MAI Location Chakan Fact - Files Production 2010-2011 SS/ 08.Feb. 2011

Upload: suresh-sivadasan

Post on 07-Apr-2018

230 views

Category:

Documents


0 download

TRANSCRIPT

8/6/2019 110203 MAI Chacan Fact -Files Backup

http://slidepdf.com/reader/full/110203-mai-chacan-fact-files-backup 1/20

8/6/2019 110203 MAI Chacan Fact -Files Backup

http://slidepdf.com/reader/full/110203-mai-chacan-fact-files-backup 2/20

Fact - File SBC

Production in Chakan plant

  1H10

2H10 Total10

 Jan-11

Feb-11

Mar-11

2Q11 2H11 Total11

PRODUCTION ( Mio Pieces)Budget ( MioPieces)

0.4 12.2 12.6 2.4 3 3 7.9 16.8 33.1

Production ( MioPieces)

0.56 12.55 13.1 1.4 - - - - -

Forecast ( MioPieces)

- - - 2.46 2.72 3.05 8.84 17.95 35

MANPOWERStaff Budget 4 6 6 6 6 6 6 6 6

Staff Actual 3.5 5 5 5 - - - - -

Operatives Budget 2 6 6 10 10 10 12 12 12

Operatives Actual 1 6 6 6 - - - - -

SCRAP RATIO ( %)

 Scrap RatioTarget ( %)

0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5

Scrap RatioActual ( %)

0.38 0.2 0.29 - - - - -

EXTERNAL PPMPPM Target 2 2 2 10 10 10 10 10 10PPM Actual 0 0 0 - - - - - -

Capacity coating system SBC: > 50 Mio pieces/year 

8/6/2019 110203 MAI Chacan Fact -Files Backup

http://slidepdf.com/reader/full/110203-mai-chacan-fact-files-backup 3/20

SBC PRODUCTION 2010/11

SS/Operations06/22/11 3

8/6/2019 110203 MAI Chacan Fact -Files Backup

http://slidepdf.com/reader/full/110203-mai-chacan-fact-files-backup 4/20

SBC OPERATIVE MANPOWER

• Only Operative Team

• Common Staff Like

Maintenance /

Logistic / Quality

function are divided in

equal proportions.

• Mubea + Contactor employees considered

Operative ManpowerDetails

SS/Operations06/22/11 4

8/6/2019 110203 MAI Chacan Fact -Files Backup

http://slidepdf.com/reader/full/110203-mai-chacan-fact-files-backup 5/20

SBC STAFF MANPOWER

• Only White collar 

• Common Staff Like

Maintenance /

Logistic / Quality

function are divided in

equal proportions.

Staff manpower Details

SS/Operations06/22/11 5

8/6/2019 110203 MAI Chacan Fact -Files Backup

http://slidepdf.com/reader/full/110203-mai-chacan-fact-files-backup 6/20

8/6/2019 110203 MAI Chacan Fact -Files Backup

http://slidepdf.com/reader/full/110203-mai-chacan-fact-files-backup 7/20

SBC PPM

06/22/11 7SS/Operations

8/6/2019 110203 MAI Chacan Fact -Files Backup

http://slidepdf.com/reader/full/110203-mai-chacan-fact-files-backup 8/20

Fact - File VS

Production in Chakan plant

 

1H10 2H10 Total10  Jan-11 Feb-11 Mar-11 2Q11 2H11 Total11

PRODUCTION ( Mio Pieces)Budget ( MioPieces)

1.9 4.25 6.15 0.8 1.3 1.5 4.4 8 16

Production ( MioPieces)

2.22 4.39 6.6 0.6 - - - - -

Forecast ( Mio

Pieces)

- - - 0.6 1.3 1.4 4.1 9 16

MANPOWERStaff Budget 7 8 8 8 8 8 8 8 8

Staff Actual 6.5 7.5 7.5 7.5 - - - - -

Operatives Budget 3 7 7 7 10 10 10 10 10

Operatives Actual 3 7 7 7 - - - - -

SCRAP RATIO ( %)

 Scrap RatioTarget ( %)6% 6% 6% 2% 2% 2% 2% 2% 2%

Scrap RatioActual ( %)

1.49%

1.34% 1.41% 1.2% - - - - -

EXTERNAL PPMPPM Target 2 2 2 2 2 2 2 2 2PPM Actual 0 0 0 0 - - - - -

Capacity VS line: 1piece / Sec; GEFF 75 %; 21 WD;16.5 Mio pieces/year 

8/6/2019 110203 MAI Chacan Fact -Files Backup

http://slidepdf.com/reader/full/110203-mai-chacan-fact-files-backup 9/20

VS Production 2010/11

06/22/11 9SS/Operations

8/6/2019 110203 MAI Chacan Fact -Files Backup

http://slidepdf.com/reader/full/110203-mai-chacan-fact-files-backup 10/20

VS STAFF MANPOWER

06/22/11 10

• Only White collar 

• Common Staff Like

Maintenance /

Logistic / Quality

function are divided in

equal proportions.

Staff manpower Details

SS/Operations

8/6/2019 110203 MAI Chacan Fact -Files Backup

http://slidepdf.com/reader/full/110203-mai-chacan-fact-files-backup 11/20

VS OPERATIVE MANPOWER

06/22/11 11

• Only Operative Team

• Common Staff Like

Maintenance /

Logistic / Quality

function are divided in

equal proportions.

• Mubea + Contactor employees considered

Operative ManpowerDetails

SS/Operations

8/6/2019 110203 MAI Chacan Fact -Files Backup

http://slidepdf.com/reader/full/110203-mai-chacan-fact-files-backup 12/20

VS SCRAP %

06/22/11 12

Action – UPS Back up provided 

SS/Operations

8/6/2019 110203 MAI Chacan Fact -Files Backup

http://slidepdf.com/reader/full/110203-mai-chacan-fact-files-backup 13/20

VS PPM

06/22/11 13SS/Operations

8/6/2019 110203 MAI Chacan Fact -Files Backup

http://slidepdf.com/reader/full/110203-mai-chacan-fact-files-backup 14/20

Continuous improvment and Trainee

Programm s Chakan Plant

Trainee program for coling process.

2 Trainee´s to Bedano from week 7 to week 15 2 Trainees Under Hot presetting machine ( Under Mr Prasad)

Continuous improvment results (last 8 weeks) :

reduction HPS setting time from 1.5 hour to 0.5hour due to standard

setting sytem

better pipe system to avoid stopage of line. Achieved Zero rejection of Fall down spring ( Before – After -

8/6/2019 110203 MAI Chacan Fact -Files Backup

http://slidepdf.com/reader/full/110203-mai-chacan-fact-files-backup 15/20

Forcast Stock of SBC

All values in millions Revised forecast date 02.02.2011

SBC INVENTORY ANALYSIS 

Feb Mar Apr May1Forecast Sales 2.86 3.10 3.25 2.59  Slow Moving 0.44 0.55 0.48 0.56

  Moving 2.42 2.55 2.77 2.03

2ORDER / TANSIST 1.9 0.56 0.2 

3Total Stock ( Chakan +CGN)

13.55 12.59 10.05 7.00

 Slow Moving 5.68 5.24 4.69 4.21

  Moving 7.87 7.35 5.36 2.78

4Closing Stock 12.59 10.05 7.00 4.40  Slow Moving 5.24 4.69 4.21 3.65

  Moving 7.35 5.36 2.78 0.75

Actions For Inventory Reduction

Weekly Order strategy -Implemented

Slowing inventory to be sold other required Mubea locations- Under

progressClear DSI implementation

8/6/2019 110203 MAI Chacan Fact -Files Backup

http://slidepdf.com/reader/full/110203-mai-chacan-fact-files-backup 16/20

Investigation DSI Target ´s for VS

DSI total (sales base 4.Q11)= 33 DSI DSI transit = 6 DSI DSI inhouse = 27 DSI

Actual DSI: 34

Lead time in total; wire ordering to shipping FG VS to EU: 114 days (5,7 month)

Detailed steps of suplier- chain

days DSI related

Average time order and processing VS-W 50 NO

Suncall/Japan 80%; Suzuki-Garphytan/China 20%

Transit /Shipping Japan/China – India 20 NO

Customs/Clearance & Transit Mumbai pune 9 YES

Stock raw material Chakan 20 YES

Production 5 YES

Stock FG Chakan (incl. monthly Container fill up) 10 YES

8/6/2019 110203 MAI Chacan Fact -Files Backup

http://slidepdf.com/reader/full/110203-mai-chacan-fact-files-backup 17/20

Investigation DSI Target ´s for SBC

DSI total (sales base 4.Q11)= 60 DSI transit = 27 DSI inhouse = 33

Actual DSI : 74 days

Lead time in total; order uncoated SBC to domestic indian customer (north): 94 days

Detailed steps of supplier chain days DSI related

Average time order and processing SBC uncoated 26 NO

MUB-Taican60%; MUB Attendorn 40%

Average Transit /Shipping from China/Germany - India 24 YES

Customs/Clearance 5 YES

Transit Mumbai-Pune 2 YES

Stock raw material Chakan 20 YES

Production 2 YES

Stock FG Chakan (35% Volumes) 10 YES

Transit FG Dehli (65% Volumes) 5 YES

Stock FG Delhi (65% Volumes) 10 (target) YES

8/6/2019 110203 MAI Chacan Fact -Files Backup

http://slidepdf.com/reader/full/110203-mai-chacan-fact-files-backup 18/20

 Project Plan Stab Bar 

06/22/11 18SS/Operations

8/6/2019 110203 MAI Chacan Fact -Files Backup

http://slidepdf.com/reader/full/110203-mai-chacan-fact-files-backup 19/20

Layout for Stab Bar project

(project plan see extra chart )

Stab bar production• end heating (Oven LPG)• end punching (Press)• bending ( Pulzer )• correction (Correction Work Station)• process flow from backside to front