Sheet1Execution Plan: Fuel Duct Installation
ProjectSr.No.Execution PlanResponsibilityHoursDay 1Day 2Day 3Day
4Day 5Day 6Remarks1Getting the work permit from Client every
dayETW12Area Barrication.ETW23Providing the Scaffolding material
and scaffolderAAC / ClientRequired ready on Day 14Removing the
instruments connectionsAAC / ClientRequired ready on Day 15Removal
of InsulationETW66De-torduing of lower flange and upper
flangeETW37Wood arrangement for lifting the duct assembly on the
ground.AAC / ClientRequired ready on Day 18Holding duct assembly
using crane for proper de-bolting of flanges.ETW69Lifting of fuel
duct assembly and placement on the wood on ground.ETW610Removal of
central flange.ETW611Cleaning of all flanges for
inspection.ETW612Inspection of all the flanges with gaskets and
bolts & Overall inspection.AAC / Client13After inspection
clearance, installtion of new feul duct lower spool using
crane.ETW614Fuel duct assembly erection, installation and
re-fitting both flanges simultaneously.ETW815Allignment inspection
for fuel duct.AAC / Client & ETW5Simultaneous
operation.16Torquing of flange's nut bolts.ETW517Inspection of bolt
torquing.AAC / Client218Fuel duct re-insulation.ETW1019Weather
shield installation.ETW620Box up and house keeping.ETW6