1118 malcolm barker maroon dam nzsold 2013 final
TRANSCRIPT
7/23/2019 1118 Malcolm Barker Maroon Dam NZSOLD 2013 Final
http://slidepdf.com/reader/full/1118-malcolm-barker-maroon-dam-nzsold-2013-final 1/28
Maroon Dam Performance and
Upgrade Design using Percentage
of Acceptable Flood Capacity –
Arewe there yet?
Malcolm Barker | GHD Principal Engineer – Dams
lireza Mojami | GHD Senior Engineer – Dams
Colin Thompson | Seqwater Senior Project Manager
7/23/2019 1118 Malcolm Barker Maroon Dam NZSOLD 2013 Final
http://slidepdf.com/reader/full/1118-malcolm-barker-maroon-dam-nzsold-2013-final 2/28
Maroon Dam NZSOLD 2013
Presentation Contents
- General Description
- Issues- Geotech Investigation
- Risk Analysis
- Acceptable Flood Capacity %
7/23/2019 1118 Malcolm Barker Maroon Dam NZSOLD 2013 Final
http://slidepdf.com/reader/full/1118-malcolm-barker-maroon-dam-nzsold-2013-final 3/28
Maroon Dam NZSOLD 2013
AFC Definition
The minimum requiredacceptable flood capacity
(AFC) all proposed and
existing referable dams in
Queensland must be able
to safely pass.
• Fallback (PMP-DF)
• Risk basis satisfy ALARP
Cost/Benefit Ratio <1.0
7/23/2019 1118 Malcolm Barker Maroon Dam NZSOLD 2013 Final
http://slidepdf.com/reader/full/1118-malcolm-barker-maroon-dam-nzsold-2013-final 4/28
Maroon Dam NZSOLD 2013
• Slope failure right abutment during construction
• Low strength clay horizons (8º friction - 13º J.Barry-Cooke)• Pore pressure uncertainty for high floods
• Low slope stability factors of safety Normal and Flood
loading
• Inadequate spillway capacity (36% to 51% AFC)
• Abutment piping Normal and Flood loading
• Spillway – back erosion into reservoir
The Issues
7/23/2019 1118 Malcolm Barker Maroon Dam NZSOLD 2013 Final
http://slidepdf.com/reader/full/1118-malcolm-barker-maroon-dam-nzsold-2013-final 5/28
Maroon Dam NZSOLD 2013
What did we do - Winston Churchill
True Genius resides in the capacity for theevaluation of
uncertain,
hazardous and
conflictingInformation”
7/23/2019 1118 Malcolm Barker Maroon Dam NZSOLD 2013 Final
http://slidepdf.com/reader/full/1118-malcolm-barker-maroon-dam-nzsold-2013-final 6/28
Maroon Dam NZSOLD 2013
Embankment Boreholes and Cross Sections
7/23/2019 1118 Malcolm Barker Maroon Dam NZSOLD 2013 Final
http://slidepdf.com/reader/full/1118-malcolm-barker-maroon-dam-nzsold-2013-final 7/28Maroon Dam NZSOLD 2013
Clay Occurrences
Three main sources of clay: – Landslide Clay – thicker up to 10 cm
– Shear zones – thinner up to 2 cm
– Extremely low strength claystone or clayey siltstone
7/23/2019 1118 Malcolm Barker Maroon Dam NZSOLD 2013 Final
http://slidepdf.com/reader/full/1118-malcolm-barker-maroon-dam-nzsold-2013-final 8/28Maroon Dam NZSOLD 2013
Claystone
7/23/2019 1118 Malcolm Barker Maroon Dam NZSOLD 2013 Final
http://slidepdf.com/reader/full/1118-malcolm-barker-maroon-dam-nzsold-2013-final 9/28Maroon Dam NZSOLD 2013
Investigation findings – Clayey
Layers
Detailed examination (samples pulled apart)
• Weathered fissured/shattered siltstone or
claystone.
• Some polished surfaces and/or slickenslided
surfaces.
• Striations on some surfaces.
• Little effort is required to break down the
shattered/fissured stiff clay fragments to a softsilty clay.
7/23/2019 1118 Malcolm Barker Maroon Dam NZSOLD 2013 Final
http://slidepdf.com/reader/full/1118-malcolm-barker-maroon-dam-nzsold-2013-final 10/28Maroon Dam NZSOLD 2013
Clay Variation along Potential Failure Plane
Potential Failure surface
Zone Lower Strength
weighting
Expected Strength
weighting
Upper Strength
weightingLandslide 30% 20% 17%
Clay Zone 60% 50% 36%
Shear Zone 10% 30% 47%
7/23/2019 1118 Malcolm Barker Maroon Dam NZSOLD 2013 Final
http://slidepdf.com/reader/full/1118-malcolm-barker-maroon-dam-nzsold-2013-final 11/28Maroon Dam NZSOLD 2013
Strength Test Results
50 200 400 800
7/23/2019 1118 Malcolm Barker Maroon Dam NZSOLD 2013 Final
http://slidepdf.com/reader/full/1118-malcolm-barker-maroon-dam-nzsold-2013-final 12/28
Maroon Dam NZSOLD 2013
Risk Analysis
Be thankful for the problems for if
they were less difficult, someoneelse with less ability would have
your job
7/23/2019 1118 Malcolm Barker Maroon Dam NZSOLD 2013 Final
http://slidepdf.com/reader/full/1118-malcolm-barker-maroon-dam-nzsold-2013-final 13/28
Maroon Dam NZSOLD 2013
Risk Analysis Flood Hydrology and %AFC Approach
7/23/2019 1118 Malcolm Barker Maroon Dam NZSOLD 2013 Final
http://slidepdf.com/reader/full/1118-malcolm-barker-maroon-dam-nzsold-2013-final 14/28
Maroon Dam NZSOLD 2013
Risk Analysis Failure Modes
Flood Normal Failure Mode Description
F1 Flood overtopping
F2a F3a Downstream stability main dam
F2b F3b Downstream stability left abutment
F2c F3c Downstream stability right abutmentF4a F5a Piping through embankment dessication cracking
F4b F5b Piping through embankment poorly compacted layer
F4c F5cPiping through embankment poorly compacted layer along
conduit
F4d F5dPiping through embankment cracking induced byfoundation movements
E5dPiping through embankment cracking induced by foundation
movements during earthquake
F6 F6 Piping through foundation right abutment
F7 F7 Spillway Back Erosion
7/23/2019 1118 Malcolm Barker Maroon Dam NZSOLD 2013 Final
http://slidepdf.com/reader/full/1118-malcolm-barker-maroon-dam-nzsold-2013-final 15/28
Maroon Dam NZSOLD 2013
Existing Risk
7/23/2019 1118 Malcolm Barker Maroon Dam NZSOLD 2013 Final
http://slidepdf.com/reader/full/1118-malcolm-barker-maroon-dam-nzsold-2013-final 16/28
Maroon Dam NZSOLD 2013
Existing Risk Contributions
Piping Foundation 68.3%
Slope Stability 29.2%
Overtopping 1.5%
7/23/2019 1118 Malcolm Barker Maroon Dam NZSOLD 2013 Final
http://slidepdf.com/reader/full/1118-malcolm-barker-maroon-dam-nzsold-2013-final 17/28
Maroon Dam NZSOLD 2013
Proposed Solution
Stage 1
Stage 2
7/23/2019 1118 Malcolm Barker Maroon Dam NZSOLD 2013 Final
http://slidepdf.com/reader/full/1118-malcolm-barker-maroon-dam-nzsold-2013-final 18/28
Maroon Dam NZSOLD 2013
Risk Contributions after Stage 1 Upgrade
Slope Stability 81.1%
Overtopping 10.3%
7/23/2019 1118 Malcolm Barker Maroon Dam NZSOLD 2013 Final
http://slidepdf.com/reader/full/1118-malcolm-barker-maroon-dam-nzsold-2013-final 19/28
Maroon Dam NZSOLD 2013
AFC Schedule for Upgrade Works
Tranche Required minimum flood
discharge capacity
Date by which the required
minimum flood capacity is to be in
place for existing dams
1 25% of AFC or at least
1:2000 AEP for erodible dam
embankments (whichever is
the bigger flood)
1 October 2015
2 65% of AFC 1 October 2025
3 100% of AFC 1 October 2035
AFC Fallback Compliance
7/23/2019 1118 Malcolm Barker Maroon Dam NZSOLD 2013 Final
http://slidepdf.com/reader/full/1118-malcolm-barker-maroon-dam-nzsold-2013-final 20/28
Maroon Dam NZSOLD 2013
Cumulative Risk Contribution 95% at RL 218.65m
7/23/2019 1118 Malcolm Barker Maroon Dam NZSOLD 2013 Final
http://slidepdf.com/reader/full/1118-malcolm-barker-maroon-dam-nzsold-2013-final 21/28
Maroon Dam NZSOLD 2013
Reservoir Start Level for Probabilistic Analysis
7/23/2019 1118 Malcolm Barker Maroon Dam NZSOLD 2013 Final
http://slidepdf.com/reader/full/1118-malcolm-barker-maroon-dam-nzsold-2013-final 22/28
Maroon Dam NZSOLD 2013
Percentage AFC Compliance (Fallback)
Description Start Reservoir Level
Initial water level 217.5 m AHD
AFC guideline start level
215 m AHD
probabilistic analysis start levelPeak water level 218.65 m AHD 218.65 m AHD
Peak inflow 516 m³/s 1,075 m³/s
Peak outflow 252 m³/s 252 m³/s
Hydrograph duration 6 hours 6 hours
Percentage AFC 15.7% 32.7%
7/23/2019 1118 Malcolm Barker Maroon Dam NZSOLD 2013 Final
http://slidepdf.com/reader/full/1118-malcolm-barker-maroon-dam-nzsold-2013-final 23/28
Maroon Dam NZSOLD 2013
Risk Analysis Flood Hydrology and %AFC Approach
Reduction25%
7/23/2019 1118 Malcolm Barker Maroon Dam NZSOLD 2013 Final
http://slidepdf.com/reader/full/1118-malcolm-barker-maroon-dam-nzsold-2013-final 24/28
Maroon Dam NZSOLD 2013
AFC % with Risk Analysis URS 25%
7/23/2019 1118 Malcolm Barker Maroon Dam NZSOLD 2013 Final
http://slidepdf.com/reader/full/1118-malcolm-barker-maroon-dam-nzsold-2013-final 25/28
Maroon Dam NZSOLD 2013
URS 25% Compliance Flood Frequency data
25%
7/23/2019 1118 Malcolm Barker Maroon Dam NZSOLD 2013 Final
http://slidepdf.com/reader/full/1118-malcolm-barker-maroon-dam-nzsold-2013-final 26/28
Maroon Dam NZSOLD 2013
Staging Compliance
AFC requirement 25% AFC 65% AFC 100% AFCDate for Compliance 2015 2025 2035
Flood frequency data
URS <25%
Abutment upgrade
65% OK <100%
Slope stability upgrade
GHD OK
60% AFC
<65%
Abutment
upgrade
<100%
Slope stability upgrade
Overtopping upgrade
Probabilistic analysis
existing spillway
RL 217.5 m
OK
60% AFC
<65%
Abutment
upgrade
<100%
Slope stability upgrade
(overtopping upgrade
may not be required)
7/23/2019 1118 Malcolm Barker Maroon Dam NZSOLD 2013 Final
http://slidepdf.com/reader/full/1118-malcolm-barker-maroon-dam-nzsold-2013-final 27/28
Maroon Dam NZSOLD 2013
Conclusions
• Maroon Dam upgrade required by 2015.
• Extensive geological modelling and analysis was used to
evaluate the nature and extent of low strength clay.
• Probabilistic flood frequency used for Risk Analysis and
AFC compliance analysis.
• The percentage AFC compliance using the risk analysis
approach was successfully used to confirm the proposed
staging of the works
•
This approach has also identified the potential fordeferral or elimination of part of the final stage of the
upgrade works in 2035 on a risk basis.
7/23/2019 1118 Malcolm Barker Maroon Dam NZSOLD 2013 Final
http://slidepdf.com/reader/full/1118-malcolm-barker-maroon-dam-nzsold-2013-final 28/28
Maroon Dam NZSOLD 2013
Stage 1 by 2015
• Abutment grouting and pressure relief systems to EL 219.5 m
• Stability upgrade with a 33 m wide berm using material
borrowed from the spillway chute