15 analysis of container berth
TRANSCRIPT
-
8/3/2019 15 Analysis of Container Berth
1/26
LECTURE - 15
ANALYSIS OF
CONTAINER BERTH
-
8/3/2019 15 Analysis of Container Berth
2/26
CONTAINER BERTH
A berth for loading an unloading of containerized
cargo to and from the ship
A berth generally with a large stacking yard for
handling containerized cargo, which may also be used
as a general cargo berth.
Department of Ocean Engineering, IIT Madras
-
8/3/2019 15 Analysis of Container Berth
3/26
ANALYSIS OF CONTAINER BERTH(Example)
Considered as a total length of berth 820 m divided
into 13 blockseach of 75 m.
Width of the container berth is 40 m span of
container crane is 30 m.
Two container cranes are considered for the analysis.
Department of Ocean Engineering, IIT Madras
-
8/3/2019 15 Analysis of Container Berth
4/26
Each container has 4 legs and each legs has 8 wheels
c/c distance between two legs is 15 m
c/c distance
between two wheel is 1.5 m.
Vessel size upto104000 DWT
Levels:
Top Level : +4.8 m
Dredge Level : -16.0 m
Founding Level : -36 m
Department of Ocean Engineering, IIT Madras
-
8/3/2019 15 Analysis of Container Berth
5/26
Pile Diameter 1200 & 1100 mm; spacing laterally
7.62 m and longitudinally7.5 m c/c
Thickness of slab and wearing coat - 0.4 m and 0.05 m.
Crane beams1m x 2.5 m
Main beams
1m x 2 m
Department of Ocean Engineering, IIT Madras
-
8/3/2019 15 Analysis of Container Berth
6/26
TIDAL DATA
Highest water level - +1.65m
Mean High water Springs - +1.158m
Mean High Water Neaps - +0.823m
Mean Low Water Springs - +0.122m
Mean Low Water Neaps - +0.396m
Indian Springs High Water Level - +1.524m
Indian Springs Low Water Level - +0.00m
Mea n High Water - Assumed to correspond to MHWSMean Low Water - Assumed to correspond to MLWS
Lowest Low Water - Assumed to correspond to ISLW
Department of Ocean Engineering, IIT Madras
-
8/3/2019 15 Analysis of Container Berth
7/26
WIND
The crane wheel loads and bollards loads given in the
design are inclusive of wind effect.
WAVES
Waves are of 1m height and 10 second period.
CURRENTS
The maximum design current shall be 0.5m/s along the
quay structure. Allowance for 100mm marine growth on all
surfaces shall be made.
Department of Ocean Engineering, IIT Madras
-
8/3/2019 15 Analysis of Container Berth
8/26
The Employer has provided soil data on the basis of specificdetailed soil investigation works carried in the proposed area of
the berth construction including laboratory testing. FIXITY LEVEL OF PILES:
The fixity level of pile considered in analysis has been
calculated as per IS 2911.
DESIGN LIFEDesign life to be 50 years.
SITE PARAMETERS
Department of Ocean Engineering, IIT Madras
-
8/3/2019 15 Analysis of Container Berth
9/26
VESSEL DATA
Size of vessel : 104,000DWT
Displacement tonnage : 145,600
Length overall : 342m
Beam : 42.8m
Depth : 27.7m
Draft of vessel : 14.5m
Berthing Speed : 0.1m/s
Berthing angle : 10 degrees
BOLLARD CAPACITYBollard of 150 tonnes capacity shall be provided at 30
meters to suit maximum Size Container Vessel.
Department of Ocean Engineering, IIT Madras
-
8/3/2019 15 Analysis of Container Berth
10/26
FENDERS
Fender of suitable design shall be provided for container
vessel of 104 000 DWT. UNIT WEIGHT
Reinforced concrete : 25 kN/m3
Plain concrete : 24 kN/m3
TEMPERATURE EFFECTCoefficient of thermal expansion for concrete is taken to
be 9 x 10-6 per C according to Clause 6.2.6 of IS 456:2000.
ELASTIC PROPERTIES
For elastic analysis of structures, the instantaneous or
short term elastic modulus of concrete (Ec) shall be
determined in accordance with Clause 6.2.3.1. of IS 456:2000.
Department of Ocean Engineering, IIT Madras
-
8/3/2019 15 Analysis of Container Berth
11/26
LOADS
DEAD LOADS
Density of reinforced concrete = 25 kN/m3
Density of plain concrete = 24 kN/m3
Density of steel = 78.5 kN/m3
Super Imposed Dead Loads
Superimposed dead load on main quay deck = 2.5kN/m2to allow for surfacing. Loads of Fenders & Bollards etc. areevaluated separately.
LIVE LOADS
Live load taken is 5 T/m2 within the crane rail afterallowing clearance of 1.5 m from crane and 1 T/m2 oncantilever slab between cope line and seaside crane rail afterallowing space for bollards, coping and slots for cabling forcontainer crane.
Department of Ocean Engineering, IIT Madras
-
8/3/2019 15 Analysis of Container Berth
12/26
VEHICLE LOADS ON DECK
IRC-Class AA-70 R Loading
Trailer Truck Loading
In accordance with the impact factor to be applied on IRC
loading and trailer truck loading will be one-third of the
impact factor specified in IRC 6.
WAVE LOADS:
Wave forces are calculated in accordance with IS 4651
Part 3. The charts given in the US Ar5my Shore protection
Manual are used.
Drag coefficient CD = 0.7
Inertia coefficient Cm = 2.0
100 mm marine growth is considered on piles.
Department of Ocean Engineering, IIT Madras
-
8/3/2019 15 Analysis of Container Berth
13/26
CURRENT LOADS:
Maximum design current shall be 0.5 m along the quay
structure. Allowance for 100 mm marine growth is kept.
Forces due to current are calculated using Morisons
equation, with CD = 0.7
BERTHING LOADS
Berthing energy shall be calculated in accordance with IS
4651 Part 3. Accident loading (with an additional 50%
berthing energy) is considered. A safety factor of 1.4 shall be
considered
MOORING LOADS
A mooring pattern, representing the head and stem lines
from two moored vessels, shall be used in the calculations.
Department of Ocean Engineering, IIT Madras
-
8/3/2019 15 Analysis of Container Berth
14/26
TEMPERATURE AND SHRINKAGE EFFECTS
Temperature load effects should be calculated assuming acoefficient of expansion of 9 x 10-6 per 0C for the concrete.
Temperature loads shall be assessed in accordance with IS
456:2000.
SEISMIC LOADS
For earth retaining structures the assessment of seismic
effect shall be carried out in accordance with IS 1893 (2002)
as specified.
Department of Ocean Engineering, IIT Madras
-
8/3/2019 15 Analysis of Container Berth
15/26
METHODOLOGY
The analysis has been carried out using conventional
STAAD Pro software. The structure is considered as a
space frame and different loads are applied as per IS 875.
the critical load case has been considered for design has
been done using Limit State Method of Collapse and
Method of Serviceability condition.
Department of Ocean Engineering, IIT Madras
-
8/3/2019 15 Analysis of Container Berth
16/26
CLEAR COVER TO BE PROVIDED
Following clear cover to be provided for main
reinforcement for various structural members.
Pile : 75 mm
Pile muff : 75mm
Beam : 50 mmSlab : 50 mm
ANALYSIS
A 3D dimensional analysis has been carried out using
STAAD Pro package.
Department of Ocean Engineering, IIT Madras
-
8/3/2019 15 Analysis of Container Berth
17/26
LOAD COMBINATIONS
The design has been carried out using limit state method.
LIMIT STATE OF SERVICEABILITY
1.0DL + 1.0 LL +1.0 CL4
0.9DL + 0.9LL + 1.0SF-T
LIMIT STATE OF COLLAPSABILITY
1.5DL + 1.5LL + 1.5BF
1.5DL + 1.5LL + 1.5MF-1
1.5DL + 1.5LL + 1.5MF-2
1.2DL + 1.2LL
1.2DL + 1.2LL +1.5SF-T
1.2DL + 1.2LL + 1.5SF-L
0.9DL + 0.9LL +1.5SF-T
Department of Ocean Engineering, IIT Madras
-
8/3/2019 15 Analysis of Container Berth
18/26
0.9DL + 0.9LL + 1.5SF-L
1.5DL + 1.5LL + 1.5CL-1(ACROSS)
1.5DL + 1.5LL + 1.5CL-1 (ALONG)
1.5DL + 1.5LL + 1.5CL-2 (ACROSS)
1.5DL + 1.5LL + 1.5CL-2 (ALONG)
1.5DL + 1.5LL + 1.5CL3
1.5DL + 1.5LL + 1.5CL4
Where,
DL = Dead load
LL = Live load
BF = Berthing force
MF = Mooring force
SF = Seismic Force
CL = Crane load
Department of Ocean Engineering, IIT Madras
-
8/3/2019 15 Analysis of Container Berth
19/26
STAAD DISCRETIZATION DIAGRAM
L
Dead Loads
-
8/3/2019 15 Analysis of Container Berth
20/26
Lo
Live Loads
-
8/3/2019 15 Analysis of Container Berth
21/26
Crane Load Position - I
-
8/3/2019 15 Analysis of Container Berth
22/26
Crane Load Position - II
-
8/3/2019 15 Analysis of Container Berth
23/26
Berthing Force
-
8/3/2019 15 Analysis of Container Berth
24/26
Mooring Force
-
8/3/2019 15 Analysis of Container Berth
25/26
Wave Load
-
8/3/2019 15 Analysis of Container Berth
26/26
Loa
Current Load