1 All Committee Meeting October 04, 2017 SALTON SEA MANAGEMENT PROGRAM PHASE I: 10-YEAR PLAN WORK PLAN

Upload: others

Post on 15-Jul-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 10-YR Plan Work Plan 10-04-17 Draft 5 [Read-Only]resources.ca.gov/CNRALegacyFiles/wp-content/uploads/2017/... · 2017-10-03 · e a (a c r e s) Exposed Area Habitat Area Dust Suppression

1

All Committee MeetingOctober 04, 2017

SALTON SEA MANAGEMENT PROGRAMPHASE I: 10-YEAR PLAN

WORK PLAN

Page 2: 10-YR Plan Work Plan 10-04-17 Draft 5 [Read-Only]resources.ca.gov/CNRALegacyFiles/wp-content/uploads/2017/... · 2017-10-03 · e a (a c r e s) Exposed Area Habitat Area Dust Suppression

2

I. Goals & Objectives

II. Overarching ProjectDevelopment &Management Needs

III. Action Plan for PriorityAreas

IV. Conclusions

WORK PLAN ORGANIZATION

Page 3: 10-YR Plan Work Plan 10-04-17 Draft 5 [Read-Only]resources.ca.gov/CNRALegacyFiles/wp-content/uploads/2017/... · 2017-10-03 · e a (a c r e s) Exposed Area Habitat Area Dust Suppression

3

Bridges SSMP concepts to design/constructionof Phase I actions

Outlines SSMP objectives

Identifies key factors, information and tasks tocontinue to move forward with Phase I actions

Provides insights to stakeholders on designprogress

Describes advisory committees & roles

I. GOALS & OBJECTIVES

Page 4: 10-YR Plan Work Plan 10-04-17 Draft 5 [Read-Only]resources.ca.gov/CNRALegacyFiles/wp-content/uploads/2017/... · 2017-10-03 · e a (a c r e s) Exposed Area Habitat Area Dust Suppression

4

Chapters

Hydrology for Project Implementation

Water Quality for New Habitat Creation

Habitat Planning & Design Tool

Air Quality Management

Environmental Compliance

Compatibility with Other Regional Plans & Projects

Additional Projects for Evaluation

II. OVERARCHING PROJECT DEVELOPMENT &MANAGEMENT NEEDS

Page 5: 10-YR Plan Work Plan 10-04-17 Draft 5 [Read-Only]resources.ca.gov/CNRALegacyFiles/wp-content/uploads/2017/... · 2017-10-03 · e a (a c r e s) Exposed Area Habitat Area Dust Suppression

5

Task in Work Plan Time Frame

Overarching Project Development TasksHydrology for Project Implementation Ongoing-Mar 2018

Water Quality for New Habitat Creation Ongoing-Mar 2018

Habitat Planning and Design Tool Dec 2017-Jun 2018

Air Quality Management Plan Dec 2017-Mar 2018

Environmental Compliance Requirements Ongoing

Evaluate Compatibility with Other Regional Planning Docs Dec 2017-Jun 2018

Near-term Priority Area Planning & DesignNew River West Restoration Design Jul 2017-Dec 2018

Alamo River North Restoration Design Jan 2018-Dec 2018

Whitewater River Area Restoration Design Jan 2018-Dec 2018

TIMELINE OF WORK PLAN TASKS

Page 6: 10-YR Plan Work Plan 10-04-17 Draft 5 [Read-Only]resources.ca.gov/CNRALegacyFiles/wp-content/uploads/2017/... · 2017-10-03 · e a (a c r e s) Exposed Area Habitat Area Dust Suppression

6

HYDROLOGY FOR PROJECT IMPLEMENTATION

On-going Mar 2018On-going Mar 2018Timeline

Page 7: 10-YR Plan Work Plan 10-04-17 Draft 5 [Read-Only]resources.ca.gov/CNRALegacyFiles/wp-content/uploads/2017/... · 2017-10-03 · e a (a c r e s) Exposed Area Habitat Area Dust Suppression

7

WATER QUALITY FOR NEW HABITATS

On-going Mar 2018On-going Mar 2018Timeline

Page 8: 10-YR Plan Work Plan 10-04-17 Draft 5 [Read-Only]resources.ca.gov/CNRALegacyFiles/wp-content/uploads/2017/... · 2017-10-03 · e a (a c r e s) Exposed Area Habitat Area Dust Suppression

8

Phase 1 project areas have been established

Next steps will involve refined conceptual designs

Develop ecological targets

Detailed topo including

LIDAR surveys

Water supply analyses

Soil & geotechnical analysis

Accommodate geothermal access

HABITAT ASSESSMENT

Dec 2017 Jun 2018Dec 2017 Jun 2018Timeline

Page 9: 10-YR Plan Work Plan 10-04-17 Draft 5 [Read-Only]resources.ca.gov/CNRALegacyFiles/wp-content/uploads/2017/... · 2017-10-03 · e a (a c r e s) Exposed Area Habitat Area Dust Suppression

9

Design Considerations

Habitat functional values

Water use / gravity vs pumping

Salinity

Water quality in constructed

habitat

Selenium management

Invasive plant management

Mosquito abatement

HABITAT LOCATIONS & TYPES

Habitat Types

Permanent wetlands withvegetation

Dry playa

Mudflat, sandflat, & beach

Mid- & deep-water

Shallow water

Existing habitat

Page 10: 10-YR Plan Work Plan 10-04-17 Draft 5 [Read-Only]resources.ca.gov/CNRALegacyFiles/wp-content/uploads/2017/... · 2017-10-03 · e a (a c r e s) Exposed Area Habitat Area Dust Suppression

10

1. Assessment: Select project five areas (2016)

2. Prioritization of project areas (2017)

3. Define and apply design criteria/targets (2017/2018)

HABITAT SELECTION PROCESS

Page 11: 10-YR Plan Work Plan 10-04-17 Draft 5 [Read-Only]resources.ca.gov/CNRALegacyFiles/wp-content/uploads/2017/... · 2017-10-03 · e a (a c r e s) Exposed Area Habitat Area Dust Suppression

11

Ecological function and performance

Consistency with Audubon’s guidelines forintegrating ecological function/bird usage

Water budgets (hydrology)

Water quality

Air quality performance of other playa treatments

HABITAT PLANNING & DESIGN TOOLS

Page 12: 10-YR Plan Work Plan 10-04-17 Draft 5 [Read-Only]resources.ca.gov/CNRALegacyFiles/wp-content/uploads/2017/... · 2017-10-03 · e a (a c r e s) Exposed Area Habitat Area Dust Suppression

12

Modeled after Salton Sea Air Quality MitigationProgram (IID, July 2016)

Evaluate Dust SuppressionMethods

Water dependent

Waterless

Coordination with IID,ICAPCD, & affectedagencies

AIR QUALITY MANAGEMENT

Dec 2017 Mar 2018Dec 2017 Mar 2018Timeline

Page 13: 10-YR Plan Work Plan 10-04-17 Draft 5 [Read-Only]resources.ca.gov/CNRALegacyFiles/wp-content/uploads/2017/... · 2017-10-03 · e a (a c r e s) Exposed Area Habitat Area Dust Suppression

13

Environmental documents & permitting completed forcurrent projects

Species Conservation Habitat - New River East & West

Red Hill Bay

Torres Martinez Wetlands

Additional areas available within SCH 3,770-ac footprint

Environmental compliance for other areas is beingevaluated & coordinated with regulatory agencies

ENVIRONMENTAL COMPLIANCE

Jul 2017 On-goingJul 2017 On-goingTimeline

Page 14: 10-YR Plan Work Plan 10-04-17 Draft 5 [Read-Only]resources.ca.gov/CNRALegacyFiles/wp-content/uploads/2017/... · 2017-10-03 · e a (a c r e s) Exposed Area Habitat Area Dust Suppression

14

Phase I: 10-Year Plan will be compared to existingRegional Plans

IID Water Conservation & Transfer Project HCP/NCCP

Coachella Valley Multiple

Species Habitat

Conservation Plan

Check for compatibility,continuity, & consistency

COMPATIBILITY WITH OTHER REGIONALPLANS/PROJECTS

Dec 2017 Jun 2018Dec 2017 Jun 2018Timeline

Page 15: 10-YR Plan Work Plan 10-04-17 Draft 5 [Read-Only]resources.ca.gov/CNRALegacyFiles/wp-content/uploads/2017/... · 2017-10-03 · e a (a c r e s) Exposed Area Habitat Area Dust Suppression

15

Evaluate potential to reconnect, inundate, ortreat harbors & boat docks along east & westshores

Reduce odors Reduce vectors Dust suppression Recreation opportunities

Water import options

ADDITIONAL PROJECTS FOR EVALUATION

Page 16: 10-YR Plan Work Plan 10-04-17 Draft 5 [Read-Only]resources.ca.gov/CNRALegacyFiles/wp-content/uploads/2017/... · 2017-10-03 · e a (a c r e s) Exposed Area Habitat Area Dust Suppression

16

Project Implementation/Construction Strategy

Focuses on key components & locations

New River East & West

Alamo River North & South

Whitewater River

Phase I project sequencing determined by

Proximity to water sources

Status of environmental clearance/permits

Availability of access to property

Other shoreline areas will be developed later

III. ACTION PLAN FOR PHASE I AREAS

Page 17: 10-YR Plan Work Plan 10-04-17 Draft 5 [Read-Only]resources.ca.gov/CNRALegacyFiles/wp-content/uploads/2017/... · 2017-10-03 · e a (a c r e s) Exposed Area Habitat Area Dust Suppression

17

PHASE I AREAS

Page 18: 10-YR Plan Work Plan 10-04-17 Draft 5 [Read-Only]resources.ca.gov/CNRALegacyFiles/wp-content/uploads/2017/... · 2017-10-03 · e a (a c r e s) Exposed Area Habitat Area Dust Suppression

18

TYPICAL CONCEPT2018 – 20232023 – 2028

Page 19: 10-YR Plan Work Plan 10-04-17 Draft 5 [Read-Only]resources.ca.gov/CNRALegacyFiles/wp-content/uploads/2017/... · 2017-10-03 · e a (a c r e s) Exposed Area Habitat Area Dust Suppression

19

Currently being updated to conform to theWater Board’s Stipulated Order

Currently moving forward with design for NewRiver West

Planning stages for Alamo North &Whitewater

CONSTRUCTION SCHEDULE

Page 20: 10-YR Plan Work Plan 10-04-17 Draft 5 [Read-Only]resources.ca.gov/CNRALegacyFiles/wp-content/uploads/2017/... · 2017-10-03 · e a (a c r e s) Exposed Area Habitat Area Dust Suppression

20

STIPULATED WATER BOARD DRAFT ORDER

ExposedArea

DustSuppression

0

10,000

20,000

30,000

40,000

50,000

2018 2020 2022 2024 2026 2028

Are

a(a

cres

)

Exposed Area Habitat Area Dust Suppression

Habitat

Page 21: 10-YR Plan Work Plan 10-04-17 Draft 5 [Read-Only]resources.ca.gov/CNRALegacyFiles/wp-content/uploads/2017/... · 2017-10-03 · e a (a c r e s) Exposed Area Habitat Area Dust Suppression

21

Provides path forward for implementingPhase 1 of 10-Yr Plan

Final section of document includes:

Timeline of Work Plan tasks References

IV. CONCLUSIONS

Page 22: 10-YR Plan Work Plan 10-04-17 Draft 5 [Read-Only]resources.ca.gov/CNRALegacyFiles/wp-content/uploads/2017/... · 2017-10-03 · e a (a c r e s) Exposed Area Habitat Area Dust Suppression

22

WORK PLAN REVIEW TIMELINE

Activity Timeframe

Draft Work Plan to Committees Sep 26, 2017

Review Comments from Committees Due Oct 27, 2017

Release to Public Early Nov 2017

Living Document / Updated as Needed

Work commencing in multiple areas while Work Plan is finalized

Page 23: 10-YR Plan Work Plan 10-04-17 Draft 5 [Read-Only]resources.ca.gov/CNRALegacyFiles/wp-content/uploads/2017/... · 2017-10-03 · e a (a c r e s) Exposed Area Habitat Area Dust Suppression

23

QUESTIONS / DISCUSSION