1 update on the 2006 transmission study lpsc b&e meeting baton rouge, la november 29, 2006
TRANSCRIPT
1
Update on the 2006 Transmission Study
LPSC B&E Meeting
Baton Rouge, LA
November 29, 2006
2
Current Status of the Amite South Area
• At the time of the Phase II Study, peak load in the Amite South area was 6,200 MW, and the Amite South import limit was 2,100 MW – resulting in a difference of 4,100 MW between load and import capability.
• Since Hurricane Katrina, peak load in the Amite South area has dropped to 5,670 MW. Meanwhile, the Amite South import limit has been increased to 2,600 MW – resulting in a difference of 3,070 MW between load and import capability.
• Reliance upon generation within Amite South on peak has dropped by more than 1,000 MW since the Phase II Study.
• One purpose of the 2006 Transmission Study is to determine whether and when additional projects should be implemented to improve the Amite South import limit at a projected cost of $32 million for Phase II and $16 million for Phase III.
3
0
1,000
2,000
3,000
4,000
5,000
6,000
1994
1995
1996
1997
1998
1999
2000
2001
2002
2003
2004
2005
2006
2007
2008
2009
2010
2011
Year
MW
ASI Capability
AS Area Peak Load *
Coly-Vignes-Sorrento 230 kV Line Constructed
ASI Phase 1Conway-Panama
230 kV Line Constructed
Expected ASI Capability of 2,950
MW upon completion of ASI Phases 2 & 3
Load Loss Due to
Hurricane Katrina
Load Loss Due to
Georgia Gulf Cogen
Load Loss Due to Occidental Cogen
* 1994-1999: Deduced* 2000-2005: Actual* 2006-2011: Projected
1,800 MW2,100 MW
2,600 MW
Amite South Load and Import Data
5,800 MW
6,170 MW
5,670 MW
4
Events/Factors AffectingAmite South Import Capability
Event Effect on ASI Capability• 1997 – Construction of the Coly-Vignes-Sorrento 230 kV line and the
installation of approximately 300 MW of cogeneration by Georgia Gulf; together with load growth and other generation additions at the Exxon facility in Baton Rouge Cost - $9.1 Million
• Increased ASI capability to 2,100 MW
• 2001 – Upgraded Willow Glen-Gonzales 138 kV line
Cost - $4.5 Million
• Dispensed with need for an operating guide and maintained ASI capability
• 2001 – Installed 230/115 kV 200 MVA autotransformer at Sorrento
Cost - $4.5 Million
• Improved reliability to 138/115 kV transmission corridor and maintained ASI capability at 2,100 MW
• 2005 – Constructed Conway-Panama 230 kV line, and installed dynamic line rating equipment on Panama-Romeville 230 kV line
Cost - $19.8 Million
• Increased ASI capability to 2,600 MW
• Future – Plans to construct Phases 2 & 3 of the ASI Improvement Plan: Phase 2 – new Panama-Dutch Bayou 230 kV line; Phase 3 – upgrades of Coly-Vignes-Sorrento & Conway-Bagatelle 230 kV lines. Need for and timing of improvements to be determined by the ongoing 2006 Transmission Study. Projected cost - $48 Million
• Phase 2 expected to increase the ASI capability to 2,835 MW; Phase 3 expectation is to 2,950 MW
5
MISSISSIPPI
EVERGREEN
DONALDSONVILLE
WELCOME
BAYOUVERRET
ST. JAMES
VACHERIE
FRISCO
CONVENTSUNSHINE
ROMEVILLE
BAGATELLE
CONWAY
GONZALES
FRENCHSETTLEMENT
SORRENTO
SORRENTO
RIVER
DUTCHBAYOU
VIGNESPLAQUEMINE
WEBRE
LUTCHER
LITTLEGYPSY
COLY
WILLOW GLEN
BELLE POINT
PANAMA
LEGEND
230 kV Line
115 kV Line
500 kV Line
New or Upgraded Line
Amite South Import Improvement Plan
1
2
3
3
Phase 1:Build 230 kV Line(Conway-Panama)Completed in 2005
Phase 2:Build 230 kV line(Panama-Dutch Bayou)
Phase 3:Upgrade 230 kV Lines(Coly-Vignes-Sorrento & Conway-Bagatelle)
1
2
3
WATERFORD
6
OASIS Postings• Beginning on June 9, 2006, the
transmission organization commenced posting on OASIS the data and information that is needed by the System Planning Organization for the PROMOD analyses to be conducted as part of the 2006 Transmission Study.
• This transmission information is being used to develop a PROMOD base case for the study, and to develop the necessary “change cases.”
• Various study scenarios will be evaluated:
– Four potential projects have been identified relating to the Amite South and DSG areas. These projects will be evaluated first.
– Five potential projects also have been identified relating to the Western Region in Texas.
• Two additional study scenarios have been identified recently by SPP. The projects proposed by SPP also will be posted and evaluated as part of the 2006 transmission Study.
Entergy’s main OASIS site: http://oasis.e-terrasolutions.com/OASIS/EES