Project Scheduling 3The Network Diagram  

Prepared by Sebghatullah Karimi(Junior Lecturer of Kabul Polytechnic University)

1392

Kardan UniversityCivil Engineering Faculty

Page 2: 11 lecture project scheduling 3

Develop an activity list for a project.Construct a network diagram for a project.

2

Page 3: 11 lecture project scheduling 3

In order to construct a network diagram for a project, we must:Identify and list all of the activities that constitute the project.For each activity, identify all activities that must be completed before that activity is started.Draw the network diagram, representing each activity as a box (or node) and using arrows to represent precedence.

3

Page 4: 11 lecture project scheduling 3

Your construction company has been awarded a contract to build a new gymnasium at the National Military Academy of Afghanistan. As part of your project planning, you will develop a network schedule for construction of the gymnasium. You begin by developing the activity list provided on the following page. Based on this list, construct a network diagram for the project.

4

Page 5: 11 lecture project scheduling 3

5

Page 6: 11 lecture project scheduling 3

Activity Duration Preceded By

1 Mobilize 1 day

2 Clear site 2 days 1

3 Excavate for footings 10 days 2

4 Install footing formwork 6 days 3

5 Fabricate and install steel footing reinforcement 2 days 4

6 Place concrete for footings 2 days 5

7 Remove Forms 1 day 6

8 Cure concrete footings 7 days 6

9 Install concrete block foundation walls 6 days 8

10 Backfill foundation 2 days 7, 9

11 Stub in Plumbing 4 days 3

12 Stub in Electrical 4 days 3

13 Fabricate and install slab reinforcement 3 days 10

14 Place concrete for floor slab 2 days 13

15 Cure concrete slab 7 days 14

16 Install column formwork 10 days 8

17 Fabricate and install steel column reinforcement 5 days 16

18 Place concrete for columns 4 days 17

19 Remove column forms 1 day 186

Page 7: 11 lecture project scheduling 3

Activity Duration Preceded By

20 Cure concrete columns 7 days 18

21 Construct exterior masonry in-fill walls 14 days 19

22 Install windows and doors 8 days 21

23 Stucco exterior walls 5 days 21

24 Install roof trusses 3 days 20

25 Install roof deck 4 days 24

26 Install standing seam metal roofing 2 days 25

27 Construct interior framing 10 days 15, 21

28 Install interior electrical 5 days 27, 12

29 Install interior plumbing 4 days 27, 11

30 Install gypsum board on interior walls 8 days 28, 29

31 Install finish floor 4 days 30

32 Paint Interior 4 days 30

33 Install basketball goals 1 day 32

34 Landscaping 14 days 10

35 Install interior lighting fixtures 3 days 28

36 Install electric heating units 4 days 21, 28

37 Project closeout 1 day 22, 23, 26, 31, 33, 34, 35, 367