Utilities Department
Orange County Board of County Commissioners
June 10, 2014
TYMBER SKAN CONDOMINIUMSTYMBER SKAN CONDOMINIUMS
2
• BackgroundBackground• Is Sub-metering the Right Is Sub-metering the Right
Approach?Approach?• Proposed PlanProposed Plan• Next StepsNext Steps
Presentation Outline
3
• BackgroundBackground• Is Sub-metering the Right
Approach?• Proposed Plan• Next Steps
Presentation Outline
Section-3Section-3(19 buildings)(19 buildings)
Section-2Section-2 (15 buildings)(15 buildings)
Section-1Section-1 (13 Buildings)(13 Buildings)
Lake Catherine
5
• Delinquent water and wastewater utility bills in Delinquent water and wastewater utility bills in Sections 1 and 3Sections 1 and 3- Orange County Utilities provides wastewater Orange County Utilities provides wastewater
serviceservice- OUC provides potable water serviceOUC provides potable water service
• Ambiguity in meter configurationAmbiguity in meter configuration- Master meter versus sub-metering- Master meter versus sub-metering
• Water shutoff was pendingWater shutoff was pending- Door hangers – June 9, 2014Door hangers – June 9, 2014- Disconnection of water – June 30, 2014Disconnection of water – June 30, 2014
Background
6
Actions Since Last MeetingActions Since Last Meeting• Inspected neighborhood for metering Inspected neighborhood for metering
configurationconfiguration- 2 site visits-Verified Sections 1 & 3 have outdated sub-metering infrastructure
• Held 3 meetings with OUCHeld 3 meetings with OUC•Outstanding debtOutstanding debt•Solutions moving forwardSolutions moving forward
Background
7
• Background• Is Sub-metering the Right Is Sub-metering the Right
Approach?Approach?• Proposed Plan• Next Steps
Presentation Outline
8
Challenges• Cost of new meters• Access and utility easements• Service disconnections
- Who has the authority?• Delta between master meter flow and cumulative
individual property flows-Leaks-Unauthorized residents-Non-payment action
Is Sub-metering the Right Approach?
9
• Background• Is Sub-metering the Right
Approach?• Proposed PlanProposed Plan• Next Steps
Presentation Outline
10
• County/OUC will negotiate settlement on debt• Forego immediate infrastructure improvements• Establish flat rate for water and wastewater services
- Based on size of dwelling- To include master meter costs and infrastructure
maintenance• All services on OUC bill• Contingent on pre-pay option
- Non-payment will result in disconnection of electricity
Proposed Plan
11
• Background• Is Sub-metering the Right
Approach?• Proposed Plan• Next StepsNext Steps
Presentation Outline
12
• Meetings with court appointed receiver- Provide authority for OUC to serve customers
directly- Trespass unauthorized residents
• Establish fixed rate • Public meetings to help residents sign up
for service• Negotiate settlement with OUC on
outstanding debt
Next Steps