16-27_735 - hkie
TRANSCRIPT
-
8/3/2019 16-27_735 - HKIE
1/12
Tunnelling and Pipejacking Techniques forTrenchless Installation of Drainage Pipelines
Hong Kong, a city on hilly natural terrain, with a total area of 1,000 square kilometres, hasa population of 7 million. Its developments mainly concentrate in 20% of the flat land in the
coastal area, mostly formed by reclamation from the sea. The rapid economic growth in the last
20 years demands new infrastructure and upgrading of existing facilities. The crowded spaghetti-
like complex of existing utilities and services underground in the limited road space, and the
busy traffic, make such upgrading and construction of new features, by the conventional open-
trench method, difficult. The use of tunnelling and pipejacking techniques could however resolve
most of the problems associated therewith, such as disturbance to traffic, major diversions of
existing utilities, earth moving, and effect of inclement weather. This would also minimise public
complaints due to inconvenience and loss of business in the nearby shops as temporary traffic
management schemes are only required at the jacking and receiving shaft locations. This paper
discusses the various types of tunnelling and pipejacking techniques adopted in Hong Kong
for drainage pipeline construction under different site constraints and ground conditions, theirperformance, the problems encountered and the recommendations made.
Keywords: Shaft Construction, Hand-dug Tunnels, Heading Construction, Earth Pressure
Balance Method, Slurry Pressure Balance Method, Tunnel Boring Machine,
Ground Settlement, Control of Tunnel Alignment, Rescue Operation
Wilson W S MOKMeinhardt (C&S) Ltd
K W MAKDrainage Services Department,
Government of the HKSAR
The Hong Kong Institution of Engineers Transactions, Vol 16, No 2, pp16-27
Introduction
The roads in the urban areas of Hong Kong are generally congested with
underground utilities and services of different types and sizes, at different
depths. To meet the development demand, new features are constantly
added and existing installations are upgraded over the years. This forms
a spaghetti-like complex network, causing problem to accommodate morenew installations due to lack of sufficient space. Diversion of existing
utilities and services to give room for such installations is difficult as other
locations in the vicinity may also be crowded with utilities and services. In
the past, the installations were commonly carried out by the conventional
open-trench method, requiring the implementation of temporary traffic
management schemes (TTMSs). These TTMSs are usually limited to no
more than 20 - 30 m in length in each stage, depending on whether
existing buildings are located adjacent to the works site, due to the
requirement of allowing space for access of fire engines under emergency
situations, and other factors, such as access to shops or premises. This
limited length of TTMSs could only allow limited utility diversion, and
therefore may not effectively resolve the problem. At some locations,
the underground is congested with existing utilities and services in
layers, rendering such new Installations by the conventional open-trench
method impossible. Tunnelling and pipejacking can however minimise
such effects as road openings are only restricted to the shaft locations,
ie jacking shaft and receiving shaft between a pipeline, which can be
selected to avoid conflicting with traffic and major utilities or minimise
their diversions. Sometimes, tunnelling and pipejacking techniques are
adopted solely to minimise traffic disruption, in extremely busy areas,
or in response to public requests or complaints on the same concern,
or even to avoid the felling of valuable trees.
Pipejacking is a technique of pipeline installation, by hydraulically pushing
a pipe string, effected either mechanically by a tunnel boring machine
(TBM) or manually for excavation, from a jacking shaft to a receiving
shaft. Jacking pipes are then added one after another to the end of the
pipe string as the preceding pipe/TBM advances. The excavated materials
are then transported to the jacking shaft through a trolley system, forhand-dug tunnels and earth pressure balance (EPB) TBMs, and then
lifted up to ground surface, or by a slurry discharge pipeline for slurry
operated TBMs. This procedure is repeated until the pipe string reaches
the receiving shaft [1].
The history of using pipejacking techniques for constructing drainage
pipelines in Hong Kong is short, with the track record in 1989 that
370 m of sewers, in diameter of 1,350 mm, located 6 - 14 m below
ground, were constructed by TBMs under 5 drives, with a length rangingfrom 40 to 80 m, passing beneath major roads [2]. Since then, the scale
of pipejacking works has increased significantly, with the deployment of
different types of TBMs operating in different modes, to account for the
ground conditions likely to be encountered, and also the introduction
of hand-dug tunnels for constructing pipelines crossing old seawalls and
congested utility zones, or ground susceptible to artificial obstructions.
In some projects, some of the works by open-trench may need to be
changed to tunnelling and pipejacking techniques during the construction
stage, to suit constraints of traffic and existing utilities, and such is usually
carried out by means of heading construction due to its simple setup
and fast operation. Up to 2002, more than 14 km long pipelines, with
a diameter range of about 450 - 3,000 mm, using such techniques,
have been completed by the Drainage Services Department (DSD) of
the Government of the HKSAR [3].Between 1996 and 2006, some of the notable projects employing
tunnelling and pipejacking techniques were the West Kowloon Reclamation
Hinterland Drainage Package 2 (Northern Portion) (with a length of more
than 1 km), the Central, Western and Wan Chai West Trunk Sewers (with
a length of 6 km), the Aberdeen, Ap Lei Chau and Pok Fu Lam Sewerage
Stage 1B (with a length of 2 km), and the Wan Chai East and North
Point Sewerage Trunk Sewers (with a length of 4 km), under different
geological conditions and depths.
The Wan Chai East and North Point Sewerage Trunk Sewers was the first
DSD project using slurry operated TBMs to construct curved sewers with
a minimum radius of 320 m, and a S-shape sewer (404 m long), with a
combination of straight and two curved sections (of radius 500 m) and
passing through an intermediate shaft and launching into the receiving
shaft, both with the completion of the permanent shaft in advance [4].
THE HKIE TRANSACTIONS Volume 16 Number 216
-
8/3/2019 16-27_735 - HKIE
2/12
Some other projects also use pipejacking or heading techniques but in
a much smaller scale.
Geological Conditions
The geological conditions in Hong Kong soils are highly variable in a
short length. The narrow strip of land along the seafront, adjacent to very
steep slopes, has been formed by cut and fill techniques in the terrain
over the years, and generally consists of a thin layer of fill underlain
by colluvium and completely to highly weathered granite near the hills
to a thick layer of fill, with different contents of boulders at differentdepths, overlying marine deposits, alluvium and completely to highly
weathered granite towards the sea. Depth to bedrock ranges from 1 to
2 m to 10 to 30 m below ground in a downslope direction. There is a
wide range in particle size between materials in different areas. Very
large boulders or corestones could exist at high levels of the ground.
Metallic objects, anchors and cannons may also be expected in the old
filling areas and in marine deposits.
Groundwater levels tend to be high, generally 2.5 to 3.5 m below ground
level, and tidal response affects much of the urban area.
Shaft Construction
In urban areas, due to constraints of traffic and existing utilities, some of
the jacking and receiving shafts have to be constructed at side streets.They are generally constructed by sheet-piles in homogeneous clayey
to sandy ground (Fig 1) and pipe-piles in mixed ground conditions
(Fig 2). Vibration and settlement monitoring are carried out during the
piling operation to avoid causing damage to adjacent utilities, services,
roads and structures. More expensive pipe-piles are sometimes used in
hard ground to minimise noise and vibration. For sheet-piles, to minimise
vibration, boulder obstructions at intermediate depths are pre-bored
before commencement of pile driving. At some locations, due to the
presence of hard materials at different depths, it would be difficult to
maintain the verticality of the sheet-piles during driving, and the toe
of the sheet-piles would easily be damaged, causing the problem of
interlocking with adjacent piles, often with insufficient embedment length,
and necessitating toe grouting as a remedial measure.
Rectangular shaft is usually constructed because it is more easily to
be modified to accommodate existing utilities and services. However,
at locations where these features are absent, circular shaft is used due
to the smaller member size of temporary works required. For a 1,800
mm diameter TBM, the typical size of a shaft is generally 8 m x 8 m
or 8 m in diameter. This generally would necessitate the occupation of
more than two traffic lanes. As such, the construction has to be carried
out in stages, with one portion completed and decked-over before the
commencement of another, such that disruption to traffic could be
minimised. At traffic sensitive locations, the receiving shaft could be
temporarily decked over after construction and re-opened to allow traffic
flow until the pipejacking drive is completed and the TBM can be lifted
up to ground surface during traffic non-peak hours.In areas of congested utilities and services, it is usually difficult, if not
impossible, to have a clear shaft, by virtue of the long time required
for utilities diversion and the limited space. Therefore, unless they
obstruct the pipejacking operation such as lowering of TBM/jacking
pipes or removal of excavated material, these utilities and services are
temporarily supported inside the shaft, by steel frames. This, however,
would create windows in the temporary works, entailing the erection of
steel lagging plates as support and to prevent ingress of groundwater
(Fig 3). Sometimes, the shape and size of a shaft need to be tailor-made
to suit utility constraint, resulting in the use of a combination of sheetpiles
and pipe-piles to overcome the problem. In some cases, raking piles
Figure 2 Temporary Shaft Formed by Pipe-piles
Figure 1 Temporary Shaft Formed by Sheet-piles
Figure 3 Steel Lagging Plates Provided in the Window of TemporaryWorks
have to be constructed to avoid interference with existing utilities and
services. The use of a concrete wall cast against the pipe-piles is always
required to ensure the stability of the shaft if watermains or drainage
pipelines are in their close proximity as their bursting/breakage could
significantly disturb the ground.
For deep shaft, grouting is always required in the perimeter to ensure
watertightness, before excavation is to commence. After the shaft has been
formed, a thrust wall and a launching/receiving eye are then constructed
to allow the pipejacking operation. For multi-direction driving, a circularthrust wall can provide better orientation and transfer of loading.
THE HKIE TRANSACTIONS Volume 16 Number 2 17
-
8/3/2019 16-27_735 - HKIE
3/12
2 bars is required to balance the water head in the excavation face and
be maintained inside the tunnel round the clock to avoid flooding which
may in turn affect tunnel stability. To ensure constant supply of air, a
standby compressor is provided for emergency situations. Pressurisation
and depressurisation is required in the air-lock installed on top of an air
deck erected in the jacking shaft, for personnel entering and leaving the
tunnel respectively. A medical lock needs to be provided at the shaft
location when the applied compressed-air pressure exceeds 1 bar. There
have been some cases that air was found leaking through the porous
ground during tunnel excavation, resulting in inflow of groundwater. This
entailed horizontal grouting from inside the handshield to stabilise theground before further excavation could be proceeded with.
The rate of excavation is generally 1 - 2 m per day for free-air tunnel
and 0.5 - 1 m per day for compressed-air tunnel, depending on the
ground conditions.
Heading Construction
Heading construction is a simple form of hand-dug tunnel, and is widely
used to construct short pipelines, usually in the range of 10 - 30 m
in length, crossing road junctions or locations of congested existing
utilities and services, in shallow depth, due to its easy setup and thus
the relatively low cost. The tunnel size could generally vary from 1.5
to 2.5 m in diameter, depending on the size of pipeline to be installed.
To tackle different site constraints and ground conditions, the methodof construction in each tunnel could vary, and the following cases are
typical examples.
To suit the limited space in the jacking shaft which is a common
phenomenon in urban areas as constrained by existing utilities, the shield
head can be tailor-made by several short sections and connected together
Depending on the size and depth of the shaft, and the ground conditions
encountered, each shallow shaft (less than 8 m in depth) generally
requires 6 to 8 weeks for completion from piling to excavation. The
construction for deep shaft (up to a depth of 22 m) would however take
a longer time, from 12 to 18 weeks, due to the high variation in ground
conditions, particularly the rock content.
These shafts are later used for construction of permanent shafts for future
maintenance. As most of the shaft locations have different degree of
utility constraints, the location, size and shape of access and desilting
openings of each permanent shaft may need to be tailor-made to suit
the site condition.
Modes of Tunnelling Operations
Three modes of operations are commonly adopted for pipejacking
works in Hong Kong. They are hand-dug tunnel, earth pressure balance
TBM and slurry pressure balance TBM. The contractor will, based on
the results of site investigation conducted in the design stage by the
client, assess the risk and carry out further investigation if doubt exists
and select the most appropriate mode for the ground conditions likely
to be encountered.
Hand-dug Tunnel
Hand-dug tunnel, formed by precast reinforced concrete segments astemporary lining and connected each other with a bolting system and a
rubber gasket at the joint to prevent ingress of water, can be constructed
under either a free-air or a compressed-air environment.
Free-air tunnel (Figs 4 and 5) is suitable for shallow pipelines crossing old
seawalls, artificial obstructions and road junctions, usually less than 50 m
in length for a drive. Prior to tunnelling, the alignment of the pipeline is
fully stabilised by grouting to ensure stability. The excavation is effected
manually by pneumatic tools or mechanically by a mini backhoe inside
the handshield (ie a protective tube in front of the pipeline to allow
manual excavation by workers), if the diameter of the tunnel permits
(usually 1,800 mm or above). The excavated materials are transported
to the jacking shaft by a trolley system and then lifted up to ground
surface. The handshield is advanced by extending the hydraulic jacks
installed with it, against the concrete segments erected at the rear as
reaction. New segments are then added after the retraction of hydraulic
jacks. The overcut between the ground and the segments is immediately
filled up with grout to prevent settlement. This procedure is repeated until
the tunnel reaches the receiving shaft. Upon completion of the tunnel
construction, a permanent pipeline is pushed inside from the jacking
shaft and its annulus is filled up with grouting materials equivalent to
the strength of the overlying ground.
Compressed-air tunnel (Figs 6 to 8) is applicable to grounds where
groundwater table is high. Depending on depth, an air pressure of 1 to
Figure 4 Launching of Hand Shield for Free Air Hand-dug Tunnel
Figure 5 Excavation in Free Air Hand-dug Tunnel
Figure 6 General View of Compressed Air Setup in Jacking Shaft
THE HKIE TRANSACTIONS Volume 16 Number 218
-
8/3/2019 16-27_735 - HKIE
4/12
one by one by welding inside the jacking shaft before launching. This
is then followed by steel sleeve pipes or precast concrete pipes which
are pushed forward into ground by a hydraulic system in the jacking
shaft (Fig 9), with lubricant constantly injected under a pressure slightly
higher than the overburden pressure, from the grout holes installed in
the pipes to minimise soil friction, and to avoid close-up of the overcut,
causing ground settlement, during the jacking operation.
To determine the ground condition, probing is carried out in every
2 - 3 m ahead of excavation. The ingress of water, if any, is controlled
by the injection of grout, by means of horizontal and inclined holes
from the shield head, prior to excavation. If instability is found in the
working face, steel shutter, in the form of plankings, needs to be erected
at the front of the shield (Fig 10), and the working personnel evacuated
until the ground treatment is completed, by specialised working gangs,
After pushing the sleeve pipeline into the receiving shaft, the annulus,
formed by overcut, is filled up with grout, with a strength equivalent to
the overburden pressure, to avoid ground settlement.
At narrow shaft locations where lowering the sleeve pipes is a problem,
the tunnel lining could be formed by steel segments connected to each
other by welding (Fig 11).
The advancement of the shield head is effected by extending the hydraulic
jacks installed with it against the steel segments erected at its rear
(Fig 12). The overcut outside the segments is immediately filled up by
grout, through the holes provided at the crown and the axis at the twosides, after the completion of each ring in the tunnel. This method is
generally applicable to the construction of small size of pipelines.
For crossing major roads where underground boulder obstructions are
expected, the temporary works in the tunnel, formed by drilling horizontal
pipe-piles from one shaft to another, could effectively penetrate through
such obstructions to act as temporary lining (Fig 13), thus ensuring the
stability during excavation. Depending on ground and groundwater
Figure 7 Excavation in Compressed Air Hand-dug Tunnel
Figure 9 Jacking of Steel Sleeve Pipe for Heading Construction
Figure 8 General View of a Completed Tunnel
Figure 11 Appearance of a Tunnel Formed by Steel Segments
Figure 10 Steel Planking Erected in Excavation Face to Prevent Ingressof Groundwater
THE HKIE TRANSACTIONS Volume 16 Number 2 19
-
8/3/2019 16-27_735 - HKIE
5/12
conditions, grouting may be required to stabilise the ground by injection,
through the slot holes provided in the pipe-piles, before excavation
takes places. The permanent pipeline is then pushed into the tunnel
after excavation (Fig 14), and its annulus is filled up with lean concrete
or grouting materials, as appropriate. This method is usually suitable for
constructing relatively large size of pipeline in deeper ground.
For tunnelling in filling ground with low rock content in shallow depth,
the temporary works could be in the form of a portal frame, constructed
by driving several short sections of steel plankings or channels, in the
direction of excavation, ahead of excavation, and then supporting them
by steel members after excavation (Fig 15). This method is howeverunsuitable for water bearing ground due to the presence of gaps between
the plankings/channels that the ingress of water could pose stability
problem in the tunnel, particularly during dewatering.
The average production rate for heading construction is generally
1 - 2 m per day. If large boulders or full-face rock are encountered in the
excavation face, their removal has to be carried out by pneumatic tools
as the size of the tunnel does not allow the use of heavy mechanical
plant. Hence, the rate of progress is generally slow, with 100 - 200 mm
in length achieved per day. In addition, maintaining stability of overlying
ground during boulder removal is always a problem.
The heading construction method also enables the alignment of a
tunnel to be adjusted, by lowering or shifting the shield head/segments
to either side, to avoid conflicting with unexpected utilities or services
encountered during excavation, thus giving more flexibility to resolvingthe problem, when compared with the TBM tunnelling.
Heading construction, by means of steel plankings and portal frames,
has become popular in Hong Kong recently, particularly for installing
branch sewers or drains where groundwater is usually not a problem.
This is due to its easy setup, not requiring heavy machinery, and its
flexibility in handling obstructions. The downside of this method is that
construction may be dangerous if the soil cover is too shallow. Its left-
in temporary works also takes up an underground space, filled with
steel sections, much larger than the pipes to be laid, typically 1.5 m x
1.5 m, to enable manual operation, thereby making the already congested
underground space even more so and also imposing difficulties for future
maintenance of the laid pipes.
Earth Pressure Balance Method
Earth pressure balance TBM (Figs 16 to 18) is adopted for tunnelling
through homogeneous ground made of clay, silt or sand, usually in the
layers of fill, marine deposits and alluvium. The cutting wheel generally
appears in spoke type, with tungsten carbide cutting bits mounted on
the surface and a screw crusher in the centre. It is capable of excavating
soft rocks of sizes up to 25% of the area of the cutting wheel.
The system works on the principle of maintaining pressure in the
excavation chamber equal to the hydrostatic pressure in surrounding
ground. This pressure is constantly monitored and controlled by varying
the speed of the screw conveyor. The excavated materials are transported
to the jacking shaft, by a trolley system, and then lifted up to ground
surface. When soft ground is encountered or excavation is carried out
Figure 13 Tunnel Formed by Horizontal Pipe-piles Figure 15 Hand-dug Tunnel Constructed by Steel Plankings with PortalFrames
Figure 12 Extension of Hydraulic Jacks in Lead Pipe for Advancement Figure 14 Permanent Pipeline Installed in the Tunnel
THE HKIE TRANSACTIONS Volume 16 Number 220
-
8/3/2019 16-27_735 - HKIE
6/12
below groundwater, high water absorbent polymer or other conditioning
agents are added to the excavation chamber firmly grabbing the soil to
stabilise the excavation face and to ease the mucking process.
For jacking shaft, the works area required is less than that of the slurrypressure balance method, due to less plant required for the operation,
and could vary from 3.5 to 5 m in width (ie the width of the shaft) and
be generally in the range of 20 - 30 m in length. At locations where
space is a problem, the size of the works area could be reduced by
stacking some of the plant. For receiving shaft, the works area is much
smaller and is only required when the TBM is lifted up from the shaft
after completion of the pipejacking works.
Common sizes of TBMs range from 1,050 mm to 1,800 mm, but the
use of 2,600 mm diameter TBMs has been experienced. Due to their
simple configuration, in particular only cutting bits are equipped in the
cutting wheel and no telescopic section is provided at the rear of the
TBM, these TBMs cannot cut through big boulder obstructions and are
therefore generally suitable for soft ground excavation. Manual removal
of artificial obstructions ahead of excavation or change of damaged
cutting tools cannot be done from behind the cutting wheel in most
of TBMs due to no man access in the front bulkhead. To account for
unexpected ground conditions, the length of each drive is usually less
than 100 m.
A production rate of 6 - 8 m per day could be achieved in filling ground
with occasional boulders.
There is another type of TBM using this operating mode but has different
configuration in the cutterhead and thus the cutting tools (Fig 19).
Consisted of two main parts in the TBM and built of heavy gauge steel,
the front bulkhead of the first part acts as support for the boring unit
and seals the front chamber for pressurisation. This part of the TBM,called the shield, houses the machine operators porthole, a spoil screw
conveyor and an access chamber to the face of the TBM for manual
excavation under a compressed-air working environment. The second
part is the telescopic tailskin which can extend to provide sufficient
thrust to the shield and is also used for connecting the precast concrete
pipes/segments behind. An articulated joint is provided between the
shield and the tailskin, to enable steering of the shield so that the line
and level of the pipeline can be adjusted.
In normal operation, this type of TBM is operated in closed mode, and
excavation is effected by a boom cutter or a mini-backhoe connected
to an articulated telescopic arm mounted on a fully rotating turret in
clockwise or anti-clockwise direction, and the mucking chamber is under
compressed-air to balance groundwater. In this mode, transportation
of the excavated materials is similar to that of the TBM with a cuttingwheel. In order to prevent loss of compressed-air, the excavated materials
in the screw conveyor are always kept full. When the TBM is operated
in open mode for removing obstructions manually, the triangular steel
panels hinged to the leading edge of the shield, which act as shutters,
are extended by hydraulic jacks operated from the drivers cabin, to
support the overlying ground during the operation.
There has been a case that the TBM was stuck in ground in the middle
of a drive, due to the accidental opening of a valve in the front bulkhead
which resulted in the ingress of soil and water in the TBM, causing
inundation and damage. This TBM was finally recovered by a rescue
tunnel constructed from the receiving shaft, and the stalled pipeline was
then pushed to the receiving shaft through the rescue tunnel.
Slurry Pressure Balance Method
Slurry pressure balance TBM (Figs 20 to 22), often called slurry shield, with
cutting bits and disc cutters installed at suitable locations in the cutting
wheel, of semi-dome type or dome type, is widely used to construct
pipelines in mixed to hard ground conditions under groundwater, to a
depth up to 30 m. Common sizes of TBMs are 1,200 mm, 1,500 mm
and 1,800 mm.
The allowable jacking load in these TBMs ranges from 500 to 1000
tonnes(T), whereas the allowable torque pressure is in the range of
100 - 300 bar. The length of driving could vary from less than 50 -
100 m to more than 500 m passing through a number of intermediate
shafts in a single drive.
The works area required for jacking shaft is generally 7 - 8 m wide and40 - 50 m long, for placing mobile crane, TBM control container, power
Figure 18 Transportation of Excavated Material in Jacked Pipeline
Figure 16 Typical Pipejacking Works Using Earth Pressure Balance TBM(Courtesy of Herrenknecht AG)
Figure 17 Mechanism of Earth Pressure Balance Method (Courtesy ofHerrenknecht AG)
THE HKIE TRANSACTIONS Volume 16 Number 2 21
-
8/3/2019 16-27_735 - HKIE
7/12
Figure 19 Operation of an EPB TBM Using Mini-backhoe for Excavation (Courtesy of CSM BESSAC)
Figure 20 Typical Pipejacking Works Using Slurry Pressure Balance TBM(Courtesy of Herrenknecht AG)
Figure 21 Mechanism of Slurry Pressure Balance Method (Courtesy ofHerrenknecht AG)
Figure 22 General View inside a Jacked Pipeline Installed by SlurryPressure Balance Method
pack, generator, desander, muck tank, bentonite mixer, grab lorry, and
jacking pipes, etc. At certain locations, some equipment have to be put
on decks to suit the limited size of the works area as constrained by site
conditions, or a satellite works area has to be provided in the vicinity.
TBMs of 900 mm in diameter or smaller may be incapable of tunnellingthrough big rocks due to the size of the cutting wheel limiting the
number and size of the disc cutters. Therefore, advanced drilling to
determine the ground conditions along the pipeline alignment needs to
be carried out prior to commencement of the work to minimise the risk
of TBM stoppage and thus the rescue operation. There has been a case
that a 600 mm diameter TBM encountered full-face rock after leaving
the jacking shaft for about 1 m (Fig 23) and was stuck. The TBM was
finally pulled back to the shaft and the rock obstruction was removed
by percussive drilling prior to resumption of tunnelling.
During the course of driving, bentonite based slurry, with a viscosity
of 40 - 50 Marsh sec for sandy ground, is constantly pumped into the
excavation chamber, through a slurry charge pipe. This forms a cake
over the excavation surface, to stabilise the face and prevent the ingress
of groundwater. The mix of slurry needs to be adjusted to suit thematerial in the excavation face. Sometimes, polymer has to be added to
THE HKIE TRANSACTIONS Volume 16 Number 222
-
8/3/2019 16-27_735 - HKIE
8/12
slurry to increase the performance in adverse ground conditions, by, for
instance, decreasing the ground porosity or improving the properties of
the excavated materials in soft ground to maintain the ground stabilityduring excavation. The excavated materials are then pumped to ground
surface and then separated by a desander, with the slurry being recycled
for use and the spoil disposed of off site. For clayey ground, no slurry
is used and water under pressure is injected for the intended purpose.
Lubricant is also injected to the overcut along the pipeline, through
the lifting holes at the crown of the jacking pipes and the holes in
their axis, by an automatic system with pre-set timer and volume of
flow (Fig 24). Intermediate jacking stations, each with 8 - 12 nos 50 -
80 T hydraulic cylinders, are installed at pre-determined locations of the
pipeline, usually every 80 - 100 m, to avoid excessive loading in the
main jacking station. However, no intermediate jacking station can be
installed in pipelines of 600 mm in diameter or smaller due to limited
space. In addition, jacking pipes of such sizes do not have the holes
for injection of lubricant. Therefore, the jacking is generally limited toshort length, say 30 - 40 m.
For rock excavation, disc cutters, each with single or double discs, with
a diameter range of 200 - 300 mm, are equipped in the cutting wheel
and each disc cutter exerts a thrust of 20 - 30 T onto the rock face,
forming vertical and radial cracks in circular kerbs at distances of 60
- 100 mm. By repeated rotations of the cutting wheel and disc cutters,
these cracks are enlarged and eventually cause the rock mass in between
to be broken into small fragments. The fragments are further reduced in
size by the conical crusher at the rear of the cutting wheel, to a size of
not more than 40 mm in diameter. In view of travelling a longer path
for excavation due to their positions, gauge disc cutters (ie near the edge
of the TBM) usually require more frequent replacement than centre disc
cutters (ie near the centre of the TBM).
For TBMs with a diameter of 1,500 mm or larger, a horizontal air-lock is
generally provided at the rear for enabling inspection of the condition of
disc cutters and making necessary replacement, through the man access
in the front bulkhead, under compressed-air. For tunnelling through hard
ground, a telescopic section is equipped in the TBM or an intermediate
jacking station is provided behind the TBM, to provide sufficient thrust
for excavation.
The advancement rate of TBM is 100 - 200 mm/min in soft ground
to 20 - 30 mm/min in hard ground. The TBM daily production rate
depends on the configuration of the TBM and could vary significantly
under different ground conditions.
Based on DSD Contract No DC/2000/11 [5], 2 m per day in hard
ground to 30 m per day in soft ground, with an average of 4.5 m per
day, could be achieved. A set of disc cutters is capable of completing
2 shallow drives and 1.5 deep drives respectively, under typical HongKong soil conditions.
In some cases, the pipeline has to pass through existing reinforced concrete
seawalls, requiring the affected portion to be completed by hand-dug
tunnel before the use of TBM to complete the remaining drive.
Ground Settlement
Tunnelling and pipejacking would induce settlement in surrounding
ground. The magnitude of settlement is greatly affected by ground
conditions, type of tunnelling method, depth of tunnel and jacking
speed. The presence of underground utilities and services above the
jacked pipeline would lead to under-measurement of surface ground
settlement due to their rigidity. It is necessary to estimate the settlement
influence zone and to assess its effect on nearby roads, structuresand utility installations such that they can be safeguarded during the
operation and remedial measures taken, if necessary. Maximum ground
settlement occurs at the centre line of the pipeline and diminishes to
zero at a distance from its two sides.
Figure 23 View of Full-face Rock outside the Launching Eye of JackingShaft
Figure 24 Conditioning and Lubrication for Jacked Pipeline
THE HKIE TRANSACTIONS Volume 16 Number 2 23
-
8/3/2019 16-27_735 - HKIE
9/12
The majority of ground settlement (70 - 80%) occur during and immediately
after completion of tunnelling and pipejacking works. Further settlement
would continue, and its stoppage depends on the ground conditions
above the jacked pipeline, for a few weeks to a few months.
Dated back to 15 - 20 years ago, the settlement was monitored using nails
installed on pavement. However, this type of installation is unable to detect
settlement accurately below rigid concrete pavement. In a project, a road
collapsed due to the presence of cavities in ground without indication by
the monitoring data. After this incident, sub-surface settlement markers, in
the form of a steel rod, by coring through rig id pavement, are generally
adopted, with their installation at suitable intervals along the alignment
of the pipeline and at offset at both sides, prior to commencement of
a pipejacking drive. In flexible pavement, nail markers are used. This is
supplemented by visual inspection that if settlement occurs, cracks would
develop in pavement. For structures sitting on shallow foundation, their
condition has to be assessed before commencement of tunnelling and
pipejacking such that suitable monitoring devices such as tilt markers
and settlement markers can be installed to monitor the ground behavior
during the course of works.
Under normal situations, the monitoring is carried out once a day. This
frequency however may have to increase if there are abnormal readings
or the magnitude of readings changes abruptly. In the event that if the
measured ground settlement exceeds the predicted value, the tunnelling
and pipejacking works have to stop and an investigation on the cause, andthe damage, if any, carried out, with remedial measures such as ground
treatment implemented, as necessary, prior to resumption of work.
Through the proper operation of works, the ground settlement for most
of the pipejacking drives using TBMs could generally be controlled
within 15 mm for most of the Hong Kong soils, although excessive
ground settlement has been noticed in some drives due to unfavorable
ground conditions.
Control of Tunnel Alignment
The pipejacking works in Hong Kong using TBMs generally follow the
Tunnelling Specification [6] as guideline for controlling tunnel alignment,
in that a tolerance of 50 mm and 35 mm is specified for line and level
respectively. For the 4 km long pipejacking drives completed in DSD
Contract No DC/2000/11, under different ground conditions, 21% for
line and 19% for level exceeded the tolerance, generally by 2 - 50 mm,
despite the fact that the excavation face had been conditioned by slurry
and sometimes by the addition of polymer, as necessary. Moreover,
deviations in more than 100 mm were recorded at some locations in a
few drives where the ground conditions were alternating. In addition,
about 2% of the pipelines exceeded the tolerated 0.5 degree angular
deflection at pipe joint, resulting in the need to carry out a detailed
inspection to ensure that there is no dislocation thereat. For excessive
opening in pipe joint, remedial measures have to be carried out. This
could be achieved by locally trimming the concrete at the pipe end for
better bonding before applying nor-shrinkage epoxy, with a strength
equivalent to the pipe, to fill up the problematic location for prevention
of ingress of water.
The tunnel alignment is corrected by suitable extension or retraction of
the steering cylinders installed in the TBM. A TBM with 4 nos steering
cylinders has better control in alignment than that with 3 nos Out-of-
tolerance in alignment requires a long length to correct in order to avoid
causing damage to the jacking pipes.
For pipejacking works using handshield for excavation and sleeve pipes/
segments to construct the temporary tunnel, no tolerance is specified
for line and level as the tunnel will be large enough for installation of
the permanent pipeline. However, allowance has to be made to account
for the irregular profile of the tunnel, due to encountering different
ground conditions during excavation, which could affect installation of
the permanent pipeline therein to the required alignment.
For the tunnel formed by horizontal pipe-piles or steel plankings/channels, its alignment may need to be adjusted to cater for unexpected
obstructions due to existing utilities and structures. In the worst case,
the design of the permanent pipeline has to be modified to suit the
actual site condition.
Rescue Operations
A TBM would be stuck in ground if obstructions are encountered during
excavation. It is necessary to carry out a detailed investigation on its
cause, and then replacement of the damaged part from inside the TBM.
These obstructions could be natural or artificial. If the problem cannot
be overcome, the stalled TBM has to be recovered by means of a rescueshaft or a rescue tunnel, as appropriate, with the obstruction removed.
The works would be delayed and new TBMs may need to be deployed
for ensuring the completion of other pipejacking drives on time, which
could disturb the programme of works.
Based on DSDs Report No RD 1005/2 [3], about 2% of the pipejacking
works encountered obstructions, resulting in rescue operation.
The selection of a rescue option depends on many factors such as
the damage in the TBM, the location of TBM stoppage with regard to
its distance from the jacking shaft and the receiving shaft, the traffic
conditions, and the ground and groundwater conditions, above the
TBM, the constraints of utilities and services, and the effects on nearby
structures and facilities. The options may include but are not limited to
change of the damaged cutting wheel so that the TBM can continue
the remaining drive to the receiving shaft, removal of the TBM through
the rescue shaft and completion of the remaining drive by another
TBM from the receiving shaft to the rescue shaft, and construction
of a rescue tunnel from the receiving shaft, to overlap the TBM and
then the pipeline is pushed into the receiving shaft from the jacking
shaft. As each option involves different degree of risk, its suitability
needs to be assessed carefully, with site investigation works carried
out at and in the vicinity of the stalled TBM, before a decision is
made.
There have been two cases that a rescue shaft, formed by a combination
of sheet-piles and pipe-piles, in the size of 1.8 m x 5.2 m on top and
2.5 m x 5.2 m at bottom and 16.5 m deep, and a rescue tunnel, with a
length of 35 m and an internal diameter of 2,440 mm, using compressed-
air pressure to balance groundwater, took about 8 months and 10months respectively for rescuing the stalled TBM, from investigation on
the cause of the problem, planning of rescue, construction, execution,
to recovery of the TBM [7].
There has however been a case that a 1,350 mm diameter slurry
operated TBM encountered a steel box section when tunnelling in river
bed and could not advance further. The cutterhead of the TBM was
moved backward by retraction of the steering cylinders, to enable the
driving, vertically, of a 900 mm diameter steel pipe for encasing the steel
section. An attempt to completely lift up this steel section through this
steel pipe was carried out but breakage occurred at the location partly
cut by the disc cutters of the TBM, during the lifting operation. To enable
man-entry for manual removal of the steel section, a steel plate, with a
prefabricated hole to accommodate the steel section, was installed in the
casing, with sandbags added on top of the plate to prevent uplift forcedue to water pressure, and the ingress of water in the steel casing was
controlled by the use of a pump. The broken steel section was finally
cut manually and removed, and the pipejacking works resumed.
Some Problems Encountered
The following problems are commonly encountered during pipejacking
works and could affect the progress:
For deep drive, high groundwater pressure requires additional jacking force
to advance the TBM against the pressure. Therefore, more intermediate
jacking stations have to be installed at suitable intervals of the pipeline
to ensure that there is sufficient thrust to push the pipeline forward. In
addition, such high groundwater pressure also makes the TBM and the
first few pipes moved back to the jacking shaft whilst new pipes arebeing added. This always requires the temporary fixing of a steel bracket
THE HKIE TRANSACTIONS Volume 16 Number 224
-
8/3/2019 16-27_735 - HKIE
10/12
in the TBM/pipe to rigidly connect to the surrounding temporary works
as support during pipe connection.
A treated soil block, formed by grouting, is usually provided in the ground
outside the launching eye of the jacking shaft and the receiving eye of the
receiving shaft, to prevent ingress of water during the jacking/receiving
operation and to support the TBM during launching and reception. In
grounds with high content of boulders, the grout may not be able to
provide effective bonding between soil and rock. This would easily
cause dispersion in the grout block when the TBM is breaking through.
As a result, soil particles would migrate into the shaft, through the eye
location, and settlement would occur in overlying ground, damaging
utilities and services.
During the course of pipejacking, zig-zag line and level would occur
in the pipeline due to encountering different ground conditions. This
would require rendering in the depressed sections to provide a uniform
profile for the pipeline, affecting hydraulic performance. Excessive out-
of-tolerance would also cause opening-up of pipe joints, causing ingress
of groundwater and instability of the pipeline.
Cracking of concrete in pipe could happen at locations where there is
excessive deviation in line and level caused by uneven distribution of
jacking force, as a result of unfavourable ground conditions encountered.
This would require a temporary steel lining for protection to complete
the remaining drive before repair is carried out. In the worst case, the
damaged pipe has to be repaired immediately, with the spalled ordefective concrete removed and replaced by high strength non-shrinkage
epoxy, before the pipejacking works can continue.
When tunnelling through clayey ground, slow transportation rates in
the slurry discharge pipe always occurs, due to the plastic material
accumulated in the inlet of the spoil disposal chamber. This necessitates
high pressure water to disperse such material through the nozzles provided
nearby. Pipe blockage is also found when obstructions such as timber,
steel bars, etc are encountered, resulting in the long time to dismantle
the respective sections of pipes for clearance.
Wear or damage in disc cutters is a normal phenomenon in TBM
during tunnelling, and replacement has to be made at the right time to
ensure their proper function. There are however cases that they could
not be replaced from inside the TBM due to damage/distortion of theirconnections, affecting the cutting capacity and losing the function of
further advancement.
Excessive ground settlement or subsidence would occur in unstable
ground or due to improper control of the TBM, causing bursting of
watermains or gas mains. Although settlement monitoring is carried out
at regular intervals, this situation would still occur when there is a sudden
change in ground conditions not immediately noticeable to the
TBM operator for necessary adjustment in the TBM. Excavation in
bouldery ground or soft ground with boulders would also have such a
phenomenon.
Repeated extension and retraction of hydraulic jacks would cause
intermediate jacking stations to leak, due to the rubber seal being torn
out by such operation. This situation would be more critical in curved
alignments under eccentric loading throughout the drive. No repair couldbe made until completion of the drive. If the leaked location is near the
TBM, the tunnelling operation might be jeopardised.
In porous ground, slurry injected from the TBM to balance groundwater
pressure would easily leak into ground, cause blockage to ductings of
utilities, and encroach into drainage features, affecting their function.
The tunnel alignment is affected by ground conditions during driving. It
would be difficult to control the alignment in soft ground with boulder
embedment or in alternating ground with soft and hard materials as the
TBM would tend to move faster towards soft materials. The hydraulic
performance of a pipeline would be affected should there be excessive
deviation in alignment.
A TBM would be stuck in ground if it cannot cut through obstruction
during the course of driving. This would result in the rescue operation,
and high frictional force would develop along the pipeline due to close-
up of the annulus, causing difficulty to further proceed with pipejacking
works.
Discussion
Appropriate Selection of Method to Avoid Delays
According to DSD Report No RD1005/2 [3], about 75% of the pipejacking
works were completed by TBMs using the slurry pressure balance method,
1% by the earth pressure balance method and 24% by hand-dug tunnels.
However, there is a rapid increase in the use of hand-dug tunnels, in
the form of heading construction, in recent years.
Each of the pipejacking techniques is beneficial when used in a proper
manner. Its performance is generally reflected by daily production rate,
capacity in dealing with hard rock, control of line and level of pipeline,
and ground settlement or heaving. It is therefore essential to choose the
appropriate method to avoid timely and costly remedial measures if the
work is stopped by obstructions or mechanical failure, which will cause
nuisance to the public and in turn lose the spirit of using them.
Cost of Installation and Choice of Techniques
The cost of pipeline installation using such techniques does not vary
with depth except for the increased cost of providing deeper shafts and
manholes. In comparison with the conventional open-trench method, the
cost of the slurry pressure balance method, the earth pressure balancemethod, the free air hand-dug tunnelling method with grouting and the
compressed air hand-dug tunnelling method is higher in the order of 2 - 10
times, whereas the construction time is usually faster in most cases.
The choice of a technique lies with the designer or the contractor and is
dependent on the degree of risk that the project can accept. This is usually
governed by access, ground and groundwater conditions and accurate
identification and consideration of all other constraints. Increase in site
investigation works would reduce the risk but could not eliminate it.
The earth pressure balance method, although relatively inexpensive of
tunnelling in soft ground, is unable to deal with large boulders and artificial
obstructions. Although access to the face through the airlock chamber
in large TBMs is feasible, their removal will be inefficient due to limited
space and the use of only hand tools. Breaking through the unknownthickness of boulders will pose a risk that there may be a sudden change
in groundwater pressure endangering the worker. Therefore, the recent
trend is that slurry operated TBMs have been used as a substitute to
minimise the risk of TBM stoppage due to the above problems.
The slurry pressure balance method has demonstrated its good rate of
progress in variable ground, but its use needs monitoring of excavation as
the machine advances to eliminate settlement (too much excavation, not
enough advance) or heave (too much advance, not enough excavation).
Hence, the operators experience, training and response when problem
arises are crucial. Change of operator during the course of work should
be avoided as much as possible as the new operator would take a long
time before he becomes familiar with the TBM and the ground conditions.
The density, viscosity, filtrate water and shear strength of the slurry have
to be tested on a regular basis and changed when any of these exceedsthe specified upper or lower bound limits to ensure its functionality. The
configuration in the cutting wheel should be capable of cutting through
extremely hard and abrasive rock and, on the other hand, excavating
soil efficiently. The disc cutters provided have to be extremely wear
resistant and capable of taking the maximum thrust of the TBMs. To
avoid excessive heat generation, disc cutters should be equipped with
water cooling system. Locally made discs are to be used with care due
to difficulty of controlling their quality during the heat treated process.
In the event that a boulder zone is identified ahead of the drive, it may
be necessary to stabilise the soil above the affected area to minimise
ground settlement caused by vibration or over-excavation during the
cutting-through operation. This would also help to control the line and
level of a pipeline. It may be worthwhile to note that up to now, no
TBM is capable of cutting through large artificial obstructions, especiallymetallic objects, resulting in its stoppage in ground.
THE HKIE TRANSACTIONS Volume 16 Number 2 25
-
8/3/2019 16-27_735 - HKIE
11/12
Problems with TBMs
The type of cutting wheel and TBM to be used and the expected advance
rate depends on ground conditions and their variability likely encountered.
A radical and unexpected change of ground conditions can prevent a
drive from being completed and require rescue operation to permit the
work to be completed. Likelihood of obstructions, natural or artificial, can
also prevent a drive from being completed, and the rescue of a stalled
TBM could be time-consuming and expensive, affecting progress.
Additional Features in New TBMs
Research in TBM technology has developed rapidly in recent years,
based on the problems encountered in different projects under different
ground conditions. New TBMs are now equipped with additional features
that allow increased and reliable performance under a range of ground
conditions. To account for the high variability in ground conditions in a
short length, which is a main characteristic in Hong Kong soils, mixed
ground slurry operated TBMs have been widely adopted by contractors
to minimise the risk.
Advantages of Lubricant
Lubricant, applied along the jacked pipelines, has demonstrated to be
effective in lowering jacking forces and reducing the risk of pipe damage
in most of the pipejacking drives. In long drives, automatic bentonite
systems with programmable valves should be used to ensure that lubricant,with the specified volume, is injected to the annulus of the pipeline in
pre-fixed intervals, to serve the intended purpose.
Laser Guidance System
In straight drives, the position of TBM is determined by the guidance
system which relies on the laser beam transmitted from the laser device
installed at the rear of the jacking shaft, to the target plate installed in
the TBM. However, in curved drives, the laser technology with the use
of reference prisms and total survey stations is generally used in TBMs
with diameters of 1,800 mm and larger. In small TBMs, the use of Gyro
compasses with hydrostatic grade correction is a common approach and
has demonstrated its accuracy.
Problems with Disc Cutters
The performance of disc cutters for pipejacking works has a short history
in Hong Kong. In 1990s, most of the works were carried out in single
drives, with a length generally not exceeding 100 m, and in shallow
depth. It was until 1996 onwards that the scale of pipejacking works
has increased to a few kilometres in a contract, with also deep drives
tunnelling through hard strata in ground. However, no complete record
on the respective performance could be traced except in DSD Contract
No DC/2000/11. This Contract showed that a total of 254 nos steel alloy
disc cutters, with a diameter range of 250 - 300 mm, had been used
for the 21 drives, averaging about 0.5 set of cutters for each shallow
drive and 1.5 sets for each deep drive. For TBMs with a diameter of
600 mm to 1,800 mm, a set of disc cutters in the cutting wheel has
6 - 12 nos. Depending on the ground conditions encountered, particularly
the location, thickness and hardness of materials, some of the disc
cutters had to be replaced after the TBM had travelled a short length.
This situation occurred in some long, curved drives with highly variable
ground conditions and the replacement of disc cutters in a 4 m drive
length had been experienced in the worst case. Replacement of more
than 30 nos disc cutters during the course of works in three drives had
been recorded. It is noted that a tunnel through moderately to slightly
decomposed granitic (M/SDG) bedrock, with strengths of 320 - 350
MPa, achieved 4 m/day on average.
Tunnel Alignment and Level Accuracy
Almost all the tunnel alignments, using TBMs, can be controlled within
75 mm for line and 50 mm for level, as evidenced by DSDs three
contracts (Nos DC/95/05, DC/98/06 and DC/2000/11) which specifiedthe use of tunnelling and pipejacking techniques. In consideration of
the steering capacity of the TBMs available in the market, the angular
deflection of the jacking pipes, and the procedure of correcting the out-of-
tolerance, a tolerance of 50 mm for line and 35 mm for level, as stated
in the Tunnel Specification, may not be applicable to all Hong Kong soils
for pipejacking works, and hence should only be used with care.
Hand-dug Tunnels and Heading Method
The adoption of compressed air hand-dug tunnelling method would
face a problem associated with air loss in porous ground, giving rise to
the necessity of carrying out ground treatment to safeguard the tunnel
and the personnel working inside. The switch on of compressors and
generators around the clock to maintain the pressure in tunnel also
causes noise problem. Although high cost and relative low production
rate make this method only applicable to short drives, the removal of
artificial obstructions can be warranted. However, after a few drives had
been completed under DSD Contract No DC/95/05, and following the
rapid development of TBM technology which allows pipejacking drives in
curved alignment and detects obstruction ahead of TBM advancement,
this method has not been used in recent years due to the risk involved
and the reasons stated above.
Free air hand-dug tunnelling method in unstable ground would require
the entire length of the drive being grouted to maintain stability of the
road above, prior to commencement of work. Vertical grouting appears
to be infeasible due to presence of congested utilities and services inshallow depths. Horizontal grouting will cause drawdown of groundwater
during the drilling operation and will blow out the ground or encroach
into ductings of utilities if the pressure is not properly controlled. If the
grouting is ineffective, compressed air still has to be used to balance
groundwater pressure.
Heading construction is a method commonly adopted to construct
short pipelines crossing road junctions, utility crossings and entrance
to carpark, in shallow depth. The completed works have demonstrated
its effectiveness due to fast mobilisation of plant, simple setup on site,
and flexibility in construction method to suit the space available. Due to
limited space, the tunnel excavation is generally carried out by hand tools.
There have been cases that unexpected full-face rock was encountered,
taking a long time for removal and affecting progress. Although problems
associated with safety, environment and ground stability could be aconcern, there is a growing demand in recent years that this method is
used to overcome site constraints, particularly those unexpected during
construction, thus minimising delay to the works.
All the above methods have merits and demerits. Their choice should be
based on technical compatibility with regard to ground and groundwater
conditions revealed by site investigation works, and other constraints
rather than only on cost. Detailed analysis of the risk, together with
the contingency plan, has to be given prior to finalising the decision.
Inspection and maintenance of tunnelling shields, TBMs and their backup
plant and equipment by competent personnel at regular intervals would
minimise the downtime and maximise the production. Since each project
is different in nature, it is advisable to consult with specialists in the field
and TBM manufacturers in the planning stage to ensure success.
Conclusion
The application of tunnelling and pipejacking techniques for drainage
pipeline construction in Hong Kong has proved to be promising, generally
with less construction time and disturbance to the public, when compared
with the conventional open-trench method. Some of the problems could
have been avoided or minimised had suitable technique been selected
based on detailed site investigation results and site constraints, and proper
planning provided in advance. It is essential to include comprehensive
rather than general requirements in the contract to fully cover each
activity of works, which should be practical and specific with regard
to the situation encountered, with the contractors responsibility and
actions being clearly defined, so that arguments between the clients
consulting engineer and the contractor on problems, when occurring,could be minimised. The experience, training and attitude of the working
THE HKIE TRANSACTIONS Volume 16 Number 226
-
8/3/2019 16-27_735 - HKIE
12/12
and supervising personnel also have a significant effect on the success
of works.
Through the rapid development of TBM technology, long, curved
pipelines have been carried out in irregular, alternating soil and rock
composition at different depths, in recent years. Tunnelling through the
already completed permanent shafts has also been carried out, with
proper control of alignment, at a number of locations, to suit the project
programme. This also gives flexibility in selecting shaft locations to get
rid of utility and traffic constraints, as well as the disturbance problems
to shops, in most cases.
By the installation of a sonic soft-ground probing system in the TBM for
detecting hard materials in front of excavation and an electronic tool
monitoring system for detecting the wear limit of disc cutters, which is
the recent technology advancement in TBM, the risk associated with
TBM stoppage, as a result of obstruction, which is a common problem
in pipejacking works, could be minimised.
Disc cutters have also been developed to have longer life and higher
capacity in dealing with the ground conditions likely to be encountered.
Artificial obstructions still have to be removed manually should there
be access in the front bulkhead of the TBM. Otherwise, the TBM would
stop in ground necessitating rescue operation. This can be carried out
by means of either a rescue shaft or a rescue tunnel, which is a time-
consuming and costly operation, affecting the progress of works and
disturbing the public. Therefore, site investigation should be carried outas much as possible at suitable locations before the tunnelling method
and TBM is finalised.
Tunnelling and pipejacking techniques will continue to become popular for
installation of drainage pipelines in the urban areas of Hong Kong as they
could eliminate most of the problems encountered by the conventional
open-trench method and hence enable the works to be completed with
least inconvenience to the public and minimum diversion of existing
utilities and services, and traffic. These techniques are continually being
refined and developed. Improvements cover both larger and smaller
diameters, longer drives, better control of alignment, faster and curved
driving, different ground conditions, and the ability to work deeper under
water. However, there are also certain constraints, such as no room for
construction of jacking and receiving shafts at suitable locations due
to congestion of existing utilities and hence the lack of space for theirdiversion or close proximity to shops, insufficient clearance between
overlying utilities and the jacked pipeline using TBM for advancement,
and unexpected underground artificial obstructions, which limit the
application of such techniques.
Acknowledgements
The authors wish to express their gratitude to the Drainage Services
Department of the Government of the HKSAR, for permission of extracting
the materials from the respective projects, to publish this paper. Special
acknowledgement is given to Herrenknecht AG, and CSM BESSAC, for
their permission of extracting the photographs from technical brochures
in making Figs 16, 17, 20 and 21, and Fig 19 respectively.
References
1. Thomson, J., Pipejacking and Microtunnelling. pp3-6. Black A&P. UK (1993).2. McFeat-Smith, I., Tunnelling in Hong Kong in the 1990s. Tunnelling in Hong
Kong Seminar. Hong Kong (1993).3. Research and Development Section. Trenchless Pipe Installation and Renovation
Techniques. Review of Pipe Jacking/Microtunnelling Techniques for Constructionof Drainage Pipelines. Research & Development Report No RD 1005/2. Drainage
Services Department, Government of the HKSAR. Hong Kong (2002).
4. Mok, W.W.S., Mak, M.K.W. & Poon, F.H.T., Sewer Installation by Pipejacking inthe Urban Areas of Hong Kong. Part I Planning, Design, Construction andChallenges. The HKIE Transactions. Volume 14, No 1, pp27-28. The Hong Kong
Institution of Engineers. Hong Kong (2007).5. Mok, W.W.S., Mak, M.K.W. & Poon, F.H.T., Sewer Installation by Pipejacking
in the Urban Areas of Hong Kong. Part II Performance of Works, LessonsLearned and Improvements Proposed. The HKIE Transactions. Volume 14, No1, pp34-35. The Hong Kong Institution of Engineers. Hong Kong (2007).
6. The British Tunnelling Society and The Institution of Civil Engineers.Specification for Tunnelling. pp36, 86-88 & 106. Thomas Telford. UK (2000).
7. Mok, W.W.S., Pipejacked Tunnels What to do If a Tunnel Boring Machine isStuck in Ground?. Trenchless Conference in Macau. Macau (2007).
Wilson W S MOK BASc BA CEng R.P.E. (Civil &Geotechnical) CSci MICE MIMMM MHKIE
Email: [email protected]
Ir Mok graduated from the University of Windsor
in Canada and has over 30 years practical workingexperience in a wide variety of geotechnical and civilengineering projects in both design office and site. Heis particularly experienced in dealing with design andconstruction associated with geotechnical investigations
and instrumentation, deep excavations, tunnels, groundimprovements, settlement analysis, reclamation, siteformation, slope preventive measures, foundations
and sewerage works. Ir Mok has been involved in the design, supervision andadministration of more than 16 km long trunk drainage pipeline construction inthe urban areas of Hong Kong, using different types of trenchless techniques from
relining, TBMs to hand-dug tunnelling, and has carried out extensive research onsuch. He is the author/co-author of several technical papers in this aspect, and hispaper titled Sewer Installation by Pipejacking in the Urban Areas of Hong Kong,in two parts, has been awarded the HKIE Transactions Prize 2007. He has beenSenior Resident Engineer on a DSD contract, which involved the construction of
4 km long trunk sewers, using pipejacking techniques.
About the Authors
K W MAK BSc Dip HE Delft PCLL MA Arb CEngMIEAust MICE MHKIE MIHT
Email: [email protected]
Ir Mak is currently Chief Engineer with DrainageServices Department. In the past few years, he hasparticipated in numerous large-scale and prestigiousdrainage and sewerage projects, including the Wan
Chai East and North Point sewerage project, the firsttertiary sewage treatment plant at Ngong Ping, thelargest ultra-violet disinfection facility installation atSin Ho Wan sewage treatment plant, as well as the5 km long rainwater-intercepting tunnel in Tsuen Wan.
Previously, he spent six years in the then Works Bureau dealing with slope andwater policies. During his earlier years with the Drainage Services Department, IrMak received post-graduate training in river engineering in the Netherlands, and
had then worked in the Shenzhen River Regulation Project. He obtained a Masterof Arts in the area of dispute resolution and arbitration. On top of his engineeringengagements, Ir Mak acquires legal qualification and is a non-practising Barrister-
at-law of the High Court of the H KSAR. Ir Mak is the co-author of the paper titledSewer Installation by Pipejacking in the Urban Areas of Hong Kong, which hasbeen awarded the HKIE Transactions Prize 2007.
THE HKIE TRANSACTIONS Volume 16 Number 2 27