PARTICULAR SPECIFICATIONS AMENDMENT LOG 6/29/2014
A P1 - THE PROJECT AND PERMANENT WORKS
1 ACCREDITED TRAINING
FOR SKILLED TRADES
P1.7 The training should be subject to availability of Training / Assessment given by
CIDB. There is no training for skilled trades provided by CIDB at the moment.
Goh Chee Young
B P6 - PRELIMINARY WORKS
1
SAMPLES, MOCK-UPS,
PROTOTYPES, AND
TRIALS
Architectural, Builder's
Works and Finishes
P6.6 Preliminary work consist of site set up and preparation for construction work to
commence. Clause P6.6 is related to Samples, Mock-ups, Prototypes and Trials for
Achitectural, Builder's Works and Finishes, it should be under architectural works.
Goh Chee Young
C P8 - CONSTRUCTION CONSTRAINTS
1 GENERAL
CONSTRUCTION
CONSTRAINTS
UTILITIES AND SERVICES
P8.1.3 "……shall comply with, TNB's requirements for working in
close proximity to overhead power lines,……"
Change to:
"……shall comply with, TNB's requirements for working in close
proximity to overhead and underground power lines,……"
To include underground power line in
the Specification. This is the current
practice in SBK Line.
Seelan
2 GENERAL
CONSTRUCTION
CONSTRAINTS
UTILITIES AND SERVICES
P8.1.3 The requirement for working beneath live overhead cables should be included. For
example, current SBK Line requirement of TNB for working under live overhead
cables are to engage 'Competent Engineer' and issuance of 'Permit of Work
Certification for Contractor'.
Goh Chee Young
D P15 - CONDITION SURVEY OF EXISTING BUILDING AND STRUCTURES (EBS), PROTECTION MEASURES AND INSTRUMENTATION AND MONITORING
1 INSTRUMENTATION AND
MONITORING
P15.4.2 All instrumentation shall be installed progressively following
the work sequence or programme of the Works Package
Contractor at least sixty (60) days prior to any construction
activity within the zone of influence of the Works, or as
otherwise approved by the Owner.
Change to:
All instrumentation shall be installed progressively following the
work sequence or programme of the Works Package Contractor
at least sixty (60) thirty (30) days prior to any construction
activity within the zone of influence of the Works, or as
otherwise approved by the Owner.
To be consistent with clause P15.4.3
which states "The Works Package
Contractor shall take the baseline
readings at least one (1) month prior to
construction activities ……"
Seelan
E P17 - PUBLIC RELATIONS
1 GENERAL P17.1.3 The Owner shall manage the dissemination of all project
information to the public and media. The Works Package
Contractor shall not disclose any information regarding
the Works to the public or media without prior approval
from the Owner.
Change to:
The Owner shall manage the dissemination of all project
information to the public and media. The Works Package
Contractor shall not disclose any information regarding the
Works to the public or media without prior approval from the
Owner.
This is not practical and has not been
practiced in current SBK Line.
2 CEREMONIES AND MEDIA
EVENTS
P17.2.14 (h) Provision of all safety arrangements, security support,
personnel to escort visitors and safety equipment, including
new safety helmets. The Works Package Contractor shall be
notified of the number of safety helmets required and provide
the safety helmets including any logos, colouring and
nameplates as may be designated by the Owner. The Works
Package Contractor shall make safety helmets available to the
Owner upon completion of the ceremonies as souvenirs for
the VIPs and guests.
Change to:
Provision of all safety arrangements, security support, personnel
to escort visitors and safety equipment, including new safety
helmets. The Works Package Contractor shall be notified of the
number of safety helmets required and provide the safety
helmets including any logos, colouring and nameplates as may
be designated by the Owner. The Works Package Contractor
shall make safety helmets available to the Owner upon
completion of the ceremonies as souvenirs for the VIPs and
guests.
This is not practical and has not been
practiced in current SBK Line.
Comments by
Dr Bhavani
RemarksNo Item Existing ClausesClausesReason (s)
(if any)Proposed Revision
1 of 5
PARTICULAR SPECIFICATIONS AMENDMENT LOG 6/29/2014
Comments byRemarksNo Item Existing ClausesClausesReason (s)
(if any)Proposed Revision
F APPENDIX H - INTERFACE SPECIFICATIONS
1 Appendix H4 to H12 For better design coordination. Independent cable containment to be provided for each of the systems Ken Lai
2 Appendix H8 To enhance interface requirements. AFC equipment quantity should be put into the corresponding Interface
Specification with AFC Package as a requirement.
Ken Lai
3 Appendix H9 To enhance interface requirements. Typical EAC door schedule needs to be included in the interface specification with
EAC Package.
Ken Lai
4 Appendix H10 To enhance interface requirements. The demarcation of interface between FSCADA and TVS needs to be clearly
identified.
Ken Lai
5 Appendix H10 &
Appendix H11
To enhance interface requirements. Open protocol requirement needs to be specified in the corresponding interface
specifications for high level interface
Ken Lai
6 Appendix H10 &
Appendix H11
To enhance interface requirements. Typical I/O Schedule needs to be included in the interface specifications with BMS
and FSCADA.
Ken Lai
7 To enhance interface specifications. Suggest to add the requirement of interface with IT and Commercial
Communication need to be identified for pre-tender stage and to be included in
the corresponding Interface Specifications.
Ken Lai
8 Enhance interface management process
with the DS/DC.
Lift, Escalator and Signage should be system-wide DC/DS under PDP/MRTC instead
of under Civil Contractor.
Ken Lai
G APPENDIX J - SPECIFICATION FOR DILAPIDATION SURVEY
1 SCOPE OF WORKS
GENERAL
1.1.6 - Add:
Survey of structures/buildings under construction within the
extent of influence shall be agreed on a case by case basis jointly
by the Works Package Contractor and the Owner depending on
the sensitivity and degree of completion.
There were some problems surveying
the buildings under construction within
the extent of influence eg. Sunway
Velocity (under construction) where
Dilap Survey could not be carried out
because under construction but remain
listed as an item for Dilap completion.
Tan Joon Gei
2 SPECIFICATIONS
TARGET STRUCTURES
2.1.1 (g) Heritage buildings/structures; Change to:
Heritage buildings/structures, including important artwork like
mural, statues etc.;
Museum mural assessment was missed
out during tender stage.
Tan Joon Gei
3 SPECIFICATIONS
DETAILED TECHNICAL
REQUIREMENTS
2.3.1 (b) Record the GPS coordinates of existing structures. For
structures with footprint larger than 10m on plan, record
additional GPS coordinates of start and end points and/or
corners.
Change to:
For Structural/Building not identified in the survey layout plan
provided, record the GPS coordinates of existing structures. For
structures with footprint larger than 10m on plan, record
additional GPS coordinates of start and end points and/or
corners.
Conventional coordinates in survey
layout plan is more accurate than GPS
coordinate. Hence GPS coordinate is not
used.
Tan Joon Gei
4 SPECIFICATIONS
DETAILED TECHNICAL
REQUIREMENTS
2.3.1 (o) One (1) copy of the report shall be provided to the owner
upon receipt of their written request.
Change to:
One (1) copy of the report shall be provided to the owner upon
receipt of their written request and with agreement with the
Owner.
It is current practice, all Dilap Report
belongs to MRTC and we cannot release
the report to owners without their
permission even though the owner
request.
Tan Joon Gei
5 SPECIFICATIONS
DETAILED TECHNICAL
REQUIREMENTS
2.3.1 (p) The Works Package Contractor shall maintain working records
of the survey for at least six (6) years.
Change to:
The Works Package Contractor shall maintain working records
of the survey for at least the same period as the Contractor
Defect liability period or six (6) years whichever is longer.
The keeping of the Dilap Survey record
must be back to back with the
Contractor Defect Liability period as it is
a legal record to be consulted to in
event of argument for defect liability.
Tan Joon Gei
6 POST-CONSTRUCTION
CONDITION SURVEY
2.4.3 The Works Package Contractor shall provide a proposal to
undertaken the post-construction condition survey to be
carried out within six (6) years of the date of pre-construction
survey. The cost of the works to be reimbursed from
Provisional Sums.
Change to:
The Works Package Contractor shall provide a proposal to
undertaken the post-construction condition survey to be carried
out within one (1) six (6) years of the date of pre-construction
surveyCertification of Practical Completion. The cost of the
works to be reimbursed from Provisional Sums.
6 years can be quite late as some of the
Dilap for the Tunnel is still in progress
now, ie 2014. 6 years after this will be
in 2020.
Tan Joon Gei
2 of 5
PARTICULAR SPECIFICATIONS AMENDMENT LOG 6/29/2014
Comments byRemarksNo Item Existing ClausesClausesReason (s)
(if any)Proposed Revision
7 DILAPIDATION SURVEY
FORM
PHOTOGRAPHIC
RECORDS
- Note: State the location clearly and identify defects (such as
cracks, signs of displacement or deformation, signs of
dampness, corrosion of steel reinforcement and existing
associated repair works etc.) on high resolution photos.
Change to:
Note: State the location clearly and identify defects (such as
cracks, signs of displacement or deformation, signs of
dampness, corrosion of steel reinforcement and existing
associated repair works etc.) on high resolution photos. High
resolution photos (>6 Megapixel) must be taken in well lighted
condition showing any discolouration. Photos of defects must be
taken with a scale or ruler for identifiable scaling.
Dark grainy photos and photos of cracks
without proper scales are a common
problem and subject to frequent
comments. To prevent and reduce this
we need to spelt it out clearly in the
specification.
Tan Joon Gei
H APPENDIX K - INSTRUMENTATION AND MONITORING
1 No comments Seelan
I APPENDIX N - DESIGN APPROVAL PROCESS
1 General 1.16 - Add:
All the design packages shall go through the design approval
processes as stipulated in Annex 6 Flow Chart 1, 2, and 3 from
Preliminary, Pre-Final to Final Stage. Finalisation of design
package colour code is subject to the Owner's approval.
It is the current practice in SBK Line. Ravi
2 FINAL DESIGN 4.7 For Code 1 and Code 2 approved drawings/documents the
Works Package Contractor and Owner shall perform the
following:
Change to:
"…...For Code 1 and Code 2 approved drawings/documents of
‘blue code’ design package (Annex 6 Flow Chart 1) the Works
Package Contractor and Owner shall perform the following:……"
This is applicable to "blue code" design
package.
Ravi
3 FINAL DESIGN 4.7 (a) For an 'Approved’ package (Drawings listed as Code 1 in
Drawing Approval Sheet)
The Works Package Contractor shall submit three (3) sets of
A1 size drawings of Code 1 approved design package together
with two (2) copies of Design Certificates (specimen sample of
which is included in Annex 2 – Exhibit 2.1). The Owner shall
return two (2) copies of the endorsed drawings and one (1)
signed copy of Design Certificate.
Change to:
For an 'Approved’ package (Drawings listed as Code 1 in Drawing
Approval Sheet)
The Works Package Contractor shall submit three (3) sets of A1
size drawings list of approved drawings of Code 1 approved
design package together with two (2) copies of Design
Certificates (specimen sample of which is included in Annex 2 –
Exhibit 2.1). The Owner shall return two (2) copies of the
endorsed drawings and one (1) signed copy of Design
Certificate.
It is the current practice in SBK Line. Ravi
4 FINAL DESIGN 4.7 (b) For an ‘Approved in Principle with Comments package
(Drawings listed as Code 2 in Drawing Approval Sheet)
The Works Package Contractor shall resubmit three (3) sets of
A1 size revised drawings incorporating amendments required
to achieve unconditional approval together with two (2)
copies of Design Certificates. The Owner shall review the
amended drawings and if satisfactory, shall return two (2)
copies of the endorsed drawings and one (1) signed copy of
Design Certificate.
Change to:
For an ‘Approved in Principle with Comments package (Drawings
listed as Code 2 in Drawing Approval Sheet)
The Works Package Contractor shall resubmit three (3) sets of
A1 size revised drawings incorporating amendments required to
achieve unconditional approval together with two (2) copies of
Design Certificates. The Owner shall review the amended
drawings and if satisfactory, assign code 1 to the relevant
drawing and shall return two (2) copies of the endorsed
drawings and one (1) signed copy of Design Certificate.
It is the current practice in SBK Line. Ravi
5 FINAL DESIGN ANNEX 6 - Add:
Annex 6: DESIGN APPROVAL PROCESSES
(FLOW CHART 1, 2 AND 3)
Added Clause 1.16 above. Ravi
3 of 5
PARTICULAR SPECIFICATIONS AMENDMENT LOG 6/29/2014
Comments byRemarksNo Item Existing ClausesClausesReason (s)
(if any)Proposed Revision
J APPENDIX P - PROVISION OF SURVEY EQUIPMENT
1 Survey Equipment
Item (b)
- Equipment
Leica Flexline TS06 c/w
2 x Leica Standard Target systems
3 x Leica wooden tripod
or equivalent.
Number of Sets
3
Change to:
Equipment
Leica Flexline TS06 c/w
2 x Leica Standard Target systems
3 x Leica wooden tripod
or equivalent.
Leica NOVA MS50 MULTISTATION SYSTEM c/w
4 x Leica Precise Target systems
5 x Leica Heavy duty wooden tripod
or equivalent.
Number of Sets
31
Replace current equipment to latest
multi function Total Station with
scanning and imaging for achieving the
accuracy required for tunneling work
Pua Boon Hin
2 Survey Equipment
Item (c)
- Equipment
Leica DNA03 Digital Level c/w
2 x Leica lnvar Staff with Bar Code.
1 x Leica Heavy duty wooden tripod
or equivalent.
Number of Sets
2
Change to:
Equipment
Leica DNA03 Digital Level c/w
2 x Leica lnvar Staff with Bar Code.
1 x Leica Heavy duty wooden tripod
or equivalent.
TRIMBLE DINI (0.3mm Acc) Digital Level c/w
2 x Leica lnvar Staff with Bar Code.
1 x Leica Heavy duty wooden tripod
or equivalent.
Number of Sets
23
More reliable and proven track record in
SBK Line survey and monitoring works
on surface and in the tunnel.
Pua Boon Hin
3 Survey Equipment
Item (d)
- Equipment
Leica Sprinter 250M c/w
2 x Sprinter fibre glass barcode staff {2m}
1 x Leica Heavy duty wooden tripod
or equivalent.
Number of Sets
4
Delete item (d)
Equipment
Leica Sprinter 250M c/w
2 x Sprinter fibre glass barcode staff {2m}
1 x Leica Heavy duty wooden tripod
or equivalent.
Number of Sets
4
Difficult to achieve the required
accuracy and requires frequent self
calibration. Limited sighting distance
and sensitive to vibration.
Pua Boon Hin
4 Survey Equipment
Item (e)
- Equipment
Leica Gee Office
Change to:
Equipment
Leica Gee Office or equivalent
To allow for other software application. Pua Boon Hin
5 Software
Item (a)
- Software
AutoDesk Civil 3D
Number of Licences/Copies
4
Change to:
Software
AutoDesk Civil 3D
Number of Licences/Copies
43
Pua Boon Hin
6 Software
Item (a)
- - Add:
Software
MultiWorx (with 3 yrs CCP) + AutoDesk Civil 3D
Number of Licences/Copies
1
Add in application to handle 3D point
cloud with image works.
Pua Boon Hin
7 Software
Item (a)
- - Add:
Software
Leica Infinity Complete Bundle or Equivalent.
Number of Licences/Copies
1
Basic tool to edit point cloud and
filtering works.
Pua Boon Hin
4 of 5
PARTICULAR SPECIFICATIONS AMENDMENT LOG 6/29/2014
Comments byRemarksNo Item Existing ClausesClausesReason (s)
(if any)Proposed Revision
8 Software
Item (b)
- Application software for Viva TPS Change to:
Application software for Viva TPS or equivalent
Pua Boon Hin
9 Software
Item (b)
- Software
(i) Smartworx Viva TS
Number of Licences/Copies
3
Change to:
'Software
(i) Smartworx Viva TS or Equivalent
Number of Licences/Copies
34
To be consistent with the number of
equipment.
Pua Boon Hin
10 Software
Item (b)
- Software
(ii) Viva TS Monitoring
Number of Licences/Copies
3
Change to:
'Software
(ii) Viva TS Monitoring or Equivalent
Number of Licences/Copies
34
To be consistent with the number of
equipment.
Pua Boon Hin
11 Software
Item (b)
- Software
(iii) Viva TS Road Runner Tunnel Application
Number of Licences/Copies
3
Change to:
'Software
(iii) Viva TS Road Runner Tunnel Application or Equivalent
Number of Licences/Copies
34
To be consistent with the number of
equipment.
Pua Boon Hin
12 Software
Item (b)
- Software
(iv) TMS Tunnel Profile plus 3.0
Number of Licences/Copies
1
Change to:
'Software
(iv) TMS Tunnel Profile plus 3.0 or Equivalent
Number of Licences/Copies
1
Pua Boon Hin
13 Software
Item (c)
- Software
NRG software
Number of Licences/Copies
3
Change to:
'Software
NRG software or TPS Survey Suite
Number of Licences/Copies
3
Proven Alternative software for Tunnel
wriggle survey report.
Pua Boon Hin
14 Software
Item (d)
- Software
STAR*NETV6
Number of Licences/Copies
3
Change to:
Software
STAR*NETV6 or Equivalent
Number of Licences/Copies
3
Pua Boon Hin
K APPENDIX T - TBM SPECIFICATIONS
1 GENERAL
REQUIREMENTS
1.1.1 The Closed Face Shielded Tunnel Boring Machines (TBMs),
including all components used, and all associated plant shall
be supplied brand new. The Works Package PROJEK MASS
RAPID TRANSIT LEMBAH KELANG Jajaran Sungai Buloh –
Kajang Tender Ref. No. KVMRT/L1/UGW/100 Particular
Specification Underground Works (Tunnels, Stations &
Associated Structures) Between Semantan North Portal And
Maluri South Portal KVMRT/PDP/SBK/GEN/UGW/PS/CS/0001
Appx T-2 Revision: 00 Contractor, shall be fully responsible for
the selection, design and supply of the TBM’s and all ancillary
equipment used, notwithstanding any of the requirements
stated in the Specifications which shall be suitable for the
conditions anticipated.
Need to re-define the term "brand new"
for SSP Line as it is using the SBK line
TBM.
Ng Hau Wei