1. welcome [documents.hants.gov.uk] · 1. welcome please take a look at the exhibition boards, ask...
TRANSCRIPT
This exhibition is an opportunity for local people to view and comment upon the preferred design for the Botley Bypass.
The progression of the scheme will be subject to securing planning permission and
funding.
Provide background for the Botley Bypass
Describe the technical work supporting the
bypass project
Describe the proposed route of the new
bypass
Describe potential mitigation measures for
the new bypass
Seek local views on the proposals to inform the
design process
www.hants.gov.uk
1. Welcome
Please take a look at the exhibition
boards, ask questions and complete
a questionnaire.
Hampshire County Council is developing a scheme for a new bypass for Botley. This exhibition aims to:
2. Botley Bypass Background
Botley Bypass has been proposed for many years and a route is formally safeguarded
in both the Eastleigh Borough and the Winchester City Local Plans.
Botley experiences a significant amount of traffic travelling along the A334 Botley High
Street, particularly during peak periods, causing noise and air quality issues and
difficulties for pedestrians and shoppers wishing to cross the High Street. The High
Street has been identified by Eastleigh Borough Council as an Air Quality Management
Area, where improvements are needed. Congestion along the route causes journey
time delays with stop-start conditions during peak periods.
Survey work has identified that whilst approximately 20% of traffic on the A334 Botley
High Street is local traffic, over 80% is through-traffic which has origins and
destinations outside of Botley Village. The through-traffic is largely associated with
vehicles travelling between the Fareham/eastern Hampshire areas and the North
Hedge End area/Winchester in the north. This includes traffic diverting from the
congested M3 and M27 motorways at peak times.
Forecast levels of new development in the wider Botley area over the next 20 years
combined with traffic growth is likely to compound existing traffic issues. The
completion of Whiteley Way associated with the build out of the proposed North
Whiteley development may also increase through-traffic in the Botley area.
For these reasons the justification for a bypass for Botley is now much greater than in
previous years. A new bypass could bring significant benefits to the High Street in
terms of reduced traffic volumes, improved pedestrian accessibility, improved air
quality, reduced noise pollution and enhanced quality of place.
3. Botley Bypass Previous Work
Key issues identified in 2013 which
required further consideration were as
follows:
• The proximity of the route to the high
voltage 132kV overhead power lines.
• The nature and location of the proposed
new bridge and associated abutments
across the River Hamble.
• The interface of the route with key
statutory undertakers plant including
Portsmouth Water 40” main water
supply, Esso pipelines and Southern
Gas Network supplies.
In 2013 a study was undertaken on behalf of Eastleigh Borough Council which investigated route options for the Botley Bypass which comprised a 1km on-line widening
of Woodhouse Lane and a 1.8km bypass from Woodhouse Lane to a new junction with the A334 and A3051. Outline design work was undertaken and options were
assessed.
Extract from Waterman Drawing CIV13798/C/SA/03/001/A02
Extract from Waterman Drawing CIV13798/C/SA/03/001/A02
4. Preferred Bypass Route
Botley Bypass Location Plan
On 31 March 2016 the County
Council’s Executive Member for
Environment and Transport
recommended that the historic route
for Botley Bypass, together with
design updates at the western end be
confirmed and that necessary design
and development work for the scheme
be progressed. In order to inform the
design process approval was also
given for consultation to be
undertaken on the preferred route.
In accordance with the
recommendation, design work has
recently been progressing for the
Botley Bypass, building upon work
previously undertaken for Eastleigh
Borough Council.
The construction cost (2015 prices) for
the Botley Bypass and the online
widening works on Woodhouse Lane
would be approximately £24 million.
New
Roundabout
New
Roundabout
Botley
Bypass Woodhouse
Lane Widening
& Realignment
A334
B3354
A3051
Maypole
Roundabout
A334
A334
• The bypass would be 1.8km in length and 7.3m wide
• The proposed route would be single-carriageway with a 40mph design speed
• The design includes a shared use footway / cycleway along the southern side
• The following modifications to the historically safeguarded route have been
made:
• The crossing of Winchester Street at the western end of the bypass
has been moved south to avoid costly statutory undertakers plant and
to reduce the impacts upon third party land.
• The River Hamble crossing has been adjusted, however it cannot yet
be totally fixed until ground investigations and ecological
investigations have been completed.
Profile of Bypass route compared to existing ground levels.
Extracts from EC Drawing EC/RJ567629/02/004/A - 21/04/16
5. Botley Bypass Design
In association with construction of the Botley Bypass it is planned to improve
Woodhouse Lane to help accommodate likely increases in traffic flow.
• It is proposed to widen Woodhouse Lane to 7.3m along 1.1km of its length
from just south of the existing junction with Winchester Street to the A334 at
Maypole roundabout.
• The improvements would include provision for right-turning traffic, an
improved facility for pedestrians and cyclists, and the realignment of a small
section of the road to the south of Woodhouse Gully to improve forward
visibility.
• Maypole roundabout is to be improved as part of committed off-site works
associated with forthcoming new development at Boorley Green.
Profile of Woodhouse Lane widening along its length
Extracts from EC Drawing EC/RJ567629/02/003/A - 21/04/16
6. Woodhouse Lane Design
7. Traffic Modelling
What is the Sub-Regional Transport Model (SRTM)
The SRTM is capable of assessing the impacts of transport schemes across the Solent sub-
region by forecasting changes in travel demand, road traffic, public transport patronage and
active mode use over time as a result of changing economic conditions, land-use policies
and development, and transport improvement and interventions (schemes).
The SRTM is a suite of linked models comprising the following components:
• The Main Demand Model (MDM) which predicts when, where and how journeys are
made.
• The Gateway Demand Model (GDM) which predicts demand for travel from ports and
airports.
• The Road Traffic Model (RTM) which determines the routes taken by vehicles through
the road network and journey times, accounting for congestion;
• The Public Transport Model (PTM) which determines routes and services chosen by
public transport passengers.
• A Local Economic Impact Model (LEIM) which uses inputs including transport costs to
forecast the quantum and location of households, populations and jobs.
All known developments for the Local Plan period and committed (funded) highway
schemes are included within the model scenarios to provide the most accurate
representation of future year conditions.
SRTM Coverage
The traffic and transport impacts of the proposed Botley Bypass have been assessed using the Solent Transport Sub Regional Transport Model.
The SRTM has been used to compare:
Year 2036 Do Minimum Scenario: including Local Plan Development in Eastleigh Borough
Vs.
Year 2036 Do Something Scenario: including Local Plan Development in Eastleigh
Borough plus Botley Bypass and associated infrastructure
8. Traffic Model Results
The traffic model output plots above show forecast changes in AM and PM traffic flows for the year 2036 through
Botley Village, comparing the Do Minimum scenario against a Do Something scenario where Botley Bypass is
implemented.
• The thick blue line represents a reduction in traffic along the A334 Broad Oak / High Street / Mill Hill
• To a lesser extent there is a decrease on the B3354 Winchester Road
• There is a slight decrease on Kings Copse Avenue
• The thick red line represents the traffic transferring onto the new bypass.
• There is an increase in traffic along Woodhouse Lane
• There is a slight increase in traffic on some of the key routes approaching Botley
2036 AM Peak Flow Difference (DM vs DS) 2036 PM Peak Flow Difference (DM vs DS)
The traffic modelling data provides a
robust evidence base which supports the
justification for a Bypass, due in part to
forecast levels of development in the wider
Botley area and traffic growth generally.
There will be significant benefits to the
A334 High Street through Botley due to
reduced traffic volumes.
Key:
Red Line = Increase
Blue Line = Decrease
Thicker line denotes larger change
Key:
Red Line = Increase
Blue Line = Decrease
Thicker line denotes larger change
9. Environment
Designated Sites A full Environmental Impact Assessment is being prepared for the scheme as part of
the planning process.
An Environmental Impact Assessment (EIA) is required to assess the potential
environmental impacts of all major schemes such as Botley Bypass. The aim of the EIA is
to protect the environment by ensuring that all potential impacts (either positive or negative)
are identified and, where appropriate, mitigation and enhancement strategies are
developed. The EIA will form a key part of the supporting information which will be required
to be submitted as part of a future Planning Application. The scope of the EIA is currently
being agreed with Statutory Consultees including the Environment Agency and Natural
England.
The preferred route for the Bypass crosses a number of locally designated sites which
need to be taken into consideration as part of the Environmental Assessment work.
In the upper reaches of the River Hamble, north of Botley Mill, the bypass would cross two
Sites of Importance for Nature Conservation (SINC), on either side of the river. Further
south from the point at which the bypass would cross, the River Hamble is designated at
European level as a Special Protection Area (SPA). Half way along its length Woodhouse
Lane crosses Woodhouse Gully. To the west of Woodhouse Lane Bushy Copse is
designated as a SINC on both sides of the Gully.
10. Environment
As part of the EIA a number of different topic areas need to be assessed. The first stage of the EIA involves the collection and review of all available baseline data along
with the identification of all potentially sensitive environmental features and receptors. Following a desktop appraisal, initial site specific survey work is undertaken to help
inform where more detailed survey work will need to follow on and to help build up a comprehensive evidence base which will be used to help identify appropriate
mitigation. Initial survey work is currently underway in order to help inform the design of the bypass. Some of the key topic areas are highlighted below.
Noise and Air Quality
Increases and decreases in noise levels are assessed in
relation to identified sensitive receptors including nearby
properties. Noise monitoring equipment is used to
identify existing levels of noise. Forecast changes in
traffic movements are used to predict the changes in
noise levels in the future both during construction and
post scheme completion. Whilst reductions in traffic
through Botley High Street are likely to lead to a
reduction in noise, conversely there is likely to be an
increase in other areas closer to the bypass route.
Botley High Street is an identified Air Quality
Management Area. Reductions in traffic will be quantified
and changes in air quality will be identified.
Ecology and Nature Conservation
Ecological surveys will be ongoing for several
months to help identify the types and numbers
of species (including protected) which could be
found on and around the site. Survey seasons
for each species vary depending upon potential
hibernation, migration, and breeding seasons;
hence the overall survey timescale can be
lengthy and in some cases as long as 24
months. As part of the ecological work stream a
Phase 1 Habitat Survey is used to help provide
an understanding of potential impacts.
Landscape and Visual Effects
The assessment of impacts upon the landscape
are assessed from identified viewpoints in the
vicinity of the preferred Bypass route and from
nearby notable features. Particular attention is
given to views from public paths or nearby
properties or roads. The impact upon trees is a
key issue and tree surveys are included as part
of the EIA in order to identify notable trees and
trees with Tree Preservation Orders. The
impacts upon heritage assets including listed
buildings are also assessed.
Water and Drainage
An assessment of the potential impacts upon
surface and ground water quality, drainage and
flood risk is a critical part of the EIA, which has
to be completed in accordance with a
substantial legislative framework.
A key issue along the route is the River
Hamble and associated flooding and
particularly flood risk during exceptional
circumstances. Predicted surface water run-off
from the new bypass is also a key area for
assessment.
11. Environmental Mitigation
Environmental Surveys
Assessment of scheme impacts
Identification of need for mitigation
Mitigation design informs highway
design
Bypass design finalised
The need for environmental mitigation will be identified for
each of the EIA topic areas following survey work. This may
result in modifications to the bypass design, or additional
features may be required to mitigate the environmental
impacts of the scheme.
Mitigation could include:
• Replacement / enhancement of ecological habitats.
• Relocation of protected species, (e.g. badgers).
• Noise attenuation measures (e.g. bunds, acoustic
fencing)
• Replacement landscape planting / screening.
• New and improved footway / cycleway provision.
• Sustainable Drainage Systems (SUDS).
• Flood management measures. Balancing Pond Swale
Bat Boxes Fish Ladder
Landscape Bund Acoustic Fence
Sustainable Drainage Mitigation
Ecological Mitigation
Noise Mitigation Badger Tunnel
Acoustic Fence & Bund
12. Where next?
June/July 2016
Public Consultation
Autumn 2016
Report to Executive Member for
Environment and Transport to provide
consultation feedback
2016/17
Transport Assessment
Progression of design
Environmental Impact Assessment
Business case
2017
Submission of Planning Application
2018/2019/2020
Delivery of Botley Bypass subject to securing funding
Contact us:
Strategic Transport
Hampshire County Council
The Castle
Winchester
Hampshire
SO23 8UJ
Email address: [email protected]
Phone:
0300 555 1388
What do you think?
Your views are important
Your feedback will help inform the design process for the Botley Bypass. A report will be taken to
Hampshire County Council’s Executive Member for Environment and Transport later in the year which
summarises the feedback from the consultation and highlights any amendments which may be required to
the scheme in light of comments received.
Please fill out a paper questionnaire to let us know what you think. Questionnaires are available at the
public exhibitions or alternatively go online at www.hants.gov.uk/botley-bypass to leave your comments.
This exhibition material is also available to download on this website.
Thank you for visiting the exhibition. We hope you found it informative.
www.hants.gov.uk