The University of Southampton School of Engineering Sciences
12. PRODUCT WORK BREAKDOWN STRUCTURE
12.1 Background and Conformance with Group Technology
Traditional shipbuilders employ work subdivisions by ships’ functional systems
which are natural and appropriate for estimating and for early design stages.
However, system orientation for planning, scheduling and execution is unnatural
and inappropriate because it leads to poor co-ordination of work and generally
results in work packages which are too large for effective control of material, man-
hours and schedules.
As explained in Chapers 3-9, ships are produced by initially procuring ore
fabricating parts and joining them to create sub-assemblies. These are then
combined through several manufacturing levels to produce increasingly larger
assemblies and moduls. Thus the ideal way to subdivide ship construction work is
to focus on the needed parts and sub-assemblies, ie. the actual interim products that
pre-occupy workers. A scheme to sub-divide work in accordance with an interim
product view is a product-oriented work breakdown structures (PWBS).
Unlike system-orientated methodologies, product orientation facilitates identifying
work by classes of problems. This implies the use f Group Technology principles.
The basis for groups or families is through the common processes for the
manufacture of all parts within the group. Thus parts are classified by both design
and manufacturing attributes which are reflected in the coding schemes. Unique
classification by certain product aspects conventionally relate a part of sub-
assembly to a system or zone in a ship design context and also to work processes by
problem area and by work stage. This concept, combines with a greater degree of
interaction between design and production, has proven to be a powerful means for
improving productivity – see Figure 12.1.
Professor R A Shenoi Part II - Ship Production Technology
12-1
![Page 2: 12. PRODUCT WORK BREAKDOWN STRUCTURE 12.1 Background …vtcang/course/SPMan-205/ontap-SPMan-205/Ch… · WELDING SHORT CYCLE TIMES AND MULTIPLE ... - for block erection purposes,](https://reader031.vdocuments.us/reader031/viewer/2022013015/5b84cc9a7f8b9ab7618c6b22/html5/thumbnails/2.jpg)
The University of Southampton School of Engineering Sciences
12.2 Work Package Classifications
Logically, the PWBS first divides the shipbuilding process into three basic types of
work, namely hull construction, outfitting and painting. Further each is readily
subdivided into fabrication and assembly types of work. It is these assembly
subdivisions that are naturally linked to zones and which are the basis for zone
dominance in the management cycles of the most competitive shipbuilding firms.
Professor R A Shenoi Part II - Ship Production Technology
12-2
![Page 3: 12. PRODUCT WORK BREAKDOWN STRUCTURE 12.1 Background …vtcang/course/SPMan-205/ontap-SPMan-205/Ch… · WELDING SHORT CYCLE TIMES AND MULTIPLE ... - for block erection purposes,](https://reader031.vdocuments.us/reader031/viewer/2022013015/5b84cc9a7f8b9ab7618c6b22/html5/thumbnails/3.jpg)
The University of Southampton School of Engineering Sciences
O TIMES
WORK BREAKDOWN STRUCTURE
PRODUCT ORIENTATED
SPECIALISATION MAXIMUM USE OF
MASS PRODUCTION PRINCIPLES
INVESTMENT HIGH
PRODUCTION STAGES
MULTIPLE STAGES FOR STEEL AND
OUTFIT
LABOUR COST HIGH HOURLY
RATE HIGH
PRODUCTIVITY
FLEXIBILITY DE-COUPLING OF
STEEL OUTFIT, MULTI-SKILLED WORK GROUPS,
ACCURCY REQUIREMENTS
HIGH DUE TO WELDING SHORT
CYCLE TIMES AND MULTIPLE
PRODUCTION STAGES
PLANNING SIMPLE
STRUCTURED HIGH LEVEL OF
DETAIL PLANNING BASED
N SHORT CYCLE
LOST CONTROL MATERIALS BY
SYSTEM LABOUR BY ZONE/STAGE
WORK ORGANISATION BY ZONE/STAGE/
INTERIM PRODUCT
MATERIALS CONTROL
BY SYSTEM & ZONE/STAGE/INTE
RIM PRODUCT
WORKING DRAWINGS
ZONE/STAGE/ INTERIM PRODUCT
ESTIMATING MATERIAL BY
SYSTEM LABOUR BY PRODUCT ZONE/STAGE
Figure 12.1: Characteristics of the Modern Shipbuilding Method
Professor R A Shenoi Part II - Ship Production Technology
12-3
![Page 4: 12. PRODUCT WORK BREAKDOWN STRUCTURE 12.1 Background …vtcang/course/SPMan-205/ontap-SPMan-205/Ch… · WELDING SHORT CYCLE TIMES AND MULTIPLE ... - for block erection purposes,](https://reader031.vdocuments.us/reader031/viewer/2022013015/5b84cc9a7f8b9ab7618c6b22/html5/thumbnails/4.jpg)
The University of Southampton School of Engineering Sciences
Secondly, PWBS classifies interim products according to their resource needs:
- Material: eg. steel plate, machinery, cable, oil, etc.
- Manpower: eg. welder, fitter, rigger, transporter, etc.
- Facilities: eg. buildings, docks, machinery, tools, etc.
- Expenses: eg. designing, transportation, sea trails, etc.
The third classification relates to four “product aspects”. Two of these, system and
zone, are related to the ship design function while the other two, area and stage, are
related to the production function.
- System: A structural or operational characteristic of a product such as
longitudinal or transverse bulkhead, deck lighting system, etc.
- Zone: This relates to a geographical division of the product such as engine
room, cargo hold, operations room, etc.
- Area: This concerns division of the work process into similar types of work
problems.
- by feature (eg. curves vs. flat panel)
- by quantity (eg. batch, vs flow line)
- by work type (eg. welding, burning, marking)
- Stage: This related to various sequences in the production cycle such as
preparation, assembly, fabrication, etc.
Figure 12.2 illustrates the three dimensional nature of PWBS.
12.3 Aspects of Work Package Definition
This section considers the link between “product aspects” outlined above and the
ship production process itself. Because inherently different types of work are
required, a product-oriented breakdown of ship construction work should
anticipate:
- Hull Block Construction Method (HBCM)
- Zone Outfitting Method (ZOFM)
Professor R A Shenoi Part II - Ship Production Technology
12-4
![Page 5: 12. PRODUCT WORK BREAKDOWN STRUCTURE 12.1 Background …vtcang/course/SPMan-205/ontap-SPMan-205/Ch… · WELDING SHORT CYCLE TIMES AND MULTIPLE ... - for block erection purposes,](https://reader031.vdocuments.us/reader031/viewer/2022013015/5b84cc9a7f8b9ab7618c6b22/html5/thumbnails/5.jpg)
The University of Southampton School of Engineering Sciences
12.3.1 Hull Block Construction Method (NBCM)
Blocks should be designed such that:
- for block assembly purposes, they are assignable to one of a minimum
number of work package groups considering similarities in problem area
and the need to minimise variations in working times,
- for block erection purposes, they will be stable configurations requiring no
temporary support or reinforcement and otherwise shaped to achieve
minimum working times,
- for on-block outfitting and painting, they are sized for maximum space (area
and/or volume).
Further there should be similarities in volume, weight, shape, etc. even at the
expense of design convenience, in order to distribute work evenly throughout the
fabrication and assembly levels which precede block assembly.
Typical groupings by product aspects are presented in Figure 12.3. The horizontal
combinations characterise the various types of work packages that are requisite and
sufficient for the work to be performed for each level. Vertical combinations of the
various types of work packages denote the process lanes for hull construction work
flow which correspond to those illustrated in Figure 12.4.
(A) Part Fabrication
As shown in Figure 12.5 (and from Chapters 4 and 5), part fabrication is the first
manufacturing level. It produces components for hull construction which can be
subdivided further. Typical work packages are grouped by zone and:
- by area, for associating raw materials, finishing fabrication processes and
relevant facilities separated for parallel/non-parallel/internal parts from plate
and parts from rolled shapes.
Professor R A Shenoi Part II - Ship Production Technology
12-5
![Page 6: 12. PRODUCT WORK BREAKDOWN STRUCTURE 12.1 Background …vtcang/course/SPMan-205/ontap-SPMan-205/Ch… · WELDING SHORT CYCLE TIMES AND MULTIPLE ... - for block erection purposes,](https://reader031.vdocuments.us/reader031/viewer/2022013015/5b84cc9a7f8b9ab7618c6b22/html5/thumbnails/6.jpg)
The University of Southampton School of Engineering Sciences
Figure 12.2: Elements of PWBS
Professor R A Shenoi Part II - Ship Production Technology
12-6
![Page 7: 12. PRODUCT WORK BREAKDOWN STRUCTURE 12.1 Background …vtcang/course/SPMan-205/ontap-SPMan-205/Ch… · WELDING SHORT CYCLE TIMES AND MULTIPLE ... - for block erection purposes,](https://reader031.vdocuments.us/reader031/viewer/2022013015/5b84cc9a7f8b9ab7618c6b22/html5/thumbnails/7.jpg)
The University of Southampton School of Engineering Sciences
- by stage, after having performed grouping by zone, area and similarities in
part types and sizes for plate joining, bending, marking and cutting.
Typical grouping of work packages for parts fabrication are illustrated in Figure
12.5.
(B) Part Assembly
The second manufacturing level is special and outside the main work flow. Typical
work package grouped by area are as:
- similar size in large quantities exemplified by large transverse frames,
girders, floors, etc.
- similar size in small quantities piece-parts for seatings for (a few) winches
or motors.
The former, regardless of design differences, can be mass produced on process
lanes whereas the latter would require a job shop approach. Figure 12.6 illustrates
typical examples of this.
(D) Semi-Block, Block and Grand Block Joining
A block, which is a key hull construction zone, may be planned in three assembly
levels depending upon circumstances. A semi-block serves the need to assemble a
partial zone separate from other to avoid disruption of work. When this is
employed, the block assembly level is where it joins its “mother” block. Grand
block joining involves combining a few blocks either in a module hall or at an open
site near the building berth/dock. It should be noted that only the block assembly is
in the main work flow.
The semi-block assembly level is divided by problem area in the same manner as
for the sub-block level.
Professor R A Shenoi Part II - Ship Production Technology
12-7
![Page 8: 12. PRODUCT WORK BREAKDOWN STRUCTURE 12.1 Background …vtcang/course/SPMan-205/ontap-SPMan-205/Ch… · WELDING SHORT CYCLE TIMES AND MULTIPLE ... - for block erection purposes,](https://reader031.vdocuments.us/reader031/viewer/2022013015/5b84cc9a7f8b9ab7618c6b22/html5/thumbnails/8.jpg)
The University of Southampton School of Engineering Sciences
PRODUCT ASPECTS CODES PLAN’G LEVEL
MFG LEVEL
ZONE AREA STAGE ZONE AREA STAGE
TEST
1
7
SHIP
FOR
E H
ULL
CAR
GO
HO
LD
ENG
INE
RO
OM
AFT
HU
LL
SUPE
RSTR
UCTU
RE
ERECTION
SHIP
NO
.
BLO
CK
CO
DE
STAG
E C
OD
E
BACK PRE-ERECTION NIL
PRE-ERECTION NIL
2
6 FLAT
PANEL CURVED PANEL
SUPE
RSTR
UCTU
RE
JOINING NIL GR
AND
BLO
CK
CO
DE
GR
AND
BLO
CK
CO
DE
STAG
E C
OD
E
BACK ASSEMBLY NIL
ASSEMBLY
FRAMING NIL
3
5
FLAT
SPEC
IAL
FLAT
CU
RVE
D
SPEC
IAL
CU
RVE
D
SUPE
RSTR
UCTU
RE
PLATE JOINING NIL
BLO
CK
CO
DE
BLO
CK
CO
DE
STAG
E C
OD
E
BACK ASSEMBLY NIL
ASSEMBLY
4
4
BLO
CK
NIL
PLATE JOINING NIL
SEM
I-BLO
CK
CO
DE
SEM
I-BLO
CK
CO
DE
STAG
E C
OD
E
BACK ASSEMBLY NIL 5 3
NIL
SIMILAR SIZE IN A LARGE QUANTITY
SIMILAR SIZE IN A SMALL QUANTITY
ASSEMBLY SUB-
BLO
CK
CO
DE
SUB
BLO
CK
CO
DE
BENDING NIL
6
2
SUB-
BLO
CK
SUB-BLOCK PART
BUILT-UP PART
ASSEMBLY
ASSE
MBL
ED
PAR
T C
OD
E
STAG
E C
OD
E
BENDING NIL
MARKING & CUTTING
7
1
PAR
T
PAR
ALLE
L PA
RT
FRO
M
PLAT
E N
ON
-PAR
ALLE
L PA
RT
FRO
M
PLAT
E
INTE
RN
AL P
ART
FRO
M P
LATE
PAR
T FR
OM
R
OLL
ED S
HAP
E
OTH
ER
PLATE JOINING NIL
PAR
T C
OD
E
PAR
T O
DE
STAG
E C
OD
E
Figure 12.3: Typical Classifications of Product Aspects for HBCM
Professor R A Shenoi Part II - Ship Production Technology
12-8
![Page 9: 12. PRODUCT WORK BREAKDOWN STRUCTURE 12.1 Background …vtcang/course/SPMan-205/ontap-SPMan-205/Ch… · WELDING SHORT CYCLE TIMES AND MULTIPLE ... - for block erection purposes,](https://reader031.vdocuments.us/reader031/viewer/2022013015/5b84cc9a7f8b9ab7618c6b22/html5/thumbnails/9.jpg)
The University of Southampton School of Engineering Sciences
Figure 12.4: Construction Lanes for Hull Block Construction
Professor R A Shenoi Part II - Ship Production Technology
12-9
![Page 10: 12. PRODUCT WORK BREAKDOWN STRUCTURE 12.1 Background …vtcang/course/SPMan-205/ontap-SPMan-205/Ch… · WELDING SHORT CYCLE TIMES AND MULTIPLE ... - for block erection purposes,](https://reader031.vdocuments.us/reader031/viewer/2022013015/5b84cc9a7f8b9ab7618c6b22/html5/thumbnails/10.jpg)
The University of Southampton School of Engineering Sciences
Professor R A Shenoi
a
Figure 12.5: Parts Classification by Are
Part II - Ship Production Technology 12-10
Figure 12.6: Sub-Assembly by Area
![Page 11: 12. PRODUCT WORK BREAKDOWN STRUCTURE 12.1 Background …vtcang/course/SPMan-205/ontap-SPMan-205/Ch… · WELDING SHORT CYCLE TIMES AND MULTIPLE ... - for block erection purposes,](https://reader031.vdocuments.us/reader031/viewer/2022013015/5b84cc9a7f8b9ab7618c6b22/html5/thumbnails/11.jpg)
The University of Southampton School of Engineering Sciences
The block assembly level is divided by problem area using distinguishing features
of the panel needed as a base for attaching parts, assembled pars of sub-blocks and
uniformity of working times involved. These characteristics determine whether
platens or pin jigs are required or whether the blocks are to be assembled in a flow
where work starts and finishes in unison.
At the grand block joining level, three classifications by area are normally required
– namely flat panel, curved panel and superstructure.
Figures 12.7-12.9 illustrate some of the relationships between semi-blocks, blocks
and grand blocks for a 22,000 DWT general cargo ship.
12.3.2 Zone Outfitting Method (ZOFM)
In a manner similar to that for hull construction, zone divisions for outfitting are
tailored to fit a new contract design. The basis could be previously-built similar
ships. ZOFM considerations need to be considered carefully, alongside those of
HBCM, when planning and defining the work sequence for the new construction.
ZOFM can be conducted on-unit, on-block and/or on-board (see Chapter 8 also).
Typical groupings of the product aspects are given in Figure 12.10.
(A) Component Procurement
As indicated in Figure 12.10, this is the first manufacturing level. This enables
production of interim products of zones for outfitting for which no further sub-
division is needed by the shipyard. Typical wok packages and material requisitions
are grouped by zone and area to address:
- in-house manufacturing,
- outside, sub-contracted work,
- purchasing off-the-shelf products.
Professor R A Shenoi Part II - Ship Production Technology
12-11
![Page 12: 12. PRODUCT WORK BREAKDOWN STRUCTURE 12.1 Background …vtcang/course/SPMan-205/ontap-SPMan-205/Ch… · WELDING SHORT CYCLE TIMES AND MULTIPLE ... - for block erection purposes,](https://reader031.vdocuments.us/reader031/viewer/2022013015/5b84cc9a7f8b9ab7618c6b22/html5/thumbnails/12.jpg)
The University of Southampton School of Engineering Sciences
Figure 12.7: Semi-Block and Block Assembly
Professor R A Shenoi Part II - Ship Production Technology
12-12
![Page 13: 12. PRODUCT WORK BREAKDOWN STRUCTURE 12.1 Background …vtcang/course/SPMan-205/ontap-SPMan-205/Ch… · WELDING SHORT CYCLE TIMES AND MULTIPLE ... - for block erection purposes,](https://reader031.vdocuments.us/reader031/viewer/2022013015/5b84cc9a7f8b9ab7618c6b22/html5/thumbnails/13.jpg)
The University of Southampton School of Engineering Sciences
Figure 12.8: Block Assembly and Grand Block Joining
Professor R A Shenoi Part II - Ship Production Technology
12-13
![Page 14: 12. PRODUCT WORK BREAKDOWN STRUCTURE 12.1 Background …vtcang/course/SPMan-205/ontap-SPMan-205/Ch… · WELDING SHORT CYCLE TIMES AND MULTIPLE ... - for block erection purposes,](https://reader031.vdocuments.us/reader031/viewer/2022013015/5b84cc9a7f8b9ab7618c6b22/html5/thumbnails/14.jpg)
The University of Southampton School of Engineering Sciences
Figure 12.9: Grand Block Joining
Professor R A Shenoi Part II - Ship Production Technology
12-14
![Page 15: 12. PRODUCT WORK BREAKDOWN STRUCTURE 12.1 Background …vtcang/course/SPMan-205/ontap-SPMan-205/Ch… · WELDING SHORT CYCLE TIMES AND MULTIPLE ... - for block erection purposes,](https://reader031.vdocuments.us/reader031/viewer/2022013015/5b84cc9a7f8b9ab7618c6b22/html5/thumbnails/15.jpg)
The University of Southampton School of Engineering Sciences
These problem areas can be further classified by requirements for manufacturing
drawings, purchase order specification and raw materials.
(B) Unit Assembly and Grand-Unit Joining
As shown in Figures 8.3, 8.4 and 8.5, unit sizes can vary significantly. Therefore
two problem areas are designated at the unit assembly level – namely large and
small sized units. The distinction is principally by lift capacity – eg. units that
weigh more or less than, say, 1T.
Problem areas at the unit level could be further subdivided into:
- machinery unit (machinery combined with all adjacent components
including foundation, pipes, valves, ladders, supports, etc) – see Figure 8.5.
- pipe unit (no machinery, just pipe pieces combined with valves, supports,
etc). – see Figures 8.3 or 8.4.
- other (hatch covers with coamings, accommodation/cabin modules, etc) –
see Figure 8.7.
The grand unit joining level, which enables combining two or more units, enables
- reduction in working times on berth and afloat in the basin.
- production of more stable assemblies for erection purposes.
Classification by area is limited to availability of adequate covered building space
and availability of lifting capability.
Professor R A Shenoi Part II - Ship Production Technology
12-15
![Page 16: 12. PRODUCT WORK BREAKDOWN STRUCTURE 12.1 Background …vtcang/course/SPMan-205/ontap-SPMan-205/Ch… · WELDING SHORT CYCLE TIMES AND MULTIPLE ... - for block erection purposes,](https://reader031.vdocuments.us/reader031/viewer/2022013015/5b84cc9a7f8b9ab7618c6b22/html5/thumbnails/16.jpg)
The University of Southampton School of Engineering Sciences
PRODUCT ASPECTS CODES PLAN’G LEVEL
MFG LEVEL
ZONE AREA STAGE ZONE AREA STAGE
1
6 SH
IP
DEC
K
ACCO
MM
ODAT
ION
MAC
HIN
ERY
ELEC
TRIC
AL
OPERATION AND TEST
SHIP
NO
.
SHIP
NO
.
OPE
RAT
ION
C
OD
E
WELDING NIL
ON-CLOSED-SPACE FITTING
WELDING NIL
2
5
ON
-BO
ARD
D
IVIS
ION
NIL
SPEC
IALI
TY/S
IMIL
AR W
OR
K IN
SM
ALL
VOLU
ME
SPEC
IALITY
/SIMILA
R W
ORK IN
LARG
E VO
LUME
SPEC
IALLIT
Y/sSIM
ILAR
WOR
K BY H
IGH S
KILL
ON-OPEN-SPACE FITTING
OU
TFIT
TIN
G
SIG
N/O
N-
BOAR
D
DIV
I SIO
N C
OD
E
BLO
CK
CO
DE
HU
LL
EREC
TIO
N
STAG
E C
OD
E
WELDING NIL
ON-FLOOR FITTING
WELDING NIL
3
4 BLOCK
NIL SPECIALITY/COMPONENTS IN A LARGE QUANTITY
SPECIALITY/COMPONENTS IN A SMALL QUANTITY ON-CEILING FITTING
OU
TFIT
TIN
G
SIG
N/B
LOC
K C
OD
E
ON
-BO
ARD
W
OR
K TY
PE
CO
DE
BLO
CK
ASSE
MBL
Y ST
AGE
CO
DE
WELDING NIL
4
3 NIL NIL
JOINING GR
AND
UN
IT
SIG
N
WELDING NIL
5 2
UNIT
LARGE SIZE UNIT
SMALL SIZE UNIT
ASSEMBLY
UN
IT A
SSEM
BLY
SIG
N/B
LOC
K O
R O
N-
BOAR
D D
IVIS
ION
OR
MAC
HIN
ERY
UN
IT
CO
DE
BLO
CK
OR
ON
-BO
ARD
DIV
ISIO
N O
R
MAC
HIN
ERY
CO
DE
UN
IT S
IGN
PALLETIZING
MANUFACTURING NIL
7
1
COMPONENT
IN-H
OU
SE
MAN
UFA
CTU
RI
NG
OU
TSID
E M
ANU
FAC
TUR
IN
G
PUR
CH
ASIN
G
DESIGN AND MATERIAL PREPARATION NIL
CO
MPO
NEN
T C
OD
E/PA
LLET
C
OD
E
CO
MPO
NEN
T PR
OC
UR
EMEN
T SI
GN
NO
SIG
N
Figure 12.10: Typical Classification of Product of Aspects of ZOFM
Professor R A Shenoi Part II - Ship Production Technology
12-16
![Page 17: 12. PRODUCT WORK BREAKDOWN STRUCTURE 12.1 Background …vtcang/course/SPMan-205/ontap-SPMan-205/Ch… · WELDING SHORT CYCLE TIMES AND MULTIPLE ... - for block erection purposes,](https://reader031.vdocuments.us/reader031/viewer/2022013015/5b84cc9a7f8b9ab7618c6b22/html5/thumbnails/17.jpg)
The University of Southampton School of Engineering Sciences
(C) On-Block Outfitting
Typically, the divisions by area address problems which are inherently different so
that each work package for outfitting can be assigned to the appropriate team of
assembly specialists for deck, accommodation, machinery or electrical. These
classifications can be further subdivided according to the work being in small or
large quantities.
(D) On-Board Outfitting
Much outfit wok at this level progresses simultaneously with hull erection and,
ideally, should be limited to:
- fitting components, units and/or grand units that are too large or heavy to fit
on-block (eg. main engines, generators, etc)
- fitting fragile or weather-vulnerable or sensitive components that could be
damaged if installed before compartments are enclosed (eg. joinery,
electronic equipment, etc)
- connecting between components, units and grand-units that are fitted on-
block or on-board.
12.4 Relevance to Contractual Context
The principal objective of PWBS is to increase productivity and quality. This
objective has to be conveyed to the “customer”, ie. the ship owner, in a formal,
contractual context as well. This is done through a Build Strategy Document which
is prepared at the outset and before commencement of the build programme.
The early specifications ought to refer to the build methods to be applied and
should define a shipyard’ intention to maximise the use of modules, orthogonal
pipe runs, or pipe banks with allocated ducts for pipe and cable runs. The build
strategy forms the basis of all planning and scheduling for the building programme.
It is designed to provide a co-ordinated approach for all departments.
Professor R A Shenoi Part II - Ship Production Technology
12-17
![Page 18: 12. PRODUCT WORK BREAKDOWN STRUCTURE 12.1 Background …vtcang/course/SPMan-205/ontap-SPMan-205/Ch… · WELDING SHORT CYCLE TIMES AND MULTIPLE ... - for block erection purposes,](https://reader031.vdocuments.us/reader031/viewer/2022013015/5b84cc9a7f8b9ab7618c6b22/html5/thumbnails/18.jpg)
The University of Southampton School of Engineering Sciences
Figure 12.11 shows an extract from a typical build strategy defining aft end
breakdown after considering and modifying engine room layout to obtain optimum
breaks not just to steelwork but also to enable maximum advanced outfit to be
possible. Figure 12.12 shows a further extract which defines the plate nesting
policy to be followed for a 60,000 DWT Products Tanker. The build strategy is
supported by timetables for (see Figure 12.13):
- key events from contract to delivery,
- material definition, ordering and delivery,
- manufacturing information release from Technical Department.
Professor R A Shenoi Part II - Ship Production Technology
12-18
![Page 19: 12. PRODUCT WORK BREAKDOWN STRUCTURE 12.1 Background …vtcang/course/SPMan-205/ontap-SPMan-205/Ch… · WELDING SHORT CYCLE TIMES AND MULTIPLE ... - for block erection purposes,](https://reader031.vdocuments.us/reader031/viewer/2022013015/5b84cc9a7f8b9ab7618c6b22/html5/thumbnails/19.jpg)
The University of Southampton School of Engineering Sciences
Figure 12.11: Build Strategy Definition of Aft End Module Figure 12.11: Build Strategy Definition of Aft End Module
The University of Southampton School of Engineering Sciences
Professor R A Shenoi Part II - Ship Production Technology
12-19
Professor R A Shenoi Part II - Ship Production Technology
12-19
![Page 20: 12. PRODUCT WORK BREAKDOWN STRUCTURE 12.1 Background …vtcang/course/SPMan-205/ontap-SPMan-205/Ch… · WELDING SHORT CYCLE TIMES AND MULTIPLE ... - for block erection purposes,](https://reader031.vdocuments.us/reader031/viewer/2022013015/5b84cc9a7f8b9ab7618c6b22/html5/thumbnails/20.jpg)
The University of Southampton School of Engineering Sciences
Figure 12.12: Build Strategy for Plate Nesting Figure 12.12: Build Strategy for Plate Nesting
The University of Southampton School of Engineering Sciences
Professor R A Shenoi Part II - Ship Production Technology
12-20
Professor R A Shenoi Part II - Ship Production Technology
12-20
![Page 21: 12. PRODUCT WORK BREAKDOWN STRUCTURE 12.1 Background …vtcang/course/SPMan-205/ontap-SPMan-205/Ch… · WELDING SHORT CYCLE TIMES AND MULTIPLE ... - for block erection purposes,](https://reader031.vdocuments.us/reader031/viewer/2022013015/5b84cc9a7f8b9ab7618c6b22/html5/thumbnails/21.jpg)
The University of Southampton School of Engineering Sciences
Figure 12.13: Key Dates Plan
Professor R A Shenoi Part II - Ship Production Technology
12-21