n e i s cons tan t . The procedure f o r
ob ta in ing the mean annual p roduc t iv i ty of the power chain, and i t s
i nd iv idua l components, i s s i m i l a r t o t h a t appl ied t o the device.
I n a d d i t i o n t o the s teady s t a t e model, a time domain s imula t ion i s
used, i n c e r t a i n cases , t o quan t i fy a f a c t o r desc r ib ing t h e e f f e c t of t h e
most ques t ionable assumptions made i n t he s teady s t a t e model. This f a c t o r
i s , when appropr i a t e , used t o g ive an improved e s t ima te of device
p roduc t iv i ty .
For reasons of s i m p l i c i t y , t he s imula t ion has been i n i t i a l l y l i m i t e d
t o a s i n g l e degree of freedom, i . e . t h e power cha in r ece ives a s i n g l e random
input . Whils t t h i s i s adequate f o r a device l i k e the NEL breakwater, i t
cannot accu ra t e ly r ep re sen t many o t h e r devices , f o r which s impl i fy ing
assumptions must be made. However, by jud ic ious choice of t hese assumptions,
the time domain s imula t ion can throw u s e f u l l i g h t on those elements of
each device whose performance i s l e a s t wel l descr ibed i n b e s teady s t a t e model.
4 / ( v i i ) I 2
5 . DEVICE DATA SHEETS & NOTES
BRISTOL CYLINDER
LEADING DEVICE PARAMETERS
(Loca t ion - South l l i s t )
BRISTOl. CYI.INI)I:,R -p----
A. Rela t ed t o 10cati.o. 1. ~ i s t a n c e o f f s h o r e (km)
2 . Water dep th (m)
3. Power i n s e a (Kwlm)
3 . Rela t cd t o d e v i c e
1. O v e r a l l s i z e - l e n g t h (m)
- b r e a d t h (m)
- v e r t i c a l d imension (m)
75
15 (d i ame te r )
2 - g r o s s c r o s s s e c t i o n a l a r e a (m )
2 . Weight of d e v i c e ( t o n n e s )
1 7 6 . 7
g000 approx.
120 approx. 3 . Weight of d e v i c e l e n g t h ( tonneslm)
C . Re l a t ed t o 2CW s t a t i o n
1. Number of d c v i c e s
2 . Spacing of d e v i c e s (m)
3 . Length o f 2GW s t a t i o n (km) ( e x c l . nav ig . gaps)
D. G e d t o p r o d u c t i v i t y
1. Ra t ing of g e n e r a t o r s (MW)
2 . Power i n s e a (Kwlm)
120 MwI25 d e v i c e s
4 7 . 8
3. Elean annua l power d e l i v e r e d t o Skye (Elw/device)*
4 . Mean annua l o u t p u t of 2GW scheme (G!.J)*
E . Rc l a t cd t o s t r u c t u r e economy and u t i l i z a t i o n of r e s o u r c e
1 . Mean annua l power delivered p c r d e v i c e I l eng th of dev i ce (Kw/m)*
2 . Mean annua l powcr d e l i v c r c d p e r d e v i c e 6 dev ice s p a c i n g (Kw/m)*
3 . O v e r a l l conve r s ion c f f i c i c n c y of schcme*
mean annua l o u t p u t of 2GW scheme ( 2 ) mean annua l power i n s e n , x l e n g t h o r 2Gli s t a t i o n
4 . Cap tu re Fac to rh*
mean a n n u a l j ' w e r c a p t u r e d by d e v i c e (il) nenn annua l power i n s e a x d e v i c c l e n g t h
F. R e l a t e d t o cost
1. Cost of ?GW s t a t i o n (und i scoun tcd ) ( L W )
2 . Cost of each d c v i c c (und i scoun ted ) (<M)
3. Cost of energy ( d i s c o u n t e d ) (p/Kwh)
G . Misc ,e l laneous
1. Hean annual powcr c h a i n e f f i c i e n c y (7.)"""
2 . A v a i l a b i l i t y of t h e 2G!4 scheme (%)
3.
4 .
* i n c l u d i n g a v a i l a b i l i t y f a c t o r
** n o t i n c l u d i n g a v a i l a b i l i t y f a c t o r
*** mean annua l power landed a t Skyc ( n o t i n c l u d i n g a v a i l a b i l i t y f a c t o r ) mean annua l power cap tu red p e r d e v i c e :.; No. of d e v i c e s i n scheme
General
I n 1981 t h i s d e v i c e was developed i n a articular form i n
c o n s i d e r a b l e d e t a i l s u f f i c i e n t f o r most o f t h e e lements o f t h e
scheme t o have been de te rmined , and w e l l enough d e f i n e d f o r
d e t a i l e d d e s i g n t o be a b l e t o proceed. However a t t h e end of 1981
t h e Team advanced t h e p r o s p e c t i v e improvements i n p r o d u c t i v i t y
which they p r e d i c t e d would be p o s s i b l e i f a s e r i e s of
m o d i f i c a t i o n s were made t o t h e d e s i g n . The e n g i n e e r i n g a s s o c i a t e d
wi th e f f e c t i n g t h e s e changes was n o t developed due t o s h o r t a g e o f
t ime s o t h e c o r r e s p o n d i n g c o s t i n g changes a r e somewhat
s p e c u l a t i v e . However al thorigh t h e r a t i n g s and numbers o f
c y l i n d e r s may be a c c o r d i n g l y a d j u s t e d t o s a t i s f y t h e 2 GW
performance requ i rement , t h e r a t i n g of t h e aggrega ted h y d r a u l i c
power convers ion t o an e l e c t r i c a l o u t p u t and i t s t r a n s m i s s i o n t o
s h o r e i s w e l l e s t a h l i s h e d . The t h r e e h y d r o - e l e c t r i c t u r b i n e
g e n e r a t o r s on each of t h e s i x o f f s h o r e p l a t f o r m s t r u c t u r e s have
f a i r l y p r e c i s e s p e c i f i c a t i o n s . Apar t from b e i n g mounted on a
o f f s h o r e p l a t f o r m , t h e g e n e r a t i n g p l a n t and i t s a s s s o c i a t e d
e l e c t r i c a l equipment a r e o t h e r w i s e e n t i r e l y c o n v e n t i o n a l i n
concep t .
Performance
The comprehensive hydrodynamic t e s t i n g programme s o f a r c a r r i e d
o u t h a s l e d t o a thorough u n d e r s t a n d i n g o f t h e b a s i c p r o p e r t i e s o f
t h e c y l i n d e r i n r e g u l a r waves. It h a s a l s o y i e l d e d v a l u e s f o r
c e r t a i n c y l i n d e r c o n f i g u r a t i o n s of e f f i c i e n c y , and b o t h peak and
r.m.s v a l u e s of rode f o r c e s and c y l i n d e r d i sp lacement i n random
s e a s . However t h e Team i s no t y e t s a t i s f i e d t h a t i t h a s f u l l y
o p t i m i s e d some d e v i c e pa ramete r s o r t h a t i t h a s provided t h e
d e v i c e w i t h t h e b e s t c o n t r o l sys tem f o r optimum r e a l s e a
performance. The r e a s o n f o r t h i s i s p u r e l y t h e t ime l i m i t a t i o n on
t ank t e s t i n g .
The p r o d u c t i v i t y o f t h e d e v i c e on which t h e f i n a l c o s t of mean
annual power and t h e s i z e and c a p i t a l c o s t o f a 2GW scheme d i r e c t l y
depend, d e r i v e s from t h e r e s u l t s of t ank t e s t s i n t h e sub-se t o f 46
s p e c t r a . The method o f i n t e r p r e t a t i o n of t h e r e s u l t s was l a i d down
i n t h e C o n s u l t a n t s ' working paper 42. I n p r i n c i p l e , t h e
p r o d u c t i v i t y c a l c u l a t i o n p recedure i s s t r a i g h t - f o r w a r d b u t t h e
Team h a s i d e n t i f i e d a s e r i e s of c o r r e c t i o n s t o t h e measured d a t a
which have a s u b s t a n t i a l e f f e c t on t h e f i n a l p r o d u c t i v i t y v a l u e .
S e v e r a l of t h e s e c o r r e c t i o n s invo lve changing t h e pa ramete r s of
t h e c y l i n d e r from t h o s e a c t u a l l y t e s t e d , s i n c e t h e team i s
convinced t h a t i t d i d n o t t e s t a model of t h e b e s t p o s s i b l e dev ice .
Also , i m p e r f e c t i o n s i n t h e t e s t i n g r i g e x i s t e d which had a n
a d v e r s e e f f e c t on model performance. F u r t h e r shor tcomings i n
t h e s e t e s t s were t h a t t h e Cadnam tank can produce wave components 0
o n l y from an a r c o f about 150 ( i n s t e a d of 360' a s i n a r e a l s e a )
and t h a t o n l y a s i n g l e c y l i n d e r was t e s t e d a t a t ime i n S. U i s t
s p e c t r a (due t o l i m i t a t i o n s i n t h e a v a i l a b l e i n s t r u m e n t a t i o n ) .
The Team knows from e a r l i e r t e s t s u s i n g an a r r a y o f t h r e e s h o r t e r
c y l i n d e r s , each w i t h o n l y f o u r r o d e s , t h a t c a p t u r e e f f i c i e n c y p e r
d e v i c e r i s e s f o r a l i n e o f d e v i c e s
The r e a l i s a t i o n t h a t c a p t u r e e f f i c i e n c y improvements a r e l i k e l y
w i t h a d i f f e r e n t c y l i n d e r came from t h e Team's s t u d y of p r e v i o u s
t e s t r e s u l t s i n r e g u l a r waves. These i n d i c a t e t h a t i n r e g u l a r
waves, improvements i n c a p t u r e can be made by;
1 ) i n c r e a s i n g t h e c y l i n d e r d i a m e t e r from 12m t o 15m.
2) v a r y i n g t h e s p r i n g and damping f o r c e s a c c o r d i n g t o t h e wave
p e r i o d .
3 ) v a r y i n g t h e r a t i o of s p r i n g s t i f f n e s s e s s and damping f o r c e s
i n t h e f o r e and a f t rodes .
I n a d d i t i o n i t i s known t h a t t h e r e i s a s i g n i f i c a n t d e t e r i o r a t i o n
i n performance i f t h e t h r e e rode s t i f f n e s s e s on one s i d e o f t h e
c y l i n d e r d i f f e r .
T h i s was known t o be t h e c a s e w i t h t h e model t e s t i n g r i g employed,
due t o i m p e r f e c t i o n s . A f u r t h e r s o u r c e o f e f f i c i e n c y l o s s i n t h e
model was i d e n t i f i e d a s t h e f r i c t i o n on t h e p u l l e y s and d r a g on t h e
c h a i n s which cause a phase s h i f t between t h e wave and c y l i n d e r
mot ions , l e a d i n g t o d e c r e a s e i n e f f i c i e n c y . There i s no means o f
q u a n t i f y i n g t h i s l o s s a t p r e s e n t b u t i t was c o n s i d e r e d t o e x p l a i n
t h e s u b s t a n t i a l d i f f e r e n c e s i n model e f f i c i e n c i e s o b t a i n e d i n t h e
same exper iments a t Edinburgh and Cadnam. As a temporary e s t i m a t e
t h e Team h a s a l lowed 9%.
For t h e p r e s e n t p r o d u c t i v i t y a ssessment of t h e form o f d e v i c e
which t h e Team i s advoca t ing i t i s t h e r e f o r e n o t p o s s i b l e i n t h e
p r e s e n t s t a t e of knowledge f o r t h e C o n s u l t a n t s t o work from a mean
annual d e v i c e performance which i s f u l l y s u b s t a n t i a t e d by t a n k
t e s t i n g i n random S. U i s t s p e c t r a . I n s t e a d , t h e Team h a s t a k e n
d a t a from t h e r e s u l t s of t e s t s on a 75m long , 12m d i a m e t e r c y l i n d e r
w i t h f i x e d and e q u a l rode s t i f f n e s s e s ( a l b e i t w i t h e r r o n e o u s
unequal r e s i d u a l v a l u e s g i v i n g reduced performance) and f i x e d
damping. These d a t a a r e t h e n modi f i ed , spect rum by spect rum, on
t h e b a s i s of r e s u l t s i n r e g u l a r 2-D waves, t h e dependant v a r i a b l e T
( t h e wave p e r i o d i n monochromatic waves) b e i n g in te rchanged f o r Te
( t h e energy pe r iod i n mixed r e a l s e a s ) . T h i s m o d i f i c a t i o n p r o c e s s
i n v o l v i n g m u l t i p l y i n g o u t p u t by a c h a i n of t h r e e f a c t o r s assumes
t h a t t h e e f f e c t o f each f a c t o r i s independant of t h e o t h e r s , which
t h e Team c l a i m s t o be s o . The C o n s u l t a n t s have no means o f
conf i rming o r denying t h e p r e d i c t e d p r o d u c t i v i t y . The l o g i c o f r t h e d e r i v a t i o n i s u n d e r s t a n d a b l e , b u t t h e c r u c i a l q u e s t i o n i s how
f a r t h e t e n d e n c i e s i n r e g u l a r waves a r e m i r r o r e d i n r e a l s e a s , and
o n l y f u r t h e r t ank t e s t i n g w i t h t h e r e q u i r e d d e v i c e c o n f i g u r a t i o n
a l t e r a t i o n s w i l l demons t ra te t h e answer. Thus i t can be s t a t e d
t h a t t h e Team h a s a r r i v e d a t a p o i n t i n i t s t e s t i n g programme i n
which i t i s now a b l e t o s p e c i f y much more e x a c t l y t h e form o f
d e v i c e d e s i r e d f o r t h e nex t s t e p and t h e f u r t h e r more r e f i n e d t e s t s
n e c e s s a r y t o r each a d e s i r a b l e p r o d u c t i v i t y l e v e l .
The c y l i n d e r l e n g t h , s p e c i f i c g r a v i t y , submergence and w a t e r dep th
have been determined f o r a 12m d iamete r c y l i n d e r h u t t h e y a r e
s u b j e c t t o m o d i f i c a t i o n f o r t h e 15 m d i a m e t e r c y l i n d e r . Regarding
l e n g t h i t i s now r e a l i s e d t h a t economic c o n s i d e r a t i o n s cou ld l e a d
t o a l o n g e r c y l i n d e r , s i n c e v i r t u a l l y t h e same v e r y expens ive
rodes ( i n c l u d i n g p i l i n g and i n s t a l l a t i o n ) would t h e n be more
economica l ly u t i l i s e d i n c o l l e c t i n g more power. The c o s t o f t h e
e x t r a l e n g t h of c y l i n d e r would be r e l a t i v e l y smal l . Although
t h e r e i s a drop i n c y l i n d e r c a p t u r e e f f i c i e n c y w i t h i n c r e a s e i n
c y l i n d e r l e n g t h , i n changing from 75m t o 100 m l e n g t h t h e r e i s
n e v e r t h e l e s s a n e t i n c r e a s e i n c a p t u r e d power p e r c y l i n d e r . There
w i l l t h e r e f o r e be a n optimum l e n g t h , which t h e proposed e s t i m a t e
o f 100 m i s gauged t o r e p r e s e n t . However f o r t h e p r e s e n t
a s s e s s m e n t , a l e n g t h o f 75m i s used s i n c e a l l e f f i c i e n c y
c a l c u l a t i o n s and c o s t i n g s r e f e r r e d t o t h i s .
C a ~ t u r e E f f i c i e n c i e s
The Device Team h a s p r e s e n t e d a range of scheme mean annual d e v i c e
c a p t u r e e f f i c i e n c i e s depending on which o f t h e i r p r e d i c t e d
improvement f a c t o r s a r e i n c l u d e d i n t h e e f f i c i e n c y c a l c u l a t i o n ,
and whether t h e c y l i n d e r remains a t i t s a s - t e s t e d l e n g t h of 75m o r
cur ren t ly -p roposed l e n g t h of 100m. These a r e a s fo l lows :
1981 Design V a r i a b l e Tuning V a r i a b l e Tunins
(F ixed t u n i n g ) (12m d i a m e t e r ) (15m d i a m e t e r )
75m long c y l i n d e r 39% 49.4% 65%
10Om long c y l i n d e r 32.8% 41.6% 56.5%
The c o r r e s p o n d i n g number of d e v i c e s i n a 2GW scheme a r e a s fo l lows
75m long c y l i n d e r 615
1OOm long c y l i n d e r 5 18
The C o n s u l t a n t s have c a l c u l a t e d cor respond ing f i g u r e s us ing t h e
Team's t ank r e s u l t s , b u t i n t e r p r e t i n g t h e e f f e c t o f t h e miss ing
wave components d i f f e r e n t l y from t h e Team a s they b e l i e v e t h e Team
h a s o v e r e s t i m a t e d t h i s e f f e c t . There is a l s o a d i f f e r e n c e between
t h e Team and the C o n s u l t a n t s i n t h e c a l c u l a t i o n o f t h e a v a i l a b l e
power. The C o n s u l t a n t s have a l lowed t h e same p r e d i c t e d pe rcen tage
improvements a s t h e Team f o r f r i c t i o n and d r a g l o s s e s i n t h e r i g ,
unequal rode s t i f f n e s s e s , v a r i a b l e t u n i n g and l o n g e r c y l i n d e r , and
they have a l s o used t h e same l o s s o f e f f i c i e n c y r a t i o i n changing
from a 75m t o lO0m long c y l i n d e r . The C o n s u l t a n t s t h u s o b t a i n t h e
f o l l o w i n g mean annua l c a p t u r e e f f i c i e n c i e s :
1981 Design Variable Tuning
Fixed Tuning (12m diameter)
75m long cylinder 28.6%
lOOm long cylinder 24.1%
and the following numbers of devices in a 2GW scheme
75m long cylinder 720
lOOm long cylinder 606
Variable Tuning
(15m diameter)
Status of Assessment Data
Simple idealised calculations, acceptable for the state of
development reached, have been completed for the cylinder itself,
the anchor piles, and the power take-off system.
The basic design and constructional details of the major
structural elements of this device are well advanced and the
Device Team has provided information on quantities and cost
estimates for certain special items which have been checked
whenever practicable and used as a basis for the Consultants' cost
estimate. The Device Team has also provided a preliminary
structural cost estimate which in total appears to be within 1% of
the Consultants' own estimate, but it should be noted that the cost
of the cylinder itself is less than 10% of the cost of the scheme.
The Team's advisers have provided comprehensive estimates for the
platform generating equipment, transformers and switchgear. The
only modification made by the Consultants is the additional cost
of the inlet manifold. The electrical collection and transmission
circuit^ have also been costed by the Team to which has been added
the cost of the Skye terminal plant. These estimates have been
accepted in part For budgetary purposes but the Consultants are of
the opinion that the costs of submarine cabling and line
construction are considerably underestimated. Furthermore some
cost centres are omitted.
'Che i n s t a l l a t i o n c o s t s have been dpvt~Loprt l i n ~ ~ a t - a l l ~ l by t h e
C o n s u l t a n t s and t h e Team and t h e i r a d v i s e r s and t h e r e i s now v e r y
good agrsernent be tween them on i n s t a l l a t i o n c o s t s f o r b o t h p i l e s
and c y l i n d e r .
Ma in tenance c o s t s have been p r o v i s i o n a l l y a s s e s s e d by t h e
C o n s u l t a n t s i n advance o f f i n a l i n f o r m a t i o n f rom t h e Device Team,
YARD and EASAMS.
I t s h o u l d be no ted t h a t a l l c o s t i n g t~ d a t e h a s been c a r r i e d o u t
assuming 12n d i a m e t e r c y l i n d e r s . The change t o 1 5 m d i a m e t e r w i l l
a l t e r r o d e and p i l e d e s i g n s and t h e r e f o r e c o s t s , a s w e l l a s a l t e r
c o s t s o f t h e c y l i n d e r i t s e l f , and i t s i n s t a l l a t i o n and
mai-ntenance. The a l t e r a t i o n came t o o l a t e f o r r e - c o s t i n g t o be
c a r r i e d o u t f o r t h i s r e p o r t i n d e t a i l , b u t a nominal 15% i s added
t o t h e a f f e c t e d i t e m s .
Development
The Team h a s pu r sued a r i g o r o u s , q u e s t i o n i n g approach t o a l l
a s p e c t s (,E t h e d e v i c e , w i t h t h e a i d o f .3 l a r g e team o f sub-
c o n t r a c t o r s , e x p e r i e n c e d i n t h e i r r e s p e c t i v e f i e l d s . The p r o c e s s
o f development i n e v i t a b l y i n v o l v e s i d e n t i f i c a t i o n o f new problems,
l e a d i n g t o a d o p t i o n o f a l t e r n a t i v e s o l u t i o n s . T h i s h a s been t h e
c a s e i n t h i s p r o j e c t , p a r t i c u a r l y f o r t h e power t a k e - o f f sys t em,
t h e r o d e s and t h e i n s t a l l a t i o n sys t em, which a r e a l l i n t e r -
r e l a t e d .
Tn sp i t . . o f r x p l o r i n g o t h e r o p t i o n s f o r power t a k e - o f f , t h e d e v i c e
h a s r e t a i n e d i t s p r e s e n t form s i n c e i t s i n c e p t i o n . The c y l i n d e r
l e n g t h had p r e v i o u s l y i n c r e a s e d i n August 1981 from 50m t o 75m i n
o r d e r t o accomodate s i x moor ing r o d e s i n s t e a d o f f o u r t o p r o v i d e
r o d e redundancy i n t h e e v e n t o f a r o d e f a i l u r e . O t h e r w i s e , r e c e n t
a l t e r a t i o n s can a l l be c l a s s e d a s development o f d e s i g n d e t a i l s
r a t h e r t h a n a 1 t e r a t i o n s .
R e c e n t l y , t h e Tearn f o c r ~ s s e d i t s a t t e q t i o n on t h e p o s s i b i l i t y o f
r is ing "tube-pumps" i n p l a c e o f t h e mechan ica l s p r i n g s c o m p r i s i n g
p i s t o n s and a c c u m u l a t o r s , which t h e y have s o f a r deve loped f o r t h e
rodes i n t h e b e l i e f t h a t they ought t o use o n l y e x i s t i n g , proven
technology. (The term " t ~ b e - ~ u m ~ " i s be ing used a s t h i s i s i t s
adopted name from o t h e r s i t u a t i o n s , b u t t h e B r i s t o l Team s e e s i t s
use i n t h e i r d e v i c e s imply a s a s p r i n g , s i n c e i t s s i n g l e a c t i n g
pumping behav iour would n o t be s u i t a b l e f o r t h e i r power o f f t a k e
system. 'tlowever s i n c e each rode c o n t a i n s s i x s p r i n g s and two
pumps, f i n a n c i a l s a v i n g i n u s i n g e l a s tomeric t u b e s f o r s p r i n g s
could be s u b s t a n t i a l , s i n c e t h e r o d e s a r e t h e major c o s t c e n t r e i n
t h i s d e v i c e ) . The a d o p t i o n of tube s p r i n g s , b e s i d e s e f f e c t i n g a
r e d u c t i o n i n c a p i t a l c o s t , would l ead t o e a s i e r (and c h e a p e r )
i n s t a l l a t i o n , s i m p l e r (and c h e a p e r ) end c o n n e c t i o n s and s i m p l e r
and cheaper replacement . P r o v i d i n g f u t u r e development can prove
i t s long term performance and r e l i a b i l i t y , and Avon Rubber
Company's c o s t e s t i m a t e s a r e c o r r e c t , t h i s component o f f e r s a v e r y
a t t r a c t i v e improvement i n t h i s d e v i c e .
F o r t h e ptlrposes o f t h i s a s sessment t h e r e f o r e , tube s p r i n g s
c o s t i n g E 1 M p e r d e v i c e have been assumed w i t h a co r respond ing
r e d u c t i o n i n t h e t e l e s c o p i c tube f l e x i - j o i n t s c o s t s a s proposed by
t h e Tearn. I t shou ld be a p p r e c i a t e d t h a t t h i s i s an e s t i m a t e made
w i t h o u t r edeve lop ing t h e e n g i n e e r i n g d e t a i l s o f i n s t a l l a t i o n , end-
c o n n e c t i o n s , f a t i g u e l i f e , and r e d e s i g n e d rode and anchor f o r c e s ,
b e s i d e s not a1 lowing f o r t h e e n g i n e e r i n g o f v a r y i n g s p r i n g and
darnping r a t e s .
The subsea n a t u r e o f t h e d e v i c e i s a t the same t ime bo th an
advantage and d i s a d v a n t a g e . The advantage i s t h a t i t i s no t
s u b j e c t t o t h e v i o l e n t e f f e c t s o f extreme s e a s and f r e a k waves.
Rode f o r c e s i n f a c t reduce i n t h e s e a s t h e c y l i n d e r i s de-tuned.
L i m i t i n g f o r c e s and d i s p l a c e m e n t s a r e t h e r e f o r e known and can be
des igned f o r w i t h some conf idence . The d i s a d v a n t a g e o f
i n a c c e s s i b i l i t y i s r e f l e c t e d i n h i g h c o s t of i n s t a l l a t i o n and
maintenance (which u s u a l l y means r e p l a c e m e n t ) , and r e l i a b i l i t y .
However t h e v u l n e r a b l e components below t h e s e a a r e r e l a t i v e l y few
( t h e pump, i t s o u t l e t v a l v e , t h e rode s p r i n g s , and s e a bed
pipework). The major p a r t o f t h e power c o n v e r s i o n p l a n t i s on t h e
p l a t f o r m , w e l l above wa te r l e v e l and e n c l o s e d i n a c o n t r o l l e d
environment and f u l l y main ta ined i n t h e same way a s a c o n v e n t i o n a l
hydro-power s t a t i o n .
The i n t e r a c t i o n w i t h YARD i s c o n t i n u i n g , b u t t h e Team h a s
i d e n t i f i e d t h a t t h e assumpt ions made BY YARD concern ing r e l a t i v e l y
minor components ( such a s t h e number of p i s t o n s e a l s , t h e type o f
accumulator b l a d d e r ) make a dominant e f f e c t on t h e r e s u l t i n g
r e l i a b i l i t y of t h e o v e r a l l scheme. They a r e t h e r e f o r e c o n f i d e n t
t h a t f u t u r e i n t e r a c t i o n w i t h YARD w i l l e n a b l e them t o show an
a c c e p t a b l e r e l i a b i l i t y . I n t h e meantime, t h e C o n s u l t a n t s a r e
us ing an assumed r e l i a b i l i t y f a c t o r o f 0 .8 .
The major mar i t ime i n s t a l l a t i o n o p e r a t i o n s w i l l be c r i t i c a l l y
s u b j e c t t o t h e wea the r , and i n o r d e r t o i n s t a l l enough d e v i c e s i n
good wea the r , a l a r g e amount o f expens ive p l a n t and manpower w i l l
have t o be a v a i l a b l e , which f o r much o f t h e t ime w i l l be o n l y
w a i t i n g f o r good wea the r . There i s a major t e c h n i c a l r e s e r v a t i o n
on t h e d u r a b i l i t y o f t h e p e l t o n t u r b i n e and n o z z l e s i n s e a w a t e r ;
t h e r e arc3 no d a t a , p r a c t i c a l o r r e s e a r c h , t o i n d i c a t e t h e l i k e l y
performancp a t t h e ve ry h i g h j e t v e l o c i t y proposed.
I d e n t i f i c a t i o n of a s u i t a b l e bucket and nozz le m a t e r i a l must be
the s u b j e c t of f u t u r e r e s e a r c h . I n p r i n c i p l e however the power
t ake -of f and t r a n s m i s s i o n t o Skye a r e e n t i r e l y f e a s i b l e .
The r e l a t i v e l y l e n g t h y submarine c a b l e s r e q u i r e d t o o p e r a t e a t 275
kV and 400 ItV would need t o be c o n s t r u c t e d w i t h a polymeric
i n s u l a t i o n i n o r d e r t o reduce r e a c t i v e c u r r e n t r equ i rements . Such
c a b l e s a r e now b e i n g developed anc! should be a v a i l a b l e when
r e q u i r e d . The seabed r o u t e s have no t been i d e n t i f i e d . There a r e
known t o be d i f f i c u l t i e s west o f t h e Oute r H e b r i d e s , b u t t h i s
d e s i g n f o r t u n a t e l y minimises t h e number of i n d i v i d u a l c a b l e r o u t e s
r e q u i r e d and does n o t r e q u i r e f l e x i b l e c a b l e s .
Apar t from doubts o v e r t h e t u r b i n e b u c k e t s and n o z z l e s , t h e
C o n s u l t a n t ' s t e c h n i c a l r e s e r v a t i o n s a r e :
i ) The f a t i g u e l i f e o f h e a v i l y loaded rode components.
T h i s shou ld not be an i n s u p e r a b l e problem w i t h c a r e f u l d e s i g n .
5 / ( i ) / 8
C o r r e c t d o s i n g and f i l t r a t i o n t r e a t m e n t shou ld overcome t h i s .
i i i ) I n t e g r i t y o f t h e h y d r a u l i c t r a n s m i s s i o n p i p e s .
The tendency of t h e p i p e s t o move under t h e h i g h i n t e r n a l f o r c e s
and t o c o r r o d e a t p i p e weld f l a w s i n t h e s a l t w a t e r environment
impose a v e r y s e v e r e d u t y on t h e p i p e l i n e . S u i t a b l e p i p e bedding
and anchorage , and c o r r o s i o n p r o t e c t i o n a r e v i t a l .
i v ) p r o v i s i o n f o r p i p e l i n e p r e s s u r e r e l i e f i n t h e e v e n t o f a
sudden drop i n e l e c t r i c a l load .
D e t a i l s o f t h e mechanism f o r t h i s have not been worked o u t b u t t h e
Team e n v i s a g e s a u t o m a t i c blow-off v a l v e s i n t h e main, d i s c h a r g i n g
d i r e c t i n t o t h e s e a . The s t a b i l i t y of t h e h y d r a u l i c sys tem i s i n
some doubt due t o t h e absence o f any h y d r a u l i c s t o r a g e on t h e h i g h
p r e s s u r e s i d e o f t h e system.
v ) P r o v i s i o n f o r t h e i s o l a t i o n of branch mains , i . e . o f
i n d i v i d u a l d e v i c e s i n t h e e v e n t o f a b ranch p i p e f a i l u r e .
The need f o r t h i s i s r e c o g n i s e d b u t t h e d e t a i l s o f r emote ly
o p e r a t i n g t h e n e c e s s a r y v a l v e s have n o t been worlced o u t .
v i ) The f l e x i b l e p i p e c o n n e c t i n g t h e rode pumps t o t h e s e a bed
main.
An e x i s t i n g product des igned t o c a r r y h igh p r e s s u r e f l u i d ( a t up t o
28,000 p s i ) e x i s t s Eor use i n t h e o i l i n d u s t r y b u t behav iour under
t h e d u t y r e q u i r e d h e r e i.s unknown and w i l l have t o be proved.
v i i ) Mechanical wear of t h e pump chamber, ist tons, and v a l v e s .
The d u t y r e q u i r e d i n s e a w a t e r i s o n r r o u s . Although I n c o n e l 625
c l a d d i n g h a s been a l lowed on t h e p i s t o n rods t h e d u r a b i l i t y of t h e
whole sys tem should be s u b j e c t t o d e t a i l e d d e s i g n and development.
( v i i i ) The i n s t a l l a t i o n o f t h e s e a bed power c o l l e c t i o n mains by
towing o u t l o n g l e n g t h s ( a p p r o x . 5km) and s i n k i n g i n one p i e c e on a
p r e p a r e d bed on t h e rocky f l o o r i s bound t o be a d e l i c a t e o p e r a t i o n
r e q u i r i n g ca lm c o n d i t i o n s . Wl~ar ton-Wil l iams r e p o r t t h a t a 2km
l e n g t h o f 36 i n c h d i a m e t e r p i p e h a s been towed 393 km f o r
i n s t a l l a t i o n i n t h e Nor th Sea and t h e y c o n s i d e r l e n g t h s o f 10 km t o
b e f e r l s i h l e . The main d i f f e r e n c e o f f t h e H e b r i d e s i s t h e n a t u r e o f
t h e s e a bed and t h e amount o f bed p r e p a r a t i o n n e c e s s a r y t o a v o i d
f i n a l d e f o r m a t i o n t h e p i p e , and t o p r e v e n t i t moving d u r i n g
s e r v i c e .
C o n c l u s i o n s
As i n d i c a t e d above t h e d e v i c e r ema ins a t a n i n t e r i m s t a g e o f
development . The f u r t h e r model t e s t i n g p l anned i n 1982 airns t o
s u b s t a n t i a t e t h e improvements i n pe r fo rmance p r e d i c a t e d i n r e a l
s e a s . The ma jo r c o s t c e n t r e i s t h e r o d e s ( w i t h t h e f l e x i b l e j o i n t s
making a v e r y l a r g e c o n t r i b u t i o n a c c o r d i n g t o SBMs f i g u r e s , b u t
t h e Team's own i n v e s t i g a t i o n s w i t h Dunlop l e a d t o a s u b s t a n t i a l
r e d u c t i o n ) . The Team i s t h e r e f o r e v i ewing t h e f u t u r e development
o f t u b e s p r i n g s w i t h g r e a t i n t e r e s t .
The p r e s e n t a s s e s s m e n t l e a d i n g t o a c o s t o f 10.2p/kWh i s t h e r e f o r e
based on a d e s i g n f o r which r e l e v a n t model t e s t s and c o s t i n g s
s t u d i e s have n o t been done i n a n y t h i n g l i k e t h e d e t a i l o f t h e
p r e v i o u s 1981 r e f e r e n c e d e s i g n (which had t h e p a r a m e t e r s l2m
d i a m e t e r , 7 5 , l o n g , f i x e d t u n i n g and mechan ica l s p r i n g s ) . T h i s
c o s t o f power i s t h e r e f o r e dependen t on t h e Team's many
a s s u m p t i o n s b e i n g conf i rmed by morp d e t a i l e d s t u d i e s i n t h e
f u t t l r e , t h e s e shou ld i n c l u d e m a t e r i a l and e n g i n e e r i n g development
o f t h e t u b e s p r i n g s and end c o n n e c t i o n s , r e d e s i g n o f t h e d e v i c e and
a n c h o r s Eor d i f f e r e n t r o d e f o r c e s , new power t a k e - o f f pump,
t e l e s c o p i c t u b e and f l e x i j o i n t a r r a n g m e n t s , t a n k - t e s t i n g w i t h t h e
new p a r a m e t e r s , new i n s t a l l a t i o n p r o c e d u r e s and c o s t s , and
m a t e r i a l s t u d i e s f o r t h e P e l t o n Wheel b u c k e t s .
LANCASTER FLEXIBLE BAG
LANCASTER FLEXIBLE BAG
A R R A Y A N D L Q C A T t o h l
WAVE FALLlrJG - WC O P E ~ I N G WAJE RtSlrJG - BAG CLoscdG
WORKING CYCLE
A . Rela t cd t o Locat ion
1. Distorlcc o f f s h o r e (km)
2 . Wntcr dep th (m)
3 . Power i n s e a (Kw/ni)
L Re la t ed t o d e v i c e
1. O v e r a l l s i z e - l e n g t h (m)
- b r e a d t h (m)
- v c r t i c a l dimension (m) 2 - g r o s s c r o s s s e c t i o n a l a r e a (m )
2 . Weight of d e v i c e ( t o n n e s )
3 . Weight of d e v i c e G l e n g t h (torrlieslm)
C . Rc l a t cd t o 2GW s ~ ~ l *
1 . Nuwber of d e v i c e s
?. Spacing of d e v i c c s (m)
2 . LcnzLh of 2GW s t i i t i n n (km! ( c s c l . nav ig . gaps )
U . Re l a t ed t o procl i l r t i \ , i tp
1. Roting of Cc1Ieratul.s (!l:.i)
2 . Power i n s e a (1:wlm)
5 . 5 and 2 . 5 t+w/device
50.8
1.35
0.48
3 . Elcnn annua l power d c l i v e r c d t o Skye ( !~f~~/ ' i ievice)*
4 . Elcan annu;ll o u t p u t of 2GW schcrnc (C\,:)*
8 . Rela t cd t o s t r u c t ~ l r c econon~y an11 u t i l i z a t i o n of r c s o o r c e p---p-.- -
1. Eleon annua l power d e l i v e r e d p e r d e v i c e f lengLir of dc'ricc (K'd/rn)*
L. Meail :rnnilal power del iverer1 pe r d e v i c e F dcv i ce spac ing (Kw/m)*
3 . O v e r a l l conve r s ion efficiency o f sciiernc"
r~iean annua l o u t p u t of ?(;Is schcnie (2) lrlcarl oiinti;il power i n s e a S l e n g t h of 2Gl i s t a t i o n
mcart annu;ll power cnpt11rc,d by rii?vicc (7;) - -. p - -. - - 111c;iir nnnunl power i n sc,i ;; d c v i c e I cng th
F . Rclotc-il t t , c o s t
1 . Cost of ?Gi4 s t a t i o n ( ~ l r i ( ~ i s c n u ~ t t e d ) (C?!)
2 . Cost <,I' r ach d e v i c e ( u n d i s c n ~ ~ n t c d ) (CPI)
3. Cost ul' energy ( d i s c o u n t e d ) (p/Kwli)
C.. f l i s c c l l a ~ i ~ ~
1. ?lean nn ru~a l powrtr cha in c f f i c i c r r c ; ( X ) * * ' :
2 . , \ v a i l n b i l i t y of t h e 2GW sciirriie ( X )
3.
* i nc l r i d ing n v n i l a b j l i ty f a c t o r
** n o t i n c l u d i i ~ p , .ivai l a b i l i ty f a c t o r
*** mean nnri:ial p n ~ i c r lanclcd n t Skye . -- ( n o t i n c l u d i n g a v a i l a b i l i t y f a c t o r ) !:lean annua l power cop tu rcd p e r d e v i c e x No. of d e v i c e s i n scheme
LANCASTER FLEXIBLE BAG
General
The LFB as presented by t h e cu r r en t re ference design i s a f i n a l
s t a g e i n the evo lu t ion of t he f l e x i b l e bag device which began with
Prof . French 's conceptual design of 1 9 7 7 . Prof . French attempted
t o develop the concept on the b a s i s . of 4 c a r d i n a l cons i d e r a t ions
which were:
i ) To provide very cheap s imple working i n t e r f a c e with the
waves ( a rubber bag).
i i ) To maximise the r a t i o of swept volume t o s t r u c t u r a l volume
of the device. This being i d e n t i f i e d a s an e s s e n t i a l
parameter fo r an economic design.
i i i ) To func t ion a s an a t t e n u a t o r r a t h e r than a terminator:
f i r s t l y because i t was seen t o be e a s i e r t o s t a b i l i s e a sp ine
spanning across t he c r e s t s and secondly because it i s
e s s e n t i a l f o r the device t o experience both wave c r e s t s and
troughs s imultaneously, w i th in the f i n i t e length of t h e
device.
i v ) To adopt low p res su re a i r a s t h e i d e a l medium f o r power o f f -
take.
S t a t u s of Assessment Data
The b a s i c sp ine des ign and c o n s t r u c t i o n a l d e t a i l i n g a r e a t an
advanced s t a g e and t h e Device Team has provided information on
q u a n t i t i e s and cos t es t imates f o r c e r t a i n s p e c i a l items which have
been checked and used a s a b a s i s f o r t h e Consul tan ts ' c o s t
es t imate . The Consul tants i n i t i a l cos t es t imate , using t h e
r e spec t ive working paper was not i n agreement with t h e Team's
f i gu res . The two s u b s t a n t i a l d i f f e r e n c e s were i n r a t e s f o r
concre te and post- tensioning. In both these a r eas t h e Device Team
designed f o r ease of cons t ruc t ion , not n e c e s s a r i l y t o minimise
q u a n t i t y . I n o r d e r t o pe rmi t c l o s e r c o r r e l a t i o n w i t h o t h e r
d e v i c e s , t h e Team's lower c o s t i n g r a t e s have been used t o
compensate f o r t h i s ' o v e r d e s i g n ' . The r e d u c t i o n i n c o s t stemming
from t h i s is o f t h e o r d e r o f 1.25pIkWh.
Very l i m i t e d machinery c o s t s have been r e c e i v e d from t h e Device
Team b u t r a t h e r more b u t s t i l l incomple te c o s t i n f o r m a t i o n on t h e
t r a n s m i s s i o n i s a v a i l a b l e . The c o n s u l t a n t s have used mainly t h e i r
own c o s t i n g s f o r mechan ica l p l a n t and c a b l i n g . The c o s t i n g s f o r
p l a n t a r e s p e c u l a t i v e b u t a r e though t t o a l l o w c o r r e l a t i o n w i t h
o t h e r a i r d e v i c e s .
The i n s t a l l a t i o n c o s t s have been developed by t h e C o n s u l t a n t s and
a s s e s s e d a g a i n s t t h e Dev ice Team's r e p o r t . The maintenance c o s t s
have been developed by t h e C o n s u l t a n t s and compare c l o s e l y w i t h
those r e c e i v e d from t h e Dev ice Team a l t h o u g h t h e r e i s some
v a r i a t i o n i n approach.
Development
I n 1 9 7 8 t h e d e v i c e was t e n t a t i v e l y a s s e s s e d a s a good p r o s p e c t , b u t
on t h e b a s i s o f v e r y l i m i t e d i n f o r m a t i o n b o t h i n r e s p e c t of
s t r u c t u r a l s i z e and p r o d u c t i v i t y . Loss through l o c a l bag f a i l u r e
and t h e d i f f i c u l t i e s o f d e s i g n i n g a s u i t a b l e bag were i d e n t i f i e d
a s problem a r e a s .
The p r e s e n t d e s i g n h a s , f o r t h e f i r s t t ime, had t h e b e n e f i t o f
wide-tank f r e e f l o a t i n g t e s t i n g and a thorough s t r u c t u r a l
e n g i n e e r i n g development. The changes t h a t have t a k e n p l a c e s i n c e
c o n c e p t i o n have been s p e c i f i c a l l y : -
i ) Development o f d i s c r e t e a i r c e l l s i n p l a c e o f t h e con t inuous
bag.
T h i s change h a s l i t t l e e f f e c t on t h e swept volume b u t
p e r m i t s a c r e d i b l e bag d e s i g n and reduces t h e damage c o n t r o l
problem.
i i ) Development o f h u l l geometry around t h e bags t o p r o v i d e a
s t a b l e r e f e r e n c e frame of a d e q u a t e s t r e n g t h .
The r e s u l t o f t h i s work h a s been t o i n c r e a s e s i g n i f i c a n t l y
t h e s t r u c t u r a l volume wi th a c o n s e q u e n t i a l economic p e n a l t y .
The p r o d u c t i v i t y o f a l l subsequen t v a r i a t i o n s o f t h e d e v i c e d u r i n g
development h a s been below t h a t measured f o r t h e o r i g i n a l
c o n c e p t u a l "bag a l o n g t h e top" d e s i g n . Not a l l t h e r e a s o n s f o r t h i s
a r e thoroughly unders tood b u t they c e r t a i n l y i n c l u d e l o s s o f power
through s p i n e mot ion and t h e "nowhere t o go" f e a t u r e o f any
manifolded d e v i c e w i t h l i m i t e d r e s e r v o i r volume. I t is a l s o c l e a r
t h a t t h e Device Team i s on ly a t an e a r l y s t a g e o f u n d e r s t a n d i n g t h e
hydrodynamics o f t h e d e v i c e and t h e c u r r e n t d e s i g n may b e f a r from
o p t i m a l .
A comparison w i t h t h e Clam i s i n e v i t a b l e and i s u s e f u l i n
h i g h l i g h t i n g s t a g e s i n t h e development which now appear
c o u n t e r p r o d u c t i v e . The o r i g i n a l concept was a double-s ided bag
o v e r a c o n c r e t e s p i n e . To pe rmi t a n e n g i n e e r i n g s o l u t i o n t h e bag
was f i r s t s p l i t i n t o two s t r i p bags-one a l o n g each s i d e o f t h e
d e v i c e - and was s u b s e q u e n t l y s p l i t f u r t h e r i n t o d i s c r e t e bag
p a n e l s . The r e s u l t o f t h e independent Clam development, f o r q u i t e
d i f f e r e n t r e a s o n s , has ended w i t h what c a n be termed t h e o r i g i n a l
French concept of a d o u b l e s i d e d bag, b u t subd iv ided i n t o
manageable l e n g t h s and then mounted on - one s i d e of t h e s p i n e . The
s i g n i f i c a n t r e s u l t o f t h i s i s t h a t t h e bag p i e r c e s t h e wa te r p l a n e
and t h e s p i n e can be d e s i g n e d independen t ly w i t h o u t t h e
requ i rement o f a p a s s i v e r e a r f a c e t o t h e bag c e l l . The
consequence i s much-improved n a t u r a l s t a b i l i t y o v e r t h e LFB and a s
a r e s u l t t h e s t r u c t u r a l s p i n e o f t h e Clam can be economical ly
des igned a s a r e f e r e n c e frame t o c a r r y wave induced f o r c e s .
Although doub le - s ided , t h e LFB i s n o t o r i e n t a t e d a s a p u r e 0 a t t e n u a t o r . More power was absorbed by i n c l i n i n g t h e d e v i c e a t 30
- 40' t o t h e predorninent wave d i r e c t i o n . The r e a s o n s f o r t h i s a r e
no t y e t f u l l y a p p a r e n t b u t i t seems t h a t i n mixed s p r e a d s e a s ,
d e s i g n o f a p u r e a t t e n u a t o r is i m p o s s i b l e and t h e optimum d e v i c e
o r i e n t a t i o n i s between t e r m i n a t o r and a t t e n u a t o r .
The f l e x i b l e membrane system i s extremely c o s t e f f e c t i v e a s an
i n t e r f a c e w i t h t h e waves. The bags have been f u l l y developed and
w i t h c o n t i n u i n g r e s e a r c h , p a r t i c u l a r l y i n t o i n t e r p l y f a t i g u e , long
l i f e shou ld be proved.
The r e f e r e n c e frame h a s been des igned comprehensively and t h e
load ings assumed a r e r e a l i s t i c and p o s s i b l y c o n s e r v a t i v e . The
d e s i g n o f t h e s p i n e however could be f u r t h e r pursued t o reduce t h e
weight by up t o 1 5 % .
The o r i e n t a t i o n o f t h e LFB a t t e n u a t o r h a s l e d t o asymmetric power
o f f t a k e r a t i n g s . Valve and d u c t d e s i g n has been f u l l y
i n v e s t i g a t e d and t h e t u r b i n e i s r e l a t i v e l y c o n v e n t i o n a l and w i t h i n
p h y s i c a l d e s i g n l i m i t a t i o n s . P l a n t d e s i g n h a s been s t u d i e d
i n d u s t r i a l l y and i s a t an advanced s t a g e , though G.E.C. have no t
y e t p r e s e n t e d t h e i r r e p o r t .
The power p l a n t i s r e l a t i v e l y c o n v e n t i o n a l and n o t approaching
p h y s i c a l d e s i g n l i m i t a t i o n s . The a l t e r n a t o r , however, i s a
v a r i a b l e speed machine f e e d i n g a s e r i e s d.c. load. A s p e c i a l
e x c i t a t i o n sys tem i s r e q u i r e d i n v o l v i n g r o t a t i n g t h y r i s t o r s and
t h i s w i l l need development .
Conc l u s ions
The o v e r a l l r e s u l t o f t h e development a t p r e s e n t i s ve ry
d i s a p p o i n t i n g t o a l l concerned and t h e c o s t p e r Kwh is t o o h igh .
Although some c o s t r e d u c t i o n s may be p o s s i b l e on t h e s p i n e and
moorings, i t is c e r t a i n t h a t t h e d e v i c e has major b u i l t - i n c o s t
impediments i n i t s p r e s e n t form which p r e v e n t i t being a
s u c c e s s f u l con tender . The development o f p r a c t i c a l a t t e n u a t o r s i s
r e a l l y s t i l l i n i t s in fancy and t h e theory i s n o t y e t f u l l y
unders tood. L a n c a s t e r a r e c o n t i n u i n g w i t h development of
a t t e n u n t o r s and have made s i g n i f i c a n t p r o g r e s s s i n c e t h e i r d e v i c e
was eng ineered i n t o i t s p r e s e n t form by WPL. WPL themselves a r e
t u r n i n g t h e i r a t t e n t i o n t o a bottom-mounted a l t e r n a t i v e .
NEL BOTTOM STANDING TERMINhTOR
-
OWC- BOTTOM STANDING-.NELl TERMINATOR
LOCATION OF S C H E M E
D I M E N S I O N S
W A V ~ F A L L I W C ; WAVE R I J ~ ~ C
B l A GRArnMhTt c REPRESBWTATls 14 QF o P ~ R A T I ~ G CYCLE
LEADING ULVICE PARAMETERS
(Loca t ion - S o i j ~ h U i s t )
NEI. BOT'rOI.1 STANDING TI:RMINATOR
11. Rela t ed t o - 1 ~ 1 ~ 1 ~ i ~ t ~ ~
1 . I)i!;t;lnce o f f s h o r e (km)
2 . Water dep th (m)
1. Power i n s e a (Kwlm)
B. Re l a t cd t o d e v i c e
1. Overcl11 s i z e - lcngt l i (m)
- b r c ; ~ d t h (m)
- v c r t i c a l d imension (m) 2 - g r o s s c r o s s sectional a r e a (m )
2 . Weight of dev i ce ( t o n n e s )
3 . Weight of d e v i c c l eng th ( tonneslm)
C . Rc l a t ed t o 2GW s t a t i o n
1 . Numbcr nf d e v i c e s
2. Spacirig of d e v i c e s (m)
3 . L e n e t l ~ of 2GIJ s t a t i o n (km) ( e x c l . n a v i g . gaps )
D . Rc l a t ed t o p r o d u c t i v i t y
1. R a t i ~ t g of ~ e ~ ~ c r a t o r s (MW) 3 X 1 . 5 5 Mwldevice
2 . Power i n s c a (Kwlm) 2 9 . 6
3 . M ~ ; I I I a nnua l power d e l i v c r r d t o Skye (Mw/dcvice)* 0 . 6 8 8
4 . Meall nnnunl o u t p u t of 2GW schc:ne (CW)" 0 .406
E . Re l a t cd t o s t r u c t u r e ceonomy and u t i l i ~ a t i o ~ n of re sour^
1 . Mean annual power d e l i v c r c d p e r d e v i c e t l e n g t h of dev i ce (Kw/m)*
2 . Mean annua l power d e l i v e r e d pc r d e v i c c ' d e v i ~ c spac ing (Kw/m)*
3 . O v c r a l l conve r s ion c f f i c i r t n c y of scheme*
mean a n l ~ u a l o u t p u t of 2614 scheme p----
( 9 ) mean annua l power i n s e a x l e n g t h of 2Gl4 < t a t i o n
4 . Cap tu re Factor**
mean annua l power cap tu red by d e v i c e (%) mean annua l power i n s e a X d e v i c e l e n g t h
F . Re l a t ed t o cost-
1. Cost of ICU s t a t i o n ( i~nd i scou t i t ed ) (£!I)
2 . Cost of each devictl ( und i scoun ted ) (EM)
3. Cost c~ f cncryy ( d i s r o u ~ ~ t ~ d ) (pIKwli)
C. ~ i s c e l l a n c o u s
1. Mean a ~ r n u a l power cl>ai,n e f f i c i e n c y (X)***
2 . A v a i l a b i l i t y of t h e 2GW scheme (7 . )
3 .
4 .
* i n c l u d i n g a v a i l a b i l i t y f a c t o r
** n o t i n c l u d i n g a v a i l a b i l i t y f a c t o r
*** mean annua l power landed a t Skye (no t i n c l u d i n g a v a i l a b i l i t y f a c t o r ) mean annua l power cap tu red p e r d e v i c e X No. of d e v i c e s i n scheme
5 ( i i i ) a ) NEL BOTTOM STANDING TERMINATOR
1. GENERAL
1 . l DESIGN
The s t r u c t u r a l c a l c u l a t i o n s f o r t h e d e v i c e a r e based on t h e
methods developed f o r t h e A t t e n u a t o r i n accordance w i t h t h e
OWC Note 30 and t o a p p r o p r i a t e and a c c e p t a b l e d e s i g n c r i t e r i a .
The Device Team' S d e s i g n ph i losophy i s f u l l y a c c e p t a b l e t o t h e
C o n s u l t a n t s .
The Device Team i s u n d e r t a k i n g a comprehensive a n a l y s i s o f
s t r u c t u r a l e f f e c t s due t o wave load ing . While i t i s accep ted
t h a t f u r t h e r work i s r e q u i r e d on t h i s l o a d i n g c a s e , t h e
C o n s u l t a n t s b e l i e v e t h a t any r e s u l t i n g m o d i f i c a t i o n s t o t h e
s t r u c t u r e found t o be n e c e s s a r y w i l l have a n i n s i g n i f i c a n t
a f f e c t on c o n s t r u c t i o n c o s t s .
The i n s t a l l a t i o n p rocedure , i n which t h e 3 - c e l l u n i t i s
o f f e r e d up t o 9 s t a b b i n g g u i d e s p r e - s e t on t h e sea-bed i s
c o n s i d e r e d by t h e C o n s u l t a n t s t o be a r e a s o n a b l e e x t e n s i o n of
accep ted e n g i n e e r i n g p r a c t i c e .
N o d i f i c a t i o n s t o t h e d e s i g n d i s c u s s e d i n t h i s Note a r e
examined i n S e c t i o n 4.
TANK TESTING
The 21m mark I1 d e v i c e h a s n o t i t s e l f been t a n k - t e s t e d . The
p r o d u c t i v i t y r e s u l t s provided a t t h i s s t a g e by NEL a r e based
on a s i m u l a t e d mathemat ica l model u s i n g a t h e o r e t i c a l
monochromatic e f f i c i e n c y curve . It i s emphasised t h a t t h e
o u t p u t o f t h i s computer programme u s i n g t h e monochromatic
c u r v e was compared w i t h t h e r e s u l t s from t h e September Cadnam
t a n k t e s t s f o r t h e 25 m mark I d e v i c e and agreement was
o b t a i n e d . The Device Team i n t e n d s t o u n d e r t a k e t h e
a p p r o p r i a t e t e s t i n g i n t h e Cadnam Tank f o r t h e 46 s p e c t r a a t a n
e a r l y d a t e and t h i s i s n e c e s s a r y b e f o r e r e s u l t s can b e
expressed w i t h con£ idence .
The t h e o r e t i c a l a n a l y s i s , shows t h a t t he device has a
hydrodynamic e f f i c i e n c y of 6 1 . 9 % , comparing favourably with
va lues obtained f o r t h e f l o a t i n g terminator of 25%.
SPECIFICATION
This i s broadly based on t h e NEL Reference Design 1980
( ~ R 2 2 : ~ a v e 00) and on NEL summary of M and E P l an t Rating and
P roduc t iv i ty 8 t h January 1982. Close l i a i s o n has been
maintained between t h e Device Team and Consul tants on the
development of t h e above.
Due t o on-going modi f ica t ions t o t he des ign , a s discussed
l a t e r , t h e Device Team has not y e t produced a formal
s p e c i f i c a t i o n .
COSTING
F u l l co-operation has been maintained between the Device Team
and t h e Consul tants on cons t ruc t ion c o s t s , and so f a r a s
poss ib l e , i n view of des ign changes, on i n s t a l l a t i o n cos t s .
Good agreement has been reached a t a l l times on information so
f a r obtained .
A formal p re sen ta t ion of cos t ing f o r t he device has not y e t
been provided by t h e Device Team f o r the reasons s t a t e d under
1 . 3 and summarised i n Sec t ion 4.
DEVELOPMENT
GENERAL
The concept of a bottom mounted device fol lows n a t u r a l l y from
an assessment of d i f f i c u l t i e s a s soc i a t ed with mooring
i n s t a l l a t i o n i n t he c a s e of f l o a t i n g devices . The long term
maintenance of such moorings and o the r f a c t o r s a l l suggest
t h a t t he reduced power cap tu re p o t e n t i a l due t o l oca t ion i n
shal lower waters i s more than compensated by ease of
maintenance and of gene ra l access a s we l l a s enabling t h e
s t r u c t u r a l d e s i g n t o be based on a more c o n v e n t i o n a l
breakwater phi losophy. The Refe rence Design 1980, r e f e r r e d t o
above, examines t h e c a s e o f a breakwater d e v i c e c o n t i n u o u s l y
mounted on t h e s e a bed a t d e p t h s o f 1 5 - 20m w i t h a concomitant
reduced c a p t u r e p o t e n t i a l .
Subsequent ly t h e Device Team i n v e s t i g a t e d a module based on
t h e 25 m dep th and founded on p i l e d p l i n t h s . Although good
c a p t u r e was achieved t h e i n s t a l l a t i o n p rocedure was expensive
mainly due t o t h e high c o s t o f t h e p i l i n g , and t h e Team h a s
t h e r e f o r e moved t h e d e v i c e t o 21 m d e p t h , e l i m i n a t i n g t h e need
f o r p i l i n g and producing a more e f f e c t i v e d e s i g n .
MANIFOLDING
I n June and J u l y o f 1981 t h e concept o f j o i n i n g t h r e e 4 - c e l l
u n i t s and mani fo ld ing t h e a i r f low t o one o r two AC power u n i t s
was examined by t h e Device Team. The Team a n t i c i p a t e d a
smoothed power i n p u t , s i m p l e r p l a n t r equ i rements and reduced
d e v i c e t o s h o r e t r a n s m i s s i o n producing u s e f u l economies w i t h
s m a l l c a p t u r e l o s s . The r e s u l t s o f t ank t e s t i n g i n September
d i d n o t suppor t t h i s . The system d i s c u s s e d i n t h i s n o t e
t h e r e f o r e comprises a 1 :l c e l l t o t u r b i n e j g e n e r a t o r r a t i o .
The p o s s i b i l i t y o f mani fo ld ing i s s t i l l be ing examined.
PLINTHS AND ROCK ANCHORS
I n o r d e r t o reduce t h e amount o f s e a bed p r e p a r a t i o n i n h e r e n t
i n t h e o r i g i n a l 1980 scheme a s w e l l a s t o e n a b l e t h e d e v i c e t o
be l o c a t e d i n deeper w a t e r , t h e Device Team decided i n
February 1981 t o s u p p o r t t h e modules on c o n c r e t e p l i n t h s , two
per f o u r - c e l l u n i t and i n 25 m dep th o f wa te r . The
i n s t a l l a t i o n of t h e p l i n t h s p r i o r t o t h e module emplacement
c r e a t e d some engi 'neering d i f f i c u l t i e s which, a l though l e s s
onerous t h a n t h o s e a p p l y i n g t o t h e o r i g i n a l b reakwate r d e s i g n
were s e e n by t h e Design Team and C o n s u l t a n t s a s r e p r e s e n t i n g
an unaccep tab ly h i g h c o s t c e n t r e .
I n t h e l i g h t o f t h e above, t h e Team examined t h e p o s s i b i l i t y o f
i n t e g r a t i n g t h e p l i n t h s wi th t h e modules and a l s o o f a v o i d i n g
t h e u s e o f p i l i n g by a d o p t i n g rock anchor ing t echn iques . The
proposed rock anchor system c o n s i s t i n g o f 57 No. 1 9 / 1 8 Dyform
tendons i s t o a proven d e s i g n and h a s t h e n e c e s s a r y s a f e t y
margins a g a i n s t s h e a r and o v e r t u r n i n g .
CHANGES TO DEVICE PROFILE
The 1980 Reference Design shape was e s s e n t i a l l y square i n
c r o s s s e c t i o n , g i v i n g a h i g h r e a c t i o n a r e a t o wave f o r c e s . The
c u r r e n t d e s i g n a s d e t a i l e d i n drawing R B / 1 0 , August 1981 is
streamed on t h e seaward f a c e w i t h a th ickened nose s e c t i o n and
a smoothed run-over s e c t i o n f o r d i m i n i s h i n g t h e e f f e c t s o f
wave load ings . I n t h e l a t e s t d e s i g n a l l s p a r e s t r u c t u r e which
i s n o t s p e c i f i c a l l y used i n wave c a p t u r e h a s been minimised.
FEASIBILITY
The C o n s u l t a n t s c o n s i d e r t h e Bottom Stand ing Terminator OWC
concept t o be f e a s i b l e . Moreover t h e scheme envisaged
p o s s e s s e s t h e n e c e s s a r y d e g r e e o f ruggedness combined w i t h
r e l a t i v e l y easy maintenance d u e t o s e l f s h e l t e r and proximity
t o shore .
As compared t o t h e 1980 OWC d e s i g n , t h e concept o f s u p p o r t i n g
t h e modules on s t a b b i n g gu ides c a l l s f o r g r e a t e r accuracy a s
r e g a r d s l o c a t i o n b u t over a s m a l l e r sea-bed a r e a . The
proposed c o n s t r u c t i o n and i n s t a l l a t i o n p rocedures p r e s e n t no
n o v e l eng ineer ing f e a t u r e s . I n summary, t h e s t a b b i n g gu ides
a r e i n s t a l l e d and rock anchored i n advance o f embedment. The
modules a r e t r a n s f e r r e d from c o n s t r u c t i o n yard t o s i t e u s i n g
a d d i t i o n a l buoyancy f o r s k i d l aunch ing and f o r lock ing down on
t o t h e s t a b b i n g g u i d e s ( 9 p e r module). Once s o l o c a t e d ,
lock ing mechanisms i n t h e g u i d e s ho ld t h e module f i r m l y w h i l e
buoyancy i s r e t a i n e d . Under t h e s e c o n d i t i o n s , i . e . b e f o r e t h e
remaining rock anchors i n t h e s t r u c t u r e a r e i n s t a l l e d , t h e
s t a b b i n g gu ides p r o v i d e an ample margin o f s t r e n g t h a g a i n s t
s h e a r and o v e r t u r n i n g . It i s t h e i n t e n t i o n o f t h e d e v i c e team
t o g r o u t benea th t h e d e v i c e b e f o r e t h e remaining rock anchors
a r e d r i l l e d and i n s t a l l e d .
The proposed system o f rock anchor ing o u t l i n e d above is based
on e s t a b l i s h e d and a c c e p t a b l e p r a c t i c e .
The maximum f o r c e s c a r r i e d p e r d e v i c e a r e 282 T/M h o r i z o n t a l
and 74 T/M v e r t i c a l . The rock anchor ing system prov ides
a c c e p t a b l e m a t e r i a l and load s a f e t y f a c t o r s t o s u s t a i n t h e
above.
The C o n s u l t a n t s b road ly a c c e p t t h e c o n s t r u c t i o n t iming
sequence o f 8 y e a r s sugges ted by t h e Device Team.
CONCLUSIONS
I n a g r e e i n g w i t h t h e Device Team's c o s t i n g and programme
e s t i m a t e s and i n r e c o g n i s i n g t h e proposed s t r u c t u r a l d e s i g n o f
t h e module a s be ing a r e a s o n a b l e one, i n v o l v i n g no s i g n i f i c a n t
e x t r a p o l a t i o n o f c u r r e n t e n g i n e e r i n g p r a c t i c e s , t h e
C o n s u l t a n t s conf i rm t h a t t h e Bottom Stand ing Terminator i s an
a c c e p t a b l e d e v i c e . Both t h e C o n s u l t a n t s and t h e Device Team
acknowledge t h a t f u r t h e r work i s r e q u i r e d a s r e g a r d s
o p t i m i s i n g t h e i n s t a l l a t i o n p rocedure and i n ' t u n i n g ' o u t t h e
wave load i n g s .
The new 21 m d e s i g n h a s e l i m i n a t e d t h e need f o r s e p a r a t e
p l i n t h s and avoided t h e u s e o f p i l i n g - a h i g h c o s t c e n t r e .
The a d o p t i o n of a x i a l - f l o w t u r b i n e s and g e n e r a l m o d i f i c a t i o n s
t o t h e geometry o f t h e d e v i c e h a s produced a compact system
o f f e r i n g good cos t - sav ing p o t e n t i a l a l l i e d w i t h a s i m p l i f i e d
embedment procedure .
VICKERS TERMINATOR
OWC -BOTTOM .STANDING-vICKER'S' TERM1 NATOR
t t t t
LEADING D E V I C E PARAMETERS p--.----
(I.oc.?tion - So11tl1 U i s t )
VTCKERS 'II:R?I INATOR ----p-
A . Rela t ed ro l o c a t i o n
1. D i s t a n c e o f f s h o r e (km)
2 . Water dep th (m)
3. Power i n s e a (Kw/m)
B . Re l a t ed t o d e v i c
1. O v e r a l l s i z e - l e n g t h (m)
- b r e a d t h (m) l - v e r t i c a l d imension (m)
2 - g r c s s c r o s s s e c ~ i o n a l a r e a (m )
2. Weight of d e v i c e ( t onnes )
3 . Weight of d e v i c e I l e n g t h ( tonneslm)
C. Re l a t ed t o 2GU s t a t i o n
1. Number of d e v i c e s
2 . Spacing of d e v i c e s (m)
3 . Length of 2GW s t a t i o n (km) ( e x c l . n a v i g . gaps)
D . Re1 l t c d t o product-
1. Ra t ing of g e n e r a t o r s (MW) 7 x 4 . 2 MW p e r 10 d e v i c e s
2 . Power i n s ea (Kw/m) 3 6 . 2
3 . Elean ~ n n u a l power delivered t o Skye (Mw/device)* 0 . 4 6 4 . Mean annua l o u t p u t of 2Gi.i scheme (CV)* 0 .50
E. Re l a t ed t o s t r u c t u r e economy and ut i l iz&oi~ of r c s o u r c e
1. blcan annual. power de l i ve rc t l pe r d e v i c e f len$:th oE d e v i c e (Kw/m)*
2 . F1c.m anntinl porscr d c l i v e r c d pcr c l e ~ ~ i c r I dev ice s p a c i n g (Kwim)*
mcan nrinual o u t p u t of 2CW scheme -- ( 9 ) mcan annua l power i n sc.1 X l c n g t h of ?G!: s t a t i o n
4 . Capture Paceor*:'(
mcan annu?-wer c a p t ~ t r e d by dev i ce (%) mean annua l power i n s e a x d e v i c e l e n g t h
F . R e l a t e d t o cos:
l Cost o f ZGW s t a t i o n (undiscoui i tcd) (£M)
2. Cost of each d e v i c e (und i scoun tcd ) (EM)
3 . Cost of energy ( d i s c o u n t e d ) (p/Xwh)
C. Mi sce l l aneous
1 . Menn annua l powcr r h a i n e f f i c i e n c y (X)***
2 . A v a i l a b i l i t y of t h e 2GW scheme ( X )
3.
* i n c l u d i n g a v a i l a b i l i t y f a c t o r
** n o t i nc lud inc : n v a i l a h i l i t y f a c t o r
*** ineon annua l power landed a t Skye mean annua l power cdp tu rcd p e r d e v i c c X No. of device., i n scherne
( n o t i n c l u d i n g a v a i l a b i l i t y f a c t o r )
VICKERS TERMINATOR
General
The p r o d u c t i v i t y d a t a f o r t h e c u r r e n t r e f e r e n c e d e s i g n have been
o b t a i n e d u s i n g a 1 /200th s c a l e model i n t h e wide t ank a t Wave Power
L td . , Cadnam. These d a t a a r e somewhat s u s p e c t b e c a u s e of t h e s m a l l
s c a l e of t h e t e s t model and t h e f a c t t h a t t h i s was t h e f i r s t d e v i c e
t o be t e s t e d i n t h e modif ied 46 s p e c t r a r e p r e s e n t i n g t h e 25m wate r
d e p t h ; some of which were l a t e r found t o b e i n c o r r e c t l y
t r ans fo rmed . The Team h a s a t t empted t o modify t h e exper imenta l
v a l u e s which a r e now approx imate ly c o n s i s t e n t w i t h comparable
a t t e n u a t o r r e s u l t s b u t must s t i l l be t r e a t e d w i t h c a u t i o n .
The C o n s u l t a n t s have r e c e i v e d t h r e e s t r u c t u r a l d rawings , a scheme
l a y o u t , a p r e c a s t i n g drawing and t h e General Arrangement.
Although some thought a p p e a r s t o have been g i v e n t o d imensioning
t h e members, no w r i t t e n d e t a i l s o f t h e s t r u c t u r a l d e s i g n have been
r e c e i v e d by t h e C o n s u l t a n t s . The c o n s t r u c t i o n , t r a n s p o r t a t i o n and
i n s t a l l a t i o n o f t h e d e v i c e have been covered i n a s e p a r a t e r e p o r t .
The C o n s u l t a n t s have been asked t o a s s e s s a r e v i s e d i n s t a l l a t i o n
p rocedure based on c o s t s a v i n g s ach ieved by t h e Team's C o n s u l t a n t s
i n t h e i r work on t h e NEL Breakwater d e v i c e . No d e t a i l s have been
r e c e i v e d b u t t h e i n s t a l l a t i o n c o s t s have been c a l c u l a t e d i n
p r o p o r t i o n t o t h e NEI, d e v i c e .
The mechanical and e l e c t r i c a l p l a n t i n f o r m a t i o n r e c e i v e d from t h e
Team i s f o r t h e a t t e n u a t o r d e v i c e r a t h e r than t h e t e r m i n a t o r b u t
t h e power o f f t a k e i s unders tood t o be s i m i l a r . The equipment f o r
t h e a t t e n u a t o r d e v i c e h a s been s p e c i f i e d i n c o n s i d e r a b l e d e t a i l
w i t h drawings and diagrams. The e l e c t r i c a l d e s i g n h a s been f a i r l y
w e l l deve loped ; more s o t h a n t h e mechanical . The d .c . s e r i e s
method o f power a g g r e g a t i o n from t h e d e v i c e s h a s been fo l lowed ,
t h e s w i t c h g e a r , i s o l a t i o n t r a n s f o r m e r s and r e c t i f i e r s be ing
accommodated i n t h e c e n t r a l p l a n t room where c o n d i t i o n s w i l l be
good and a c c e s s r e a d i l y a v a i l a b l e . The t u r b i n e i s l o c a t e d i n a
r a t h e r more h o s t i l e environment a t approx imate ly 2 a tmospheres
p r e s s u r e and s e a l e d o f f from t h e p l a n t room. Access f o r
maintenance can be o b t a i n e d e i t h e r by c l o s i n g t h e i s o l a t i o n v a l v e s
o r by s e a l i n g and p r e s s u r i s i n g t h e p l a n t chamber.
S t a t u s of Assessment Data
The b a s i c d e s i g n o f t h e major e lements o f t h e c i v i l works
a s s o c i a t e d wi th t h i s d e v i c e i s a t an advanced s t a g e and t h e Team
h a s provided p r e l i m i n a r y i n f o r m a t i o n on q u a n t i t i e s and c o s t s which
have been independen t ly checked and found t o be a c c u r a t e t o w i t h i n
about 1% of t h e t o t a l d e v i c e c o s t . The only major d i f f e r e n c e
between Device Team and Consu l tan t s i n t h e s t r u c t u r a l c o s t c e n t r e s
is over t h e type o f f a c i l i t y t o be used. The Team h a s assumed a
s i n g l e l a r g e f a c i l i t y which t h e Consu l tan t s a g r e e would lead t o a
c o s t s a v i n g o f 0.2p/kwh i f cons idered p r a c t i c a b l e .
The p l a n t and t r a n s m i s s i o n d e s i g n i s now reasonab ly w e l l d e f i n e d .
The C o n s u l t a n t s o r i g i n a l l y i n c o r p o r a t e d t h e i r own assessment o f
t h e p l a n t c o s t s and a r e l i a b i l i t y a n a l y s i s i n t o t h e i r c o s t
f i g u r e s . The r e l i a b i l i t y a n a l y s i s was based on f a i l u r e r a t e s
g iven by Y-ARD, and a l though t h e Team's comments on t h e power c h a i n
model have been i n c o r p o r a t e d , t h e C o n s u l t a n t s have n o t a l t e r e d t h e
b a s i c d a t a . The Team subsequen t ly provided t h e i r own c o s t i n g
which s u b s t a n t i a l l y a g r e e s w i t h t h e Consu l tan t s i n a l l b u t two
i tems: t h e t u r b o g e n e r a t o r s e t and t h e t r a n s m i s s i o n scheme. The
c o s t o f t h e t u r b o g e n e r a t o r has now been reso lved and t h e c u r r e n t
c o s t e s t i m a t e s r e v i s e d . However, t h e Consu l tan t s have r e c e n t l y
r e v i s e d upwards t h e c o s t o f a l l t h e Teams ' t r a n s m i s s i o n schemes.
Th is g i v e s an i n c r e a s e of 62% over t h e p r e v i o u s l y agreed f i g u r e ,
a l though t h e C o n s u l t a n t s c o n s i d e r t h a t t h e Team could recoup
approximately 18% ( 0 . 2 p/kwh) by r e d e s i g n i n g t h e t r ansmis S i o n
scheme.
The o r i g i n a l i n s t a l l a t i o n procedure s p e c i f i e d by t h e Device Team
was checked by t h e C o n s u l t a n t s who e s t i m a t e a c o s t approximately
0.2pIkwh h i g h e r than t h e Teams. However t h e c o s t o f m a t e r i a l s used
i n t h e i n s t a l l a t i o n was n o t agreed f o r t h i s procedure . The
C o n s u l t a n t s have r e v i s e d t h e i r c o s t i n g o f t h e d e v i c e i n s t a l l a t i o n
programme i n l i n e w i t h t h e s i m i l a r NEL breakwater d e v i c e and have
e s t i m a t e d a s a v i n g o f 0.55pIkwh over t h e o r i g i n a l method. However
f a c e breakwa
he dep th of W
?board a r e
; ing t h e b r e a
n t ed d e v i c e s ,
i o n of c u r
l l o w i n g d e t ~
r e £ l e c t o r .
ind t h e s t a t
Dn programme,
t o p rov ide a
moment S .
~ b t a i n e d f ror
t h e Team ha:
h t h e Consul
:hod o f e x c i t
l i t a b i l i t y .
i n c r e a s i n g
~ l e f o r t h e
.y s e l f a c t u a
formance .
v i i ) An i n h e r e n t d i s a d v a n t a g e w i t h t h e submerged d e v i c e i s t h a t
t h e enc losed a i r i s above a tmospher ic p r e s s u r e and needs a
compressor supp ly - leakage w i l l e v e n t u a l l y f l o o d t h e
t u r b i n e .
Conclus ion
The major c o s t c e n t r e s i n t h i s d e v i c e a r e s t r u c t u r e ( 4 0 % ) , p l a n t
(16%) and i n s t a l l a t i o n ( 3 0 % ) . Because o f t h e ext reme
env i ronmenta l c o n d i t i o n s o f f t h e c o a s t o f South U i s t i t i s
d i f f i c u l t t o conce ive how t h e c o s t o f t h e b reakwate r element of t h e
s t r u c t u r e could be s u b s t a n t i a l l y reduced.
I t i s p o s s i b l e t h a t a s a v i n g i n s t r u c t u r a l c o s t s could be made i n
t h o s e e lements no t loaded by r e f l e c t i n g waves o r b r e a k i n g wave
f o r c e s . The p l a n t d e s i g n and i n s t a l l a t i o n sequence have been w e l l
though t o u t and would seem u n l i k e l y t o y i e l d s i g n i f i c a n t sav ings .
The most l i k e l y s o u r c e of i n c r e a s e d c o s t e f f i c i e n c y would b e a g a i n
i n p r o d u c t i v i t y , e s p e c i a l l y c o n s i d e r i n g t h e s m a l l amount o f work
t h a t h a s been s p e n t o p t i m i s i n g t h e c u r r e n t d e s i g n . It i s a l s o
p o s s i b l e t h a t d u c t l o s s e s and s c a l e e f f e c t s which have been shown
t o c a u s e s i g n i f i c a n t e r r o r s i n t h e a t t e n u a t o r t e s t s could b e
s i m i l a r l y reduced i n t h e t e r m i n a t o r by b e t t e r d e s i g n o f t h e d u c t
bend.
The t h e o r e t i c a l e f f i c i e n c y o f t h i s d e v i c e i n s e a s which do n o t
o v e r t o p t h e r e f l e c t o r i s 100%. Because t h e r e f l e c t o r i s o n l y 2m
above mean s e a l e v e l t h i s r e s t r i c t s t h e maximum e f f i c i e n c y t o s e a s
w i t h wave h e i g h t s of l e s s t h a n 4m. S ince t h e b o r e and s t r o k e of
t h e d e v i c e is l i m i t e d , t h i s o v e r t o p p i n g is a d e s i r a b l e f e a t u r e and
a l s o c o n s i d e r a b l y reduces t h e f o r c e s on t h e d e v i c e . One of t h e
main d i s a d v a n t a g e s o f t h e d e v i c e i s i t s r e l i a n c e on t h e c r e s t -
spanning mode o f o p e r a t i o n which i s imposed by t h e c l o s e d a i r
c y c l e . D e s p i t e l i n k i n g d e v i c e s i n t o 800m long b l o c k s , t h e
C o n s u l t a n t s s u s p e c t t h a t t h i s is one r e a s o n f o r t h e r e l a t i v e l y low
e f f i c i e n c y o f t h e d e v i c e .
One f e a t u r e of t h e d e v i c e is i t s h i g h power a v a i l a b i l i t y because o f
t h e common mani fo lds which connec t seven g e n e r a t i n g s e t s i n
p a r a l l e l . T h i s p e r m i t s 30% of t h e r a t e d c a p a c i t y t o b e l o s t w i t h
o n l y a 10% r e d u c t i o n i n mean annua l power o u t p u t .
PLAN ON e ~ e t ----W OF aEvrtL-2 A R R ~ Y
LEADIN(; D E V I C E I'ARAFlEl'RRS -p--
(Lociltic>n - South Llist)
ii. Rela t ed t o ldc&02
1. Dis t ance o f f s h o r e (km)
2 . [ l a t e r dep th (or)
3 . Power i n s e a (Kwlm)
B . Re l a t ed t o d e v i c e
1. O v e r a l l s i z e - l e n g t h (m)
- b r e a d t h (m)
- v e r t i c a l d imension (m) 2
- g r o s s c r o s s s e c t i o n a l a r e a (m )
2 . Weight of d e v i c e ( t o n n e s )
3 . Wcight of d e v i c e I l e n g t h ( tonneslm)
C. Reca t ed t o LGIJ s t a t i o n
1. Number of dev i ce s
2 . Spacing of dev i ce s (m)
3 . 1,ength of 2CW s t a t i o n (km) ( e x c l . n a v i g . gaps)
u . w e d t o p r o d u c t i v i t y
1. R a t i n g of g e n e r a t o r s (MW)
2 . Yrwer i n s e a (Kwim)
3. Mrnn annual power d e l i v e r e d t o Skye (Mw/device)*
4. Plean annua l o u t p u t of 2CW scheme (CV)*
E . Re l a t ed t o s t r u c t u r e economy and u t i l i z a t i o n of r e s o u r c e
l . Mean annua l power d e l i v e r e d pe r d e v i c e 5 l eng th of d e v i c e (Kw/n)*
2 . Mean a n n u ~ l power d e l i v e r e d p e r rlcvice I g c v i c e s p a c i n g (Kw/m)*
3. O v e r a l l conve r s ion c f f i c i e n c y o f scheme*
mcJn annua l o u t p u t of 2GW schen~e -- ( X ) mean annua l power i n s e a x l e n g t h of 26W s t a t i o n
4 . Capture Factor**
nican i~iinital power yapcured by d e v i c e ( 2 ) nrcnn anr>ual power I n s e a x d e v i c e l e n g t h
F . Re l a t ed t o c o s t
1. Cost of 2GM s t a t i o n (und i scoun tcd ) (EPI)
2 . Cost of each d e v i c e (und i seoun ted ) (:Pi)
3. Cos t of energy ( d i s c o u n t e d ) (p1Kwh)
C . ? i i s c e l l a n c o u s
1. Eleaii annua l powcr c h a i n c f f i c i e n c y (H)***
2 . A v a i l a b i l i t y of tiic 2CW scheme ( I )
* ir icludiny. a v a i l a b i l i t y f a c t o r
** riot i l~c l c rd ing a v a i l a b i l i t y [ a c t o r
*** mean annua l power landed a t Skye -- ( n o t including a v a i l a b i l i t y f a c t o r ) mean annua l power cap tu red p c r d e v i c e x No. of d e v i c e s i n sclieme
5 ( i i i ) c
General
VICKERS ATTENUATOR
A l / l O o t h s c a l e model o f t h e c u r r e n t r e f e r e n c e d e s i g n h a s been
thorough ly t e s t e d i n t h e wide t ank of Wave Power L t d . , Cadnam. The
p r o d u c t i v i t y d a t a were then o b t a i n e d from t e s t s on t h i s and a
1 1 6 7 ~ " s c a l e model of t h e optimum d e v i c e c o n f i g u r a t i o n i n t h e 46
s e l e c t e d I O S s p e c t r a . The 1167 th s c a l e t e s t s i n d i c a t e a much
b e t t e r performance than t h e s m a l l e r s c a l e t e s t s . Th i s i s p a r t l y
due t o a r e f i n e m e n t i n t h e i n t e r n a l geometry o f t h e d u c t and p a r t l y
due t o t h e f a c t t h a t t h e Team has c a l i b r a t e d t h e l a t e r model s o
t h a t t h e o u t p u t power r e a d i n g i n c l u d e s t h o s e l o s s e s which they
e x p e c t t o d i s a p p e a r a t f u l l s c a l e . The C o n s u l t a n t s have agreed t h e
g e n e r a l p r i n c i p l e of t h i s method bu t a r e i n t h e p r o c e s s o f checking
t h e d e t a i l e d a p p l i c a t i o n . U n f o r t u n a t e l y i t h a s been d i s c o v e r e d
t h a t t h e Team was g i v e n i n c o r r e c t i n f o r m a t i o n abou t t h e s p e c t r a i n
t h e wave t ank and a f a c t o r h a s been a p p l i e d t o t h e i r r e s u l t s t o
accoun t f o r t h i s . Although t h e Device Team is c o n t i n u i n g t o r e f i n e
t h e hydrodynamic performance of t h e d e v i c e , t h e b a s i c concept i s
w e l l developed and h a s n o t changed i n t h e l a s t y e a r .
The on ly s t r u c t u r a l drawing r e c e i v e d by t h e C o n s u l t a n t s , a s y e t ,
i s t h e Genera l Arrangement. Although some thought a p p e a r s t o have
been g i v e n t o dimens i o n i n g t h e members, t h e on ly w r i t t e n d e t a i l s
o f t h e s t r u c t u r a l d e s i g n r e c e i v e d by t h e C o n s u l t a n t s r e f e r t o t h e
wave loads . However, i n s t a l l a t i o n and c o n s t r u c t i o n a r e w e l l
documented .
The mechanical and e l e c t r i c a l p l a n t , a n c i l l a r y equipment and
t r a n s m i s s i o n sys tem have been s p e c i f i e d i n c o n s i d e r a b l e d e t a i l
w i t h drawings and diagrams. The e l e c t r i c a l d e s i g n h a s been f a i r l y
w e l l developed - more s o t h a n t h e mechanical . The d.c. s e r i e s
method o f power a g g r e g a t i o n from 4 MW d e v i c e s h a s been fol lowed,
t h e s w i t c h g e a r , i s o l a t i o n t r a n s f o r m e r s and r e c t i f i e r s b e i n g
accommodated i n t h e c e n t r a l p l a n t room where c o n d i t i o n s w i l l be
good and a c c e s s r e a d i l y a v a i l a b l e .
S t a t u s o f Assessment Data
Although t h e b a s i c d e s i g n o f t h e major e lements o f t h i s d e v i c e is
f a i r l y advanced t h e Team have asked f o r s e v e r a l amendments t o t h e
d e s i g n t o be c o n s i d e r e d a t a v e r y l a t e s t a g e . For v a r i o u s r e a s o n s
t h e s e amendments have n o t been p r o p e r l y d e t a i l e d b u t d e s p i t e t h e
u n s a t i s f a c t o r y n a t u r e o f t h e p r e s e n t a t i o n t h e C o n s u l t a n t s have
a t t empted t o i n c o r p o r a t e t h e s e r e v i s i o n s i n t o t h e l a t e s t c o s t
e s t i m a t e s . The c o s t s o f t h e c i v i l a s s o c i a t e d w i t h t h e d e s i g n which
was though t t o b e E ina l a t t h e beg inn ing of January 1982 were
agreed w i t h t h e Device Team. M o d i f i c a t i o n s made t o t h e s h e l l
s t u c t u r e o f t h e d e v i c e have a l s o been c o s t e d and more o r l e s s
ag reed w i t h t h e Device Team. However, t h e m o d i f i c a t i o n t o t h e
c o s t of t h e end s u p p o r t h a s been made u n i l a t e r a l l y by t h e
C o n s u l t a n t s s i n c e i t i s d i f f i c u l t t o e x t r a c t t h e r e q u i r e d f i g u r e
from t h e Dev ice Team's o v e r a l l i n s t a l l a t i o n c o s t .
The p l a n t and t r a n s m i s s i o n d e s i g n is now reasonab ly w e l l d e f i n e d .
The C o n s u l t a n t s o r i g i n a l l y i n c o r p o r a t e d t h e i r own assessment of
t h e c o s t o f t h e p l a n t and a r e l i a b i l i t y a n a l y s i s i n t o t h e i r c o s t
f i g u r e s . The r e l i a b i l i t y a n a l y s i s was based on f a i l u r e r a t e s
s p e c i f i e d by Y-ARD i n a s s o c i a t i o n w i t h t h e power c h a i n s p e c i f i e d
by t h e Team. Th i s f i g u r e h s n o t been modi f i ed . The Team
s u b s e q u e n t l y provided t h e i r own c o s t i n g which s u b s t a n t i a l l y a g r e e s
w i t h t h e C o n s u l t a n t s i n a l l b u t two i t ems : t h e t u r b o g e n e r a t o r s e t
and t h e t r a n s m i s s i o n scheme. The c o s t o f t h e t u r b o g e n e r a t o r h a s
now been r e s o l v e d and t h e c u r r e n t c o s t e s t i m a t e s r e v i s e d . However,
t h e C o n s u l t a n t s have r e c e n t l y r e v i s e d upwards t h e c o s t o f a l l t h e
Teams' t r a n s m i s s i o n schemes. Th i s g i v e s a n i n c r e a s e o f 62% over
t h e p r e v i o u s l y agreed f i g u r e , a l t h o u g h t h e C o n s u l t a n t s c o n s i d e r
t h a t t h e Team could recoup approx imate ly 18% (0.2pIkwh) by
r e d e s i g n i n g t h e t r a n s m i s s i o n scheme.
The i n s t a l l a t i o n c o s t s have been developed by t h e C o n s u l t a n t s w i t h
v e r b a l i n p u t s from t h e Device Team. Subsequen t ly t h e Team h a s
i s s u e d an i n s t a l l a t i o n manual and s e v e r a l amendments which have
been checked by t h e C o n s u l t a n t s and found t o a g r e e i n most
p a r t i c u l a r s . Maintenance c o s t s have been p r o v i s i o n a l l y a s s e s s e d
by t h e C o n s u l t a n t s u s i n g i n f o r m a t i o n from t h e Device Team, YARD
and EASAMS.
Development
Although t h e d e v i c e d e s i g n h a s remained more o r l e s s f i x e d s i n c e
l a t e 1980, two r e c e n t m o d i f i c a t i o n s have been made t o i n c r e a s e i t s
c r e d i b i l i t y and performance. The f i r s t was t o change from a n
a l t e r n a t i n g f low t o a r e c t i f i e d f low scheme w i t h a c e n t r a l p l a n t
chamber and a more c o n v e n t i o n a l u n i - d i r e c t i o n a l a i r t u r b i n e . Th i s
has a l lowed t h e g e n e r a t o r and a n c i l l a r y p l a n t t o b e l o c a t e d i n a
c l o s e d machinery h a l l a t a tmospher ic p r e s s u r e g i v i n g b e t t e r
r e l i a b i l i t y and e a s i e r a c c e s s t o t h e e l e c t r i c a l p l a n t f o r
maintenance. The t u r b i n e i s p r e s s u r i s e d and needs a means o f
i s o l a t i o n . The second change was t o i n c r e a s e t h e bend r a d i u s i n
t h e w a t e r column d u c t . Th i s a l t e r a t i o n h a s been i n c o r p o r a t e d i n t o
t h e new 1 1 6 7 ~ ~ s c a l e model made f o r t h e p r o d u c t i v i t y t e s t s .
F e a s i b i l i t y
The c u r r e n t r e f e r e n c e d e s i g n s t r u c t u r e i s made up o f t h r e e
d i f f e r e n t components, t h e c a i s s o n , t h e o u t e r s u p p o r t s and t h e OWC
c e l l modules, each o f which can be compared t o a s i m i l a r
c o n v e n t i o n a l s t r u c t u r e . The on ly e x t r a p o l a t i o n from c u r r e n t
p r a c t i c e i s t h e i n s t a l l a t i o n o f t h e s e s t r u c t u r e s i n a n exposed
l o c a t i o n . However t h e Team's proposed i n s t a l l a t i o n method h a s
been c o n s i d e r e d i n d e t a i l by t h e C o n s u l t a n t s and t h e c o s t s have
been based on t h e C o n s u l t a n t s ' t iming of each s t e p i n t h e
procedure .
The mechan ica l and e l e c t r i c a l power c h a i n i s r e l a t i v e l y
convent i o n a l . A 1 though a c c e s s t o t h e g e n e r a t o r and a n c i l l a r y
p l a n t i s s t r a i g h t f o r w a r d , t h e t u r b i n e and v a l v e boxes a r e r a t h e r
more d i f f i c u l t t o m a i n t a i n b e i n g s i t u a t e d i n p r e s s u r i s e d a i r .
G e n e r a l l y , however, t h e r e appear t o be no major p r a c t i c a l
d i f f i c u l t i e s invo lved i n t h e c o n s t r u c t i o n , i n s t a l l a t i o n o p e r a t i o n
o r maintenance o f t h i s d e v i c e .
The C o n s u l t a n t s have some r e s e r v a t i o n s abou t d e t a i l e d a s p e c t s o f
t h e des ign . These a r e :
i ) Acknowledged u n c e r t a i n t i e s i n t h e a n a l y s i s o f t h e b reak ing
wave loads on t h e c a i s s o n which w i l l p robab ly r e q u i r e a
model s tudy .
i i ) Loads between t h e c e l l modules and t h e f o u n d a t i o n s d u r i n g
emplacement .
i i i ) The s m a l l t o l e r a n c e s r e q u i r e d on t h e s e a bed p r e p a r a t i o n
under t h e c a i s s o n .
i v ) The r e s i s t a n c e t o s l i d i n g of t h e c a i s s o n s t r u c t u r e . The
C o n s u l t a n t s would p r e f e r t o s e e a d e f i n i t e s h e a r key.
v ) The i n t e r n a l OWC l o s s e s measured by t h e Team a r e v e r y h i g h
and t h e C o n s u l t a n t s would l i k e a more thorough i n v e s t i g a t i o n
o f t h e mechanism o f t h e s e l o s s e s t o e n s u r e t h a t they w i l l n o t
be s i g n i f i c a n t a t f u l l s c a l e .
v i ) The g e n e r a t o r i t s e l f i s c o n v e n t i o n a l b u t t h e Team h a s n o t
adopted b r u s h l e s s t h y r i s t o r e x c i t a t i o n which t h e C o n s u l t a n t s
cons i d e r i s e s s e n t i a l . Furthmore t h e method of e x c i t a t i o n
proposed by t h e Team i s of d o u b t f u l s u i t a b i l i t y . The
C o n s u l t a n t s a l s o c o n s i d e r t h a t t h e speed i n c r e a s i n g b e l t
d r i v e f o r t h e p i l o t e x c i t e r i s u n d e s i r a b l e f o r t h e d u t y
r e q u i r e d .
v i i ) The c e l l a i r v a l v e s a r e l a r g e and a p p a r e n t l y s e l f a c t u a t i n g .
Any l eakage w i l l n u l l i f y column performance.
Conc l u s i o n
The major c o s t c e n t r e s i n t h i s d e v i c e a r e s t r u c t u r e ( 4 2 % ) , p l a n t
(20%) and i n s t a l l a t i o n ( 2 2 % ) . The l a t e s t m o d i f i c a t i o n t o t h e
d e v i c e h a s been t o r educe t h e t h i c k n e s s and s i m p l i f y t h e
c o n s t r u c t i o n of t h e main OWC h u l l s . The Team h a s i n d i c a t e d t h a t i t
would l i k e t o go f u r t h e r and change t h e c o n f i g u r a t i o n of t h e d e v i c e
by r e v e r s i n g t h e f low and p l a c i n g o s c i l l a t i n g wa te r columns a t t h e
o u t s i d e w i t h t h e i n l e t d u c t between them. By t h i s means t h e Team
hope t o i n c r e a s e t h e h u l l s t r e n g t h and d e v i c e e f f i c i e n c y w i t h a
r e d u c t i o n i n t h e q u a l i t y o f m a t e r i a l s r e q u i r e d . Furthmore, by
i n c r e a s i n g t h e swept volume o f t h e d e v i c e t h e Team f e e l t h a t they
would reduce t h e u n i t c o s t a l l o c a t e d t o t h e p l a n t c a i s s o n , p l a n t
module, i n s t a l l a t i o n and t h e c o l l e c t i o n network. The Team
c o n s i d e r t h a t t h e o p t i m i s a t i o n of t h e model s c a l e by which t h i s
d e v i c e was d e f i n e d d i d n o t f u l l y accoun t f o r t h e h i g h f i x e d c o s t s
a s s o c i a t e d w i t h each d e v i c e .
The i n s t a l l a t i o n method h a s a l r e a d y been c o n s i d e r e d i n some d e t a i l
and can on ly be s i g n i f i c a n t l y reduced by e l i m i n a t i n g c e r t a i n key
o p e r a t i o n s which r e q u i r e c o n c e r t e d a c t i o n between d i v e r s and
s u r f a c e p e r s o n n e l . Th i s type of o p e r a t i o n h a s been r e s t r i c t e d t o
lm s e a s t a t e s i n d a y l i g h t and t h e r e f o r e i n v o l v e s a l a r g e amount o f
w a i t i n g t ime f o r t h e e x p e n s i v e i n s t a l l a t i o n p l a n t .
T h i s type o f d e v i c e , b e i n g submerged, can never hope t o be a s
e f f i c i e n t a s a s u r f a c e p i e r c i n g d e v i c e i n p r a c t i c e , a l t h o u g h t h e
t h e o r e t i c a l e f f i c i e n c y o f a n a t t e n u a t o r a r r a y i s 100%. The
C o n s u l t a n t s c o n s i d e r t h a t t h e r e i s some room f o r improvement i n
t h e d e v i c e e f f i c i e n c y and t h a t t h e s t r u c t u r a l c o s t s could s t i l l be
reduced. The main a t t r a c t i o n of a submerged d e v i c e i s t h e lower
f o r c e t o which i t i s s u b j e c t e d . T h i s a l lows o p t i m i s a t i o n of t h e
d e v i c e c o n f i g u r a t i o n w i t h o u t major s t r u c t u r a l c o n s t r a i n t s and t h e
C o n s u l t a n t s c o n s i d e r t h a t some improvements i n t h e d e s i g n ,
i n c l u d i n g an i n c r e a s e i n of t h e swept volume, can s t i l l b e
ach ieved .
BELFAST
3 W C - BOTTOM STANDING- BELFAST PO I NT ABSORBER
LOCATION OF SCHEME
18m.dia. 7 1
€LE V A T l ON ARRAY
DIMENSIONS
h / a d ~ dt;rctt'om __C -
--b. Yi. -' -1-z , - ~ c -- - * P > * -
WAVC R I S I N G WAVE; FALLJNC
W O R K IMG C Y C L E
I.E.4DlNG i)i:VT(:I:. 1'AIUMT:TI:RS - - - - - - --W -- - - - (Locnt ion - Scluth U i s t ) - - . -. . . - - -
I%l<l.FAS'S
A . Rc ln t ed t o l o c a t i o n
1 . D i s t ancc o f f s l i o r e (km)
2. Watcr r l c l ~ t l ~ (m)
3. Powcr i n s e a (Kwlm)
B. Re l a t cd t o d e v i c e
1 . O v e r a l l s i z e - 1eni:th (m)
- b r e a d t h (m) 18m d i ame te r
- v e r t i c a l d imension (m) 5 1 2 - g r o s s c r o s s s e c t i o n a l a r e a (m ) 254
2 . Weight of d e v i c e ( t o n n e s )
3 . Weight of d e v i c e ? l e n g t h ( t onnes im)
C . Re l a t ed t o 2GW s t a t i o n
l . Number of d e v i c e s
2 . Spacing of d e v i c e s (m)
3 . Lengtlr o i 2GW s t a t i o n (km) ( e x c l . n a v i g . gaps )
D . R e l a t e d t o p r t l d u c t i v i t y
1 . Ratin:: o f g e n e r a t o r s (MW) 6 x 0 . 2 5 Mwidcvice
2 . Power i n s e a (Kwlm) 41.7
3 . Elcan annua l powcr delivered t o Skye (PLw/drvicc)* 0 . 2 5
4. Meali ;~rill~i:il o u t p u t of 2 G W scheme ((;IJ)* 0 .48
I:. Re l a t ed t o structure cconomy iinci u t i l i z a t i o n of r e s o u r c c -p- - -
1 . Mcnri . ~ n ~ i u . ? l power- d e l i v e r e d p e r dcvicc? + l eng th of dev i ce (Kw/m)*
2 . Plc:iri nr?n:l;tl powcr d e l i v e r e d p e r d e v i c e + c!evicc spac ing (K1,7/m)*
3 . O v c r a i l coriversiou r [ Eicic,nvy oC achcne*
rnenri :~nntinl ~ , u t p u ~ 01' :'.G\\' :;ch(.rt~c . - - . - - - - - - - -. - - - .- - . (1) Inearl ;rnnunl powt!r i r i :,cc1 7. lcngt.11 01 iCI; !; ta t io i \ .
mean annua l power capturccl l>y d e v i c e ( 9 ) mean annua l powcr i n s e a u rlcvice l c n g t l ~
F. Rela t ed t o c o s t
1. Cost of 2GW s t a t i o n (undiscountc!d) ( E M )
2. Cost of each d e v i c e (und i scoun ted ) ( E M )
3. Cost of cnergy (discounted) (p/Kwh)
G . Mi sce l l aneous
1 . Mc.m .lrrnual powcr c h a i n e t t i c i e n c y ( % ) " * A
2 . A v a i l a b i l i t y of t h e 2GW schcmc ( I )
1900
90m i n a r r a y
85.5
* i n c l u d i n g a v n i l n l ~ i l i t y f a c t 0 1
""lot i n c l u d i n g a v a i l . i b i l i t y f a c t o r
**" mean annua l p ~ i . r e ! _ ~ n t l c c l a t Sky? - -- -- (no t i n c l u d i n g a v a i l a b i l i t y f a c t o r ) mran annua l powPr cap tu red pe r d e v i c e X No. of d e v i c e s h scheme
COST BREAKDOlm 6
f X 10 discounted 2GW Scheme Per 3svice
6 f X 10 undiscounted P------ - 2GW Scheme Per Device
QUEENS UNIVERSITY BELFAST
Structure Construction facility and operation Launch devices Device structure
932.3 C!. $9 96.3 2.05 156.3 (3.08 1184.9 0.62
Valves and ducts Ancillary
Installation Bed reparation Plant and operations
Transmission Generator output to islands Inverters and substations on islands Transmission to Skye
CAPITAL COST 7266.1
Ma i.n t enanc e Maintenance base overheads and operations Vessels, divers and technicians for inspection & repair M & E Spares
MAINTENANCE COSTS 2595.7 --
5 ( i i i ) d QUEEN'S U N I V E R S I T Y , BELFAST DEVICE
The Team h a s c a r r i e d o u t t e s t i n g i n i t s own narrow t a n k and h a s
a l s o worked i n t h e wide t ank a t Edinburgh, producing p r o d u c t i v i t y
r e s u l t s f o r t h e 46 IOS s e l e c t e d s p e c t r a . The Team h a s n o t c a r r i e d
o u t any measurements r e l a t i n g t o wave load ing on t h e d e v i c e .
The C o n s u l t a n t s have n o t r e c e i v e d any c a l c u l a t i o n s o r
s p e c i f i c a t i o n from t h e Team. QUB s a y they have des igned f o r 1 i n
50 y e a r waves and t h a t o u t l i n e c a l c u l a t i o n s f o r t h e s t r u c t u r e ,
c o n s i s t e n t wi th the r a t e o f development, have been made. The
s t r u c t u r e i s a n i n h e r e n t l y s t r o n g shape and should work
s a t i s f a c t o r i l y i n t h e form proposed.
The Team h a s submi t t ed a r e p o r t on c o n s t r u c t i o n and i n s t a l l a t i o n ;
t h e C o n s u l t a n t s g e n e r a l l y a g r e e wi th t h e methods proposed and
c o n s i d e r t h a t they a r e t e c h n i c a l l y f e a s i b l e .
QUB i n t e n d u s i n g s i x Wel ls t u r b i n e s f o r each d e v i c e , coupled t o a
d i r e c t l y d r i v e n 2 5 0 kW g e n e r a t o r . The d e t a i l e d d e s i g n o f t h e
t u r b i n e g e n e r a t o r u n i t and i t s a s s o c i a t e d d u c t i n g h a s r e c e n t l y
been submi t t ed . The Team i s p ropos ing a twin t u r b i n e hav ing two
s t a g e s , mounted on a h o r i z o n t a l a x i s . A s a n a l t e r n a t i v e t o t h e
u s u a l , 4 4 0 V synchronous type a l t e r n a t o r s , QUB a r e a l s o unwisely
c o n s i d e r i n g o p e r a t i n g t h e machine a t f u l l d .c . loop v o l t a g e ,
r e t a i n i n g t h e d i o d e r e c t i f i e r b u t e l i m i n a t i n g t h e t r a n s f o r m e r .
The method o f power c o l l e c t i o n i s t h a t g e n e r a l l y adopted f o r
v a r i a b l e speed g e n e r a t i n g sys tems. Cos t s have n o t y e t been g i v e n
by t h e Team.
S t a t u s o f Assessment Data
The b a s i c d e s i g n and c o n s t r u c t i o n a l d e t a i l i n g o f t h i s d e v i c e a r e
i n o u t l i n e form o n l y and t h e C o n s u l t a n t s ' c o s t e s t i m a t e i s based on
t h e i r own a p p r a i s a l o f t h e l i k e l y form o f t h e c o n s t r u c t i o n a l
d e t a i l s . However, t h e Device Team h a s provided t h e i r own c o s t
e s t i m a t e f o r a s u b s t a n t i a l p a r t o f t h e works which a p p e a r s t o be i n
resonab ly c l o s e agreement wi th t h e C o n s u l t a n t s e s t i m a t e .
The assessment o f t h i s d e v i c e h a s been c a r r i e d o u t u s i n g t h e
C o n s u l t a n t s ' p r e l i m i n a r y e s t i m a t e of t h e e l e c t r i c a l p l a n t c o s t s i n
c o n j u n c t i o n w i t h a c o s t f o r t h e mechanical p l a n t provided by t h e
Team. Cabl ing f o r power c o l l e c t i o n h a s been e s t i m a t e d assuming
S e r i e s i n t e r c o n n e c t i o n o f d e v i c e s and t h e remainder o f t h e
t r a n s m i s s i o n h a s been c o s t e d a s f o r o t h e r s i m i l a r schemes.
The c o s t s o f i n s t a l l a t i o n have been developed by t h e C o n s u l t a n t s
w i t h v e r b a l i n p u t s from t h e Device Team. Maintenance c o s t s have
been p r o v i s i o n a l l y a s s e s s e d by t h e C o n s u l t a n t s i n advance o f f i n a l
i n f o r m a t i o n from t h e Device Team, YARD and EASAMS.
The r e f e r e n c e d e s i g n under c o n s i d e r a t i o n h a s m a i n t a i n e d , s i n c e i t s
i n c e p t i o n i n 1977, t h e p r i n c i p l e s of a p o i n t a b s o r b i n g o s c i l l a t i n g
wa te r column d e v i c e . I t u s e s a i r d r i v e n Wells t u r b i n e s .
Throughout, t h e Team's phi losophy h a s been t o keep t h e d e v i c e
s imple , bo th i n terms o f s t r u c t u r e and power t a k e o f f . Development
h a s been aimed a t improving and o p t i m i z i n g performance, p r i m a r i l y
by means o f p a r a m e t r i c hydrodynamic s t u d i e s and fundamental
r e s e a r c h i n t o improved Wells t u r b i n e c h a r a c t e r i s t i c s .
The major change t o s i x c e l l s was made i n January 1981. The
d e c i s i o n t o bottom mount t h e d e v i c e was made i n August 1981
fo l lowing i n i t i a l wide t ank t e s t i n g i n Edinburgh and t h e form o f
t h e r e f e r e n c e s t r u c t u r e was f r o z e n i n November 1981.
F e a s i b i l i t v
Using a m u l t i s t a g e t u r b i n e n e c e s s i t a t e d by column damping
requ i rements w i l l add t o t h e c o s t and complexi ty o f t h e power t a k e
o f f . Other teams have found t h a t i n l e t g u i d e vanes ( b i -
d i r e c t i o n a l ) improve performance: t h i s may be a l s o t h e c a s e f o r
t h e B e l f a s t Device. The d e s i g n o f a s i n g l e s t a g e t u r b i n e provided
by t h e Team's i n d u s t r i a l a d v i s e r s appears t o be e n t i r e l y
p r a c t i c a b l e , a l though performance under s imula ted wave c o n d i t i o n s
needs t o b e i n v e s t i g a t e d . The p r o p o s a l t o o p e r a t e t h e g e n e r a t o r a t
d . c . sys tem v o l t a g e s a v e s l i t t l e c o s t and i n v o l v e s a l a r g e r
machine and probably a h i g h e r e l e c t r i c a l f a i l u r e r a t e .
The key a r e a s o f t h e s t r c l c t u r a l d e s i g n which r e q u i r e f u r t h e r
deve l opment a r e :
i ) d e s i g n o f t h e p i l e t o c a i s s o n j o i n t ; no d e t a i l s o f t h i s have
been p roposed . The a r e a i s h i g h l y s t r e s s e d and i m p o r t a n t t o
t h e i n t e g r i t y o f t h e s t r u c t u r e . The c o n n e c t i o n h a s t o be
made unde r w a t e r . KPT c o n s i d e r t h a t a s u i t a b l e d e s i g n f o r
t h i s j o i n t c a n be made.
i i ) d e s i g n and development o f a s emi - submers ib l e jack-up
d r i l l i n g v e s s e l c a r r y i n g t h r e e o r s i x d r i l l h e a d s . A v e s s e l
o f t h i s t y p e i s r e q i r e d by most o f t h e b o t t o m s t a n d i n g
d e v i c e s and RPT do n o t q u e s t i o n t h e f e a s i b i l i t y o f t h e
c o n c e p t .
C o s t s
The Team h a s s u b m i t t e d c o s t s f o r c i v i l c o n s t r u c t i o n and
i n s t a l l a t i o n ; t h e s e f i g u r e s a r e i n g e n e r a l ag reemen t w i t h t h e
c o s t s e s t imated by t?ir Cons111 t a n t s . The ~ o n s n l t a n t s ' c o s t s a r e
based on 1900 d e v i c e s t o be c o n s t r u c t e d o v e r a 10 y e a r p e r i o d .
Based upon t h e i r l a t e s t p r o d u c t i v i t y f i g u r e s , t h e Team c a l c u l a t e d
t h a t 1336 d e v i c e s a r e r e q u i r e d t o f u l f i l t h e 2 GW scheme
r e q u i r e m e n t , b u t R P r have i n s u f f i c i e n t i n f o r m a t i o n t o v e r i f y t h i s .
Conc l u s i o n
T h e r e i s no doub t t h a t t h e B e l f a s t Dev ice i s t e c h n i c a l l y f e a s i b l e
i n a l l r e s p e c t s , and a p r o t o t y p e c o u l d be c o n s t r u c t e d and
i n s t a l l e d u s i n g t e c h n i q u e s a l r e a d y p roven . The b a s i c c o n c e p t i s
r o b u s t and s h o u l d prove r e l i a b l e . The Device i s n o n - d i r e c t i o n a l
and n e c e s s a r i l y over-p1 a n t e d .
The C o n s u l t a n t s s h a r e w i t h t h e Team t h e v iew t h a t t h e r e i s
cons i d e r a b l e s cope f o r deve lopmen t o f t h e d e v i c e , which i n i-ts
p r e s e n t form h a s o n l y been s t u d i e d f o r a few months . QUB i s a iming
a t h a l v i n g t h e c o s t o f power i n t h e s h o r t t e rm by a c o m b i n a t i o n o f
improved p r o d u c t i v i t y and by h a v i n g an o p t i m i z e d s t r u c t u r a l s i z e .
The most impor tan t a r e a f o r development is on p r o d u c t i v i t y which
t h e Team admits i s d i s a p p o i n t i n g l y low, due l a r g e l y t o t h e d e v i c e
hav ing t o o low a r e s o n a n t p e r i o d . F u r t h e r narrow tank t e s t i n g i s
c u r r e n t l y be ing performed, s t u d y i n g p r i m a r i l y t h e r e s u l t s of a
v a r i a t i o n o f t h e J - tube e n t r a n c e a n g l e .
The Team h a s s t u d i e d o p t i m i z a t i o n of t h e s t r u c t u r a l and
i n s t a l l a t i o n c o s t s , t a k i n g i n t o accoun t t h a t a b i g g e r d e v i c e w i l l
c a p t u r e more power, p a r t i c u l a r l y i n t h e longer p e r i o d waves. Th i s
s t u d y showed t h a t c o s t was a lmost independent of s i z e and
t h e r e f o r e t h e Device s i z e h a s n o t been changed. F u r t h e r
o p t i m i z a t i o n s t u d i e s could a l s o be made on t h e d e p t h below w a t e r
l e v e l o f t h e p i l e / c a i s s o n j o i n t .
I n t h e longer term, i t w i l l be n e c e s s a r y f o r t h e Team t o c a r r y o u t
wide t ank t e s t i n g on a r r a y s o f p o i n t a b s o r b e r s i n o r d e r t o o p t i m i z e
spac ing and t o improve t h e r e s o u r c e u t i l i z a t i o n , which a t t h e
moment i s low. The Team c o n s i d e r s t h a t more i n f o r m a t i o n on t h e
v a r i a t i o n o f a v a i l a b l e energy w i t h d e p t h must be o b t a i n e d b e f o r e
meaningful s t u d i e s on d e p t h o p t i m i z a t i o n can be c a r r i e d o u t .
NEL FLOATING TERMINATOR
OWC-SPI NE FLOAT1 NG -NEL TERMINATOR L 2 4 kB1
I -- -- 2 6 3 . m -
f ' r eda$s* \ - . . t t f w a v e d I ~ Q L ~ \ o ~ , PLAN ON FLOAT\NG M Q D U L E
WAVE FALLIMG WAVE RISI dG
D1 AGRAMMPTc REPRESENTATION OF O P E R A ~ l t d 4 CYCLE: .
LEADING IIEVICE PARAMETERS -- (Loca t ion - !;out\\ U i s t )
N.E.L. 1:LOh'TINf: TIZHMINATOR
A . Rela t ed t o l o c a t i o n
1 . D i s t , ~ n c c o f f s h o r e (km)
2 . Water dep th (m)
D. Powcr i n s e a (KwJm)
3 . Rela t ed t o d e v i c e
1. O v c r ; ~ l l s i z e - lengl-h (m)
- b r e a d t h ( m )
- v e r t i c a l dinlension (m) 19 2 - g r o s s c r o s s s e c t i o n a l a r e a (m ) 532
2 . Weight oC ~ i c v i c e ( t o n n e s ) 66000
1. Weigiit of J c v i c c + l e n g t h (tonncs/tn) 251
2 . Spacillg oE dev i ce s (111)
3 . 1.cngth ~f 2GM s t n t i o r ~ (km) ( e x c l . 17avig. 8 . 1 ~ ~ )
n. l < e l a t e l t o p r o d u c t i v i t y
1. R.itinp, of g e n e r a t o r s (Elw)
2 . Povcr i n s e a (Kwlm)
3 . Mcau nnrur;il power d e l i v e r e d t o S1:yc (Mw/device)* 2 . 1 1
4 . Mean annua l o u t p u t of 2CW schci!!c ((; id)* 0.389
E . _Rciaivd t u s t r u c t . u r e ocol1umv and u t i l i z a t i u 1 1 U E rcsorircc:
l . Ple;ln nnriu.11 power d c l i v c r e d p e r dcvii-c + l eng th o f i levice ( ~ v l r n ) "
2 . Picnn :int~u.rl power ~ l e l i v e r e d ;irr i levicc f d e v i c , ~ spac ing (Kw/m)*
3. Ovc rn l l conve r s ion c f f i c i c i l c y of r,cl~cnie*
mean annual o u t p u t of 2CId s ~ h ~ -- ( X ) mcnn annua l powfr i n s e a x l c n g t h of 2GW s t a t i o n
4 . Cap tu re Factor**
mean annua l poucr cap tu red 11y d e v i c e ( X ) rncan annual powcr i n s e a x d e v i c e l e n g t h
F . !elated t o c o s t
1. Cost of 2CW s t a t i o n (unciiscouilted) (01)
2 . Cost o f e a c i ~ d e v i c e ( i lndiscoi~ntc t ! ) (LP[)
3 . Cost of cl\erp,y ( d i s c o u n t e d ) (p/Kwh)
C . ? ~ i s c e l l a n r o u s
1. Hean anr:ual power cha in e f f i c i e n c y ( X ) " " *
2 . A v a i l a b i l i t y of chc 2CW scheme ( X )
3 .
4 .
fi i l iclrlding avili l a b i l i t y f a c t o r
*;? no t i nc lud in l : a v n i l n h i l i t y f a c t o r
h** 111ea1i i~r inual 1~uwcr-la11ded a t Skye ( n o t i n c l u d i n g a v a i l e b i l i t y f a c t o r ) mcnn aniiudl power cap tu red p e r d c v i c e X No. of d e v i c e s i.n schenle
5 ( i i i ) e NEL FLOATING TERMINATOR
1. GENERAL
1.1 DESIGN
The s t r u c t u r a l c a l c u l a t i o n s f o r t h e d e v i c e a r e based on t h e
methods developed f o r t h e d e s i g n of t h e A t t e n u a t o r and a r e i n
accordance w i t h t h e NEL OWC Note 30 and t o a p p r o p r i a t e d e s i g n
c r i t e r i a . The d e v i c e team's d e s i g n phi losophy i s f u l l y
a c c e p t a b l e t o t h e C o n s u l t a n t s .
The Team h a s r e c o g n i s e d t h a t t h e d e v i c e l e n g t h o f 263m w i l l
c a l l f o r a thorough check on t o r s i o n a l load ing d u r i n g
i n s t a l l a t i o n and o p e r a t i o n . T h i s work i s b e i n g under taken
w i t h f u l l l i a i s o n w i t h t h e C o n s u l t a n t s and i t i s n o t
a n t i c i p a t e d t h a t any m o d i f i c a t i o n s t h a t may be found n e c e s s a r y
t o i n c r e a s e t h e t o r s i o n a l r i g i d i t y w i l l have a s i g n i f i c a n t
e f f e c t on c o n s t r u c t i o n c o s t s .
I t i s apparen t t h a t t h e mooring sys tem i s v e r y much a p a r t o f
t h e o v e r a l l d e s i g n bo th a s r e g a r d s s t a t i c and dynamic l o a d i n g
on t h e device/mooring i n t e r f a c e . The C o n s u l t a n t s a r e i n
c o n t a c t w i t h t h e f u r t h e r d e s i g n work b e i n g under taken by SBM
and a r e aware o f i t s p o s s i b l e i m p l i c a t i o n s on t h e s t r ~ i c t u r a l
d e s i g n of t h e d e v i c e . Again i t i s n o t expec ted t h a t any
n e c e s s a r y m o d i f i c a t i o n s w i l l have a s i g n i f i c a n t c o s t p e n a l t y .
1.2 TANK TESTING
The d e v i c e h a s been t e s t e d f o r t h e 46 s p e c t r a and t h e s e t e s t s
t o g e t h e r w i t h p a r a l l e l a n a l y s e s under taken by NEL i n d i c a t e
t h a t t h e d e v i c e h a s a hydrodynamic e f f i c i e n c y o f 25%. T h i s i s
low i n comparison w i t h o t h e r d e v i c e s b u t , a s d i s c u s s e d l a t e r ,
i s compensated by t h e o v e r a l l c a p t u r e p o t e n t i a l a t l O O m d e p t h
and t h e h i g h e r number o f c e l l s t h a t can be i n c o r p o r a t e d i n one
module (12 no. c e l l s ) r e s u l t i n g i n an o v e r a l l need f o r on ly 185
d e v i c e s a s compared t o 589 d e v i c e s i n t h e c a s e o f t h e Raised
Breakwater , b o t h f o r a nominal 2 GW s t a t i o n . T e c h n i c a l
Advisory Group 2 have r e c e n t l y recommended a r e d u c t i o n i n t h e
t h e power a v a i l a b l e a t 100m dep th which h a s been i n c o r p o r a t e d
i n t o the d e v i c e assessment b u t not t h e d e v i c e o p t i m i s a t i o n .
L . .3 S P E C 1 FICA'CION
I n f o r m a t i o n t o d a t e i s b r o a d l y based on t h e NEL summary of
Mechanical and E l e c t r i c a l P l a n t Ra t ing and P r o d u c t i v i t y 20th
November, 1981, on the s t r u c t u r a l d e s i g n phi losophy a s used i n
t h e A t t r n u a t o r d e s i g n and on t h e e a r l i e r NEL r e f e r e n c e
d e s i g n s . Close l i a i s o n h a s been mainta ined between t h e Device
Team and t h e C o n s ~ ~ l t a n t s on any developments and major
m o d i f i c a t i o n s .
Due t o on-going work on. t h e d e s i g n and t h e c a p t u r e phi losophy
a s d i s c u s s e d l a t e r , t h e Device T ~ a m h a s n o t y e t produced a
forrnal s p e c i f i c a t i o n .
F u l l co -opera t ion h a s been main ta ined between t h e Device Team
and t h e C o n s u l t a n t s on c o n s t r u c t i o n c o s t s a n d t h e in fo rmat ion
t h a t i s becoming a v a i l a b l e on i n s t a l l a t i o n c o s t s a s t h e
mooring d e s i g n approaches complet ion. Good agreement h a s been
reached on t h e s t r u c t u r a l c o s t i n g and t h e mooring phi losophy.
Owing t o t h e above c o n t i n u i n g m o d i f i c a t i o n s a formal
p r e s e n t a t i o n of c o s t i n g f o r t h e d e v i c e h a s n o t y e t been
provided by the Device Team.
2 . DEVELOPMENT
2.1 GENERAL
rhe F l o a t i n g Termina to r r e p r e s e n t c the most up-to-date of t h e
Osc i l l a t ing Water Column d e v i c e s a s o r i g i n a l l y conce ived ,
namely a moored t e r m i n a t o r s q u a r e t o the s e a . I t i s
immediately e v i d e n t t h a t any c o s t and e n g i n e e r i n g p e n a l t i e s
r e l a t e d t o t h e i n s t a l l a t i o n and up-keep of t h e moorings i s
compensated by t h e long-term average s e a power o b t a i n i n g a t
lOOm dep th ( 5 3 . 5 ~ w / m ) .
2.2 MAN IFOLD I N G
I n J u n e and J u l y o f t h i s y e a r t h e concept o f man i fo ld ing s i x o f
t h e 1 2 c e l l s i n t o o n e AC power u n i t , i . e . two such power u n i t s
p e r 1 2 c e l l d e v i c e , was examined by t h e Device Team. It was
a n t i c i p a t e d t h a t t h e smoothed power i n p u t , t h e s i m p l e r p l a n t
r equ i rement and t h e reduced dev ice - to - shore t r a n s m i s s i o n could
produce u s e f u l economies w i t h a s m a l l c a p t u r e l o s s . The
r e s u l t s o f t ank t e s t i n g d i d n o t s u p p o r t t h i s view and t h e
sys tem d i s c u s s e d i n t h i s n o t e t h e r e f o r e comprises a 1 :l c e l l
t o t u r b i n e l g e n e r a t o r r a t i o . The p o s s i b i l i t y o f man i fo ld ing is
s t i l l b e i n g examined and t h e c u r r e n t Cadnam t e s t s on a r a i s e d
b reakwate r d e v i c e u s e s a manifolded model.
2 . 3 CHANGES TO DEVICE PROFILE
I t i s expected t h a t t h e p r o f i l e of t h e d e v i c e w i l l be
e s s e n t i a l l y i n accordance w i t h drawing No. FT11 r e v i s i o n 1 of
September 1981. The m o d i f i c a t i o n s t o t h i s w i l l be due t o t h e
i n c o r p o r a t i o n of one p l a n t u n i t p e r c e l l b u t i t i s a n t i c i p a t e d
t h a t t h i s w i l l be l o c a t e d i n t h e a r e a p r e s e n t l y occupied by t h e
HP and LP d u c t s w i t h adequa te f a c i l i t i e s b e i n g provided f o r
a c c e s s , maintenance and p a r t replacement .
3 . FEASIBILITY
Although a c c e p t i n g t h a t some m o d i f i c a t i o n s may be n e c e s s a r y
due t o t h e mooring systems and t o mooring load ing on t h e
d e v i c e , t h e C o n s u l t a n t s cons i d e r t h a t t h e F l o a t i n g Terminator
OWC concep t is f e a s i b l e .
E s s e n t i a l l y t h e c o n s t r u c t i o n sequence is based on w e l l
e s t a b l i s h e d methods, a compara t ive ly s m a l l number o f 1 2 c e l l
modules w i l l be r e q u i r e d t h u s e a s i n g any problems a s s o c i a t e d
w i t h o p t i m i s i n g t h e c o n s t r u c t i o n sequence and i n tow-out and
i n s t a l l a t i o n .
The d e v i c e o b v i o u s l y s u f f e r s from t h e problems o f any moored
d e v i c e i n t h i s w a t e r d e p t h , namely maintenance f o r t h e
moorings themselves and a c c e s s f o r maintenance o f t h e p l a n t .
4 . CONCLUSIONS
I n a g r e e i n g wi th t h e Device Team's c o s t i n g and programme
e s t i m a t e s and i n r e c o g n i s i n g t h e proposed c o n s t r u c t i o n o f t h e
module a s b e i n g a r e a s o n a b l e one , i n v o l v i n g no s i g n i f i c a n t
e x t r a p o l a t i o n o f c u r r e n t e n g i n e e r i n g p r a c t i c e s , t h e
C o n s u l t a n t s c o n f i r m t h a t t h e f l o a t i n g t e r m i n a t o r i s a n
a c c e p t a b l e d e v i c e . Both t h e C o n s u l t a n t s and t h e Device Team
acknowledge t h a t f u r t h e r work i s r e q u i r e d on t h e t o r s i o n a l
r i g i d i t y o f t h e s t r u c t u r e and a l s o p o s s i b l e i n t e r a c t i o n wi th
t h e proposed mooring sys tem when f i n a l l y agreed . Both t h e s e
a s p e c t s a r e a c t i v e l y under examina t ion by t h e Device Team wi th
fu1.l i n t e r a c t i o n w i t h t h e C o n s u l t a n t s . I t i s n o t a n t i c i p a t e d
t h a t any f i n a l and n e c e s s a r y m o d i f i c a t i o n s w i l l have
s i g n i f i c a n t c o s t o r i n s t a l l a t i o n t ime p e n a l t i e s .
NEL FLOATING ATTENUATOR
OWC'SPI NE FLOATING - NEL ATTENUATOR
LEADIN(; DEVICE PAPJMt;'I'I:RS p-p.-.-- -
(ILo_caticin - .+ i~ th U i s t )
A . Re l a t ed t ~ l o c a t i o n
1 . Dis L ~ I I C C c1ffs11orc (k:i)
2 . Water dell ti1 (nil
3. Power i n s e a (Kw/m)
U. Rcla t cd t o d e v i c e
1 . O v e r a l l s i z c - Icnp,th (m)
- breadt l i (in)
- v e r t i c a l dinicnsion (m) 16 2 - g r o s s c r o s s s e c t i o n a l a r e a (m ) 320
2 . Weight c': dev ice ( t o n n e s )
3 . \icip,lit a: d e v i c e f i c n g t h (L-onnesln:)
C . Re l a t ed t o 2GIJ s t ; ~ t i o n
1. Number of d e v i c e s
2 . Sp . ic i~ig of devi c c s (-1)
3 . Lcnqrll [of 2Ci.l s t a t i o n (km) ( e x c l . i invig . z aps )
D . Rc in t ed t o ~ ~ r n ~ l u t t i v i t y
1 . Ra t ing of g e n e r a t o r s (Mu) 1 . 8 + 2 x O . l @ ?!w/device
2 . Powcr jn s c : ~ (Kwlrn) j 3 . 5
3. )!em annua l pcwer de l i ve re t1 t o Skye (Nw/dcvicc)* 0 . 322
1 1 . Mean anrlrial o u t p u t of 2GW n(.he~ne ((;U)* 0 . 4 6 5
1:. Relctccl t o structure cronomy and u t i l i z n t i on of r e s o u r c e ------p- -
1. Elcan nnrlunl povcr d e l i v e r c d p e r d c v i c c f l c n ~ t h of dev i ce (Kw/m)*
2 . Mcan ailnun1 powcr d e l i v e r e d p e r d e v i c e d c v i c e s p a c i n g ( K w / m ) *
3 . O v e r a l l convcrs io i l e f f i c i e n c y of sclicme*
mean annua l o u t p u t oE ?GW schcnie --W -- ( X ) mcnn annuill power iii s e a X leii!:th of 2(;1; s t a t i o n
ineiln . . . . -- snnDwcr . - c ; i p t ~ - ~ i by d e v i c e (7 . ) me:iii oniiual powcr i n sczi x d e v i c e l e n g t h
L ~ $ l a t e ~ l t o cost_
1. Cost o f P(;\< s t a t i o n (uniliscouritcrl) ( £ P I )
? Cost of each dc\, ici . ( u n d i s r o r ~ ! ~ t c d ) (£PI)
3 . Cost o f ci1crGy (disr:ouilted) (Ii/Kwh)
* i nc l i i d ing a v a i l a b i l i t y f a c t o r
* nu t i n c l u d i n g a v a i l i i b i l i t y f a c t o r
*"* mean annua l ~ w e r la~iclcd a t Skye -p- ---- ( n o t i n c l u d i n g a v a i l a b i l i t y f a c t o r ) ~ n e ~ ~ n annua l power cap tu red p c r d e v i c e x No. of d e v i c e s i n scheme
w o r n O d m
S . .
0 0 0
(I]
o 03
0
a3
m I-- m a cl
+ v \ o o m a . . . . . r n L n 4 N C I c n c O 0 \ 0 4 m w ~ . - - c - i -
r-4
o c ~ c o a . . . . m m o n c . l m - 4 0 3 c a a - 4 m
m t - m S . .
o a r . Goad o m r n
-i 7-4
NEL FLOATING ATTENUATOR
1 GENERAL
1.1 DESIGN
The s t r u c t u r a l f e a s i b i l i t y o f t h e t h r e e d e v i c e s p r o p o s e d by
NEL was o r i g i n a l l y examined i n t h e c o n t e x t of a d e t a i l e d d e s i g n
of t h e A t t e n u a t o r , t h i s d e s i g n b e i n g i n a c c o r d a n c e w i t h t h e NEL
OWC Note 30 and t o a p p r o p r i a t e and accep ta* d e s i g n c r i t e r i a ,
The d e s i g n p h i l o s o p h y and t h e c a l c u l a t i o n s a r e f u l l y a c c e p t a b i e
t o t h e C o n s u l t a n t s .
Of t h e t h r e e d e v i c e s , t h e A t t e n u a t o r s u s t a i n s t h e l e a s t o n e r o u s
l o a d i n g b o t h i n i n s t a l l a t i o n and d u r i n g i t s o p e r a t i o n a l l i f e .
F u r t h e r d e s i g n m o d i f i c a t i o n s may be n e c e s s a r y when t h e moor ing
s y s t e m h a s b e e n f i n a l l y d e c i d e d though t h i s is n o t e x p e c t e d t o
g i v e r i se t o any m o d i f i c a t i o n s t o t h e s t r u c t u r e t h a t would
s i g n i f i c a n t l y e f f e c t c o n s t ~ u c t i o n c o s t s .
1 . 2 TANK TESTING
D u e t o e a r l i e r t es t s i n d i c a t i n g i n h e r e n t l i m i t a t i o n s i n c a p t u r e
p o t e n t i a l , o n l y p r e l i m i n a r y t a n k t e s t s have b e e n c a r r i e d o u t on
t h e A t t e n u a t o r . B e a r i n g i n mind t h a t t h e d e v i c e c o m p r i s e s one
f r o n t column w i t h a hydrodynamic e f f i c i e n c y o f 41% and two s i d e
columns o f o n l y 4.6% it is a p p a r e n t t h a t t h e pe r fo rmance o f t h e
A t t e n u a t o r mus t compare un favourab ly w i t h t h e o t h e r d e v i c e s
where e a c h c e l l is f u l l y u t i l i s e d . F o r t h e above r e a s o n s t h e
A t t e n u a t o r h a s b e e n t e s t e d i n t h e N E L t a n k f o r PM c o n d i t i o n s b u t
n o t f o r t h e 46 d e s i g n a t e d s p e c t r a .
1 . 3 SPECIFICAT I O N
T h i s is b r o a d l y b a s e d on t h e NEL summary o f Mechan ica l and
E l e c t r i c a l P l a n t R a t i n g and P r o d u c t i v i t y 20 November 1981 .
C l o s e l i a i s o n h a s b e e n m a i n t a i n e d be tween t h e D e v i c e Team and
C o n s u l t a n t s on s u c h d e v e l o p m e n t s and m o d i f i c a t i o n s t h a t have
b e e n c a r r i e d o u t , t hough e s s e n t i a l l y t h e d e s i g n was f r o z e n
i n J u l y 1981 .
The D e v i c e Team are n o t i n a p o s i t i o n t o p roduce a f o r m a l
s p e c i f i c a t i o n b e f o r e moor ing d e t a i l s have b e e n f i n a l i s e d .
1 . 4 COSTING
F u l l c o - o p e r a t i o n h a s b e e n m a i n t a i n e d be tween t h e Dev ice Team
and t h e C o n s u l t a n t s on c o n s t r u c t i o n c o s t s and close ag reemen t
h a s b e e n r e a c h e d on t h i s . An a s s e s s m e n t o f i n s t a l l a t i o n c o s t s
h a s t o a w a i t c o m p l e t i o n o f moor ing d e s i g n .
2 DEVELOPMENT
2 .l GENERAL
The A t t e n u a t o r forms a v a r i a t i o n on t h e o r i g i n a l NEL theme
of a f l o a t i n g d e v i c e o r i g i n a l l y c o n c e i v e d a s b e i n g normal
t o t h e wave f r o n t . It was a p p a r e n t t h a t , a s i n o t h e r d e v i c e s ,
some advankage c o u l d b e g a i n e d by c a p t u r i n g t h e waves on a
l o n g i t u d i n a l b a s i s and , by s u i t a b l e s p a c i n g o f t h e d e v i c e s ,
b e i n g a b l e t o e x t r a c t t h e same amount o f e n e r g y f rom a p a s s i n g
wave a s t h a t a b s t r a c t e d by t h e T e r m i n a t o r d e v i c e from a r e f l e c t e d
wave. The Dev ice Team c o n s i d e r e d d e v i c e l e n g t h s of lOOm - 200m
and f i n a l l y d e c i d e d upon t h e lOOm a s b e i n g t h e m o s t economic
a s r e g a r d s c o n s t r u c t i o n , p r e l i m i n a r y t a n k t e s t i n g h a v i n g i n d i c a t e d
t h a t t h e t h r e e c e l l u n i t p r o p o s e d was m a r g i n a l l y less e f f i c i e n t
t h a n a f o u r c e l l u n i t - one f u l l s i z e c e l l i n t h e b o w , one f u l l
s i z e c e l l i n t h e s t e r n and t w o h a l f ce l l s o n t h e A t t e n u a t o r s i d e s .
A f u r t h e r m o d i f i c a t i o n was t h e s h a p i n g o f t h e f o r w a r d c e l l i n t o
t h e c o n v e n t i o n a l b o w s h a p e t h u s making tow-out and emplacement
c o m p a r a t i v e l y e a s y and g e n e r a l s e a - k e e p i n g b e h a v i o u r t o l e r a b l e .
2 - 2 AC GENERAT ION
Between J u l y and September 1981 s o m e a t t e n t i o n w a s d i r e c t e d t o
t h e p o s s i b i l i t y o f AC g e n e r a t i o n u s i n g a x i a l f l o w t u r b i n e s and
synchronous a l t e r n a t o r u n i t s w i t h t h e a s s o c i a t e d advanbage o f
f ewer c a b l e s t o s h o r e a t t h e e x p e n s e o f a m a r g i n a l l y r e d u c e d
o v e r a l l e f f i c i e n c y . T h i s i d e a was abandoned a t t h e same t i m e
a s t h e i d e a o f m a n i f o l d i n g f o r t h e o t h e r two d e v i c e s w a s
d i s c o n t i n u e d , m a i n l y b e c a u s e o f t h e a p p a r e n t f a i l u r e o f
m a n i f o l d i n g .
3 FEASIBILITY
A t 105m w a t e r l i n e l e n g t h t h e d e s i g n is c r e d i b l e and t h e s e a -
k e e p i n g c h a r a c t e r i s t i c s would be e x p e c t e d t o be s a t i s f a c t o r y .
However, due t o t h e low c a p t u r e p o t e n t i a l and hence t o t h e f a c t
t h a t some 1300 modules a r e r e q u i r e d it i s s e e n t h a t on economic
g r o u n d s t h e A t t e n u a t o r d e v i c e c a n n o t be c o n s i d e r e d a f e a s i b l e
one and it c a n n o t compete w i t h t h e NEL F l o a t i n g T e r m i n a t o r o r
R a i s e d B r e a k w a t e r . The e f f i c i e h c y g a p c a n n o t be compensa ted
by hydrodynamic o r o v e r a l l h y d r o m e c h a n i c a l c h a i n improvements
and t h e d e v i c e is e s s e n t i a l l y a p o i n t a b s o r b e r o n l y .
Mooring d e t a i l s a r e n o t f i n a l i s e d b u t it is e x p e c t e d t h a t some
form o f f i x e d p o i n t mooring a t t h e b o w and two t r a i l i n g moor ings
a t l e a s t a t t h e s t e r n w i l l be r e q u i r e d . I f t h e d e v i c e s a r e
t o be p o s i t i o n e d s u f f i c i e n t l y close t o g e t h e r f o r c a p t u r e t o be
o p t i m i s e d , n o t more t h a n loom, t h e n some d i f f i c u l t i e s w i t h t h e
mooring s y s t e m c a n be a n t i c i p a t e d t h o u g h t o no g r e a t e r e x t e n t
t h a n t h a t o b t a i n i n g i n t h e F l o a t i n g T e r m i n a t o r .
4 CONCLUSIONS
Whi le a g r e e i n g w i t h t h e Dev ice Team ' s c o n s t r u c t i o n c o s t i n g and
d e s i g n p h i l o s o p h y t h e C o n s u l t a n t s b e l i e v e t h a t s u f f i c i e n t work
h a s b e e n u n d e r t a k e n o n t h e A t t e n u a t o r d e v i c e t o i n d i c a t e t h a t
it h a s no f u t u r e , i t s o v e r a l l p e r f o r m a n c e c a n n o t be made t o
match t h a t o f t h e F l o a t i n g T e r m i n a t o r and t h e R a i s e d B r e a k w a t e r .
E D I N B U R G H DUCK
EDINBURGH DUCKS
Duct! -.-
SECTION A - A
GGrcERAL L A Y O U T I S p i n e u n ~ k 3 0 ~ - l o n g -- -.
,I
C L E V 4 T i Q N
P b o d y .
1,I:AT)INC Ili.VI(:l~: l'.ZIb'iY!~'i'I:l~S
(Loc:it ion - S~iil t l i [ l i s t ) - -- - .- - .. - ' l : l ~ I ! i ~ l ~ ! ~ ~ H l)l!CK .--
A . R e l a t e d t o l o c a t i o n
1 . U i s t a n c c o f f s h o r o (km)
2 . Idater d e p t h (m?
3. Powcr i n s e a (Kw/m)
l;. R e l a t e d t o c levi re
1 . O v e r a l l s i z e - l e n g ~ h (m)
- b r c a d t h (m)
- v e r t i c a l d in i r i l s i o i~ (m) 2 - g r o s s c r o s s s c c t i o n n l a r e a (m )
2 . Wcil:ht of d e v i ~ : e (tonne:;)
3 . Weigl~r o f J c v i c e f l r n g t l ~ ( t o n n e s l n ~ )
C . _Rc.l_;~vLl:y.:_ZgL s~15.i p n
1 . Numbcr C I F d c v i c c s
2 . Spiicii~l: <lcvic:cs (in)
3 . I.rrly,tli <;I 2GW s t a t i o n (km) ( c x c l . n:ivig. gal,::)
2 . Powcr i n sc:! (Kwlm) 53 .5
3 . Mcnr; annual powcr d e l i v e r e d t o Skye (,blw/devic.c)" (0 . h 2 3
4 . Eie:in anilunl o u t p ~ l t of 2GW scheme (GU)* 0 . 5 9 5
E. nf_Ia ted t o s t r u c t u r e economy i111d i i t i l i z n t i o n of r c s o u r r c
1 . Menn nnriunl powcr < l c l i v e r c d p<, r d e v i c e l e n e t h o f d e v i c e (Kw/m)*
2 . Elenn : ~ n ~ l u ; l l powcr i!eLiverc<l p e r d c v i c c ~ l e v i c e s p a c i n g (K~e!m)*
. Overnl l r:nriver:;ian e f f i c i c n c y of schcme*
l'. Ri.i:ltcli t o c o s t . - -. --- -- - - l . Cor,t n l :C!J s t n r i c n (undi!;courl~ ~ . d ) ( f E l )
2 . Cos t of r.lcl1 dcvic t . ( i i n d i s c o ~ ~ n t c ( ! ) (FM)
3. Cost <;E c,ncr!:y (<! js i :ountcd) (ji!Kw11)
C. P l i s c r l l i i neous .- - l . Near1 nnniial power cll;iin cE1ici.enc.y (X)"""
2 . A v a i l a b i l i t y < I £ t h e %(;id sclleinc ( X )
'3 . 4.
' inc luc i ing a v n i 1 : l b i l i t y f a c t o r
*+ not i l , c l i~ t i inf i . ? \~ :~i la! ) i l i t y I n c t o r
* A * mean annun1 y w c r landed a t Gkyc -. - .- --.-- -----W
(no t i n c l u d i n g a v a i l a b i l i t y f a c t o r ) mean ;in;ui.il powcr cnpttirecl pcLr d c v i c c x Xo. of J e v i c c s i n scheme
EDINBUKGH DlJCK
Gene ra l
I t i s assumed t h a t t h e members o f WESC a r e f a m - l i a r w i t h t h e Duck,
f o l l o w i n g p r e s e n t a t i o n s by t h e Team e a r l i e r i n 1981.
The Duck, a s p r o p o s e d , i s a t t h e e x t r e m e end o f t h e r anga f o r most o f t h e
p a r a m e t e r s used t o measure t h e e f f e c t i v e n e s s o f wave e n e r g y d e v i c e s .
I t h a s ,
- t h e h i g h e s t o u t p u t / m o f s e a
- t h e l o w e s t m o o r i n g f o r c e s
- t h e second l o w e s t mass/kW
- t h e second h i g h e s t swept volume r a t i o
- c o n c e p t u a l l y t h e most c o s t e f f e c t i v e power c h a i n
- t h ~ g r e a t r s t number o f i n t e r l o c k i n g and i n t e r d e p e n d e n t sys t ems
- and i n c o n s e q u e n c e tllr l o w e s t a v a i l a b i l i t y
- a u n i q u e d ~ p e n d e n c ~ o n s u c c e s s f u l mPchanica l e n g i n e e r i n g development
t o a c h i e v e v i a b i l i t y .
T h i s i s r e s u l t s f rom a c o n s c iolis d e c i s i o n by t h e Team t o match t h e complex
randomness o f t h e i n p u t e n e r g y o f t h e s e a by a damping s y s t e m c a p a b l e o f
i n s t a n t a n e o u s i n t e l l i g e n t r e s p o n s e , and t o meet t h e damaging h i g h wave
amp1 i . tudes w i t h a c o n t r o l 1 a b l y compl i a n t s p i n e . Resul t i n g from t h i s
p h i l o s o p h y , power o u t p u t i s maximised and s t r l l c t u r a l and a n c h o r i n g f o r c e s
a r e min imised . The r e s u l t i s a d e s i g n which must be n e a r o p t i m a l i n
w e i g h t and e f f i c i e n c y , and which must b e a s s e s s e d i n terms o f t h e
p r o b a b i l i t y o f s u c c e s s o r f a i l u r e a t t h e end o f a s i g n i f i c a n t deve lopment
phase .
Assessment of t h e Concept
Primary I n t e r a c t i n g Sur face
This i s probably t h e most e f f i c i e n t i n t h e wave energy programme. The
wedge a c t i o n allows a high swept volume and t h e n a t u r a l movement of t h e
sea i s wel l matched. The f a c i l i t y t o f l i p over i n a high s e a i s a va luab le
means of l i m i t i n g forces i n h igh seas .
Ref erence Frame
This i s l i kewi se very e f f i c i e n t , i n t h a t f o r most working seas t h e sp ine
can be kept r i g i d ( i f r equ i r ed ) t o maximise output . I n s ea s where t h e r e
i s an excess of energy the s p i n e is a b l e t o "break" a t hinge po in t s t o
l i m i t f o r c e s , both on the sp ine s t r u c t u r e and on t h e moorings. Use of
gyroscopes t o r e s i s t r o t a t i o n makes t h e whole device concept poss ib le .
Power Of f t a k e
High p re s su re hyd rau l i c s us ing a m u l t i p l i c i t y of pumps on cam r i n g s
confers a high volumetr ic e f f i c i e n c y which leads t o low i n s t a l led swept
volume and r e l a t i v e l y low machinery cos t . It a l s o makes p o s s i b l e t h e
system of energy in te rchange wi th t h e two f l y wheels, which i n t u r n allows
t h e power smoothing over many wave cyc l e s , and synchronous genera t ion .
The gyros a l s o provide a l a r g e r e s e r v e of s t o r e d energy, t he b e n e f i t of
which has not been costed.
Given t h e engineer ing means of r e a l i s i n g i t , t h e concept i s hard t o f a u l t .
A s S es sment of t h e Engineer ing
The dev ice i s engineered round t h e concept o f "sealed for l i f e " power
c a n i s t e r s i n each of which 256 r i n g cam pumps, 5 swash p l a t e motors, and
two gyroscopes work cont inuously without maintenance f o r up t o 25 years .
Pumps and motors a r e over provided t o g i v e some redundancy t o a l low f o r
breakdown, bu t e s s e n t i a l l y t h e engineer ing s t ands o r f a l l s on t h e
f e a s i b i l i t y of ach iev ing a very c o n s i s t e n t maintenance f r e e l i f e a s
i nd i ca t ed . Experts consul ted (Mr. Baggett of Commercial Hydraul ics Ltd.
t h e Nat ional Centre of Tribology a t Rise ly and o t h e r s ) a r e no t prepared t o
discount t h e p o s s i b i l i t y t h a t t h i s may be achieved i f t h e necessary e f f o r t
i s made a v a i l a b l e .
An at tempt t o draw comparisons between t h e requi red l i f e of components of
t h e Duck power t r a i n and s i m i l a r components i n presen t day s e r v i c e a r e
presented i n F igs . A and B.
The Duck flywheel bear ings r o t a t e i n excess of 1 0 l 0 r evo lu t ions over a 25
year per iod which is g r e a t e r by 1 o r 2 o rde r s of magnitude than most
r o t a t i n g machinery; b u t i t i s equal led by t h e bear ings i n l a r g e turbo-
a l t e r n a t e r s e t s (660 MW), and by ind iv idua l r o l l e r s i n c r i t i c a l r o l l e r
bear ings i n equipment a s d i v e r s e a s t h e Ro l l s Royce RB 211 engine and i n
t h e main t r a c t i o n a x l e hubs on t h e London Underground. The bear ing
l i n e a r s u r f a c e t r a v e l on l a rge T/A and hydrose ts exceeds t h a t on t he Duck
and provides some reassurance t h a t t he l i f e expectancy requi red on
bear ings can be a t t a i n e d .
The t o t a l p i s t o n t r a v e l on t h e swash p l a t e motor pump i s considerably i n
excess of t h a t f o r o t h e r equipment such a s i n t e r n a l combustion engines of
a l l s i z e s - but t h e s e have t o cope wi th high temperatures causing
ox ida t ion of t h e o i l , contaminat ion of t h e o i l from products of
combustion, and expose t o unclean a i r and f u e l , and meta l p a r t i c l e s from
wear of bear ings . The long l i f e necessary f o r t h i s c r i t i c a l component and
f o r t h e whole high p re s su re hyd rau l i c system i s t o be achieved by ensuring
complete i n t e g r i t y of c l ean o i l supply i n a d ry low p re s su re environment.
This has t o be proved but t h e unce r t a in ty r e s t s heav i ly on achieving an
accep tab l e l e v e l of r e l i a b i l i t y of t he whole system and hence a l l i t s
component p a r t s . The r e l i a b i l i t y a n a l y s i s by YARD g ives an unfavourable
r e s u l t . Notwithstanding t h a t i t has had t o be based on some d a t a obtained
from non comparable a p p l i c a t i o n s t h e f a c t remains t h a t i t c l e a r l y shows
t h a t an order of magnitude improvement i n r e l i a b i l i t y i s r equ i r ed fo r t h e
dev ice t o approach v i a b i l i t y .
The environmental f a c t o r ( t o be appl ied t o t h e f a i l u r e r a t e s ) chosen by
YARD does not r e f l e c t t h e Team's c la im t o c r e a t e a near p e r f e c t working
environment by enc l o s ing equipment w i th in low p re s su re S e a l ed power
c a n n i s t e r s , and t h e r e may be some immediate g a i n t o be i d e n t i f i e d here . . The Consul tants a s se s s t h a t an i n c r e a s e i n r e l i a b i l i t y of about 50 times
over t h e YARD assumptions i s needed t o meet t he system r e l i a b i l i t y
requ i rements c o n c o m i t a n t w i t h t h e a v a i l a b i l i t y o f 80% used i n t h e d e v i c e
c o s t i n g . Marg ina l ly lower component r e l i a b i l i t y might b e accommodated by
more redundancy and system r e d e s i g n .
However t h e d e s i g n o f t h e power t r a i n a l r e a d y i n c o r p o r a t e s redundancy i n
some components which a r e i n p a r a l l e l " f a i l t o s a f e t y " , and t h i s h a s been
allowed f o r a l r e a d y .
P r o d u c t i v i t y
The Duck h a s on ly been t e s t e d i n P-M s e a s i n a narrow tank and
p r o d u c t i v i t y h a s been a s s e s s e d by assuming l i n e a r i t y o f performance w i t h
r e s p e c t t o combinat ion of i n c i d e n t waves from v a r i o u s d i r e c t i o n s .
One s e t of t e s t s i n t h e wide t ank has g i v e n encouraging r e s u l t s , b u t more
r e s u l t s a r e r e q u i r e d b e f o r e one can be s u r e t h a t t h e Duck w i l l n o t s u f f e r
t h e l o s s o f e f f i c i e n c y exper ienced by o t h e r d e v i c e s i n t h e wide t anks .
Meanwhile t h e C o n s u l t a n t s have based t h e i r p r o d u c t i v i t y assessment on t h e
assumption t h a t t h e r e w i l l be no such d rop i n e f f i c i e n c y .
Conc l u s i o n
The C o n s u l t a n t s a r e c u r r e n t l y c o n c e n t r a t i n g a l l t h e i r e f f o r t s t o o b t a i n
t h e b e s t assessment of t h e chance o f a c h i e v i n g s u c c e s s by say 1995.
The c a s e f o r c o n t i n u i n g work r e s t s on t h e i n h e r e n t l y h i g h e f f i c i e n c y o f
t h e d e v i c e , and i t s i n h e r e n t l y low use of raw m a t e r i a l s . It o f f e r s t h e
most scope t o b e n e f i t from advances i n technology i n t h e f u t u r e .
EDINBURGH DUCK - FLYWHEEL BEARINGS
COMPARED TO EXISTING COMPARABLE COMPONENTS
10" Revo lu t ions B e t w e e n Overhau ls
1
660 M W - T / A S ~ . l?
DUCK X
R B 211 c o [ \ e r bear'lnq. X
I( L T E- Underground t r u ~ n mum axle rol ler bear \ng .
l oM
Hy droset X
R .R . Dart X
Taxi use.
I f
10
16 - 10' m (U L * a, 2 V
a, U 0 rC
L
3 cn
16 . - L (3 0 d]
C 0
d
a,
U\gh cipeod macme d i o s ~ . ] . JC
> 0 t t-
a,
18 cc- L 3 m L c3 a C . - .J
16-
X
LOW s p e d
mw,ne d \ ~ ~ c \ .
c /
~ e c t t c Y' use.
D O ~ P S ~ ; ~ f ri dge X
1 08 l 0'
EDINBURGH DUCK - PISTON TRAVEL COMPARED
W I T H EXISTING COMPARABLE COMPONENTS
Revo lu t i ons Between Overhauls
FIG. B
LANCHESTER CLAM
LANCHESTER CLAM
LOCATION OF SCHEME
OPERATING CYCLE
A . R c l a t c d t o l o c a t i o n
1. D i s t a n c c o f f s h o r e (km)
2 . Va t c r dep th (in)
3. Power i n s e a (Kwlm)
U . Re l a t ed t o d e v i c ?
1. O v e r a l l size - l e n g t h (m)
- b r e a d t h (m)
- v c r t i c a l dinlerlsioll (n~)
- g r o s s c r o s s sectional a r e a ( m L )
2 . Weil:lit of dev i ce ( t o n n e s )
3. Weight of d e v i c e f l e n g t h (toilnes/m)
C. Re l a t ed t o 2(iW s t a t i o n
l . N~imbcr of d c v i c c s
2 . Spacing of d e v i c c s (m)
3 . Lcngilt of :!GW s t a t i o n (km) ( e x c l . navig. gaps)
c . !elated t o p r a d u c t i v i t v
1. Ra t ing of g c n c r a t o r s (MW)
2 . Powcr i n s e a (Kw/m) 51.3
3 . Mean annua l power d e l i v e r e d t o Skye (Elw/dcvice)* 1 .77
4 . Mean n n n u ~ l o u t p u t of 2GW scheme (GW)* 0 . 6 0
l:. Re l a t ed t o s t r u c t u r e eLonowy and u t i l i z a t i o ~ ~ of r e s o u r c e
1. Plean annua l powcr [ i c l i ve red p c r d c v i c r f l eng th of d c v i c c (Kw/m)*
2 . Plcno aniirial powcr d e l i v c r c d pe r t icvice + dcv icc s p a c i n g (Y,w/rn)*
3 . Ovc rn l l r onvc r s io l i r f f i c i c n c y o i schclnc*
mean annua l o u t p u t of ?L:\! sche~nc ( X ) mean annu.11 powcr i n sea x I c n g t l ~ of 2GW s t a t i o r l
'I . Capture Pactor**
iw:all a111iua11)o~~r - r ~ r c ~ l - . . - by d e v i c e (%) !nc,nn annua l powcr i n s c n X d c v i c c lengt l i
F. _Related t o c o s t
1. Cost of 2CW s t a t i o n ( u ~ i d i s c o u n t c d ) ( E E f j
2 . Cost of each d e v i c e (undiscot in tcd) (fM)
3. Cost of cncrgy (d i s coun ted ) (p/Kwh)
G. Mi sce l l aneous
1. Mean annua l power c h a i n e f f i c i e n c y (%l*""
L. h v ; ~ i l a b i l i t y of t h e 2GN scltemc ( X )
* i n c l u d i n g a v a i l a b i l i t y f a c t o r
** no t i n c l u d i n g a v n i l n h i l i t y f a c t o r
*** me3n annua l power landed a t Skye P- -- (no t i n c l u d i n g a v a i l a b i l i t y f a c t o r ) mean annua l power cap tu red p e r d e v i c e x No. oE d e v i c e s i n scheme
5 ( ~ ) LANCHESTER CLAM
General
The Lanches te r Clam developed from t h e e a r l y Duck programme and
was o r i g i n a l l y conceived a s an a t t e m p t t o y i e l d a n e n t i r e l y
c r e d i b l e , s i m p l e d e v i c e i n c o n t r a s t t o t h e complexi ty o f t h e Duck.
A c o n c l u s i o n of t h e e a r l y Duck work i n Loch Ness was t h a t s h o r t
f i n i t e s p i n e s work and t h e Clam a r o s e a s a ' s h o r t ' sp ined s i m p l e
wave maker a c t i n g i n r e v e r s e .
The f i r s t engineered r e f e r e n c e d e s i g n y i e l d e d a c r e d i b l e sys tem
w i t h r i g i d f l a p s on h inges and a r u b b e r membrane be l lows between
t h e f l a p and s p i n e . Cos t ing o f t h i s d e v i c e produced very
encouraging f i g u r e s b u t t h e f l a p and a s s o c i a t e d h inges a t t r a c t e d
bo th c o s t and c r e d i b i l i t y p e n a l t i e s . The p r e s e n t d e s i g n u t i l i s e s
a double faced s o f t rubber bag which removes t h e c o s t problem and
cons i d e r a b l y improves t h e c r e d i b i l i t y .
Th i s d e v i c e h a s been t e s t e d i n t h e wide t ank a t Cadnam and h a s ,
s i m i l a r l y t o t h e LFB, y i e l d e d lower p r o d u c t i v i t y than expected.
The e f f i c i e n c y o f t h e Clam is s i g n i f i c a n t l y h i g h e r t h a n t h e LFB.
Th is i s p a r t l y exp la ined by mani fo ld ing l o s s e s i n t h e LFB. The
d e v i c e h a s , however, had on ly one t e s t i n g p e r i o d i n t h e wide t a n k
w i t h a model t h a t i s n o t t r u l y r e p r e s e n t a t i v e o f t h e r e f e r e n c e
d e s i g n . A l / l o t h s c a l e working model i s a t p r e s e n t i n Loch Ness
and r e s u l t s w i l l soon be a v a i l a b l e . T h i s should p r o v i d e some
u s e f u l c o n f i r m a t i o n o f what must be regarded a s c r u d e power
measurements a t Cadnam where a i r power from a s i n g l e c e l l o f l e s s 6 t h a n ' A 3 ' s i z e is measured and s c a l e d by a f a c t o r o f 1 0 .
S t a t u s o f Assessment Data
The b a s i c d e s i g n and c o n s t r u c t i o n a l d e t a i l i n g o f t h e s p i n e a r e a t a
f a i r l y advanced s t a g e and t h e Device Team h a s provided i n f o r m a t i o n
on q u a n t i t i e s which h a s been checked and used a s a b a s i s f o r t h e
C o n s u l t a n t s ' c o s t e s t i m a t e . The Device Team h a s a l s o provided
f u l l d e t a i l s o f t h e i r own e s t i m a t e which i n t o t a l i s w i t h i n
approx imate ly 5% of t h e C o n s u l t a n t s ' e s t i m a t e . A t p r e s e n t a f o u r
cons t ruc t ion f a c i l i t y system is used f o r cos t i ng purposes. The
Device Team i s working on opt imis ing t h e cons t ruc t ion c o s t s by
us ing only two f a c i l i t i e s .
Main and a u x i l i a r y p l a n t c o s t s have been provided by t h e Device
Team and have been accepted p rov i s iona l ly by t h e Consul tants u n t i l
f u r t h e r information from t h e Working Par ty i s a v a i l a b l e .
Transmission c o s t s have been provided based on t h e Consul tants
c u r r e n t working Paper. This working Paper is about t o be rev ised
s i g n i f i c a n t l y and t h e t ransmiss ion c o s t s have been modified t o
take account of t h e s e major r ev i s ions .
I n s t a l l a t i o n c o s t s have been developed by t h e Consul tants f o r t h e
deadweight anchor system proposed by t h e Team. Costing of t h e
mooring components i s t h e Device Teams cos t i ng and has no t been
v e r i f i e d . The o v e r a l l mooring c o s t s inc lud ing i n s t a l l a t i o n f o r
t h e Clam a r e about 25% of t h a t taken f o r t h e LFB. This r educ t ion
i s t o t a l l y a r e s u l t of lower a b s o l u t e mooring loads. The v a l i d i t y
of lower peak mooring loads f o r t h e Clam has no t y e t been
e s t ab l i shed .
Maintenance c o s t s have been assessed by t h e Consul tants and
c o r r e l a t e reasonably w i th t h e Easams Study. A v a i l a b i l i t y has been
der ived from t h e f a i l u r e r a t e s tudy c a r r i e d ou t by YARD.
Development
The des ign philosophy adopted by Lanchester has been t o minimise
t h e r e f e r ence frame c o s t . This they have succeeded i n doing.
Although t h e method of a r r i v i n g a t des ign moments is t o t a l l y
d i f f e r e n t from t h a t adopted by WPL they a r e i n agreement over t h e
magnitude of t h e s e fo rces . By u t i l i s i n g t h e a l lowable s t r e s s e s i n
t h e sp ine t o t h e l i m i t and by avoiding the need t o widen t h e
s t r u c t u r e f o r r o l l s t a b i l i t y , t h e sp ine , a l though 7% longer i s i n
f a c t over 30% l i g h t e r than t h e LFB.
It i s i n t e r e s t i n g t o no t e t h a t a l though conceived a s a pure
te rmina tor , power was opt imised i n t h e wide tank by o r i e n t a t i n g
t h e device 55' from t h e predominant wave d i r e c t i o n . The des i r ed
o r i e n t a t i o n i s a s a r e s u l t w i th in about 15' of t h a t f o r t h e double
s ided ' a t t e n u a t o r ' LFB.
F e a s i b i l i t y
A s mentioned f o r t h e LFB, a rubber membrane i s a very c o s t
e f f e c t i v e system. It has n o t , so f a r , been p o s s i b l e t o develop t h e
shape of t h e Clam bags t o t h e ex t en t t o which t h e LFB bags have
been developed, bu t work on t h e l a t t e r a s regards manufacture,
des ign and handl ing a l l c o n t r i b u t e t o confidence i n t h e Clam bag.
This does have a more complex shape and w i l l t h e r e f o r e r e q u i r e
e x t r a development p a r t i c u l a r l y i n t h e region of t h e duct
connect ions. The bag cords a r e always i n t ens ion whi le t h e
i n t e r n a l a i r p r e s su re i s above atmospheric ( ~ e a n i n f l a t i o n
p re s su re 1.5 atmospheres). This t ens ion permits t h e bag t o t ake a
s i g n i f i c a n t shear load be fo re t h e cords a r e put i n t o compression.
This shea r capac i ty appears g r e a t e r than t h e l a t e r a l wave loading.
It i s however c o n d i t i o n a l on i n t e r n a l p r e s s u r i s a t i o n .
The r e f e r ence frame has been developed i n s u f f i c i e n t d e t a i l t o
permit r e a l i s t i c c o s t and des ign capac i ty e s t ima te s t o be made. A s
mentioned prev ious ly , t h e sp ine is f u l l y s t r e s s e d under extreme
environmental loadings. No weight reduc t ions a r e t h e r e f o r e
conceivable .
The mooring system adopted must be considered a s near t h e lower
bound wi th regard t o c o s t , and inc ludes a number of f e a t u r e s which
a r e a t p r e sen t unproven:-
i ) S u f f i c i e n t compliance i s provided by t h e lead ing l o o T buoy
t o prevent maximum des ign loads being exceeded.
i i ) A Doris type 'Deadweight Anchor' would be a v a i l a b l e o f
s u f f i c i e n t s i z e and shape t o hold when dropped onto t h e
s eabed .
i i i ) Po lyes t e r p a r a f i l rodes , t e rmina t ions and j o i n t s assumed t o
have 25 year l i f e .
Although t h e Clam r e q u i r e s t en i nd iv idua l power u n i t s u t i l i s i n g
s i n g l e s t a g e Wells t u r b i n e s , each u n i t con ta in s only t h e s i n g l e
r o t a t i n g s h a f t . The power u n i t s a r e t h e r e f o r e s imple and should be
r e l i a b l e . Cycl ic e f f i c i e n c i e s a r e reasonably high.
Conc lu s ions
P roduc t iv i t y t e s t i n g of t h i s dev ice i n mixed spread seas i s very
l imi ted and t h e r e may be cons ide rab l e scope f o r improvement. The
p roduc t iv i t y assumed f o r t h i s dev ice however i s a cons ide rab l e
mod i f i ca t i on of t he raw t e s t d a t a measured a t Cadnam and al though
t h e adopted f i g u r e i s agreed, p a r t must be considered a s
specu la t i ve . The Loch Ness t e s t i n g a t l / l o t h s c a l e and t h e
r e t e s t i n g a t Cadnam i n March should permit g r e a t e r confidence i n
t h e assumed va lues and may even demonstrate g r e a t e r p roduc t iv i t y .
6 . WHERE THE MONEY HAS GONE
7. WHAT IS THE AVAILABLE RESOURCE
AT SOUTH UIST ? -
WHAT I S 'THE AVAILAULLl RLSOUKCL A'l' SOU'l'11 ULS'P?
Real s e a s comprise a m u l t i t u d e o f component waves o f v a r i o u s h e i g h t s and
p e r i o d s p r o p a g a t i n g i n a l l d i r e c t i o n s of t h e compass. The power i n t h e
s e a i s c a l c u l a t e d u s i n g wave r e c o r d s from buoys, t h r e e of which have
been deployed by IOS o f f South U i s t t o c o l l e c t d a t a f o r t h e Wave Energy
Programme. However, t h e s e buoys can on ly g i v e i n f o r m a t i o n about t h e
o v e r a l l v e r t i c a l d i sp lacement of t h e wa te r s u r f a c e and n o t t h e
d i r e c t i o n i n which p a r t i c u l a r wave t r a i n s a r e t r a v e l l i n g . Thus a f t e r
F o u r i e r a n a l y s i s of t h e raw d a t a i t i s p o s s i b l e t o c a l c u l a t e o n l y t h e
t o t a l power i n a g iven s e a s t a t e . Conven t iona l ly t h i s i s expressed a s a
power d e n s i t y i n k i l o w a t t s p e r m e t r e , which i s most u s e f u l l y v i s u a l i s e d
a s t h e r a t e a t which energy c r o s s e s a c y l i n d e r of one m e t r e d i a m e t e r ,
s t r e t c h i n g v e r t i c a l l y from t h e seabed t o t h e w a t e r s u r f a c e . It i s t h i s
f i g u r e which i s a t p r e s e n t t a k e n t o be t h e a v a i l a b l e r e s o u r c e .
I n f a c t t h i s i s a f a l l a c y . The power e x p r e s s e d i n t h i s way i s a v a i l a b l e
on ly t o a s i n g l e , i s o l a t e d p o i n t a b s o r b e r . Such a d e v i c e i s p e r f e c t l y
symmetr ica l and responds t o a l l waves i n a s i m i l a r manner r e g a r d l e s s of
t h e i r d i r e c t i o n o f approach. Thus i t can c a p t u r e an e q u a l amount o f
ene rgy from a g i v e n wave t r a i n independen t ly of t h e d i r e c t i o n of
i n c i d e n c e of t h e wave t r a i n . The behav iour o f p o i n t a b s o r b e r s i s r e a l l y
o n l y an e x t e n s i o n of t h a t o f t h e wave measur ing buoys, r a t h e r than
merely measur ing power t h e a b s o r b e r i s a b l e t o c a p t u r e some o f i t .
Thus, i n an i s o l a t e d s i t u a t i o n , remote from any o t h e r mechanisms f o r
removing energy from t h e s e a , a s o l i t a r y p o i n t a b s o r b e r i s exposed t o
t h e whole power which i s ' s e e n ' by t h e buoy, t h e s o - c a l l e d a v a i l a b l e
r e s o u r c e .
More commonly, wave energy d e v i c e s t a k e t h e form o f a t e r m i n a t o r . These
may be s i t e d i n t h e same a r e a a s t h e p o i n t a b s o r b e r , b u t by t h e n a t u r e
o f t h e d e v i c e t h e energy a v a i l a b l e t o be c a p t u r e d i s l e s s t h a n t h a t a t a
s o l i t a r y r e c o r d i n g buoy. For example c o n s i d e r t h e f o l l o w i n g diagrams
showing u n i d i r e c t i o n a l s e a s approaching a p o i n t a b s o r b e r and a
t e r m i n a t o r .
In the latter diagram, it is seen that the effective resource available
to the terminator is reduced from that available to a buoy by a factor
of cos 8. This is purely a consequence of the reduction in device
length presented to the wave crests because of its oblique attitude. It
is not to be confused with any variation in the energy captured by the
device due to alterations in its capture efficiency due to variations in
the angles of wave incidence.
An alternative way of looking at the reduced resource available to a
terminator is to imagine a multi-directional spectrum resolved into two
orthogonal components, one normal to the device, the other parallel.
An isolated point absorber would be able to capture from both components
but for the terminator,once the parallel component has been captured by
the end cells it no longer exists and is not available to the remaining
cells along the line. This effect is particularly pronounced for an
array of terminators many kilometres long. The energy which may be
captured from waves travelling along the line of the array is
negligible. This argument applies to any linear array of devices, not
just to terminators. The array acts as a very long attenuator in which
only the end few devices capture any appreciable energy from wave trains
travelling parallel to the array. It has been suggested that
diffraction will take place to transfer energy along wave crests and
replenish that which is extracted. However, from evidence of
diffraction around breakwaters it seems unlikely to be of significant
consequence.
It should be realised that due to space limitations it is not possible
to study the behaviour of long arrays of devices by wide tank testing.
Therefore care is needed in the assessment of results from single or
small groups of models. One of the limitations of the wide tanks
presently used for testing at Cadnam and Edinburgh is that they can
produce waves only from an arc of approximately - + 75' about a central
direction for a device central in the tank.
waves Generated within this anz
-- I M o d e l - --
I
In the RPT estimation of the productivity of arrays of devices off the
Hebrides this limitation has been regarded as removing from the sea
those components which contribute to the available resource as measured
by buoys, but are not effectively available to the devices. This is an
approximation which the Consultants believe to be reasonable within the
current state of knowledge. However, some Teams disagree with this
approach.
The above has implicitly assumed that devices will be sited in one
straight line array. However, in practice a wave energy station would
require a number of arrays which would be deployed to suit sea bed
conditions. They would change course to follow contours and avoid
unsuitable underwater topography. It is clear that arrays and devices
will interfere with each other's resource, some devices shielding
certain directional components from others.
Typical device,
In the above sketch arrays ( A ) and (C) will shield devices in array (B)
and reduce the resource available to (B). Thus model tests based on the
appreciated that spectral data used for model testing and assessment of
productivity, whilst being a significant advance from monochromatic and
Pierson-Moskowitz seas, is far from perfect and can only be used to give
comparisons and approximate estimates.
As has already been stated, devices have been proposed which would be
sited in depths different from 42m. Estimates for the resource at these
sites have been made by interpolation between data available for water
depths of 15m, 25m and 100m. Long term mean power levels have been
predicted by IOS for these depths by comparing spectra recorded
simultaneously by buoys at these locations and the buoy at 42m.
Buoy Depth Long term mean
(m) power density (kw/m)
Deep water 100 59.2
Offshore 4 2 47.8
Inshore 3 2 5 36.2
Inshore 1 15 15.3
Values are related to the reference power density of 47.8 kw/m at 42m,
but measured data is such that the proportions can be expressed with
confidence. Thus it may be thought at first sight that the available
resource is reducing in shallower water depths. Several mechanisms
have been suggested to explain the reducing values, but there is no
complete, satisfactory explanation. Power can be lost in a number of
ways, eg. turbulence from waves breaking or friction applied by bed
roughness and submarine growth. Such means are necessary to explain the
rapid decay of power in depths shallower than 25m, but work by HRS using
a refraction model suggests that no power is lost in water deeper than
this. The apparent reduction in power density is merely due to dilution
as wave crests are turned and lengthened.
Shore
Orfhogonal --- P&-allel covlburs
No energy c r o s s e s t h e o r t h o g o n a l s and hence t h e d e n s i t y r educes a s t h e
c r e s t l e n g t h s i n c r e a s e . The energy d e n s i t y i s what i s measured by a
buoy. The energy f l u x normal t o t h e c o n t o u r s i s unchanged. It should
be no ted t h a t t h e d imension between two o r t h o g o n a l s measured p a r a l l e l
t o t h e c o n t o u r s i s c o n s t a n t . Thus t h e l e n g t h o f c o a s t l i n e occupied by a
wave does no t p r o g r e s s i v e l y i n c r e a s e a s i t moves i n s h o r e , a common
m i s i n t e r p r e t a t i o n o f t h e above diagram and one which would c l e a r l y be
i m p o s s i b l e .
The HRS r e f r a c t i o n model i n c o r p o r a t e s t h e c h a r t e d s e a bed c o n t o u r s o f f
t h e Hebr ides . The i r r e g u l a r i t y of t h e s e c o n t o u r s i s such t h a t t h e
p a t t e r n o f r e f r a c t i o n of waves i s v e r y complex and n o t e a s y t o v i s u a l i s e
a s i n t h e above i d e a l i s e d s k e t c h . R e f r a c t i o n c a u s e s power d e n s i t y t o be
l o c a l l y c o n c e n t r a t e d and s p r e a d . T h e r e f o r e t h e d i s t r i b u t i o n of power
d e n s i t y o f f South U i s t v a r i e s a long contours. a s w e l l a s w i t h d e p t h .
E s t i m a t e s a t f i v e d i f f e r e n t l o c a t i o n s on t h e 25m c o n t o u r u s i n g t h e model
range from 27.7 kW/m t o 37.3 kW/m w i t h a mean of 30.6 kW/m. Thus
a c c o r d i n g t o HRS i t a p p e a r s t h a t t h e v a l u e o f 36.2 kW/m p r e d i c t e d from
I n s h o r e buoy 3 cou ld be a n o v e r e s t i m a t e o f t h e mean power d e n s i t y
a v a i l a b l e on t h a t c o n t o u r . F u r t h e r work i s n e c e s s a r y . M o d i f i c a t i o n of
s p e c t r a by r e f r a c t i o n o v e r p a r a l l e l c o n t o u r s runn ing nor th - sou th a long
t h e Hebr idean c o a s t w i l l y i e l d a more t y p i c a l mean power d e n s i t y
d i s t r i b u t i o n f o r a long l e n g t h o f c o a s t l i n e , which would be r e q u i r e d f o r
an a r r a y o f wave energy d e v i c e s . T h i s i s y e t a n o t h e r i l l u s t r a t i o n of
t h e u n c e r t a i n t y a s s o c i a t e d w i t h t h e a v a i l a b l e r e s o u r c e o f f South U i s t .
R e f r a c t i o n i s b e l i e v e d t o p l a y a major r o l e i n modifying t h e waves from
t h e Of f shore t o t h e Inshore-3 buoy. However, HRS do n o t r e g a r d i t a s
b e i n g a s i g n i f i c a n t e f f e c t i n d e e p e r w a t e r . Thus f u r t h e r mechanisms
have t o be sought f o r t h e a p p a r e n t l y enhanced r e s o u r c e a t 100m. The
s i t e l i e s approx imate ly 30 km o f f s h o r e and hence h a s a g r e a t e r f e t c h
a v a i l a b l e t o t h e e a s t t h a n t h e o t h e r buoy s i t e s f o r s e a s t o be g e n e r a t e d
by winds blowing o f f s h o r e . Also i t i s i n a more exposed l o c a t i o n and
t h e r e f o r e could be i n a p o s i t i o n t o be a f f e c t e d by waves from around t h e
n o r t h c o a s t of S c o t l a n d which would be s h i e l d e d from t h e o t h e r buoy
s i t e s by t h e Monach I s l a n d s and North U i s t . S a l t e r h a s pu t forward a
t h e o r y t h a t r e l a t i v e l y s m a l l , r e g u l a r u n d u l a t i o n s i n t h e sandy bed a t
t h i s d e p t h a r e r e s p o n s i b l e f o r s e l e c t i v e l y a t t e n u a t i n g c e r t a i n wave
f r e q u e n c i e s . However, t h e answer i s a s y e t unknown,
For the present, with no further data for tank testing and productivity
assessment, RPT have set out a linear transformation for the IOS spectra
determined for 42m depth to produce an available wave climate for
devices at other depths. This is based on the long term power density
predicted for all the buoy sites. The transformation applies to water
depths deeper than 30m for which depths it has had to be assumed that
the directionality remains constant. For 25m depth, where the
directional band of wave energy has been narrowed due to refraction,
spectra resulting from the HRS refraction model have been used. Doubts
concerning their representativeness have already been expressed.
In conclusion, the answer to the question posed at the beginning of this
discussion is that after nearly 6 years of recording there are still
many unknowns and it is not possible to state with confidence the mean
power a device will be exposed to during its lifetime. At the site with
the best data (42m depth) the accepted value for long term mean power
density of 47.8 kW/m used as a reference for all sites, is an estimate
and its directional distribution has had to be inferred from wind data.
Even less confidence can be put on data for other sites owing to
refraction, shielding, energy dissipation and perhaps other, as yet
unidentified effects. Tank tests at this stage should be used to
compare devices, not to assess their absolute productivity, but even so
it must be realised that fair comparisons may not be possible without
further understanding of wave behaviour off South Uist. Finally it is
important to realise what is implied in defining the available resource
using a power density only. Due to device shape, interaction and
shielding this is not the power per metre run the devices are exposed
to.