1_122_paper

Upload: kamaljeet-kaur

Post on 03-Apr-2018

213 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/28/2019 1_122_paper

    1/6

    Environmentally Significant Operational Loss

    Reduction on the Full GB Transmission NetworkPeter Macfie, Haibin Wan, Rachel Morfill, Martin Bradley

    Data & Analysis, National Grid,

    [email protected]

    Gary Taylor, Malcolm Irving

    Brunel Institute of Power Systems, Brunel University,

    [email protected]

    Abstract- A theoretical reduction of 1.4% in Great Britains(GB) transmission MW losses has been demonstrated on post-BETTA network simulations using Security ConstrainedOptimal Power Flow (SC-OPF) techniques. The simulatedefficiency saving applied to the live GB network could inprinciple save the power industry around 3.8 million and 45000tonnes of carbon dioxide over a full year. Such a saving wouldsupport with the European Union target of a 20% cut in carbondioxide emissions on 1990 levels [1]. Previous SC-OPF research[2] determined that between 1.1 and 1.7% transmission lossreduction is achievable on pre-BETTA networks. The SC-OPFalgorithm utilised voltage constraints that were consistent with

    the GB Security and Quality of Supply Standards (SQSS) andincluded more than 50 of the worst credible contingencies on theGB network. The SC-OPF algorithm proceeded bymanipulating GB controls including the voltage target ofgenerators, Static VAR Compensators (SVC), and the status ofshunt capacitors and reactors to reduce the transmission MWloss objective function. Our optimised network simulationresults showed significant increases in system VAR gain, whichmeant that the reactive generation requirement was reduced inthese studies. This paper will present these results, and discusspractical issues with utilising SC-OPF on the GB network data.

    I. INTRODUCTION

    National Grid, which is based in the UK and has a large

    business in the United States, is the system operator (SO) for

    the high voltage electricity transmission system in Great

    Britian (England, Wales, and Scotland). National Grid is also

    the owner of the transmission system in England and Wales,

    which comprises approximately 7200 kilometers of 400 and

    275 kV overhead line, 677 kilometers of underground cable,

    and 313 substations. National Grid is committed to its duty

    under the Electricity Act of 1989 to develop and maintain an

    efficient, coordinated and economical system. Since the

    implementation of the British Electricity Trading and

    Transmission Arrangements (BETTA) on 1st April 2005National Grids SO responsibilities were extended to include

    the transmission network in Scotland, which has meant

    around a 30% increase in the size of the network that needs to

    be operated and managed in the GB energy balancing

    mechanism.

    Transmission losses are reported annually by National Grid

    as the difference between electricity units entering and

    leaving the system, these losses include fixed and variable

    losses. During system design timescales, which occur around

    7 years before real time, National Grids policy is to

    implement network infrastructure that has been designed to

    optimise lifetime operating costs including the expected cost

    of transmission losses. This research however is concerned

    with operational timescales, which occur close to real time.

    National Grid considers losses while operating the

    transmission system when deciding a secured network

    configuration and voltage profile. National Grid has

    commissioned this research, jointly with Brunel University,

    to determine the potential for further reduction intransmission losses through changes in operational

    procedures. The GB Security and Quality of Supply

    Standards (SQSS) [3] set out the minimum requirements for

    the planning and operation of the GB transmission system.

    These standards include definitions of acceptable voltage

    conditions that have to be maintained during normal

    operation, and in the event of at least an n D contingency

    criterion, where the D refers to the loss of a double circuit.

    At present the transmission system relies on manual

    adjustment of operational conditions, this is in contrast with

    the perception of the power system community that optimal

    power flow tools can be exploited to reduce losses. The longterm aim of this research is concerned with the direct or

    indirect implementation of SC-OPF results to provide advice

    in the reactive power operational planning and real-time

    control of the live GB transmission system to reduce

    transmission losses.

    Loss minimisation OPF studies based on the Spanish

    transmission network have recently been performed by

    Ramos, Exposito, and Quintana [5], who demonstrated that

    transmission MW loss reduction of around 3% on state

    estimator data was achievable in theory using OPF with

    reactive constraints, and generator voltage controls. Thesestudies indicated that OPF tools could be a valuable technique

    in achieving transmission loss reduction on a large-scale

    power system, but are possibly optimistic, as security

    constraints were not included.

    SC-OPF has been exploited in this research to manipulate

    the voltage profile of the network by changing the state of

    reactive control devices to reduce transmission losses.

    Finding a feasible global minimum is a complex problem

  • 7/28/2019 1_122_paper

    2/6

    when minimising the non-separable MW loss objective

    function, including discrete voltage control devices (such as

    shunt capacitor and reactors), local controls and securing the

    network against a large number of credible contingencies.

    Ensuring that the final SC-OPF solution is feasible is an

    important criterion that has to be met, before any control

    switching result could be implemented, however a sub-

    optimality in the solution could be tolerated if it led to an

    improvement in the objective function. This paper presents

    results showing that SC-OPF can be utilised on an already

    well run large-scale power system to further reduce

    transmission losses. Issues relating to the application of theseSC-OPF techniques for practical use by National Grid will

    also be discussed in the context of this research.

    II. OPERATIONAL REACTIVE POWER MANAGMENT

    National Grid holds the sole licence to operate the

    transmission network in England, Wales, and Scotland. The

    Transmission Requirements (TR) group is responsible for

    detailed operational planning from 13 weeks ahead to day

    ahead, including preparing system access requirements to

    allow maintenance and construction work on the GB

    transmission system. This process includes optimisation of

    the network voltage profile taking into account all planned

    outages due to maintenance and construction work on the

    transmission system. TR will ensure that the SQSS

    requirements are satisfied and that ancillary services costs are

    minimised [4]. One of the major TR deliverables is a secured

    day-ahead peak demand network study, which is the focus of

    this research. These studies are adjusted by TR for each day

    to take account of changes in predicted demand, generation

    and changes in outage patterns.

    A hand-over document is prepared and delivered to thecontrol room, which includes network plans, outages, active

    constraints on MW flows, and post-fault actions to be taken

    in the event of fault outages. While the emphasis of the day-

    ahead deliverable is on active power management there is an

    obligation under the SQSS to secure voltage, which means

    that reactive power management is also considered. The

    SQSS includes regulatory requirements relating to generation

    margin, frequency control, voltage condition, thermal

    overload condition [3]. These regulatory voltage condition

    requirements must be carefully considered in this research, as

    reactive controls are manipulated by the optimisation

    algorithm. It is essential to ensure that available dynamic

    reactive reserves are maintained on SVCs and generators in

    order to secure the post-fault system voltages in the event of

    the most onerous credible fault. The steady state voltage

    condition must be secured both pre and post fault, as shown

    in Fig. 1 below. The figure shows the SQSS voltage

    requirements at customer connected buses (including grid

    supply points to the low voltage network), and also shows the

    requirements at all other buses. The steady state voltage limit

    information is indicated at each voltage level; the network

    must be secured to meet these limits for both the intact

    network and in the case of a fault outage. At customer

    connections the voltage must not change more than the

    regulated limits shown in the event of either a single circuit(SC) or double circuit (DC) outage.

    The day-ahead deliverable from TR is presented to control

    engineers, and is then used to derive a voltage profile target at

    several key demand points during the day. The control room

    transmission despatch engineer (TDE) then dynamically

    switches reactive equipment and issues instructions to

    generators in order to ensure system security and adequate

    MVAR reserves, while using the voltage profile target as a

    Fig. 1. Acceptable voltage conditions on the GB HV transmission system. SC=Single Circuit, DC=Double Circuit. Sourced from [11].

  • 7/28/2019 1_122_paper

    3/6

    guide. Control decisions include switching of shunt capacitors

    and reactors, changes to automatic reactive switching control,

    and issuing MVAR targets to generators. The reactive

    switching decision will be heavily influenced by the

    anticipated change in future demand. The peak demand point

    study produced by TR will have been securely configured at a

    snap-shot in time, but provides no information to the TDE on

    how to evolve the network from one time period to the next.This highlights the key difference between off-line

    snapshot studies used to ensure that the system is secure for

    a given generation/demand/outage pattern, and the on-line

    practical implementation of a secured network. The biggest

    source of reactive power is the system network MVAR gain

    (shunt gain BV2 minus series losses I2X ). This gain performs

    a vital role in the reactive balance:

    MVAR import + MVAR generated + MVAR gain =

    MVAR absorbed by generators + consumer MVAR demand + MVAR export

    (1)

    The TDE will utilise this system gain to achieve the desiredvoltage profile by increasing system global voltage profile to

    increase network gain prior to an increase in demand, so that

    when demand does increase the voltage profile of the system

    does not sag and lose MVAR gain. The snapshot day-ahead

    study produced by TR is used by control engineers as a guide,

    and represents the system at the peak demand point

    reasonably accurately. The results presented in section 4 are

    based on such day-ahead studies.

    III. PROBLEM FORMULATION

    Finding the minimum losses by manipulating reactivecontrols is a reactive management problem, which can be

    formulated as a security constrained optimal reactive

    dispatch. The solution is a state of the system that provides

    optimal settings of reactive controls, while maintaining

    system security in the event of any of the credible

    contingencies. The SC-OPF technique utilised in this

    research is the same as that presented by Dandachi [6], which

    is essentially a linear program formulated in terms of only

    control variables in a compact form. In this research the

    starting point for the SC-OPF is a day-ahead study, which is a

    feasible solution; this study also forms a reference to

    determine any improvement in the objective function. Thealgorithm evolves toward the final solution through

    successive iterations, which act to reduce the MW losses

    objective function, while alleviating all constraint violations

    that maybe encountered. Convergence is achieved when:

    There are no constraint violations.

    Changes in the objective function are within a user

    defined tolerance.

    The control movements are within user definedtolerances.

    A. Objective FunctionThis research is based on minimising a transmission MW

    losses objective. Such an objective is highly non-separable

    [7], as it cannot be approximated using separate active and

    reactive power components. This makes finding a global

    solution more difficult, because of the increased complexity.

    An additional challenge arises because the transmissionlosses objective function is not usually convex, which means

    that it can have many minima. The SC-OPF solution is

    therefore typically a minimum, but not necessarily a unique

    global minimum.

    B. Control VariablesThe modelled control variables within the SC-OPF are:

    Generator voltage targets.

    Static VAR compensator (SVC) voltage targets.

    Discrete shunt capacitors on/off

    Discrete shunt reactors on/off.

    The voltage targets were only defined for reactive controls

    which possess a wide enough reactive range to support the

    voltage (typically >100 MVAR range). These reactive

    controls were set-up to control the voltage level at the high-

    voltage side to achieve the voltage target determined by the

    SC-OPF.

    C. System ConstraintsThe system constraints included [6]:

    Control limits (e.g. generator, and SVCs). MVAR interchange between user defined reactive

    power areas.

    Voltage limits. Generator MVAR reserves relaxed for

    contingency cases.

    When contingencies are included in the optimization, the

    resulting reactive generation pattern will have adequate

    MVAR reserves, so that the voltage can be secured in theevent of any of these occurring. A large number of included

    contingencies should therefore imply widespread MVAR

    reserves, which would make the need to define reserve

    constraints redundant. MVAR reserve constraints are

    however included for several reasons including:

    To hold back the voltage profile, as this could be

    raised to the limit of feasibility by the objective

    function.

    To allow for error in the network data.

  • 7/28/2019 1_122_paper

    4/6

    The system constraints that define the SC-OPF problem

    include all the intact system constraints, and all the modelled

    security constraints for the around 50 of the worst credible

    contingencies on the network. Since the day-ahead data

    forms the starting point for the SC-OPF no constraints are

    initially violated in either the intact system or in contingency

    cases.

    D. Data model formulationSC-OPF algorithms have been extensively researched [6],

    but practical applications of reactive SC-OPF have not been

    successfully implemented within National Grid on a

    permanent basis. Therefore the underlying algorithms are

    relatively mature, and the challenge now lies in

    implementation and documentation of these techniques to

    solve current practical issues on large scale power systems.

    Network data preparation and appropriate setting up of OPF

    parameters are necessary to achieve successful and

    meaningful results. Ensuring that that a well conditionednetwork is utilised is important, because OPF is much more

    sensitive to network data inaccuracies than conventional

    power flow.

    This research was based on the National Grid tool Coldstart

    [12], which utilised SC-OPF to remove infeasibilities and set-

    up a voltage profile to give a feasible and economic solution.

    This tool was modified so that it could be used for secure

    MW transmission loss reduction. The Coldstart process

    converts day-ahead network data into an appropriate format

    for analysis, which included adding OPF related data such as:

    Acceptable voltage conditions - See figure 1.

    Flagging voltage controlled nodes

    Flagging shunts as optimisable

    Reactive reserve requirements

    MVAR interchanges

    Contingency information - 50 cases

    The initial voltage targets and the initial shunt switching

    pattern were set-up to be identical to the day-ahead study.

    The in-service shunts needed to be accurately represented in

    the data, so that they can be switched in as required to

    achieve the objective. An intact network power flow, and

    contingency power flows, were performed on this initial

    converted day-ahead data to form a reference for the MW

    losses objective, and to form a starting point for the OPF

    process. Many of the difficulties encountered achieving

    convergence during the SC-OPF process were due to

    inaccuracies in the network data, or inappropriate settings in

    the OPF.

    E. Issues with implementing OPF on a large-scale networkSpecific problems with using the MW losses objective

    function have already been discussed. Some general

    problems with optimal power flow (OPF) were outlined by

    Tinney [8]. These included the use of equivalent networks

    causing errors. For example, a problem could be encountered

    if a reduced section of network had a negative impedancebranch. In this case the minimise MW losses objective would

    attempt to maximise the flow in this branch, which would

    lead to a misleading reduction in the total MW losses. To

    avoid this problem in the network models presented in this

    research we only flagged non-equivalent branches as

    optimisable to be included in the loss minimization objective.

    A second difficulty discussed by Tinney relates to the

    discrete variable sub-problem in the OPF whereby some

    variables can only be adjusted in discrete steps, which can

    cause a problem when all variables are treated as continuous

    in the optimisation procedure. The SC-OPF procedure treatsall variables as continuous, and then rounds all the discrete

    variables to their nearest discrete value. This not only causes

    sub-optimality, but can cause constraint violations making the

    final solution infeasible. There are several methods of

    dealing with this problem described in [13].

    IV. LOSS MINIMISATION STUDIES ON GB NETWORKS

    A. ResultsAll studies presented are based on 2007 weekday day-ahead network studies produced by TR. These studies have

    been manually configured around one of the demand peaks of

    the day occurring between 10:30-13:00, so that they

    represented the system state using the best information

    available at the time. Figure 2 shows the day-ahead MW

    losses and optimised MW losses for Tuesday studies at

    monthly intervals across the year of 2007 referenced against

    the scale on the right hand side (RHS), and are represented

    with solid square blocks. The difference between the day-

    ahead MW losses and optimised MW losses is the MW loss

    reduction. Figure 2 also shows the MW demand, day-ahead

    MVAR generation and day-ahead MVAR gain, as well as the

    optimised MVAR generation and optimised MVAR gain

    referenced against the scale on the left hand side (LHS). The

    total demand has been scaled down to 20% of its value, so

    that it can be included on the LHS scale. Figure 3 highlights

    the relationship between the percentage MW loss reduction,

    which is the success of the SC-OPF at achieving lower losses,

    and the percentage MVAR gain change for the network upon

    optimisation of the weekday 2007 day-ahead networks.

    Figure 3 also shows the sum total lagging MVAR reserve

    percentage change between the day-ahead and the optimised

    studies. The lagging MVAR reserve is the amount of MVAR

  • 7/28/2019 1_122_paper

    5/6

    generating capability that is remaining on generators and

    SVCs on the system.

    B. Conclusions and Further WorkMW loss reductions of between 0.51 and 2.56%, with a

    mean average of 1.4%, have been achieved by SC-OPF on a

    selection of 2007 weekday day-ahead network studiesproduced by TR shown in Figure 2. These results indicate

    that the GB electricity transmission network is already well

    managed, so exhibits low losses; however a small but

    significant savings could still be achieved if the optimised

    solutions derived by SC-OPF could be implemented in

    practice. A 1.4% MW loss saving would have saved around

    45000tCO2 based on the 6.10TWh 2006/07 outturn

    transmission losses [9, 10]. This represents a 3.8 million

    saving to the power industry as a whole based on a 45/MWh

    average generation cost [9]. Efficiency savings play a key

    role in the UK governments commitment to tackling climate

    change, so any successful implementation of SC-OPFtechnology to reduce GB transmission losses in National

    Grids network operations process would be beneficial for all

    stakeholders. These efficiency savings can be compared to

    the result of Bansal et al [2], which showed that up to 1.7%

    MW loss savings can be achieved on a single pre-BETTA

    day-ahead network. The results in figure 2 cover more day-

    ahead networks than previous research, with a variety of

    demands spread across the year for post-BETTA day-ahead

    data covering the whole of GB. Figure 2 also shows that the

    minimising MW losses objective achieved not only an

    improvement in MW losses, but also increased system gain,

    and reduced the MVAR generation. Both these

    improvements (MW losses and MVAr generation) would

    save industry money, and this would be partly shared with

    National Grid through the incentive scheme described in [2].

    Figure 3 shows a strong correlation between lower MW

    losses and increased MVAR system gain. Figure 3 also

    shows that the SC-OPF is also achieving a beneficial increase

    in lagging MVAR reserves on the system with the minimise

    MW losses objective. This figure confirms, the expected

    relationship, that greater MVAR gain implies greater MVAR

    reserves. It is likely that the MW losses objective is reducing

    losses through reduced line currents by increasing the systemvoltage profile. The increased voltage profile increases the

    system MVAR gain, which reduces the MVAR generation

    requirement in the reactive balance, which in turn implies

    greater MVAR reserves.

    Further studies are needed to deepen our understanding

    about the state changes made by SC-OPF when applied to the

    National Grid transmission network when utilising a

    minimise transmission losses objective function. These

    studies are required to derive useful advice detailing optimal

    control patterns, which securely minimise transmission

    losses, the later part of this research will need to be carried

    out closely with TR in order to get continuous feedback and

    adapt advice accordingly. Future SC-OPF research is likely

    to investigate alternative objective functions such as reactive

    losses, and reactive generation costs. The results from these

    differing objectives will be used to assess their suitability forminimising transmission losses, and their effects on reactive

    reserve and system security. Effective solution procedures

    for optimization problems involving such multi-objective

    functions will also be explored.

    ACKNOWLEDGMENT

    The authors acknowledge the use of and user support for

    Nexants SCOPE software, which was used to perform the

    SC-OPF analysis in this research. The authors also wish to

    acknowledge the assistance and support of National Grid and

    the EPSRC.

    REFERENCES

    [1] DTI, Meeting the energy challenge - A White Paper on Energy 2007,published May 2007, p9, retrieved 6th December 2007 from

    www.berr.gov.uk.[2] J. Bansal, G.A. Taylor, Y.H. Song, H.B. Wan, A.M. Chebbo and M.E.

    Bradley, The scope for further loss minimisation on the National Gridtransmission system, UPEC 2006, Newcastle upon Tyne, UK, 6-8

    September 2006.[3] Ofgem, GB Security and Quality of Supply Standard, Version 1.0,

    published September 22 2004, retrieved 14th February 2008 fromwww.ofgem.gov.uk.

    [4] Ofgem, National Grid Electricity Transmission System Operator

    Incentives from 1 April 2007, published 27 February 2007, ref 35/07,retrieved 23rd January 2008 from www.ofgem.gov.uk.

    [5] J. Ramos, A. Gomez Exposito, V.H. Quintana, Transmission power

    loss reduction by interior-point methods: implementation issues andpractical experience, IEE Proceedings-Generator Transmission

    Distribution, Vol 152, No 1, pp 90-98, 2005.[6] N. Dandachi, Improved algorithm for the voltage/VAR management

    on the NGC system, IEE Colloqium, Issue 24, pp4/1 pp 4/6,1997.[7] O. Alsa, J. Bright, M. Praise, B. Stott, Further Developments in LP-

    Based Optimal Power Flow, IEEE Transaction on Power Systems,Vol 5, pp.697 711, 1990.

    [8] W.F. Tinney, Some Deficiencies In Optimal Power Flow, IEEETransactions on Power Systems, Vol 3, No 2, pp 676 683, 1988.

    [9] Ofgem, Zonal transmission losses assessment of proposals to modifythe Balancing and Settlement Code, published 23 February 2007,

    retrieved 21st February 2008 from www.ofgem.gov.uk.[10] R. Price, Network Operations Energy Requirements Transmission

    Losses Report, Internal National Grid document, 2007.[11] National Grid, Application of Security and Quality of Supply

    Standards in Operational Timescales, Internal National Grid document,National Grid, BP 1883 Issue 6 18 March 2005.

    [12] F. Ali, ELLA and COLDSTART User Guide, Internal National Griddocument, National Grid, Issue 2 Draft 1, November 2002.

    [13] Y. Song, M. Irving, Optimisation techniques for electrical powersystems Part 2 Heuristic optimisation methods, Tutorial:

    Optimisation techniques, IEE Power Engineering Journal, Vol.15,No.3, pp.151-160, 2001.

  • 7/28/2019 1_122_paper

    6/6

    2000

    4000

    6000

    8000

    10000

    12000

    14000

    0 10 20 30 40 50 60

    We ek Number

    MV

    ARgeneration,gainandMW

    Demand

    0

    200

    400

    600

    800

    1000

    1200

    1400

    MWlosses

    MVAR gain

    optimised

    MVAR gain

    MVAR

    generation

    optimised

    MVAR

    generation

    MW Demand

    - Scaled

    down

    MW Losses

    optimised

    MW losses

    Fig. 2. This graph shows Tuesday day-ahead results from SC-OPF studies spread at monthly intervals across 2007.

    -10

    0

    10

    20

    30

    40

    50

    60

    0 10 20 30 40 50 60

    Week Number

    %MV

    ARgainand%

    MVARreservechange

    uponoptimisation

    0

    0.5

    1

    1.5

    2

    2.5

    3

    %M

    W

    losseschangeuponoptimisation

    % MVARgain change

    % MVARReservechange

    % MW losssavings

    Fig. 3. Shows the same set of SC-OPF studies from figure 2. MVAR gain and MVAR reserve change % are on LHS axis, and MW loss change %

    on RHS axis. The changes relate the percentage change between the day-ahead study and the optimised study.