110 - marine and coasts · 2017-03-28 · 2.12 piles are assumed to be free issue at portsea,...

36

Upload: others

Post on 25-Dec-2019

1 views

Category:

Documents


0 download

TRANSCRIPT

Figure 5. Shoreline Movement history at Point Franklin

60.0

70.0

80.0

90.0

100.0

110.0

Department of Environment,

Land, Water and Planning

Portsea Front Beach

Remediation

Long Term Options Assessment

Advisian 49

THIS PAGE LEFT BLANK

Department of Environment,

Land, Water and Planning

Portsea Front Beach

Remediation

Long Term Options Assessment

Costing Appendix C:

Department of Environment,

Land, Water and Planning

Portsea Front Beach

Remediation

Long Term Options Assessment

Advisian 51

THIS PAGE LEFT BLANK

C:\Users\mathew.cuolahan\Documents\Working folder\301311-11231 Portsea Front Beach Options\06. Cost Estimates\301311-11231 Portsea Front Beach Options Estimates Rev B.xlsx

CLASS 2a EVALUATE Estimate +/-30%

SYNOPSIS

PROJECT DESCRIPTION

Disclaimer

M. Cuolahan L. Nielsen

M. Cuolahan L. Nielsen L. Nielsen

Project 301311-11231 - Portsea Front Beach Options Assessment

For further detail please refer to the Portsea Front Beach Options Assessment report.

This report has been prepared on behalf of and for the exclusive use of Victorian State Government Department of Environment, Land, Water and Planning., and is subject to and issued in accordance with the agreement between Victorian State Government Department of Environment, Land, Water and Planning. and WorleyParsons. This document is not to be used, copied or relied upon except in accordance with the contract.

CLIENT APPROVAL DATEDESCRIPTION ORIG REVIEW WP APPROVAL DATEREV

B Issued for customer review 9-Sep-16

A Issued for internal review 01-Aug-16

This document presents the EVALUATE (+/-30%) Estimate.The estimates have been developed for the Victorian State Government Department of Environment, Land, Water and Planning.This doument provides an understanding of the cost items by option for total insatalled costs. It cannot be relied on to make any financial decisions without further analysis and understanding of the qualifications, exclusions and scope issues.

C:\Users\mathew.cuolahan\Documents\Working folder\301311-11231 Portsea Front Beach Options\06. Cost Estimates\301311-11231 Portsea Front Beach Options Estimates Rev B.xlsx Page 3

Date: 09-September-2016Rev: BBy: M. CuolahanChecked: L. Nielsen

1.0 Estimate Key Qualifications

1.01 Estimate accuracy is concept screening level (WOR EVALUATE phase) and based on conceptual information.

1.02 Estimate base date is July 2016.

1.03 Direct manual labour rates and unit rates are based on recent ‘typical’ historical data.

1.04 Labour productivities are based on historical data (PF @ 1.4)

1.05 No detailed Contract and Procurement plans have been developed as part of this estimate, therefore the estimate is based on typical.

1.06 No detail mobile piling, cranage & rigging studies were completed.

1.07 No geotechnical investigations were completed.

1.08 No formal logistics study has been completed.

1.09 No project or construction schedule developed to support estimate basis.

1.10 Estimate allows for EPCM execution. (Engineering, Procurement, Construction and Management)

1.11 Contracting Strategy is by Sub-Contracts.

1.12 Contingency was included as per WOR estimate classifications.

1.13 Estimate allows for Common Distirbutables Costs. This scope covers:

1.13.1 Temporary Construction facilities

1.13.2 Construction support

1.13.3 Inductions (Cost for manual labour to attend site specific inductions when not included in contractor distributable costs.)

2.00 Estimate Assumptions

2.01 Unit weight used in estimate for rock is 2.6 MT per CM.

2.02 Supply rate of rock armour (shot rock) is between $AUD 30 - 50 per MT - $AUD 35 per MT has been used.

2.03 Pricing will be subject to quantity purchased and location of hard rock quarry.

2.04 Dredging sub contractor distributlabes, accommodation, maintenance and fuel - Included in dredging rates

2.05 Dredging downtime for seastate i.e. environmental / Fish / Whale migration and inclement weather included.

2.06 Piling / sheet supply and install rates are from historical / contracted rates

2.07 The pricing reflects the cost of driving piles / sheets as per scope i.e. no ancillary work such as support work for precast, concreting of pile toes, etc. has not been costed.

2.08 The impact of shipping operations or beach use during summer has not been assessed or allowed for in the productivities used. Assume beach will be closed.

2.09 The assumptions made about the availability of works areas have not been validated.

2.10 A pile / sheet driving analysis has not been carried out .

2.11 Detailed methods, the sequence of construction and overall project program duration have not been evaluated as yet. As such the pricing does not reflect plant and labour balancing for the project durations,

2.12 Piles are assumed to be free issue at Portsea, within 1km of the site and can be road transported to site in full lengths.

2.13 Dredging Ship Mob assumed from local port.

2.14 Dredging rates are based on local historical data.

3.00 Estimate Exclusions

3.01 Variations to exchange rates other than those nominated in the estimate.

3.02 Owners costs is excluded.

3.03 No allowance for any variation to scope.

3.04 No allowances for deferred capital costs.

3.05 Finance and interest charges for project duration.

3.06 No allowance for salvage value for any demolished equipment and materials.

Portsea Front Beach Options AssessmentWORLEYPARSONS JOB NUMBER: 301311-11231

ESTIMATE BASIS EVALUATE Estimate +/-30% Location: Portsea, Victoria

C:\Users\mathew.cuolahan\Documents\Working folder\301311-11231 Portsea Front Beach Options\06. Cost Estimates\301311-11231 Portsea Front Beach Options Estimates Rev B.xlsx Page 4

3.07 Any special environmental requirements.

3.08 Costs of environmental testing.

3.09 Any environmental requirement not identified in this estimate.

3.10 Taxes / Import duties.

3.11 No allowance for abnormal land and seastate weather conditions.

3.12 No allowance has been made for soil remediation for any in situ contaminants if required.

3.13 No allowance has been included for extended periods of industrial unrest.

3.14 No allowance has been made for delay costs associated with obtaining statutory approvals

3.15 Sunk costs (eg. Cost of this and previous studies etc.)

3.16 Market forces & escalation.

3.17 Assessment of total direct manhours for dredging.

C:\Users\mathew.cuolahan\Documents\Working folder\301311-11231 Portsea Front Beach Options\06. Cost Estimates\301311-11231 Portsea Front Beach Options Estimates Rev B.xlsx Page 5

Date: 09-September-2016Revision: BOriginator: M. CuolahanChecked: L. NielsenCurrency: AUD

3 4 10 13 14 15 16 17 18 19 20 21 22 23

Item Major Commodities Qty UoM Unit Man Hrs Man Hours Labour

Rate Plant &

Equipment Vendor Reps Bulk Material Freight Labour Contractor Distribs

Const. Equipment

Sub Total Direct Cost

Common Distributables EPCM Costs Owner's Costs Contingency Escalation Sub Total

Indirect Costs Total Installed

Costs

DIRECT COSTS INDIRECT COSTS

A. Configuration Dredging Offshore 1 LOT 1,610 1,610 80 - - 44,993,018 29,942 128,800 346,840 5,579,800 51,078,400 2,553,920 7,661,760 - 15,323,520 - 25,539,200 76,617,600 67% 3% 10% 0% 20% 0% 33%

B. Detached Rubblemound Breakwater 1 LOT 5,221 5,221 80 - - 3,150,300 315,030 417,680 1,096,824 1,426,000 6,405,834 320,292 960,875 - 1,921,750 - 3,202,917 9,608,750 67% 3% 10% 0% 20% 0% 33%

C. Detached SPW Breakwater 1 LOT 11,717 11,717 80 - - 1,663,309 166,331 937,333 2,032,199 1,736,500 6,535,672 326,784 980,351 - 1,960,702 - 3,267,836 9,803,508 67% 3% 10% 0% 20% 0% 33%

D. Attached Rubblemound Breakwater 1 LOT 12,248 12,248 80 - - 6,790,750 679,075 979,800 1,878,640 12,103,750 22,432,015 1,121,601 3,364,802 - 6,729,605 - 11,216,008 33,648,023 67% 3% 10% 0% 20% 0% 33%

E. Portsea Front Beach Headline Rock Groyne 1 LOT 2,444 2,444 80 - - 7,322,625 125,063 195,500 696,900 1,207,500 9,547,588 477,379 1,432,138 - 2,864,276 - 4,773,794 14,321,381 67% 3% 10% 0% 20% 0% 33%

F. Port Franklin Headland Rock Groyne 1 LOT 2,846 2,846 80 - - 11,077,375 132,538 227,700 754,860 2,645,000 14,837,473 741,874 2,225,621 - 4,451,242 - 7,418,736 22,256,209 67% 3% 10% 0% 20% 0% 33%

G. Sand Nourishment 1 LOT 805 805 80 - - 21,240,500 14,950 64,400 230,920 2,150,500 23,701,270 1,185,064 3,555,191 - 7,110,381 - 11,850,635 35,551,905 67% 3% 10% 0% 20% 0% 33%

H. Rock Revetment 1 LOT 2,979 2,979 80 - - 876,875 87,688 238,317 543,970 28,750 1,775,600 88,780 266,340 - 532,680 - 887,800 2,663,399 67% 3% 10% 0% 20% 0% 33%

I. Rock Revetment with sand nourishment 1 LOT 3,784 3,784 80 - - 22,070,225 97,923 302,717 659,890 2,179,250 25,310,005 1,265,500 3,796,501 - 7,593,001 - 12,655,002 37,965,007 67% 3% 10% 0% 20% 0% 33%

J. Configuration Dredging Nearshore 1 LOT 1,400 1,400 92 - - 299,418 29,942 128,800 346,840 15,088,000 15,893,000 15,893,000 0% 0%

Portsea Front Beach Options AssessmentWORLEYPARSONS JOB NUMBER: 301311-11231

EVALUATE Estimate +/-30% Estimate Detailed Summary

SCOPE BASE UNIT RATES DIRECT COSTS (AUD)

C:\Users\mathew.cuolahan\Documents\Working folder\301311-11231 Portsea Front Beach Options\06. Cost Estimates\301311-11231 Portsea Front Beach Options Estimates Rev B.xlsx Page 6

Portsea Front Beach Options AssessmentWORLEYPARSONS JOB NUMBER: 301311-11231

ESTIMATE DETAILS BY COMMODITY EVALUATE Estimate +/-30% Location: Portsea, VictoriaDate: 09-September-2016Rev: BBy: M. CuolahanChecked: L. NielsenCurrency : AUD

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23

Facility Pricing Basis

Quantity Basis

Commodity Code - Description

Details Qty UoM Unit Price, UP ($)

Base Unit Hrs, BUH

Loc. Factor,

LF

Prod. Factor,

PF

Unit Man hrs, UMH

Man hrs, MH

Labour Rate, LR

Contract.Distribs

(% of direct LC)

Plant & Equipment,

PE

Vendor Reps, VR

Bulk Material, BM

Freight, FC

Labour, LC

Contractor Distribs,

CD

Construction Equipment, CE

Total, TC=

Unit Cost (Cost Per

Unit)

% of TICs % of Direct Costs

DIRECT COSTS

A. Configuration Dredging Offshore

A CD Preliminaries (Included in Subcontractor Distribs) 1 LOT 100,000 - 1.00 1.40 - - 80.00 180% n/a - - - 100,000 - 100,000 100,000 0.0% 0.1%A CD Site Establishment/dis-establishment 1 LOT 370,000 - 1.00 1.40 - - 80.00 180% n/a - - - - 370,000 370,000 370,000 0.0% 0.2%

SD H CD Configuration Dredging/place sand on beach 300,000 CM 10 - 1.00 1.40 - - 80.00 180% n/a - - - - 3,000,000 3,000,000 10 0.0% 1.7%SC H CD Sidecasting 260,000 CM 5.70 - 1.00 1.40 - - 80.00 180% n/a - - - - 1,482,000 1,482,000 6 0.0% 0.8%

E CD Foredune planting and fencing 20,000 SM 13.02 0.05 1.00 1.40 0.07 1,400.0 80.00 180% n/a 260,364 26,036 112,000 201,600 - 600,000 30 0.0% 0.3%E CD Maintenance - redo every 6 years for 44 years 7 LOT 5,552,000 - 1.00 1.40 - - 80.00 180% n/a 38,864,000 - - - - 38,864,000 5,552,000 0.0% 21.9%

DA DA AZ - Site Development Allowances Design and Pricing Allowance - 15% 1 LOT 210.0 - - 5,868,655 3,905 16,800 45,240 727,800 6,662,400 6,662,400 0.0% 3.8%A. SITE SITE TOTAL 1 LOT 1,610.0 - - 44,993,018 29,942 128,800 346,840 5,579,800 51,078,400 51,078,400 0.0% 28.8%

B. Detached Rubblemound Breakwater

A CD Preliminaries (Included in Subcontractor Distribs) 1 LOT 300,000 - 1.00 1.40 - - 80.00 180% n/a - - - 300,000 - 300,000 300,000 0.0% 0.2%A CD Site Establishment/dis-establishment 1 LOT 400,000 - 1.00 1.40 - - 80.00 180% n/a - - - - 400,000 400,000 400,000 0.0% 0.2%

RF H CD Rock fill for breakwater core (2.6 MT per CM) 22,000 CM 91 0.05 1.00 1.40 0.07 1,540.0 80.00 180% n/a 2,002,000 200,200 123,200 221,760 - 2,547,160 116 0.0% 1.4%RA H CD Rock armouring (2.6 MT per CM) 5,300 CM 91 0.36 1.00 1.40 0.50 2,650.0 80.00 180% n/a 482,300 48,230 212,000 381,600 - 1,124,130 212 0.0% 0.6%SD H CD Sand dredging & placement on beach 84,000 CM 10 - 1.00 1.40 - - 80.00 180% n/a - - - - 840,000 840,000 10 0.0% 0.5%

E CD Foredune planting and fencing 5,000 SM 13.02 0.05 1.00 1.40 0.07 350.0 80.00 180% n/a 65,091 6,509 28,000 50,400 - 150,000 30 0.0% 0.1%A CD Marker piles 2 EA 60,000 - 1.00 1.40 - - 80.00 180% n/a 120,000 12,000 - - - 132,000 66,000 0.0% 0.1%A CD Rock work maintenance 1 LOT 70,000 - 1.00 1.40 - - 80.00 180% n/a 70,000 7,000 - - - 77,000 77,000 0.0% 0.0%

DA DA BZ - Earthworks Allowances Design and Pricing Allowance - 15% 1 LOT 681.0 - - 410,909 41,091 54,480 143,064 186,000 835,544 835,544 0.0% 0.5%B. EARTH EARTH TOTAL 1 LOT 5,221.0 - - 3,150,300 315,030 417,680 1,096,824 1,426,000 6,405,834 6,405,834 0.0% 3.6%

C. Detached SPW Breakwater

A CD Preliminaries (Included in Subcontractor Distribs) 1 LOT 300,000 - 1.00 1.40 - - 80.00 180% n/a - - - 300,000 - 300,000 300,000 0.0% 0.2%A CD Site Establishment/dis-establishment 1 LOT 670,000 - 1.00 1.40 - - 80.00 180% n/a - - - - 670,000 670,000 670,000 0.0% 0.4%H CD Supply & install AZ14-770 SPW 260 MT 2,741 2.53 1.00 1.40 3.54 920.4 80.00 180% n/a 712,660 71,266 73,632 132,538 - 990,096 3,808 0.0% 0.6%H CD Pile Cut off 190 EA - 5.00 1.00 1.40 7.00 1,330.0 80.00 180% n/a - - 106,400 191,520 - 297,920 1,568 0.0% 1.3%H CD Supply 12m long CHS460x16x174kg/m piles 88 MT 2,242 - 1.00 1.40 - - 80.00 180% n/a 197,296 19,730 - - - 217,026 2,466 0.0% 0.1%H CD Install raker piles 504 LM - 5.50 1.00 1.40 7.70 3,880.8 80.00 180% n/a - - 310,464 558,835 - 869,299 1,725 0.0% 0.5%H CD Pile Cut off 42 EA - 10.00 1.00 1.40 14.00 588.0 80.00 180% n/a - - 47,040 84,672 - 131,712 3,136 0.0% 0.1%H CD Supply/Install 400 m 310UBPx110kg/m walers 44 MT 5,600 22.00 1.00 1.40 30.80 1,355.2 80.00 180% n/a 246,400 24,640 108,416 195,149 - 574,605 13,059 0.0% 0.3%E CD Supply/install fabricated steel pin joints 42 EA 2,500 30.00 1.00 1.40 42.00 1,764.0 80.00 180% n/a 105,000 10,500 141,120 254,016 - 510,636 12,158 0.0% 0.3%

SD H CD Sand dredging & placement on beach 84,000 CM 10 - 1.00 1.40 - - 80.00 180% n/a - - - - 840,000 840,000 10 0.0% 0.5%E CD Foredune planting and fencing 5,000 SM 13 0.05 1.00 1.40 0.07 350.0 80.00 180% n/a 65,000 6,500 28,000 50,400 - 149,900 30 0.0% 0.1%A CD Marker piles 2 EA 60,000 - 1.00 1.40 - - 80.00 180% n/a 120,000 12,000 - - - 132,000 66,000 0.0% 0.1%

DA DA CZ - Concrete Allowances Design and Pricing Allowance - 15% 1 LOT 1,528.3 - - 216,953.40 21,695.34 122,260.80 265,069.44 226,500 852,479 852,479 0.0% 0.5%C. CONCRETE CONCRETE TOTAL 1 LOT 11,716.7 - - 1,663,309 166,331 937,333 2,032,199 1,736,500 6,535,672 6,535,672 0.0% 3.7%

D. Attached Rubblemound Breakwater

A CD Preliminaries (Included in Subcontractor Distribs) 1 LOT 100,000 - 1.00 1.40 - - 80.00 180% n/a - - - 100,000 - 100,000 100,000 0.0% 0.1%A CD Site Establishment/dis-establishment 1 LOT 25,000 - 1.00 1.40 - - 80.00 180% n/a - - - - 25,000 25,000 25,000 0.0% 0.0%H CD Supply and place rock fill (2.6 MT per CM) 45,000 CM 91 0.05 1.00 1.40 0.07 3,150.0 80.00 180% n/a 4,095,000 409,500 252,000 453,600 - 5,210,100 116 0.0% 2.9%

RA H CD Supply and place rock armour (2.6 MT per CM) 15,000 CM 91 0.36 1.00 1.40 0.50 7,500.0 80.00 180% n/a 1,365,000 136,500 600,000 1,080,000 - 3,181,500 212 0.0% 1.8%A CD Maintenance of rock armour 1 LOT 325,000 1.00 1.40 - - 80.00 180% n/a 325,000 32,500 - - - 357,500 357,500 0.0% 0.2%A CD sand bypassing 350,000 CM 30 1.00 1.40 - - 80.00 180% n/a - - - - 10,500,000 10,500,000 30 0.0% 5.9%A CD Marker Piles 2 EA 60,000 1.00 1.40 - - 80.00 180% n/a 120,000 12,000 - - - 132,000 66,000 0.0% 0.1%

DA DA DZ - Structural Steel Allowances Design and Pricing Allowance - 15% 1 LOT 1,597.5 - - 885,750 88,575 127,800 245,040 1,578,750 2,925,915 2,925,915 0.0% 1.6%D. STEEL STEEL TOTAL 1 LOT 12,247.5 - - 6,790,750 679,075 979,800 1,878,640 12,103,750 22,432,015 22,432,015 0.0% 12.6%

E. Portsea Front Beach Headline Rock Groyne

A CD Preliminaries (Included in Subcontractor Distribs) 1 LOT 300,000 - 1.00 1.40 - - 80.00 180% n/a - - - 300,000 - 300,000 300,000 0.0% 0.2%A CD Site Establishment/dis-establishment 1 LOT 400,000 - 1.00 1.40 - - 80.00 180% n/a - - - - 400,000 400,000 400,000 0.0% 0.2%H CD Supply and place rock fill (2.6 MT per CM) 7,500 CM 91 0.05 1.00 1.40 0.07 525.0 80.00 180% n/a 682,500 68,250 42,000 75,600 - 868,350 116 0.0% 0.5%

RA H CD Supply and place rock armour (2.6 MT per CM) 2,500 CM 91 0.36 1.00 1.40 0.50 1,250.0 80.00 180% n/a 227,500 22,750 100,000 180,000 - 530,250 212 0.0% 0.3%SD H CD Dredge and place sand 65,000 CM 10 - 1.00 1.40 - - 80.00 180% n/a - - - - 650,000 650,000 10 0.0% 0.4%

E CD Foredune planting and fencing 5,000 SM 13 0.05 1.00 1.40 0.07 350.0 80.00 180% n/a 65,000 6,500 28,000 50,400 - 149,900 30 0.0% 0.1%A CD Nav aid 1 EA 60,000 1.00 1.40 - - 80.00 180% n/a 60,000 6,000 - - - 66,000 66,000 0.0% 0.0%A CD Rock armour maintenance 1 LOT 52,500 1.00 1.40 - - 80.00 180% n/a 52,500 5,250 - - - 57,750 57,750 0.0% 0.0%A CD Sand maintenance 1 LOT 5,280,000 1.00 1.40 - - 80.00 180% n/a 5,280,000 - - - - 5,280,000 5,280,000 0.0% 3.0%

DA DA FZ - Building Allowances Design and Pricing Allowance - 15% 1 LOT 318.8 - - 955,125 16,312.50 25,500 90,900 157,500 1,245,338 1,245,338 0.0% 0.7%F. BUILD BUILD TOTAL 1 LOT 2,443.8 - - 7,322,625 125,063 195,500 696,900 1,207,500 9,547,588 9,547,588 0.0% 5.4%

F. Port Franklin Headland Rock Groyne

A CD Preliminaries (Included in Subcontractor Distribs) 1 LOT 300,000 - 1.00 1.40 - - 80.00 180% n/a - - - 300,000 - 300,000 300,000 0.0% 0.2%A CD Site Establishment/dis-establishment 1 LOT 400,000 - 1.00 1.40 - - 80.00 180% n/a - - - - 400,000 400,000 400,000 0.0% 0.2%H CD Supply and place rock fill (2.6 MT per CM) 7,500 CM 91 0.05 1.00 1.40 0.07 525.0 80.00 180% n/a 682,500 68,250 42,000 75,600 - 868,350 116 0.0% 0.5%

RA H CD Supply and place rock armour (2.6 MT per CM) 2,500 CM 91 0.36 1.00 1.40 0.50 1,250.0 80.00 180% n/a 227,500 22,750 100,000 180,000 - 530,250 212 0.0% 0.3%

%SCOPE UNIT RATE, (Units) COSTS, ($)

C:\Users\mathew.cuolahan\Documents\Working folder\301311-11231 Portsea Front Beach Options\06. Cost Estimates\301311-11231 Portsea Front Beach Options Estimates Rev B.xlsx Page 7

Portsea Front Beach Options AssessmentWORLEYPARSONS JOB NUMBER: 301311-11231

ESTIMATE DETAILS BY COMMODITY EVALUATE Estimate +/-30% Location: Portsea, VictoriaDate: 09-September-2016Rev: BBy: M. CuolahanChecked: L. NielsenCurrency : AUD

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23

Facility Pricing Basis

Quantity Basis

Commodity Code - Description

Details Qty UoM Unit Price, UP ($)

Base Unit Hrs, BUH

Loc. Factor,

LF

Prod. Factor,

PF

Unit Man hrs, UMH

Man hrs, MH

Labour Rate, LR

Contract.Distribs

(% of direct LC)

Plant & Equipment,

PE

Vendor Reps, VR

Bulk Material, BM

Freight, FC

Labour, LC

Contractor Distribs,

CD

Construction Equipment, CE

Total, TC=

Unit Cost (Cost Per

Unit)

% of TICs % of Direct Costs

%SCOPE UNIT RATE, (Units) COSTS, ($)

SD H CD Dredge and place sand 190,000 CM 10 - 1.00 1.40 - - 80.00 180% n/a - - - - 1,900,000 1,900,000 10 0.0% 1.1%E CD Foredune planting and fencing 10,000 SM 13 0.05 1.00 1.40 0.07 700.0 80.00 180% n/a 130,000 13,000 56,000 100,800 - 299,800 30 0.0% 0.2%A CD Maintenance Beach Nourishment 1 LOT 8,480,000 1.00 1.40 - - 80.00 180% n/a 8,480,000 - - - - 8,480,000 8,480,000 0.0% 4.8%A CD Rock armour maintenance 1 LOT 52,500 1.00 1.40 - - 80.00 180% n/a 52,500 5,250 - - - 57,750 57,750 0.0% 0.0%A CD Nav aid 1 EA 60,000 1.00 1.40 - - 80.00 180% n/a 60,000 6,000 - - - 66,000 66,000 0.0% 0.0%

DA DA GZ - Miscellaneous Design and Pricing Allowance - 15% 1 LOT 371.3 - - 1,444,875 17,288 29,700 98,460 345,000 1,935,323 1,935,323 0.0% 1.1%G. SCAFF SCAFF TOTAL 1 LOT 2,846.3 - - 11,077,375 132,538 227,700 754,860 2,645,000 14,837,473 14,837,473 0.0% 8.4%

G. Sand Nourishment

A CD Preliminaries (Included in Subcontractor Distribs) 1 LOT 100,000 - 1.00 1.40 - - 80.00 180% n/a - - - 100,000 - 100,000 100,000 0.0% 0.1%A CD Site Establishment/dis-establishment 1 LOT 370,000 - 1.00 1.40 - - 80.00 180% n/a - - - - 370,000 370,000 370,000 0.0% 0.2%

SD H CD Dredge and place sand 150,000 CM 10 - 1.00 1.40 - - 80.00 180% n/a - - - - 1,500,000 1,500,000 10 0.0% 0.8%E CD Foredune planting and fencing 10,000 SM 13 0.05 1.00 1.40 0.07 700.0 80.00 180% n/a 130,000 13,000 56,000 100,800 - 299,800 30 0.0% 0.2%A CD Maintenance (next 40 years) 1 LOT 18,340,000 - 1.00 1.40 - - 80.00 180% n/a 18,340,000 - - - - 18,340,000 18,340,000 0.0% 10.3%

1.00 1.40 - - 80.00 180% n/a - - - - - - - 0.0% 0.0%DA DA HZ - Handling Equipment

Allowances Design and Pricing Allowance - 15% 1 LOT 105.0 - - 2,770,500 1,950 8,400 30,120 280,500 3,091,470 3,091,470 0.0% 1.7%H. MOD MOD TOTAL 1 LOT 805.0 - - 21,240,500 14,950 64,400 230,920 2,150,500 23,701,270 23,701,270 0.0% 13.4%

H. Rock Revetment

A CD Preliminaries (Included in Subcontractor Distribs) 1 LOT 100,000 - 1.00 1.40 - - 80.00 180% n/a - - - 100,000 - 100,000 100,000 0.0% 0.1%A CD Site Establishment/dis-establishment 1 LOT 25,000 - 1.00 1.40 - - 80.00 180% n/a - - - - 25,000 25,000 25,000 0.0% 0.0%

RA H CD Supply and place rock armour (2.6 MT per CM) 4,100 CM 91 0.36 1.00 1.40 0.50 2,050.0 80.00 180% n/a 373,100 37,310 164,000 295,200 - 869,610 212 0.0% 0.5%H CD Supply and place rock underlayer (2.6 MT per CM) 1,100 CM 91 0.10 1.00 1.40 0.14 154.0 80.00 180% n/a 100,100 10,010 12,320 22,176 - 144,606 131 0.0% 0.1%E CD Supply and place gtx 2,300 SM 11 0.12 1.00 1.40 0.17 386.4 80.00 180% n/a 25,300 2,530 30,912 55,642 - 114,384 50 0.0% 0.1%A CD Rock armour maintenance 1 LOT 264,000 - 1.00 1.40 - - 80.00 180% n/a 264,000 26,400 - - - 290,400 290,400 0.0% 0.2%

DA DA JZ - Jetties Allowance Design and Pricing Allowance - 15% 1 LOT 388.6 - - 114,375 11,437.50 31,084.80 70,952.64 3,750 231,600 231,600 0.0% 0.1%J. JETT JETT TOTAL 1 LOT 2,979.0 - - 876,875 87,688 238,317 543,970 28,750 1,775,600 1,775,600 0.0% 1.0%

I. Rock Revetment with sand nourishment

A CD Preliminaries (Included in Subcontractor Distribs) 1 LOT 100,000 - 1.00 1.40 - - 80.00 180% n/a - - - 100,000 - 100,000 100,000 0.0% 0.1%A CD Site Establishment/dis-establishment 1 LOT 25,000 - 1.00 1.40 - - 80.00 180% n/a - - - - 25,000 25,000 25,000 0.0% 0.0%

RA H CD Supply and place rock armour (2.6 MT per CM) 4,100 CM 91 0.36 1.00 1.40 0.50 2,050.0 80.00 180% n/a 373,100 37,310 164,000 295,200 - 869,610 212 0.0% 0.5%H CD Supply and place rock underlayer (2.6 MT per CM) 1,100 CM 91 0.10 1.00 1.40 0.14 154.0 80.00 180% n/a 100,100 10,010 12,320 22,176 - 144,606 131 0.0% 0.1%E CD Supply and place gtx 2,300 CM 11 0.12 1.00 1.40 0.17 386.4 80.00 180% n/a 25,300 2,530 30,912 55,642 - 114,384 50 0.0% 0.1%A CD Rock armour maintenance 1 LOT 223,000 1.00 1.40 - - 80.00 180% n/a 223,000 22,300 - - - 245,300 245,300 0.0% 0.1%A CD Establishment for nourishment 1 LOT 370,000 1.00 1.40 - - 80.00 180% n/a - - - - 370,000 370,000 370,000 0.0% 0.2%

SD H CD Dredge and place sand 150,000 CM 10 - 1.00 1.40 - - 80.00 180% n/a - - - - 1,500,000 1,500,000 10 0.0% 0.8%E CD Foredune planting and fencing 10,000 SM 13 0.05 1.00 1.40 0.07 700.0 80.00 180% n/a 130,000 13,000 56,000 100,800 - 299,800 30 0.0% 0.2%A CD Sand maintenance next 40 years 1 LOT 18,340,000 - 1.00 1.40 - - 80.00 180% n/a 18,340,000 - - - - 18,340,000 18,340,000 0.0% 10.3%

DA DA KZ - Turnkey packages Allowances Design and Pricing Allowance - 15% 1 LOT 493.6 - - 2,878,725 12,772.50 39,484.80 86,072.64 284,250 3,301,305 3,301,305 0.0% 1.9%K.TURNKEY TURNKEY TOTAL 1 LOT 3,784.0 - - 22,070,225 97,923 302,717 659,890 2,179,250 25,310,005 25,310,005 0.0% 14.3%

J. Configuration Dredging Nearshore

A CD Preliminaries (Included in Subcontractor Distribs) 1 LOT 100,000 - 1.00 1.40 - - 80.00 180% n/a - - - 100,000 - 100,000 100,000 0.0% 0.1%A CD Site Establishment/dis-establishment 1 LOT 370,000 - 1.00 1.40 - - 80.00 180% n/a - - - - 370,000 370,000 370,000 0.0% 0.2%H CD Configuration Dredging/place sand on beach (1500 CM per hr) 200,000 CM 10 - 1.00 1.40 - - 80.00 180% n/a - - - - 2,000,000 2,000,000 10 0.0% 1.1%H CD Dredge hardpan, sidecast and sweep 430,000 CM 25 - 1.00 1.40 - - 80.00 180% n/a - - - - 10,750,000 10,750,000 25 0.0% 6.1%E CD Foredune planting and fencing 20,000 SM 13.02 0.05 1.00 1.40 0.07 1,400.0 80.00 180% n/a 260,364 26,036 112,000 201,600 - 600,000 30 0.0% 0.3%

DA DA LZ - Insulation Allowances Design and Pricing Allowance - 15% 1.0 LOT - - - 39,054.55 3,905.45 16,800 45,240 1,968,000 2,073,000 2,073,000 0.0% 1.2%L. INSULATION INSULATION TOTAL 1 LOT 1,400.0 - - 299,418 29,942 128,800 346,840 15,088,000 15,893,000 15,893,000 0.0% 9.0%

Department of Environment,

Land, Water and Planning

Portsea Front Beach

Remediation

Long Term Options Assessment

Marine Ecology Appendix D:

Department of Environment,

Land, Water and Planning

Portsea Front Beach

Remediation

Long Term Options Assessment

Advisian 53

THIS PAGE LEFT BLANK

Department of Environment,

Land, Water and Planning

Portsea Front Beach

Remediation

Appendix D: Marine Ecology

Project No: 301311-11231- – Portsea Front Beach Remediation: Appendix

D: Marine Ecology

Rev Description Author Review

Advisian

Approval Date

A Draft

HH

AFN

AFN

9 Sept 2016

0 Final

HH

AFN

AFN

16 November

2016

Department of Environment,

Land, Water and Planning

Portsea Front Beach

Remediation

Appendix D: Marine Ecology

Contents

1 Introduction ........................................................................................................................... 1

2 Methods .................................................................................................................................. 2

2.1 Field ............................................................................................................................. 2

2.2 Survey Transects ..................................................................................................... 3

2.3 Data Analysis ............................................................................................................ 3

3 Results ...................................................................................................................................... 4

3.1 Transect 1 .................................................................................................................. 4

3.2 Transect 2 .................................................................................................................. 4

3.3 Transect 3 .................................................................................................................. 5

3.4 Transect 4 .................................................................................................................. 5

3.5 Transect 5 .................................................................................................................. 6

3.6 Transect 6 .................................................................................................................. 7

3.7 Transect 7 .................................................................................................................. 7

3.8 Transect 8 .................................................................................................................. 8

3.9 Transect 9 .................................................................................................................. 8

3.10 Summary ................................................................................................................... 9

4 Initial Assessment of Impacts ........................................................................................ 10

4.1 Configuration Dredging ..................................................................................... 10

4.2 Breakwaters ............................................................................................................ 10

4.2.1 Detached Breakwater.........................................................................................10

4.2.2 Attached Breakwater Option ..........................................................................11

4.3 Groynes .................................................................................................................... 11

4.3.1 Point Franklin Groyne ........................................................................................11

Department of Environment,

Land, Water and Planning

Portsea Front Beach

Remediation

Appendix D: Marine Ecology

4.3.2 Portsea Front Beach Groyne ...........................................................................11

4.4 Beach Renourishment......................................................................................... 11

4.5 Rock Revetment .................................................................................................... 12

4.6 Summary of Potential Impact .......................................................................... 12

5 Regulatory Requirements ............................................................................................... 13

5.1 Coastal Management Act Consent ................................................................ 13

5.1.1 Preliminary Assessment ....................................................................................13

5.1.2 Process and Timeframe .....................................................................................13

5.1.3 Supporting Technical Studies Required .....................................................13

5.2 Environment Effects Act 1978 .......................................................................... 14

5.2.1 Preliminary Assessment ....................................................................................14

5.2.2 Process and Timeframe .....................................................................................14

5.3 Other Considerations .......................................................................................... 16

6 Conclusions .......................................................................................................................... 17

Appendices

Appendix A: Fieldwork Records

Figures

Figure 1. Towed Video System ......................................................................................................................................... 2

Figure 2. Towed video transects derived from GPS (indicated by the orange lines) .................................. 3

Figure 3 Sandy seabed (4A) and colonies of blue mussels (4B) .......................................................................... 4

Figure 4. Sandy seabed (5A) and colonies of blue mussels with sparse seagrass (5B) .............................. 4

Figure 5. Colonies of blue mussels (6A) and sandy seabed with shell (6B) .................................................... 5

Figure 6. Sandy seabed with light cover of macroalgae (7A) reef with dense cover of macroalgae

(7B) ............................................................................................................................................................................................... 6

Department of Environment,

Land, Water and Planning

Portsea Front Beach

Remediation

Appendix D: Marine Ecology

Figure 7. Macroalgae dominated reef at Point Franklin (8A) mixed seagrass/ macroalgae

assemblage (8B) ...................................................................................................................................................................... 6

Figure 8. Ecklonia macroalgae and Amphibolis seagrass (9A) mixed macroalgae assemblage (9B)..... 7

Figure 9. Point Franklin Reef, Ecklonia macroalgae (10A) rocky reef with sponges and macroalgae

(10B) ............................................................................................................................................................................................ 7

Figure 10. inshore section of transect 8 (11A) midway section of transect 8 (11B) ..................................... 8

Figure 11. Mixed mussels, seagrass and algae (12A) toward end of transect 9 (12B). ............................... 9

Tables

Table 1. Options Assessed in the Long Term Options Assessment Report .................................................... 1

Table 2 Summary of impact on existing habitat associated with each option ........................................... 12

Department of Environment,

Land, Water and Planning

Portsea Front Beach

Remediation

Appendix D: Marine Ecology

1 Introduction

Severe erosion at Portsea Front Beach in recent times has resulted from changes to the distribution

of wave energy along the Weeroona Bay foreshore.

The options considered in the main investigative report to ameliorate the erosion process at

Portsea Front Beach can be summarised as follows:

Table 1. Options Assessed in the Long Term Options Assessment Report

No. Option Description

1. Configuration Dredging Modify the distribution of wave energy along the Portsea Front

Beach shoreline to minimise erosion by shaping the seabed

with dredging. Dredged material could be used to restore the

beach.

2. Breakwaters This is a shore-parallel structure offshore of Portsea Pier that

would block the incoming swell wave energy that is causing

erosion at Portsea Front Beach. This includes consideration of

an attached and detached breakwater option.

3. Groynes A structure extending seaward from the shore that would

capture sand drift to the east, thereby building the beach and

providing a sand buffer to erosion. This includes consideration

of two options, one at Point Franklin and a second option

along the beach.

4. Replace sandbag revetment

with a rock revetment

A rock revetment would halt recession of the shoreline.

5. Beach restoration with sand

nourishment

The periodic placement of sand mined from the offshore sand

banks to feed the erosion process.

6. Remove sandbag revetment This explores what would be the extent of erosion that could

occur if no remedial works are undertaken.

This marine ecology report provides a description of the nearshore benthic environment that

potentially may be affected by the options assessed in the long term options assessment report.

Department of Environment,

Land, Water and Planning

Portsea Front Beach

Remediation

Appendix D: Marine Ecology

2 Methods

2.1 Field

The field assessment was undertaken on the 23rd

August 2016. Conditions on the day of survey

were ideal with very light winds and no swell. Underwater visibility was also exceptional with the

seabed visible at most sites to 8m (vertical) depth.

The survey vessel used was operated by the skipper at a speed between 1 and 2 knots while an

Advisian marine scientist was operating the underwater camera system to collect the required

video data. To ensure good quality of the recorded images, priority was given to vessel speed over

heading direction.

Before deploying the camera system, the coordinates of the centre point for the configuration

dredging option were entered into the on-board GPS to assist the skipper with orientation during

navigation. Video footage was collected along directional transect grids to survey the proposed

study area. A high definition underwater tow camera system with live feed was used to document

the conditions on the seabed (Figure 1). Underwater visibility was excellent and the camera was

towed at between 0.5m and 1.0m off the seabed.

Figure 1. Towed Video System

Department of Environment,

Land, Water and Planning

Portsea Front Beach

Remediation

Appendix D: Marine Ecology

2.2 Survey Transects

A series of transects was completed for the towed camera survey so that all areas potentially

affected by the options assessment were surveyed.

A total of nine transects were undertaken. Four of the transects were over the nearshore trench

and across the general area where the detached breakwater was proposed and four transects

across the area where the beach groyne options were proposed. A transect was also run along the

western length of the Portsea Pier where the attached breakwater option is located Figure 2).

A series of video points were also collected from within the nearshore trench to compliment the

transect imagery.

Figure 2. Towed video transects derived from GPS (indicated by the orange lines)

2.3 Data Analysis

All video footage was assessed and the key habitats classified.

Department of Environment,

Land, Water and Planning

Portsea Front Beach

Remediation

Appendix D: Marine Ecology

3 Results

3.1 Transect 1

Transect 1 was located close to the centre of the proposed nearshore trench option in 9 to 9.5m

depth of water. Much of the seabed was composed of consolidated sand with a rippled seabed

(Figure 3a). Lower frequency but larger sand waves were evident in the footage which is more

typical of seabed affected by swell waves. Patches of blue mussel colonies (Mytilus edulis) were also

observed regularly throughout the footage collected Figure 3b.

Figure 3 Sandy seabed (4A) and colonies of blue mussels (4B)

3.2 Transect 2

Transect 2 was located along the seaward edge of the nearshore trench in a similar depth range to

Transect 1. The seabed was predominantly consolidated sand with very little epibenthos present

(Figure 4a).

Figure 4. Sandy seabed (5A) and colonies of blue mussels with sparse seagrass (5B)

4A 4B

5A 5B

Department of Environment,

Land, Water and Planning

Portsea Front Beach

Remediation

Appendix D: Marine Ecology

Patches of the blue mussel, Mytilus edulis, were common and varied in abundance and cover. A

very sparse cover of seagrass was also present in some of the footage (Figure 4b). The species

present was most likely Zostera nigricaulis, which is the most common seagrass species recorded in

Port Phillip Bay.

3.3 Transect 3

Transect 3 was located along the landward edge of the nearshore trench and in the general vicinity

of the detached breakwater option in 8.5 to 9.2m water depth. The habitat observed along

Transect 3 was very similar to that observed in Transect 1 and 2, although no seagrass was

detected in the footage.

Figure 5. Colonies of blue mussels (6A) and sandy seabed with shell (6B)

3.4 Transect 4

Transect 4 was located from the easterly end of nearshore trench toward Point Franklin and

followed the approximate alignment of the groyne at Point Franklin option. The seaward end of

the transect was in 10m water depth and shallowed with increasing proximity to Point Franklin. The

initial section of the transect was sand (Figure 6a) which then progressively changed into substrate

dominated by macroalgal reef (Figure 6b). The Point Franklin site has been monitored as part of

the Victorian Subtidal Reef Monitoring Program for Parks Victoria and has been surveyed by

Edmunds et al. (2003).

The most dominant algae at Point Franklin that was observed in the video footage was the kelp

Ecklonia radiata and to a lesser extent other brown algae such as Cystophora and Sargassum

species. Common invertebrates include the sea urchin Heliocidaris erythrogramma, the feather star

Cenolia trichoptera and very low abundances of abalone Haliotis spp. (Edmunds et al. 2003).

Fish were not observed in any of the footage at Point Franklin and Edmunds et. al. (2003)

confirmed that the Point Franklin reef had very low abundances of all fish species, including the

typically abundant blue throat wrasse, Notolabrus tetricus. The only observed species in higher

6A 6B

Department of Environment,

Land, Water and Planning

Portsea Front Beach

Remediation

Appendix D: Marine Ecology

abundance were the small species such as mado Atypichthys strigatus and juvenile toothbrush

leatherjackets Acanthaluteres vittiger. Edmunds et al. (2003) also indicated that the Point Franklin

site is subject to exceptional line and spear fishing pressure, with casual observations indicating the

site is likely to have the highest spear-fishing pressure in Victoria. The location is frequented by

novice fishers and indiscriminate spearing may have resulted in the observed paucity of all fish

species. At least two snorkelers were observed at Point Franklin during the field visit.

Figure 6. Sandy seabed with light cover of macroalgae (7A) reef with dense cover of macroalgae (7B)

3.5 Transect 5

Transect 5 was started at Point Franklin and completed 200 m westward toward Portsea Pier in 4 m

water depth. The transect commenced over reef and then intersected a mixed assemblage habitat

that was dominated by seagrass and macroalgae. The seagrass observed at the site was

predominantly Amphibolis antarctica which within Port Phillip Bay is usually restricted to the more

exposed locations around the Heads. Seagrass cover was patchy but dense (Figure 7b). These areas

of high density are clearly visible in the aerial imagery from the site.

Figure 7. Macroalgae dominated reef at Point Franklin (8A) mixed seagrass/ macroalgae assemblage

(8B)

7A 7B

8A 8B

Department of Environment,

Land, Water and Planning

Portsea Front Beach

Remediation

Appendix D: Marine Ecology

3.6 Transect 6

Transect 6 extends from the western edge of the Point Franklin reef in a south westerly direction

toward the middle section of the main beach. The transect covered the area potentially affected by

construction of a groyne on the Portsea Front Beach.

The transect was dominated by mixed assemblages of macroalgae and seagrass as shown in Figure

Figure 8a and Figure 8b.

Figure 8. Ecklonia macroalgae and Amphibolis seagrass (9A) mixed macroalgae assemblage (9B)

3.7 Transect 7

Transect 6 extends from the western edge of the Point Franklin reef in a north easterly direction

across the reef. The transect covered the area potentially affected by construction of a groyne at

Point Franklin.

Figure 9. Point Franklin Reef, Ecklonia macroalgae (10A) rocky reef with sponges and macroalgae (10B)

9A 9B

10A 10B

Department of Environment,

Land, Water and Planning

Portsea Front Beach

Remediation

Appendix D: Marine Ecology

A review of the footage showed that the habitat was predominantly reef (Figure 9) with mixed

assemblages of seagrass and macroalgae as described previously in Section 3.4. The seabed is

colonised by dense Amphibolis, a seagrass that forms meadows on calcareous sands, the

interweaving roots and leaves of which consolidate the substrate, protecting it from erosion by

currents and waves. Only toward the end of the transect, in approximately 10m water depth does

the substrate revert to a more sand dominated seabed.

3.8 Transect 8

Transect 7 was run in a northerly direction from the shallows immediately west of the existing Pier,

from a starting depth of 2.3 m to an end depth of 8.0 m This transect was intended to cover the

approximate alignment of the western wing associated with the attached breakwater option.

The initial section of transect was dominated by a mixed assemblage of seagrass and macroalgae.

The presence of the Amphibolis seagrass and macroalgae would indicate the presence of a hard

substrate for attachment like shell and broken rubble. No high relief reef was observed but is likely

to be present closer to shore where a small section of intertidal reef is visible at the base of the

seawall immediately west of the Pier. The inshore section of seagrass and macroalgae (Figure 10a)

eventually grades into unvegetated, sandy seabed at approximately 3.6 m depth (Figure 10b).

Toward the end of the transect, patches of blue mussel become more evident.

Figure 10. inshore section of transect 8 (11A) midway section of transect 8 (11B)

3.9 Transect 9

The final transect was run in a west to east direction, approximately 100m from the end of the

Portsea Pier at depths of 5.5m to 7.0m. This transect was intended to cover the approximate

alignment of the “T” associated with attached breakwater option.

Most of the transect, in particular the initial section, was over sandy seabed that graded into a

mixed assemblage of mussels, sparse seagrass and smaller algae (Figure 11a). The proportion of

11A 11B

Department of Environment,

Land, Water and Planning

Portsea Front Beach

Remediation

Appendix D: Marine Ecology

macroalgae increased toward the end of the transect, which may have been related to the

increasing proximity to the extensive reef at Point Franklin.

Figure 11. Mixed mussels, seagrass and algae (12A) toward end of transect 9 (12B).

3.10 Summary

The nearshore coastal and marine habitats that are present adjacent to the Portsea Front Beach

foreshore consist of a range of commonly occurring species that are found throughout the

southern section of Port Phillip Bay. The area of seabed in the vicinity of the nearshore trench and

offshore breakwater options are predominantly sand, whereas the habitat most likely affected by

the headland and beach groyne options are reef and seagrass.

12A 12B

Department of Environment,

Land, Water and Planning

Portsea Front Beach

Remediation

Appendix D: Marine Ecology

4 Initial Assessment of Impacts

4.1 Configuration Dredging

Offshore, in some 8 m depth between the Pier and Portsea Hole, a seabed area of some 700 m ×

340 m (24 ha) would be disturbed. One third of this area would be lowered by some 8 m with the

remainder raised by some 4 m. This would introduce new habitat over a portion of a somewhat

regular flat area, which may enhance local biodiversity.

Near the shoreline, some 1200 m × 100 m (12 ha) of nearshore seabed would be smothered with

sand. This would result in a temporary loss of some seagrass in the area although the majority of

habitat affected will be soft sediment.

If some of the exposed material is hard (rubble), rather than (soft), the resultant habitat may

become dominated by reef and other macroalgal species. The most likely species to recolonise the

disturbed habitat will be species already present in surrounding habitat such as those found at

Portsea Hole and Point Franklin.

Across Point Franklin the seabed is colonised by dense Amphibolis, a seagrass that forms meadows

on calcareous sands, the interweaving roots and leaves of which consolidate the substrate,

protecting it from erosion by currents and waves.

4.2 Breakwaters

4.2.1 Detached Breakwater

The footprint of either the sheet pile wall option or the rubble mound option would be relatively

small and cause an insignificant amount of disturbance to the seabed. A rubble mound option

would enhance biodiversity locally by introducing hard substrate to an area that is currently

dominated by soft sediment fauna.

This option also includes provision of a borrow site that will be a source of sand to re-nourish the

beach. It is estimated that 8 ha of active seabed could be disturbed to provide the volume of sand

required for renourishment. These sand shoals that will be the source of sand are subject to

dynamic tidal processes and would be restored naturally over time.

At the beach face where nourishment would be placed some 6 ha of seabed would be smothered,

impacting some seagrass and benthic fauna. This nearshore habitat is subjected to dynamic beach

processes and would be restored naturally.

There would be little adverse impact on the marine ecology either at the nourishment borrow site

or at the beach face where nourishment would be placed. The footprint of the rubble mound

option would be relatively small. A rubble mound option would provide hard substrate for the

colonization of reef species such as those currently found at Point Franklin for example.

Department of Environment,

Land, Water and Planning

Portsea Front Beach

Remediation

Appendix D: Marine Ecology

4.2.2 Attached Breakwater Option

The footprint of the attached breakwater option is significantly larger compared with the detached

option when the entire footprint of the “T type” structure is taken into account. As a result, a

correspondingly larger area of existing habitat will be directly affected by construction and a range

of potential indirect impacts will also require further consideration.

4.3 Groynes

4.3.1 Point Franklin Groyne

The rock groyne would cover a relatively small area of existing reef and would have a minimal

adverse impact on the local marine ecology. The structure would provide additional new habitat

which would offset the loss of natural reef habitat under the footprint of the groyne. The buildup

of sand over time on the beach side facing side of the groyne would also prevent the

establishment of reef flora and fauna.

At the nourishment borrow site, some 19 ha of active seabed could be disturbed. These sand

shoals are subjected to dynamic tidal processes and would be restored naturally. At the beach face

where nourishment would be placed some 7 ha of seabed would be smothered, impacting some

seagrass and benthic fauna. This nearshore habitat is subjected to dynamic beach processes and

would be restored naturally.

4.3.2 Portsea Front Beach Groyne

The rock groyne would cover a relatively small area of existing seabed that is predominantly sand

and would have a minimal adverse impact on the local marine ecology. The structure would

provide additional new hard substrate for colonization by a range of native species of flora and

fauna.

At the nourishment borrow site some 7 ha of active seabed could be disturbed. These sand shoals

are subjected to dynamic tidal processes and would be restored naturally. At the beach face where

nourishment would be placed some 3 ha of seabed would be smothered, impacting some seagrass

and benthic fauna. This nearshore habitat is subjected to dynamic beach processes and would be

restored naturally.

4.4 Beach Renourishment

At the nourishment borrow site some 15 ha of active seabed could be disturbed. These sand shoals

are subjected to dynamic tidal processes and would be restored naturally. At the beach face where

nourishment would be placed some 5 ha of seabed would be smothered, impacting some seagrass

and benthic fauna.

This nearshore habitat is subjected to dynamic beach processes and would be restored naturally.

Department of Environment,

Land, Water and Planning

Portsea Front Beach

Remediation

Appendix D: Marine Ecology

4.5 Rock Revetment

The longer term impact of a rock revetment without beach nourishment would be the complete

loss of the sandy beach and the progressive lowering and deepening of the seabed in front of it.

4.6 Summary of Potential Impact

Table 2 provides a summary of the potential impacts on the marine ecology associated with each

of the remediation options. The initial assessment does not take into account socio-economic,

visual or aesthetic factors associated with the presence of the structures.

Table 2 Summary of impact on existing habitat associated with each option

Option Reef Seagrass Sand

Configuration Dredging

Attached Breakwater

Detached Breakwater

Point Franklin Groyne

Front Beach Groyne

Beach Renourishment

Change revetment

No revetment

- no or minimal impact on the habitat indicated

- some impact on habitat shown but not significant and recovery likely

- high impact on habitat shown with permanent change likely

Department of Environment,

Land, Water and Planning

Portsea Front Beach

Remediation

Appendix D: Marine Ecology

5 Regulatory Requirements

A range of approvals will be required depending on the option selected.

5.1 Coastal Management Act Consent

All options will require assessment (as a minimum) under the Coastal Management Act.

All use or development of coastal Crown land by any party, including committees of management

and municipal councils, requires consent under the Coastal Management Act 1995. Coastal Crown

land is generally all Crown land within 200 m of the high tide mark and the seabed of Victorian

coastal waters.

The consent process applies to all coastal Crown land, regardless of status in a planning scheme

and ensures that the Crown has the opportunity to represent the broader public interest in matters

affecting the coast and seabed.

5.1.1 Preliminary Assessment

Dredging, beach renourishment, construction of groynes and breakwaters will require CMA Act

consent.

5.1.2 Process and Timeframe

Once a Consent form is accepted as valid, the Minister (or delegate) must make a decision within

28 days. DEPI may request additional information in writing depending on the nature of the works

and the information provided.

Under section 40(3) of the Coastal Management Act 1995, if the Minister does not make a decision

within 28 days, the application is deemed to be refused.

Where the proposal includes dredging of coastal Crown land, as will be required for a range of

options that require a source of sand, the application must include a completed application form

that is specific to dredging.

5.1.3 Supporting Technical Studies Required

A range of supporting technical studies is likely to be required to support the CMA Consent. These

would include but not be limited to:

sediment characterisation study to demonstrate the sediments are clean (free of toxicants)

sediment characterisation study to demonstrate that sand is of suitable grade for placement

on the beach.

Department of Environment,

Land, Water and Planning

Portsea Front Beach

Remediation

Appendix D: Marine Ecology

5.2 Environment Effects Act 1978

The need for an EES referral is triggered by criteria set out in ministerial guidelines. The referral

criteria are focused on the potential for a significant effect on the environment.

The Minister, when deciding whether an EES is required, will consider the following:

The potential for significant adverse effects on individual environmental assets, taking into

account the magnitude, geographic extent and duration of change in the values of each asset.

The likelihood of effective avoidance and mitigation measures.

The likelihood of adverse effects and associated uncertainty of available predictions.

The likelihood that available environmental standards provide a sufficient basis for managing

key issues.

The likelihood that the project is not consistent with applicable policy.

The range and complexity of potential adverse effects.

The availability of project alternatives that may warrant investigation to assess opportunities to

avoid or minimise adverse environmental effects.

Other available assessment processes that may be suitable to address potential environmental

effects.

The likely level of public interest in a proposed project.

5.2.1 Preliminary Assessment

An assessment of the various options was undertaken, however this is only preliminary in nature

and it is likely that ongoing consultation with the public and the Department will determine the

level of assessment that will eventually be required:

Options requiring construction of groynes and beach renourishment are unlikely to require

assessment under the EES Act.

Options requiring construction of a detached breakwater and configuration dredging may

require assessment under the EES Act although this could be avoided if enough supporting

technical information can be provided with the referral to demonstrate that any impact is

manageable. There are existing precedents elsewhere in Port Phillip Bay where similar

structures and projects have not required an EES.

The attached breakwater option which has the largest footprint of all the options considered is

likely to require an assessment under the EES Act.

5.2.2 Process and Timeframe

All options will require a referral which would recommend to the Minister whether an EES is

required or not. The EES process can be broken down into several discrete steps:

Department of Environment,

Land, Water and Planning

Portsea Front Beach

Remediation

Appendix D: Marine Ecology

Referral

Project referred to Minister for

Planning

A project is referred by a proponent or decision-maker in accordance with

the referral criteria.

Decision

Minister's decision on the

need for an EES

The Minister will make one of three decisions, normally within 20 business

days of accepting a referral:

Yes, EES is required

Approval decisions are put on hold until the EES process is completed.

No, EES is not required

Decision-makers can proceed with their approval process.

No, EES is not required but conditions must be met

Conditions might relate to the location or dimensions of the project or

mitigation measures, or alternately requirements for further studies or

consultation.

Scoping

Scoping requirements for EES

studies and report set by

Minister

The matters to be investigated and documented in an EES are set out in the

'scoping requirements' issued by the Minister.

Draft scoping requirements are released for public comment for at least 15

business days before the final scoping requirements are published.

Preparing the EES

Proponent prepares the EES

The proponent must prepare EES, as well as a study program and

consultation plan consistent with the scoping requirements.

A Technical Reference Group, with members from government agencies,

local government and statutory authorities, is appointed to provide advice

to the proponent and the Department during the preparation of the EES.

Public review

Exhibition of EES and

lodgement of submissions

When the Minister is satisfied that the EES is suitable, it is released for public

comment for between 20 and 30 business days. During this time, the public

can make written submissions.

The Minister may appoint an inquiry to evaluate the effects of the project,

having regard to the EES studies and public submissions.

Making an assessment

Minister's Assessment of

environmental effects

As the final stage of the EES process, the Minister prepares an Assessment

considering all relevant information. The Minister's Assessment is normally

provided within 25 business days of the inquiry report being finalised.

The Assessment includes findings on the environmental effects, and may

conclude that the project:

Will have an acceptable level of environmental effects; or

Department of Environment,

Land, Water and Planning

Portsea Front Beach

Remediation

Appendix D: Marine Ecology

Will not have an acceptable level of environmental effects; or

Would need major modifications and/or further investigations to

establish that acceptable outcomes would be achieved.

Informing decisions

Decision-makers consider the

Assessment

Decision-makers must consider the Minister's Assessment in deciding

whether to approve a project under Victorian law or to authorise public

works. While the recommendations in the Assessment are authoritative,

they are not usually binding on decision-makers.

5.3 Other Considerations

The Sea Dumping Act does not apply where dumping is to occur entirely in Internal Waters

such as Port Phillip Bay so no sea dumping permit will be required for dredging and sand

renourishment activities. However, the suitability of sediment will need to be characterised in

accordance with the NAGD (Commonwealth of Australia, 2009).

An EPBC referral is unlikely to be required however under Part 3 of the EPBC Act, there are nine

matters of national environmental significance of which two are potentially relevant to this Project

including:

Nationally threatened species and ecological communities (Section 18, 18A, 19) and

Migratory species (Section 20, 20A, 20B)

These two matters would require additional assessment to confirm the requirement.

Department of Environment,

Land, Water and Planning

Portsea Front Beach

Remediation

Appendix D: Marine Ecology

6 Conclusions

Of all the options assessed those which require the construction or placement of solid structures

on the seabed will have the greatest potential ecological impact.

Although the configuration dredging option does require the dredging and excavation of a

relatively large area of seabed, the resultant area will be available for recolonization by equivalent

benthic species, hence the net environmental impact is considered low.

The T groyne attached breakwater option will have a much greater impact than the detached

breakwater option by virtue of the size of the construction footprint and that it intersects a range

of inshore and offshore habitat types.

Construction of the Point Franklin groyne option over an area of natural reef is also likely to have a

greater ecological impact than the Portsea front beach groyne option which mainly intersects sand.

The reef at Point Franklin has lower biodiversity than comparable reefs elsewhere in southern Port

Phillip Bay. However, it is a popular ecological site due its accessibility. Construction of a rock

groyne using rock armour at the site will partially offset the loss of habitat. However, at least half of

the effective area available for recolonization will be lost due to the build-up of sand on the beach

side of the groyne.

All options will require assessment under the Coastal Management Act and CMA Consent will be

required for the project to proceed. An EES is unlikely to be required for most of the options

considered in this report. However, the decision will be contingent on likelihood of adverse effects

and associated uncertainty of available predictions associated with the option and the level of

public interest.

Department of Environment,

Land, Water and Planning

Portsea Front Beach

Remediation

Long Term Options Assessment

Advisian 53

THIS PAGE LEFT BLANK