111205-30-yg-qph-met-010 erection of hvac itp rev 01

6
K&M ENGINEERING AND CONSULTING This document contains proprietary information of METKA S.A. and is to be used solely for the Project and the purpose for which it is furnished. It may not be disclosed to others for a different use without the written permission of METKA S.A. Project: SAMRA POWER STATION PHASE III ADD ON COMBINED CYCLE PROJECT Title: ERECTION OF HVAC INSPECTION AND TEST PLAN KKS Document No: 111205-30- YG-QPH-MET-010 Rev: 1 METKA Document No: SEPCO Document No: Purpose of issue: General Use Date: 2014-2-3 Prepared: QA/QC DEPARTMENT Reviewed: DIMITRIS KOUKLAKIS Approved: DIMITRIS POULAKIS

Upload: amer-y-k

Post on 18-Apr-2017

216 views

Category:

Documents


3 download

TRANSCRIPT

Page 1: 111205-30-Yg-qph-met-010 Erection of Hvac Itp Rev 01

K&M ENGINEERING AND CONSULTING

This document contains proprietary information of METKA S.A. and is to be used solely for the Project and the purpose for which it is furnished. It may not be disclosed to others for a different use without the written permission of METKA S.A.

Project:

SAMRA POWER STATION PHASE III ADD ON COMBINED CYCLE PROJECT

Title:

ERECTION OF HVAC INSPECTION AND TEST PLAN

KKS Document No: 111205-30- YG-QPH-MET-010 Rev: 1

METKA Document No:

SEPCO Document No:

Purpose of issue: General Use Date: 2014-2-3

Prepared: QA/QC DEPARTMENT

Reviewed: DIMITRIS KOUKLAKIS

Approved: DIMITRIS POULAKIS

Page 2: 111205-30-Yg-qph-met-010 Erection of Hvac Itp Rev 01

SAMRAPOWERSTATIONPHASEIIIADDONCOMBINEDCYCLEPROJECT

c

This document contains proprietary information of METKA S.A. and is subject to the restrictions set forth on the title page

CLASSIFICATION

Contains information for the design of structures, systems or components: Yes No

Design verification : Not applicable Head of OU/Supervisor Verifier Level 1 Level 2

CONTROL OF MODIFICATIONS

Revision Modifications

1

First issue

PRELIMINARY OR PENDING INFORMATION

Revision Paragraphs Subject Status

1

Fields identified as pending or blank

DISTRIBUTION

External Internal No. copies/Format

Page 3: 111205-30-Yg-qph-met-010 Erection of Hvac Itp Rev 01

SAMRAPOWERSTATIONPHASEIIIADDONCOMBINEDCYCLEPROJECT

c

This document contains proprietary information of METKA S.A. and is subject to the restrictions set forth on the title page

TABLE OF CONTENTS 

ERECTION OF HVAC

INSPECTION AND TEST PLAN

 

Page 4: 111205-30-Yg-qph-met-010 Erection of Hvac Itp Rev 01

KKS No: 111205-30-YG-QPH-MET-010

Revision: 1

Date: 3/2/2014

Point Standards / Specifications

/ Procedures Document / Record Subcontractor METKA SEPCO Notes

1

1.1 Drawings / Packing List E

1.2 Certificates R R

2

2.1 Drawings, Erection Manual E SW SW

2.1.1 Drawings, Erection Manual E SW SW

2.1.2 Drawings, Erection Manual E SW SW

2.1.3 Drawings, Erection Manual E SW SW

2.1.4 Drawings, Erection Manual E SW SW

2.2 Drawings, Erection Manual E SW SW

2.2.1 Drawings, Erection Manual E SW SW

2.2.2 Drawings, Erection Manual E SW SW

INSPECTION AND TEST PLAN

SAMRA POWER STATION PHASE III ADD ON COMBINED CYCLE PROJECT: Erection of HVAC

Αctivity

Materials Certificates Control

Site Delivery and incoming inspection

Visual inspection/Quantity inspection

Casing insatllation

Motor installation

Installation of equipment

Air Handling Units

Casing (installation, fixing, sealing)

Axial Fans

Centrifugal fans installation

Air heating coils installation

Pre filters, Filters, dampers

Page 5: 111205-30-Yg-qph-met-010 Erection of Hvac Itp Rev 01

KKS No: 111205-30-YG-QPH-MET-010

Revision: 1

Date: 3/2/2014

Point Standards / Specifications

/ Procedures Document / Record Subcontractor METKA SEPCO Notes

INSPECTION AND TEST PLAN

SAMRA POWER STATION PHASE III ADD ON COMBINED CYCLE PROJECT: Erection of HVAC

Αctivity

2.3 Drawings, Erection Manual E SW SW

2.3.1 Drawings, Erection Manual E SW SW

2.3.2 Drawings, Erection Manual E SW SW

2.4 Drawings, Erection Manual E SW SW

2.5 Drawings, Erection Manual E SW SW

2.6 Drawings, Erection Manual E SW SW

2.6.1 Drawings, Erection Manual E SW SW

2.7 Drawings, Erection Manual E SW SW

2.8 Drawings, Erection Manual E SW SW

2.9 Drawings, Erection Manual E SW SW

Installation , fixing, fittings

Natural Smoke & Heat Ventilators Installation

VRV Units Installation

Heat Exchanger Units Installation

Packaged Units Installation

Ductwork and Accessories

Casing installation

Enclosure smoke & Heat Exhaust Centrifugal Fans

Motor installation

Grilles / Smoke Dampers Installation

Page 6: 111205-30-Yg-qph-met-010 Erection of Hvac Itp Rev 01

KKS No: 111205-30-YG-QPH-MET-010

Revision: 1

Date: 3/2/2014

Point Standards / Specifications

/ Procedures Document / Record Subcontractor METKA SEPCO Notes

INSPECTION AND TEST PLAN

SAMRA POWER STATION PHASE III ADD ON COMBINED CYCLE PROJECT: Erection of HVAC

Αctivity

3

3.1 Drawings E SW SW

3.2 Drawings E SW SW

4

4.1 Drawings E W W

4.2 Inspection & Test Plan Final Erection Quality Dossier E H R

Νotes

AbbreviationsE : Works Exexution W : Witness point SW : Spot Witness point

R : Records review Η : Hold point

Prepared byDKOU

4

3

Modifications Approved by Date

Final inspection

Walk down / System Verification

Revision

2

1 DPOU 3/2/2014

Alignment - Adjustment -Slope

Installation

Supports

Technical File