10 rob stephen - current trends in designing overhead transmission lines
TRANSCRIPT
1CIGRE
OPTIMAL LINE DESIGNS
R. StephenESKOM
PRESENTATION TO SC B2 ICELAND 2011
2CIGRE2
What is a power line?
• A device to transmit power over distances.• Design of the line can be tailor made to meet planner’s
requirements.• Load flow depends on R, X and B values.
3CIGRE
3
Maximise Power Transfer
• Zs is surge impedance• SIL is the surge
impedance loading• Reduce L and
increase C to maximise transfer
L is series inductance
C is shunt capacitance
VLL is phase to phase
voltage
4CIGRE4
Determination of R, X and B
• Resistance is a function of– Conductor construction material and line length
• Lay ratio, ACSR, AAAC, number of layers, diameter of strands.
– Temperature• The higher the temperature the higher the resistance
– Current and frequency• Transformer effect• Eddy currents.
5CIGRE5
Variation with current
Penguin(1+6)Tcond=80°C
1.00
1.02
1.04
1.06
1.08
1.10
1.12
1.14
0 100 200 300 400 500 600 700 800I(A)
Rac/
Rdc
Falcon(19+54)Tcond=80°C
1.00
1.02
1.04
1.06
1.08
1.10
0 1000 2000 3000 4000 5000 6000 7000 8000 I(A)
Rac
/Rdc
107 mm2
800 mm2
6CIGRE
6
Determination of L
• L is a function of GMR and GMD
• Larger bundle radius and closer phase spacing gives lower L
r’=0.7788xradius of conductor (m)
Rb=radius of bundle n=number of subconductors
7CIGRE7
GMD EXAMPLES
8CIGRE
8
Determination of C
• To increase capacitance keep phases closer together.
• P=1/C
9CIGRE
9
LINE MODEL
• X = jωL• B=jωC/2• R=R
10CIGRE10
Summary
• SIL (L and C) can be varied by– varying phase spacing closer is better– Increasing bundle size larger is better
• Resistance can be improved by– Varying lay ratios per layer (not practical)– Different materials– Homogeneous conductors
11CIGRE11
Corona limitations
• Corona (often producing audible noise) is a function (inter alia) of phase spacing and bundle size– Smaller bundle radius better– Wider phase spacing better– More sub conductor bundles better.
12CIGRE12
Audible noise as a function of voltage
13CIGRE13
Mechanical considerations
• Wind load is major consideration in tower design– Less conductors in the bundle the better– Less UTS the better (Lighter strain towers). Higher tension to
increase height.
14CIGRE
14
Thermal loading
• Load at which the safety or annealing criteria of the line is met– Current at which the height above the ground is in line with OHS
act– Height determined by voltage and flashover distance
• Heat Balance equation used.
15CIGRE15
Joule and magnetic heating
• Joule dependent on AC resistance and temperature• Magnetic heating dependent on current and conductor
layers.
16CIGRE
16
Solar heating
• Darkness of conductor• Diameter of conductor• Solar radiation
17CIGRE
17
Convective cooling
• Dependent on – the conductor diameter (bigger is better)– Wind speed– Temperature difference (bigger is better)– Roughness
18CIGRE
18
Templating temperature
• Templating temperature is the conductor temperature at which the height above ground is in accordance with the OHS act
ConductorTemplating temperature deg C
Normal Amps
Emergency Amps
TERN 50 611 814TERN 60 784 991TERN 70 911 1138TERN 80 1023 1257ZEBRA 50 642 859ZEBRA 60 818 1049ZEBRA 70 963 1203ZEBRA 80 1080 1325
19CIGRE19
SUMMARY
SIL Corona Mechanical loading
Thermal rating
Phase spacing decrease
Good Bad Good Neutral
Large al area/cond (less conductors)
Bad Bad Good Bad
Diameter Bundle increase
Good Bad Bad Neutral
High steel content
Neutral Neutral Bad Good
20CIGRE20
Planning requirements
• Planners need to specify the following– Load transfer requirements– Load profile daily, annual– RXB parameters, high and low– Line Voltage for AC– Length of line– Location, start and end points– Reliability requirements
21CIGRE21
Conductor size and temp
22CIGRE22
Material considerations
23CIGRE23
Material - core
24CIGRE
24
Conductor type
25CIGRE25
Selection of conductor
26CIGRE26
Indicator to determine best design
• Need to combine – SIL– Thermal rating– Cost initial and life cycle
• (Taking into account corona, magnetic fields, mech loading etc)
27CIGRE27
FACTOR 1 Life Cycle Cost (k1)
• Covers determination of optimum aluminium area required. (Kelvin’s law)
• Cost of maintenance (estimate)• Cost of losses – use system losses not line losses. (Due
to power flow in interconnected system)
28CIGRE28
FACTOR 2 THERMAL (k2)
• Cost is directly proportional to Thermal rating– Higher rating higher initial cost
• A ratio is therefore needed– Initial cost/MVA thermal (emergency or normal)
• The lower the ratio the better.
29CIGRE29
FACTOR 3 SIL (k3)
• The higher the SIL the higher the initial cost (normally)• Ratio is therefore also required
– Initial cost/MVA sil
30CIGRE30
COMBINATION OF THE FACTORS
• Objective Matrix method– Present practice is given 3/10– 0 or 10 level is determined (normally trial and error) and a linear
interpolation used.
• ATI = w1k1+w2k2+w3k3– wn are weighting factors
31CIGRE31
CONDUCTOR SELECTION
CONDUCTOR OPTIMISATION
0.00
100.00
200.00
300.00
400.00
500.00
600.00
700.00
800.00
900.00
0 100 200 300 400 500 600 700 800 900 1000 1100 1200 1300 1400
Pmean(MVA)
LCC
(Rm
il)
2 X IEC8004 X KINGBIRD3 X BERSFORT3 X TERN3 X YEW4 X TERN3 x Bersfort
4 x Tern
4 x Kingbird
3 x Tern
32CIGRE32
TOWER SELECTION
+ +
+
++
+
+ + + + +
+
+
+
+ +
+ ++
+
+
+
+
+
+
+
+
+
+
+
+ + +
+
+ +
+ +
+
+
+
+
+
+
+
+
+
+
+ +
+
+
+
+
SERVITUDE AND
suspensionCross- Rope
+
+
400kV
8.5m
Min.Conducto rclearance
Servitude
21.0m55.0m
28.0V V
VV
VV
V
V
36.0m(average)
+ +
+
+
MinimumConducto rclearance
+
+ +
+
+ + +
+
+ +
+
+ +
+ + +
+ + +
8.5m
V
VV
V
VV
+ + + +
+++
+ + + + +
+
+ +
+
+
+ + + + + + +
+
+ +
+ +
+
+
+
+ +
+
+
+
+
+ +
+ +
SERVITUDE AND400kV
Guyed suspensiontype
26.0m
Servitude
55.0m V
33.0m(average)
23.0mV V
33CIGRE33
Tower development
Proposed CRS 6% saving on line cost
Existing guyed V
34CIGRE34
Cost Savings
0-15 degree structures 15-30 degree structures
R0
R75,000
R150,000
R225,000
R300,000
R375,000
R450,000
Misc CostsInsulationHardwareTower ErectionTower SupplyFoundations
52% Saving
46% Saving
35CIGRE35
Performance comparison
Improved performance can give
0.05-0.1faults/100km/annum
36CIGRE
705A tower at NETFA
37CIGRE
EXAMPLE LINE
– .Quad “Zebra” guyed Vee tower– .Triple “Bunting” conductor guyed Vee tower– .Quad “Bunting” cross rope suspension (CRS) tower with a phase
spacing of 6,5m.– .Quad “Rail” conductor with a CRS tower with a 6,5m phase
spacing.– .Triple “Bittern” conductor with a CRS tower with a 6,5m phase
spacing.– .Quad “Boblink” conductor with a CRS tower with a 6,5m phase
spacing.– .Triple “Bersfort” conductor with a CRS tower with a 8,2m phase
spacing.
38CIGRE38
ATI SCORES
CASE AL AREA mm2
DESCRIPTION K1 (LCC) K2 (CI/MVAth)
K3 (CI/MVAsil)
1 1715 4XZEB V 103,53 [3,30]
28,13 [3,07]
7,43 [3,19]
2 1817 3XBUNT V 84,4 [6,25]
19.48 [5,20]
6,31 [5,38]
3 2423 4XBUNT CRS 6.5m
88,36 [5,64]
13.27 [6,73]
7,02 [3,96]
4 1935 4XRAIL CRS 6.5m
87,76 [5,73]
14.32 [6,47]
5,94 [6,12]
5 1933 3xBIT CRS 6.5m
82,91 [6,48]
17.86 [5,60]
6,31 [5,38]
6 2901 4Xbob CRS 6.5m
93,33 [4,87]
17.04 [5,80
8,06 [1,88]
7 2059 3xBers CRS 8.2m
80,41 [6,81]
16.23 [6,00]
6,30 [5,40]
39CIGRE39
ATI WEIGHTING
CASE W1;W2;W3 W1;W2;W3 W1;W2;W3 W1;W2;W3 0,8;0,1;0,1 0,6;0,2;0,2 0,4;0,3;0,3 0,2;0,4;0,4 1 2,82 [7] 2,89 [7] 2,96 [7] 3,03 [7] 2 5,80 [3] 5,67 [4] 5,55 [4] 5,42 [4] 3 5,23 [5] 5,18 [5] 5,14 [5] 5,09 [5] 4 5,56 [4] 5,74 [3] 5,93 [2] 6,11 [1] 5 6,04 [2] 5,90 [2] 5,77 [3] 5,63 [3] 6 4,33 [6] 4,21 [6] 4,08 [6] 3,96 [6] 7 6,42 [1] 6,24 [1] 6,06 [1] 5,88 [2]
40CIGRE40
FINDINGS/BENEFITS
• Tower, foundation, hardware, electrical designers work together with planners (iterative process)
• Indicator very sensitive and detects errors rapidly• Line optimisation is possible looking at overall line design.• Reliability is assumed constant for options• Cost system is critical• Most aspects of the line design are taken into account
41CIGRE
Double Circuit developments
42CIGRE
Comparison self supporting vs CRS
Bulk power transfer capacity 5,000 MWMax tower height (Self Support) 77,5 mMax tower height (Cross Rope) 53,2 mPerformance (Faults / 100 km / year) < 0,3Visually acceptable YesEfficient land use 57 %Conductor Bundle 8 x BersfortMax Altitude (AMSL) 1,650 mCountry wide application Yes
Self Support Tower (Figure 3a) Electric field (max) 9,7 kV /m Audible Noise 43,5 dBA Radio Interference 48,3 dBμV/m Magnetic Field (@ 523 A) 3,9 μT SIL 2,581 MW
Cross Rope Tower (Figure 3b) Electric field (max) 10 kV/m Audible Noise 49,8 dBA Radio Interference 56,3 dBμV/m Magnetic Field (@ 523 A) 4,3 μT SIL 2,904 MW
43CIGRE
CONCLUSIONS
• Line design options can be objectively determined• ATI is a guide from which options can be finalised.• Alignment with Planners requirements
44CIGRE
REFERENCES/ACKNOWLEDGEMENTS
• [Stephen 2004] Stephen R. “Use of indicators to optimise design of overhead transmission lines”. Paper 330-1 Shanghai Symposium, Cigré 2003. (Held in Lubljana April 4-6 2004)
• [Muftic]. Muftic D, Bisnath S, Britten A, Cretchley DH, Pillay T, Vajeth R “The Planning design and construction of overhead power lines” Published by Crown publications 2005 ISBN 9780620330428
• [Southwire] Overhead Conductor Manual First edition copyright 1994.
• Prof. C.T.Gaunt (UCT) acknowledged for comments and input.