1.5 mg elevated water storage tank - poggemeyerof the existing 500,000 gallon elevated tank with a...

4
Reference Tom Stalter, P.E., Manager of Engineering Northwestern Water & Sewer District 12560 Middleton Pike Bowing Green, Ohio 43402 419.354.9090 ext. 174 [email protected] PDG was hired by Northwestern Water and Sewer District to provided professional engineering and bidding services for the design and construction of the Colony Area Inflow & Infiltration Reduction Improvements in Rossford, Ohio. This project consisted of pipe bursting of approximately 9,000 LF of 8” and 10” Vitrified Clay Sanitary Sewers with new 8” and 10” Certa- Flo Green Line PVC pipe. Sewer service laterals were also burst and replaced to the R/W. Pipe Bursting was specified for the replacement of this aging sewer system for several reasons. Due to the existing pipe being in such poor condition lining was ruled out. This system is also located within a historical neighborhood in the City of Rossford. The Colony sub-division has many mature trees, landscaped islands and a variety of architectural monuments which are locally sensitive. Pipe bursting allowed the re-construction of the sewers to be significantly less of a disturbance to the neighborhood then would have been experienced in a traditional open-cut method. It also proved to be more cost effective when evaluated against open cut-replacement. For these reasons, pipe bursting was chosen for the replacement of the sewers and has been well received by residents. This project was funded wholly through EPA’s WPCLF. COLONY AREA I/I REDUCTION IMPROVEMENTS - PIPE BURSTING Location Rossford, Ohio Services Provided Engineering and Construction Administration Cost $1,275,000 Engineers Estimate $1,213,753 Bid Amount Funding $1,213,753.50 WPCLF Schedule Professional Services 2013 Construction Services 2014 Project Team Neal R. Materni, Project Manager Project Relevance Sanitary Sewer Pipe Bursting

Upload: others

Post on 21-Jan-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 1.5 MG ELEVATED WATER STORAGE TANK - Poggemeyerof the existing 500,000 gallon elevated tank with a new 1.5 million gallon tank located in the . City’s north side industrial and commercial

ReferenceTom Stalter, P.E., Manager of Engineering Northwestern Water & Sewer District 12560 Middleton Pike Bowing Green, Ohio 43402 419.354.9090 ext. [email protected]

PDG was hired by Northwestern Water and Sewer District to provided professional engineering and bidding services for the design and construction of the Colony Area Inflow & Infiltration Reduction Improvements in Rossford, Ohio. This project consisted of pipe bursting of approximately 9,000 LF of 8” and 10” Vitrified Clay Sanitary Sewers with new 8” and 10” Certa-Flo Green Line PVC pipe. Sewer service laterals were also burst and replaced to the R/W. Pipe Bursting was specified for the replacement of this aging sewer system for several reasons. Due to the existing pipe being in such poor condition lining was ruled out. This system is also located within a historical neighborhood in the City of Rossford. The Colony sub-division has many mature trees, landscaped islands and a variety of architectural monuments which are locally sensitive. Pipe bursting allowed the re-construction of the sewers to be significantly less of a disturbance to the neighborhood then would have been experienced in a traditional open-cut method. It also proved to be more cost effective when evaluated against open cut-replacement. For these reasons, pipe bursting was chosen for the replacement of the sewers and has been well received by residents. This project was funded wholly through EPA’s WPCLF.

COLONY AREA I/I REDUCTION IMPROVEMENTS - PIPE BURSTING

Location ∙ Rossford, Ohio

Services Provided ∙ Engineering and Construction Administration

Cost ∙ $1,275,000 Engineers Estimate ∙ $1,213,753 Bid Amount

Funding ∙ $1,213,753.50 WPCLF

Schedule ∙ Professional Services 2013

∙ Construction Services 2014

Project Team ∙ Neal R. Materni, Project Manager

Project Relevance ∙Sanitary Sewer

∙Pipe Bursting

Page 2: 1.5 MG ELEVATED WATER STORAGE TANK - Poggemeyerof the existing 500,000 gallon elevated tank with a new 1.5 million gallon tank located in the . City’s north side industrial and commercial

ReferenceMr. Brian O’Connell Director of Utilities, City of Bowling Green 304 North Church Street Bowling Green, Ohio 43402 419.354.6246

The final phase of the City of Bowling Green Master Plan Improvements was the replacement of the existing 500,000 gallon elevated tank with a new 1.5 million gallon tank located in the City’s north side industrial and commercial corridor. This area was identified as the optimal location for a new tank due to it’s proximity to the 20” and 36” transmission mains that are the main feeds from the City water treatment plant. As a supplement to the original master plan, PDG performed water age analysis and the effects of the recommended improvements to optimize the system and enable the City to maintain current and future compliance with the Ohio EPA disinfection byproducts rules and regulations. This analysis will help the City maintain a healthy water supply to their customers.

Project Relevance ∙Composite Concrete/Steel

∙Municipal Water Storage

∙Residential and Commercial Units

∙No Service Interruptions

more...

1.5 MG ELEVATED WATER STORAGE TANK

Location ∙ Bowling Green, Ohio

Services Provided ∙ Environmental Engineering ∙ Grant Writing

Cost ∙ Engineers Estimate–$3,400,000 ∙ Project Cost–$3,255,000 New Construction ∙ Project Cost- $ 88,900 Demolition

Project Funding ∙ $325,000 OPWC Grant

Size ∙ 1.5 MG Storage

Schedule ∙ Professional Services 2012-2015

∙ Construction: 2013-Fall 2014

Project Team ∙ Jack A. Jones, P..E., Principal-in-Charge ∙ Michael Atherine, P.E., Project Manager ∙ Thomas Borck, P.E. Project Engineer ∙ Tank Industry Consultants (TIC)

Page 3: 1.5 MG ELEVATED WATER STORAGE TANK - Poggemeyerof the existing 500,000 gallon elevated tank with a new 1.5 million gallon tank located in the . City’s north side industrial and commercial

Quality control was accomplished through detailed and regular review meeting with the City Engineer, operators, Utility Director, and the Board of Public Utilities, resulting in few field change orders. Careful coordination with the County water district and other utility companies made the final project successful and under the original estimated project budget.

PDG teamed with TIC and provided the following:

∙Tank Style Analysis Review And Recommendation

∙Preliminary Engineering

∙Distribution System Study

∙Design of Water Transmission Main Lines to connect the new tank.

∙Preliminary Estimate of Probable Construction Cost

∙Preparation of Specifications and Drawings

∙Detailed plans, technical specifications, and contract documents

∙Coating System Design

∙Scada System Design

∙Contract Administration

∙Construction Observation

∙Preparation of plans and specifications for existing tank demolition

1.5 MG Elevated Water Storage Tank

Page 4: 1.5 MG ELEVATED WATER STORAGE TANK - Poggemeyerof the existing 500,000 gallon elevated tank with a new 1.5 million gallon tank located in the . City’s north side industrial and commercial

ReferenceDave Westbrook Upper Sandusky Water Department Supervisor 119 North 7th Street Upper Sandusky, Ohio 43351 419.294.3862

PDG assisted the City of Upper Sandusky with engineering and project financing for replacement of water lines in the NE quadrant of the City. The project was divided into 3 sections.

Section A was the replacement of water lines on Church, Front, and Bigelow Streets. The project was approximately 3062 LF of 12” water line; 4369 LF of 8” water line and 330 LF of 6” water line with vales and hydrants. The project also included street resurfacing and curb replacement.

Section B was water line replacement on Third, Fourth, and Fifth Streets; and Guthrie Streets. The project included 9065 LF of 8” water line, valves, and hydrants, street resurfacing, curb and sidewalk replacement.

Section C was 2658 LF of water line replacement on Shafer, Second, Shafer, Finley and Parkview Streets. The project also included valves and hydrants and some street resurfacing.

Location ∙ Upper Sandusky, Ohio

Services Provided ∙ Environmental Engineering, Inspection and Construction Administration

Cost ∙ Section A = $740,100–funded 100% by OPWC and DEFA ∙ Section B = $932,010–funded 100% by OPWC & DEFA low-interest and 0% loans ∙ Section C = $1,169,615–funded by a 1.71% DEFA loan

Size ∙ Various lengths of 6”, 8” and 12” waterline

Schedule ∙ Professional Services: 2012 ∙ Construction: 2013

PDG Project Team ∙ Neal Materni, Project Manager

Project Relevance ∙City Waterline Replacement

∙Residential and Commercial Units

∙No Service Interruptions

∙ Temporary Concrete Pavement

UPPER SANDUSKY NE QUADRANT WATERLINE Projects A, B & C