17.10 - nigel grigg - silver concentrate leaching presentation 2012 final

Upload: angel-canales-alvarez

Post on 02-Apr-2018

216 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/27/2019 17.10 - NIGEL GRIGG - Silver Concentrate Leaching Presentation 2012 Final

    1/42

    Use of Intensive Cyanidation to treatSilver Flotation Concentrates

    Presenter: Nigel Grigg, General Manager, Gekko Systems SA

    Nick Katsikaros, Product Improvement Manager, Gekko SystemsVictor Delgado, Manager, Metallurgical Processes, Hochschild Mining PLC

    Tim Hughes, R & D Manager, Gekko Systems

  • 7/27/2019 17.10 - NIGEL GRIGG - Silver Concentrate Leaching Presentation 2012 Final

    2/42

  • 7/27/2019 17.10 - NIGEL GRIGG - Silver Concentrate Leaching Presentation 2012 Final

    3/42

    Intensive Cyanidation leaching is carried out at elevatedlevels of sodium cyanide levels ranging between 5,000 50,000 ppm, in rich oxygen environment >15 ppm dO

    High Metal Volume Leaching Rates ConcentratedRecovery

    Compare CIL and IC producing ~500oz/day

    Medium grade CIL producing ~500 oz/day @ 150 t/h at 4 ppm Au; 45% solids; 24h leach; 5800m 3Volumetric leaching rate = 0.1 gAu/m 3 /hr IC treating BCC concentrate ~500 oz/day @ 2 t/day conc at 7500 ppm Au; 1.5m 3 active volume; 15 hleachVolumetric leaching rate = 700 gAu/m 3 /hr

    IC is 7,000 times more space efficient than CIP.

    What is Intensive Cyanidation

  • 7/27/2019 17.10 - NIGEL GRIGG - Silver Concentrate Leaching Presentation 2012 Final

    4/42

    What is the ILR?

    ILR (Inline Leach Reactor) is Gekko Systems IC concentratetreatment system for gold and silver

    Batch and continuous designs Suitable for high and low grade concentrates Based on a rolling drum system Fully automated

  • 7/27/2019 17.10 - NIGEL GRIGG - Silver Concentrate Leaching Presentation 2012 Final

    5/42

  • 7/27/2019 17.10 - NIGEL GRIGG - Silver Concentrate Leaching Presentation 2012 Final

    6/42

    2. The Continuous Flowsheet

  • 7/27/2019 17.10 - NIGEL GRIGG - Silver Concentrate Leaching Presentation 2012 Final

    7/42

    Partially Leached Gold Particle Showing Diffusion Layer Continuous removal of this layer significantly improves

    leach kinetics The rolling action attritions this layer providing high shear

    required for IC conditions

    Mixing Drives IC Kinetics

  • 7/27/2019 17.10 - NIGEL GRIGG - Silver Concentrate Leaching Presentation 2012 Final

    8/42

    1)The high shear mixing zoneremoves the attrition layer fromthe gold speeding up cyanideaccess to the gold surface

    2) Solution mixing zone Solutionis drawn out and oxygen is drawn

    in.

    3) Pure oxygen Zone ensuring highdissolved oxygen levels aresustained.

    4) High surface area forsolution/oxygen interface

    5) Solution solid mixing zone forfast kinetics and an efficientchemical reaction

    ILR Cross Section

    ILR Cross Section

  • 7/27/2019 17.10 - NIGEL GRIGG - Silver Concentrate Leaching Presentation 2012 Final

    9/42

  • 7/27/2019 17.10 - NIGEL GRIGG - Silver Concentrate Leaching Presentation 2012 Final

    10/42

    CASE STUDY - MINE BACKGROUND

    HOCHSCHILD SELENE MINE Underground silver mine in Peru ~1,000 tonne/day plant (2006)

    ~13.5 tonne/day high grade Au concentrate Sold the flotation concentrate to smelters Started an Investigation into cheaper way to treat the

    concentrates Contacted Gekko to look at a leach facility at the Ares plant

  • 7/27/2019 17.10 - NIGEL GRIGG - Silver Concentrate Leaching Presentation 2012 Final

    11/42

  • 7/27/2019 17.10 - NIGEL GRIGG - Silver Concentrate Leaching Presentation 2012 Final

    12/42

  • 7/27/2019 17.10 - NIGEL GRIGG - Silver Concentrate Leaching Presentation 2012 Final

    13/42

    ILR10000 Module Ares Site

  • 7/27/2019 17.10 - NIGEL GRIGG - Silver Concentrate Leaching Presentation 2012 Final

    14/42

    Site Specific - Modifications

    Modifications - Fine Feed (

  • 7/27/2019 17.10 - NIGEL GRIGG - Silver Concentrate Leaching Presentation 2012 Final

    15/42

    ARES - ILR COMMISSIONING

    CommissioningTake 1

    Only peroxideavailable

    Buildingincomplete

    Temp slightlylower thanpreviouslyconsidered asambient!

  • 7/27/2019 17.10 - NIGEL GRIGG - Silver Concentrate Leaching Presentation 2012 Final

    16/42

    ARES - ILR COMMISSIONING

    0

    10

    20

    30

    40

    50

    60

    70

    80

    90

    100

    0 10 20 30 40 50

    R e c o v e r y

    %

    leaching time hr

    Batch 1 Peroxide and Lead Nitrate

    Au Recovery Ag Recovery d O2

    Batch 1 Summary Lead Nitrate added twice

    (6h and 24h) Effectively leaching was

    completed in 18h DO at target after 10h Poor leaching

    performance ? 60% recovery Panic? No not yet...

  • 7/27/2019 17.10 - NIGEL GRIGG - Silver Concentrate Leaching Presentation 2012 Final

    17/42

    ILR COMMISSIONING

    0

    10

    20

    30

    40

    50

    60

    70

    80

    90

    100

    0 10 20 30 40 50 60

    R e c o v e r y

    %

    leaching time hr

    Batch 2 Peroxide and Lead Nitrate

    Au by solid Ag by solid sO2

    Batch 2 Summary 82% Au Recovery 80% Ag Recovery Total leach time 57.5h Low DO until 16 hours Lower peroxide addition Suspected some form of

    silver coating orcompound was forming

  • 7/27/2019 17.10 - NIGEL GRIGG - Silver Concentrate Leaching Presentation 2012 Final

    18/42

    ILR COMMISSIONING

    0

    10

    20

    30

    40

    50

    60

    70

    80

    90

    100

    0 10 20 30 40 50

    R e c o v e r y

    %

    leaching time hr

    Batch 3 Peroxide and Lead Nitrate

    Au Recovery Ag Recovery d O2

    Batch 3 - Summary 15kg/t lead nitrate;

    peroxide before cyanide A Pre-oxidation process? Solution assays gave erratic

    results 71% Au Recovery 91% Ag Recovery Some promise!

  • 7/27/2019 17.10 - NIGEL GRIGG - Silver Concentrate Leaching Presentation 2012 Final

    19/42

  • 7/27/2019 17.10 - NIGEL GRIGG - Silver Concentrate Leaching Presentation 2012 Final

    20/42

    ILR COMMISSIONING

    CommissioningTake 2

    Installation 99%complete

    Oxygen andperoxide available

  • 7/27/2019 17.10 - NIGEL GRIGG - Silver Concentrate Leaching Presentation 2012 Final

    21/42

    ILR Commissioning

    Reground conc. in processwater

    Constant peroxide add

    Leach time +50 hours96% Au Recovery87.8% Ag Recovery

    Fast initial leaching but

    then slowed. Recoveries measured by

    solids assay

    Batch 4 - Summary

    0

    10

    20

    30

    40

    50

    6070

    80

    90

    100

    0 10 20 30 40 50

    R e c o v e r y

    %

    leaching time hr

    Batch 4 - Process Water Regrind and Peroxide

    Au Recovery Ag Recovery d O2

  • 7/27/2019 17.10 - NIGEL GRIGG - Silver Concentrate Leaching Presentation 2012 Final

    22/42

    ILR Commissioning

    Batch 5 - Summary 65 hours

    97.1% Au Recovery92.6% Ag Recovery

    Slow rates initially

    limited by oxygen flow Final leach rate faster

    than Batch 4 DO increases as oxygen

    demand drops Leach time is +60 h Leaching incomplete

    0

    10

    20

    30

    40

    50

    60

    70

    80

    90

    100

    0 10 20 30 40 50 60

    R e c o v e r y

    %

    leaching time hr

    Batch 5 - Process Water Regrind and Oxygen

    Au Recovery Ag Recovery d O2

  • 7/27/2019 17.10 - NIGEL GRIGG - Silver Concentrate Leaching Presentation 2012 Final

    23/42

    ILR Commissioning

    Peroxide additionreduced to keep dObelow 10ppm.

    Fast initial rates andimproved final rates. 48 hours

    97.5% Au Recovery94.3% Ag Recovery

    Getting closer.. .

    Batch 6 - Summary

    0

    10

    20

    30

    40

    50

    60

    70

    80

    90

    100

    0 10 20 30 40 50

    R e c o v e r y

    %

    leaching time hr

    Batch 6 - Barren Solution Regrind and ControlledPeroxide Addition

    Au Recovery Ag Recovery d O2

  • 7/27/2019 17.10 - NIGEL GRIGG - Silver Concentrate Leaching Presentation 2012 Final

    24/42

    ILR Commissioning

    Peroxide until dO < 6ppm;with oxygen

    48 hours

    97.7% Au Recovery96.4% Ag Recovery

    End of Gekko

    commissioning on site Optimization...

    Batch 7 - Summary

    0

    10

    20

    30

    40

    50

    60

    70

    80

    90

    100

    0 10 20 30 40 50

    R e c o v e r y

    %

    leaching time hr

    Batch 7 - Barren Solution Regrind and CombinedOxidant

    Au Recovery Ag Recovery d O2

  • 7/27/2019 17.10 - NIGEL GRIGG - Silver Concentrate Leaching Presentation 2012 Final

    25/42

    ILR Commissioning

    Hypothesis was that high peroxide concentration was creating aslow leaching silver phase or causing a passivation coating.

    Reducing peroxide to keep dO below 6ppm improved recovery.

    Oxygen generator eventually returned as at high altitude itwas inefficient and expensive. Oxygen was not required.

    Operational optimisation of other steps, including clarificationreduced total cycle times.

    Batch 8 onwards ...

  • 7/27/2019 17.10 - NIGEL GRIGG - Silver Concentrate Leaching Presentation 2012 Final

    26/42

    Conclusion

    Hochschild now produce Silver dore from high grade flotationconcentrates at the Ares site.

    Recoveries of + 98% for gold and silver using dO controlled

    peroxide addition, achieved within the 48hrs Recoveries matched the testwork predictions. Able to produce dore or sell to the smelter dependant on

    requirements.

    5 more ILR5000 units purchased to increase production capacity

  • 7/27/2019 17.10 - NIGEL GRIGG - Silver Concentrate Leaching Presentation 2012 Final

    27/42

  • 7/27/2019 17.10 - NIGEL GRIGG - Silver Concentrate Leaching Presentation 2012 Final

    28/42

  • 7/27/2019 17.10 - NIGEL GRIGG - Silver Concentrate Leaching Presentation 2012 Final

    29/42

    Leach Kinetics Grind Sensitive

    P80 = 212 um 12hrs - 96% recovery Combined gravity and

    flotation concentrates

  • 7/27/2019 17.10 - NIGEL GRIGG - Silver Concentrate Leaching Presentation 2012 Final

    30/42

  • 7/27/2019 17.10 - NIGEL GRIGG - Silver Concentrate Leaching Presentation 2012 Final

    31/42

  • 7/27/2019 17.10 - NIGEL GRIGG - Silver Concentrate Leaching Presentation 2012 Final

    32/42

    PFD - Proposed

    ILR18hrs Filtration Direct EWC Bleed to MC Detoxification Silver Dore

  • 7/27/2019 17.10 - NIGEL GRIGG - Silver Concentrate Leaching Presentation 2012 Final

    33/42

    Electrowinning Modelling?

    Electrowinning modelling Very high current effeciencies are achieved at high silver

    grades Direct electrowinning a cost effective recovery option

  • 7/27/2019 17.10 - NIGEL GRIGG - Silver Concentrate Leaching Presentation 2012 Final

    34/42

    Other Elements?

    Other elements inleach into solution?

    Need to consider a

    zero discharge circuit

    But locked cycle testshowed a drop in leachrecovery

    Require Detoxification

    of a bleed stream

    Ag Silver 2677 Cu Copper 223

    Al Aluminium

  • 7/27/2019 17.10 - NIGEL GRIGG - Silver Concentrate Leaching Presentation 2012 Final

    35/42

    Detoxification -Cyanide Oxidation

    Natural Degredation Alkaline Chlorination Ozone CAROs Acid

    H2O2 SO2/AIR

    The last 2 options peroxide and INCO process arethe most common.

  • 7/27/2019 17.10 - NIGEL GRIGG - Silver Concentrate Leaching Presentation 2012 Final

    36/42

    Terminology Total, WAD, Free

    Fe CNAu CN

    Ni CN

    Cu CNZn CNAg CN

    CN-, HCN= CN F

    CN WAD

    CNTOT

    stronglycomplexed

    CNF = Free Cyanide CN WAD = Weak Acid DissociableCNTOT = Total Cyanide OCN - = Cyanate

  • 7/27/2019 17.10 - NIGEL GRIGG - Silver Concentrate Leaching Presentation 2012 Final

    37/42

    After H 2O2 Test work ?

    Detox able to get WAD cyanide levels down well under

    international discharge to a TSF standards (50ppmWAD) Detox also precipitated out other metals and so we were able

    to maintain leach recoveries.

    Feed CNwad Peroxide:CNwad Ratio Final Solution CNwad\

    16.2 gpl 10:1 2.93 ppm

    16.2 gpl 5:1 7.16 ppm

    1.62 gpl 10:1 1.16 ppm

    1.62 gpl 5:1 2.81 ppm

  • 7/27/2019 17.10 - NIGEL GRIGG - Silver Concentrate Leaching Presentation 2012 Final

    38/42

    ILR Models ILR45K for Silver Concentrates

    ILR Models - increasing in size

    6 x ILR5000 = 1 x Super ILR45K Design for High Volumes 56tpbatch Flotation concentrates 5tph @ 10hrs residence time

  • 7/27/2019 17.10 - NIGEL GRIGG - Silver Concentrate Leaching Presentation 2012 Final

    39/42

    ILR Models ILR45K for Silver Concentrates

    Super ILR45K

    Design for High Volumes

    i.e. Flotation concentrates

    56tpbatch @ 24hrsresidence time

    5tph @ 10hrs residencetime

  • 7/27/2019 17.10 - NIGEL GRIGG - Silver Concentrate Leaching Presentation 2012 Final

    40/42

    Conclusion

    Intensive Cyanidation of Silver Flotation concentratesis feasible

    It offers many financial benefits to the company The ILR is a suitable IC unit Ensure locked cycle test work is performed and

    modelling is performed with locked cycle testsolutions

    Gekko are continuing to develop a range of technology and services to provide clients withsuitable options

  • 7/27/2019 17.10 - NIGEL GRIGG - Silver Concentrate Leaching Presentation 2012 Final

    41/42

  • 7/27/2019 17.10 - NIGEL GRIGG - Silver Concentrate Leaching Presentation 2012 Final

    42/42

    Questions