    Assistant Executive Engineer, Junior Engin

    Agricultural Engineering Department, Agricultural Engineering

    Krishnagiri. Krishnagiri.

    Hamlet of Jawalagiri Revenue village in Thally block, Denkanikottai Taluk, Krishnagiri

    district has been proposed at a cost of Rs.80,000/- and submitted for technical sancti

    The estimate for the construction of Farm ponds in S.F.No of Chennama

    As the guide lines new farm ponds of size 20m x 20m x 3m are to be establishe

    be lined by plastic sheets of 500 microns. How ever it has also been permitted to alte

    of the farm ponds based on the site conditions.

    A preliminary study of the project area indicated that the soil condition in Thall

    does not suit deep farm ponds of 3m depth. It was also felt that there will be no nee

    lining as the soil profile indicated, soft density rock strata below a depth of 1.50 mts.

    farmers were also not willing to go for plastic lining. Hence it has been decided to est

    ponds with a depth of 3 mts. And to decide the linear measurements as per the site c

    and catchment area. These issue were placed before the district committee and have

    As such the size and depth of the farm ponds have been decided as per the site

    and estimates had been prepared.

    fields. Based on the feasibility of the catchment area.

    DISTRICT

    JAWALAGIRI

    CHENNAMALAM

    THALLY

    DENKANIKOTTAI

    KRISHNAGIRI

    TALUK

    INTRODUCTION;

    The Govt. of Tmailnadu is implementing Integrated Development of pulses villa

    Areas in 5 Districts during the year 2011-2012. In the rain fed areas do not have assur

    irrigation, it has been proposed to establish Farm ponds in the project area in order t

    life saving irrigation for the pulse crops. The farm ponds will be established in the far

    S.F. No.

    VILLAGE

    HAMLET

    BLOCK

    NAME OF THE WORK

    NAME OF THE FARMER

    FORMATION OF FARMPOND

    REPORT TO ACCOMPANY THE ESTIMATEG.O.M.S.No.198,Agriculture(API)Dept.Dated:31.10.2011

  • 7/29/2019 15X30X1.60-40000

    2/17

  • 7/29/2019 15X30X1.60-40000

    3/17

    eer,

    epartment,

    on.

    lam

    and to

    r the size

    block

    of plastic

    The

    ablish farm

    ondition

    been approved.

    conditions

    ges in rain fed

    ed

    o provide

    er's

  • 7/29/2019 15X30X1.60-40000

    4/17

  • 7/29/2019 15X30X1.60-40000

    5/17

    DEPTH in

    metreQUANTITY in cum

    FORM POND 45.00 + 41.00 15.00 + 11.00

    2 2

    33.75 23.75

    x 35.32 x 10-6

    = mcft

    Asst.Executive Engineer Junior Engineer,

    Agrl Engineering Dept Agrl Engineering Dept

    Krishnagiri Krishnagiri

    1118.000

    0.039

    Capacity of the pond =

    DISTRICT:KRISHNAGIRI/ TALUK:DENKANIKOTTAI / BLOCK:THALLY

    VILLAGE:JAWALAGIRI ; SF.NO:

    NAME OF WORK : FARM POND under RKVY

    CAPACITY OF THE POND

    LENGTH in metre BREADTH in metreNO

    2.001 1118.000

  • 7/29/2019 15X30X1.60-40000

    6/17

  • 7/29/2019 15X30X1.60-40000

    7/17

    NAME OF WORK : FARM POND under RKVY

    VILLAGE:JAWALAGIRI ; SF.NO:

    1 Rough stone for revetm 1 Cu.M Nalroad 11 60.65 200.00 260.65

    2. The rates adopted are as per the current P.W.D. Schedule of rates for the year 2008-09

    Countersign

    Assistant Exeutive Engineer, Junior Engineer,Agricultural Engg, Department, Agricultural Engg, Department,

    Krishnagiri Krishnagiri

    LEAD STATEMENT

    Sl.No.Description of

    MaterialsQuantity

    Source of

    supply

    Lead Distance

    in K.m.

    Ordinary Hill

    DISTRICT:KRISHNAGIRI/ TALUK:DENKANIKOTTAI / BLOCK:THALLY

    1. The distance furnished are correct and minimum to the best of my Knowledge.

    Destinatio Lead charges

    Ordinary Hill

    Cost of

    Materials

    Total

    Cost

    Rs.

    Worksite

  • 7/29/2019 15X30X1.60-40000

    8/17

    NAME OF WORK : FARM POND under RKVY

    DISTRICT:KRISHNAGIRI/ TALUK:DENKANIKOTTAI / BLOCK:THALLY

    VILLAGE:JAWALAGIRI ; SF.NO:

    Rate Amount

    Rs Ps Rs Ps

    1 M3 SI-62 36.40 M3 36.40

    2 M3 SI-61 38.80 M3 38.80

    3 M3 SI-67 54.20 M3 54.20

    4 M3 SI-72 95.50 M3 95.50

    5 M3 SI-78 2.30 M3 2.30

    Extra for every additional 10M. Lead or part thereofover the initial lead. I Lead SI-76 4.60 M3 4.60

    II Lead 9.20 M3 9.20

    III Lead 13.80 M3 13.80

    IVI Lead 18.40 M3 18.40

    V Lead 23.00 M3 23.00

    7 Nos 3100.00 1No 3100.00

    Assistant Executive Engineer,

    Agricultural Engineering Department, Agricultural Engineering Department,

    Gobichettipalayam #REF!

    Junior Engineer,

    Gobichettipalayam

    Description of work

    For inlet & outlet 600mm dia RCC pipes 2.50m length

    including loading, unloading & transporting to worksite.(Rate

    local rate)

    HGS SS.20.A. Earth work excavating and depositing on bank

    with initial lead of 10 m & initial lift of 2m in Hard stiff clay,

    stiff black cotton, hard red earth, shales,murram, gravel,

    stoney earth and earth mixed with small size boulders

    SS.20.A(For Bund qty).

    SDR-(Not Requiring Blasting) Earth work excavating and

    depositing on bank with initial lead of 10 m & initial lift of 2m

    in Soft disintegrated rock, laterite, soft rock or kankar, not

    requiring blasting(FOR DEEPENING OF POND).

    MR-&-DMR (Not Requiring Blasting) Earth work excavating

    and depositing on bank with a initial lead of 10 m & initial lift

    of 2m in medium rock and dense medium rock not requiring

    blasting(FOR DEEPENING OF POND).

    Breaking clods, consolidating and sectioning

    6

    DATA SHEET

    Sl

    noQty Unit

    HGS SS.20.B. Earth work excavating and depositing on bank

    with initial lead of 10 m & initial lift of 2m in Hard stiff clay,

    stiff black cotton, hard red earth, shales,murram, gravel,

    stoney earth and earth mixed with small size boulders SS.20B

    M3

  • 7/29/2019 15X30X1.60-40000

    9/17

    Depth Quantity

    M

    1 6 71

    45.00 + 43.00 15.00 + 13.00 1.00

    2 2

    616.00

    2

    3.00 + 1.00

    2280.00

    3

    1 x 1 43.00 + 41.40 13.00 + 11.40

    2 2

    411.87

    4

    1 x 1 41.40 + 41.00 11.40 + 11.00 92.29

    2 2

    92.29

    5 Breaking clods, consolidating and sectioning 280.00

    6 - III Lead 504.16

    1 x 4 4.00

    8 Provision for TNCLW Fund 0.3% LS

    9 Provision for Unforeseen items LS

    Asst.Executive Engineer Junior Engineer

    Agrl Engineering Dept Agrl Engineering Dept

    Krishnagiri Krishnagiri

    7

    1x1For Bund qty

    Extra for every additional 10 metres lead or part thereof over the initial lead

    For inlet & outlet 600mm dia RCC pipes 2.50m

    length including loading, unloading &

    transporting to worksite.

    For DEEPENING OF POND0.20

    Total

    For DEEPENING OF POND 1x1

    HGS SS.20.B. Earth work excavating and depositing on bank with initial lead of 10 m & initial lift of 2m in Hard

    stiff clay, stiff black cotton, hard red earth, shales,murram, gravel, stoney earth and earth mixed with small size

    boulders SS.20B

    SDR-(Not Requiring Blasting) Earth work excavating and depositing on bank with initial lead of 10 m & initial lift

    of 2m in Soft disintegrated rock, laterite, soft rock or kankar, not requiring blasting.

    MR-&-DMR (Not Requiring Blasting) Earth work excavating and depositing on bank with a initial lead of 10 m

    & initial lift of 2m in medium rock and dense medium rock not requiring blasting.

    For DEEPENING OF POND

    Total

    Total

    0.80

    140 1.00 280.00

    411.87

    Total

    HGS SS.20.A. Earth work excavating and depositing on bank with initial lead of 10 m & initial lift of 2m in Hard

    stiff clay, stiff black cotton, hard red earth, shales,murram, gravel, stoney earth and earth mixed with small size

    boulders SS.20.A.

    616.00

    2 3 5

    DETAILED ESTIMATE FOR FARM POND

    Sl

    no Description of work

    No Breadth

    M M

    Length

    NAME OF WORK : FARM POND under RKVY

    DISTRICT:KRISHNAGIRI/ TALUK:DENKANIKOTTAI / BLOCK:THALLY

    VILLAGE:JAWALAGIRI ; SF.NO:

  • 7/29/2019 15X30X1.60-40000

    10/17

  • 7/29/2019 15X30X1.60-40000

    11/17

    M3

    M3

    M3

    M3

    M3

    M3

    M3

    Nos

    M3

    M3

    M3

  • 7/29/2019 15X30X1.60-40000

    12/17

  • 7/29/2019 15X30X1.60-40000

    13/17

    NAME OF WORK : FARM POND under RKVY

    DISTRICT:KRISHNAGIRI/ TALUK:DENKANIKOTTAI / BLOCK:THALLY

    VILLAGE:JAWALAGIRI ; SF.NO:

    Rate Amount

    Rs Ps Rs Ps

    1 616.00 M3 36.40 M3 22422.40

    2 280.00 M3 38.80 M3 10864.00

    3 411.87 M3 54.20 M3 22323.35

    4 92.29 M3 95.50 M3 8813.70

    5 280.00 M3 2.30 M3 644.00

    Extra for every additional 10M. Lead or part thereof

    220.00 M3

    over the initial lead as per Sl.No 78 II Lead 9.20 M3 2024.00

    7 4.00 Nos 3100.00 1No 12400.00

    8 Provision for TNCLW Fund 0.3% 240.00

    9 LS Provision for Unforeseen items LS 268.55

    80000.00

    (Rupees Eighty thousand only) weir 7075.50

    Assistant Executive Engineer,

    Agricultural Engineering Department, Agricultural Engineering Department,

    Krishnagiri 87075.50

    6

    Breaking clods, consolidating and sectioning

    For inlet & outlet 600mm dia RCC pipes 2.50m length

    including loading, unloading & transporting to worksite.

    ABSTRACT ESTIMATE FOR FARM POND

    Sl

    noDescription of work

    HGS SS.20.B. Earth work excavating and depositing on bank

    with initial lead of 10 m & initial lift of 2m in Hard stiff clay,

    stiff black cotton, hard red earth, shales,murram, gravel,

    stoney earth and earth mixed with small size boulders SS.20B

    Krishnagiri

    Qty Unit

    Total

    Junior Engineer,

    SDR-(Not Requiring Blasting) Earth work excavating and

    depositing on bank with initial lead of 10 m & initial lift of 2m

    in Soft disintegrated rock, laterite, soft rock or kankar, not

    requiring blasting(FOR DEEPENING OF POND).

    MR-&-DMR (Not Requiring Blasting) Earth work excavating

    and depositing on bank with a initial lead of 10 m & initial lift

    of 2m in medium rock and dense medium rock not requiring

    blasting(FOR DEEPENING OF POND).

    HGS SS.20.A. Earth work excavating and depositing on bank

    with initial lead of 10 m & initial lift of 2m in Hard stiff clay,

    stiff black cotton, hard red earth, shales,murram, gravel,

    stoney earth and earth mixed with small size boulders

    SS.20.A(For Bund qty).

  • 7/29/2019 15X30X1.60-40000

    14/17

  • 7/29/2019 15X30X1.60-40000

    15/17

    3.00 1.00 2.00 2.00 1.00 3.00

    1.00 1.00

    GL 1.00 GL

    3.00 1.00 HGS 3.00

    2.00 0.80 SDR GL

    0.20 MDR 1.0

    1.0

    3.0

    0

    1.0

    1.0

    CS 2

    .0

    41.00 HGS

    SDR

    MDR

    LS LS 1.0

    0

    1.0

    0

    0.8

    0

    0.2

    0

    11.00

    41.00

    CS 2

    .0

    45.00 1.0

    1.0

    1.0

    1.0

    GL

    3.0

    0

    PLAN

    15.00 15.00

    LONGITUDINAL SECTION

    45.00

    11.0

    0

    15.0

    0

    2.0

    0

    SCALE:NO

    PLAN SHOWING THE PROPOSED FARM POND

    NAME OF WORK : FARM POND under RKVY

    DISTRICT:KRISHNAGIRI/ TALUK:DENKANIKOTTAI / BLOCK:THALLY

    VILLAGE:JAWALAGIRI ; SF.NO:

    41.00

    45.00

  • 7/29/2019 15X30X1.60-40000

    16/17

    Sl. No. Details Rs Per

    1 Mason (for stone work) Iclass 291.00 day

    2 Mason (for stone work) IIclass 261.00 day

    3 Mazdoor Category-I 183.00 day

    4 Mazdoor Category-II 165.00 day

    5 Stone cutter I Class 224.00 day

    Rates for Works (2012-2013)

    Sl.No Description of works

    1 Clearing heavy jungle SI (A) 1 2.70 /sqm

    2 Clearing light jungle SI (A) 2 2.05 /sqm

    3 Clearing scrub jungle SI (A) 3 1.90 /sqm

    4 Earth work excavating and Depositing on Banks

    with initial lead of 10 m and lift of 2 m ina Sand silt or other loose soil, wet sand or silt not under

    water, light black cotton soil, sandy loam and ordinary

    soil including excavated earth as per S S 20 A. SI (D) 49 26.75 /cum

    b Sand silt or other loose soil, wet sand or silt not under

    water, light black cotton soil, sandy loam and ordinary

    soil including excavated earth as per S S 20 B. SI (D) 50 24.35 /cum

    c Hard stiff clay,stiff black cotton, hard red earth,shales,

    murram,gravel,stoney earth and earth mixed with small

    size boulders asper SS 20 A. SI (D) 61 38.80 /cum

    d Hard stiff clay,stiff black cotton, hard red earth,shales,

    murram,gravel,stoney earth and earth mixed with small

    size boulders asper S S 20 B. SI (D) 62 36.40 /cume Soft disintegrated rock, laterite, soft rock or kankar

    not requiring blasting SI (D) 67 54.20 /cum

    f Medium rock and dense medium rock not requiring

    blasting SI (D) 72 95.50 /cum

    g MR and DMR requiring blasting SI (C) 40A 132.30 /cum

    5 Extra for every additional 10 metre lead or

    part thereof over the initial lead SI (D) 76 4.60 /cum

    6 Extra for every additional 1 metre lift or

    part thereof over the initial lift SI (D) 77 3.70 /cum

    7 Add to relevant TNDSS 20A rates for new tank bunds or

    canal bunds or closing breaches or new road formation

    or for works requiring extra watering and consolidation

    (a) By Hand Roller Sl (D) 79 A 7.65 /cum

    DATA SHEETName of scheme: Artificial recharge to ground water