1) the existing and proposed facilities and capacities

23
Compliance to the additional information sought by EAC w.r.t EC of M/s Vikram Private Ltd. Ref: Item No-31.4, 31 st meeting of Expert Appraisal Committee on Industry-I, 7 th -9 th May, 2018. 1) THE EXISTING AND PROPOSED FACILITIES AND CAPACITIES ALONG WITH THEIR CUMULATIVE SHALL BE GIVEN IN TABULAR FORM. Sl No Facilities Existing Configuration as per EC- J11011/533/2010- IA.II(I), 26.12.2012 Existing capacity Proposed configuration Proposed capacity Final configuration Cumulative capacity 1 DRI kiln 2x100 TPD 66,000 TPA Nil NA 2x100 TPD 66,000 TPA Sponge iron 2 Iron Ore Beneficiation 0.85 MPTA Under construction Nil NA 0.85 MTPA 3 Pelletization Plant 0.60 MTPA Under construction Nil Nil 0.60 MTPA 6,00,000 TPA pellet 4 CPP(WHRB + AFBC) 4MW WHRB 6MW-AFBC Under construction Nil NA 4MWWHRB 6MW-AFBC 10 MW 5 Induction Furnace with LRF & CCM Nil Nil IF 3x15T LF 1x30T 1,07,000 TPA IF 3x15T LF 1x30T 1,07,000 TPA , Hot metal 6 Rolling Mill Nil Nil 20 TPH 1,00,000 TPA 20 TPH 1,00,000 TPA TMT rods

Upload: others

Post on 24-May-2022

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 1) THE EXISTING AND PROPOSED FACILITIES AND CAPACITIES

Compliance to the additional information sought by EAC w.r.t EC of M/s Vikram

Private Ltd.

Ref: Item No-31.4, 31st meeting of Expert Appraisal Committee on Industry-I, 7th -9th

May, 2018.

1) THE EXISTING AND PROPOSED FACILITIES AND CAPACITIES

ALONG WITH THEIR CUMULATIVE SHALL BE GIVEN IN TABULAR

FORM.

Sl

No

Facilities Existing

Configuration as

per EC-

J11011/533/2010-

IA.II(I),

26.12.2012

Existing

capacity

Proposed

configuration

Proposed

capacity

Final

configuration

Cumulative

capacity

1 DRI kiln 2x100 TPD 66,000 TPA Nil NA 2x100 TPD 66,000 TPA

Sponge

iron

2 Iron Ore

Beneficiation

0.85 MPTA Under

construction

Nil NA 0.85 MTPA

3 Pelletization

Plant

0.60 MTPA Under

construction

Nil Nil 0.60 MTPA 6,00,000

TPA pellet

4 CPP(WHRB

+ AFBC)

4MW –WHRB

6MW-AFBC

Under

construction

Nil NA 4MW–WHRB

6MW-AFBC

10 MW

5 Induction

Furnace

with LRF &

CCM

Nil Nil IF 3x15T

LF 1x30T

1,07,000

TPA

IF 3x15T

LF 1x30T

1,07,000

TPA , Hot

metal

6 Rolling Mill Nil Nil 20 TPH 1,00,000

TPA

20 TPH 1,00,000

TPA TMT

rods

Page 2: 1) THE EXISTING AND PROPOSED FACILITIES AND CAPACITIES

2) CERTIFIED COMPLIANCE REPORT OF THE EXISTING EC

CONDITIONS FROM THE REGIONAL OFFICE OF THE MINISTRY.

Page 3: 1) THE EXISTING AND PROPOSED FACILITIES AND CAPACITIES
Page 4: 1) THE EXISTING AND PROPOSED FACILITIES AND CAPACITIES

3) DETAILED PLAN FOR 100% UTILIZATION OF SOLID WASTES.

COMMITMENT THAT NO SOLID WASTE SHALL BE DUMPED WITH THE

PLANT PREMISES.

DRI kilns will produce char and beneficiation plant will produce tailings. The steel

melting shops and other downstream units will produce scrap, slag and dust where as

the raw material handling and preparation plant will generate dust and fines.

Unit Solid Waste Existing

generation

quantity

(TPA)

Proposed

generation

Quantity

(TPA)

Total

quantity

(TPA)

Management

DRI Plant Dolochar 44,000 - 44,000 Fuel for AFBC

Power Plant

Accretion 3,000 - 3,000 Low land filling

&road

construction

Refractory 40 - 40 Sale

I/O Beneficiation

Plant

Slime Cake 1,18,000 - 1,18,000 Concrete

aggregate

making or sale

I/ O Pelletisation

Plant (+62 % Fe )

with dry grinding

Pellet Fines 12,500 - 12,500 Recycled to Pellet

plant

I/O Pelletisation

Plant (55-62 % Fe)

with wet grinding

Pellet Fines 25,000 - 25,000 Recycled to Pellet

plant

Power Plant Fly Ash &

Bottom Ash

84,475 - 84,475 Brick making

Steel Making

Shop

IF Slag - 10,500 10,500 construction

work after iron

recovery

Page 5: 1) THE EXISTING AND PROPOSED FACILITIES AND CAPACITIES

Refractory - 200 200 Sale

Damaged

Mould

- 300 300 Recycle to IF

Rolling Mill Mill Scale - 3,000 3,000 Recycle to

IF/Sale to Sinter

Plant

Miss-rolled

Bar

- 4,000 4,000 Recycle to IF

Damaged Roll - 25 25 Recycle to IF

Total 2,10,500 18,025 2,71,565

Fly Ash

Fly Ash generated from DRI Kiln : 60 tpd x 300 days = 18,000 TPA

Ash generated from coal burning @ 40% ash with 3325 kcal/kg = 20,000 TPA

Fly Ash from dolochar burning @ 82 % ash with 1100 kcal/kg = 41,000 TPA

Bottom Ash generation due to use of bed material = 5,475 TPA

Total Fly ash & Bottom ash generated = 84,475 TPA

The fly ash generated from process is fully utilized in company’s brick manufacturing

machine of capacity 1,00,000 bricks per day. The company also purchases fly ash from

outside to meet the demand of production. Fly ash brick requires 70% fly ash & Bottom

Ash, 7 % lime & gypsum/cement and 15 % sand. The bricks produced are 3.5 kg

confirming to IS 12894:2002 specification.

1,00,000 nos. x 0.7 x 0.0035 T x 360 = 88,200 T

SMS Slag

Solid waste like scraps from SMS & Rolling mill and raw material fines shall be recycled

to IF. Other non-hazardous disposable solid waste like IF slag contains about 15 % iron

and rest silica hence, shall be disposed in low lying areas & used in road making after

crushing of slag and magnetic separation of Iron.

Page 6: 1) THE EXISTING AND PROPOSED FACILITIES AND CAPACITIES

Thus it can be concluded that with the adequate solid waste management practices, the

impact of solid waste on various attributes of environment like; air, water, soil, land,

ecology and socio-economic aspects will be marginal. In this way the waste from

proposed expansion steel plant will be minimized through reuse/recycle/recover

process.

Tailing Management

M/s Vikram Private Ltd has proposal for 0.85 MTPA iron ore fine beneficiation plant.

Iron ore fines received from mine end will have two fractions, one having +62% Fe

content and other having 55-62% Fe content. These are to be screened separately. +5mm

products will be directly used in DRI Kilns for production of Sponge iron. -5mm high

grade product having +62% Fe will be ground dry and pelletized. This will constitute

0.2 MTPA pelletization.

Balance from 0.85 MTPA i.e. 0.65 MTPA with Fe content 55-62%, will be ground wet

and undergo wet beneficiation to get 0.40 MTPA concentrate having Fe content > 65%

and 0.25 tailings having Fe content < 40%. Tailings will undergo thickening using

flocculants, pass through filter press and tailing cake having about 15% moisture comes

to be 0.28 MTPA. The cakes will be stacked over concrete floor and under shed for

disposal. The company is in the process of making agreement with M/s S.A. Halim

Mines, Koira for disposal of tailing cakes in abandoned Iron Ore Mines.

However exploration will be made for utilization of Iron ore tailings cakes as a partial

substitute for natural sand to prepare concrete. It reduces the amount of natural sand,

solves the environmental pollution problem of iron ore tailings, and promotes the

development of green building projects.

Findings showed that the performance of the concrete with 35% replacement of iron ore

tailings is basically equivalent to that of natural sand concrete. Hence, it can be utilized

in engineering applications.

Source: Advances in Materials Science and Engineering, Volume 2016, Article ID 8606505,

4) DISASTER MANAGEMENT SHALL BE BASED ON HIRA. THERE ARE

SEVERAL HAZARDS OTHER THAN FIRE IN LDO AND FO STORAGE

TANKS.

The process of HIRA (Hazard Identification and Risk Assessment) is to :

A. Spot the Hazard (Hazard Identification)

B. Assess the Risk (Risk Assessment)

C. Make the Changes (Risk Control)

Page 7: 1) THE EXISTING AND PROPOSED FACILITIES AND CAPACITIES

Hazard can be spotted from

1. Machinery & Equipments

Hence following steps are to be taken

Machineries & Equipments are to be regularly serviced and maintained

according to the manufacturer’s instructions.

Operators must have the appropriate knowledge and training necessary to

handle

Machinery and equipment.

All equipments must have guarding to prevent operators and others

accessing hazardous parts.

2. Slips, trip and falls

All walkways/stairways/ramps to be kept clear of boxes, rubbish, leads, or

other trip hazards.

Floor surfaces must have sufficient grip to prevent slipping when wet or

contaminated. Workers to be provided with safety shoes that is suitable for

the work environment.

All areas must be well lit so people can do their jobs safely.

All ladders for use must be stable and in good condition and only to be used

for the purpose for which these were designed. (ladders should be rated for

industrial use and have a load rating of at least 120 kg.)

3. Electrical

All electrical equipments must be in good condition and free from damage.

All electrical equipments must be inspected and tested by a competent person

(e.g. electrician) and connected through a safety switch.

Leads to be kept away from sources of damage (e.g. water, heat or vehicles)

Damaged equipment, plugs, leads and/or sockets must be immediately

removed from service

Page 8: 1) THE EXISTING AND PROPOSED FACILITIES AND CAPACITIES

4. Anticipated Hazard Scenarios

Sl. No.

Area/Activity Hazard Impact

1 Storage and Handling of LDO

Pool fire / Fire ball may occur in case of direct contact with flame.

Fire may propagate to the nearby areas leading into fire hazard.

2 Storage and Handling of Furnace Oil (FO)

Pool fire/ fire ball may occur in case of direct contact with flame.

Fire may propagate to the nearby areas leading into fire hazard

3 Transfer of molten metal from I F to tundish of Rolling mill

Failure of sling and spill liquid iron on ground

Burning of equipments, injure work men, may be fatal accident. If molten iron comes in contact with water can immediately form Hydrogen, which is flammable and has explosive range in air from 4 to 74 %. Explosion is sudden expansion of volume which can damage confined building.

4 LDO firing in DRI Kilns

Back firing. Back firing may take place means flame may travel back to out side kiln

Injure even burn operator, specially face.

5 Taking up job inside DRI kiln, ESP, bag filter and other confined vessels

Heavy electric shock, suffocation

Electrocution and suffocation may cause even death.

6 Billet caster & Rolling mill section

Personal contact with red hot billet

Burn injuries

Pool Fire in LDO Storage Tank.

Out of three models done for this scenario it is found that, Credible Hazard shall

occur in Winter Season at Night Time. In this case, the Significant Heat Levels

(SHL), of interest for the Pool Fire, as predicted by the model shall be as per the

following table:

Page 9: 1) THE EXISTING AND PROPOSED FACILITIES AND CAPACITIES

There are three significant “Heat Levels” of interests which are as follows:

Significant

Heat Level

Value Experience

at Distance

Of

Indication

SHL-1 4.5 kW/m2 9.57m Causes pain if unable to cover the

body within 20sec.

SHL-2 12.5 Kw/m2 5.91m Minimum energy required for

melting of plastic.

SHL-3 37.5kW/m2 3.51m Sufficient to cause damage to the

equipment.

Therefore, the three levels of thermal radiations of interest i.e. 4.5 kW/m2, 12.5kW/m2,

37.5kW/m2 shall be experienced at a distance of 9.57m, 5.91m and 3.51m respectively.

As there may be other nearby establishments, the fire from LDO tanks can easily spread

causing extensive damage to the materials. Therefore vulnerable equipments are not to

be installed within 10m radius of LDO tank. On the basis of above consideration the

pool fire due to fire hazard in the LDO storage tank is not considered as most credible

scenario.

Explosive mixture formation due to spillage of liquid metal on wet ground

Spillage of liquid Iron on watery area produces Hydrogen. Hydrogen has Low

Explosive Level at 4% in air and 74% is high explosive Level. Below 4% Hydrogen does

not burn in air and beyond 74% it burns without explosion. In this case it comes under

explosive range, but in open space this can not damage things due to sudden increase of

volume. But spillage causing damage to equipments and injury or even death to

working personnel can not be ruled out. Hence although transfer of liquid metal

transfer is over head, area below to be barricaded during transfer of liquid metal.

Back firing in DRI kilns

Flame has a propagation velocity depending upon characteristic of fuel and oxygen rich

atmosphere. Hence velocity of fuel mixture must be higher than flame velocity, other

wise flame may travel towards fuel, causing back fire and burn injury to working

personnel. Tripping of ID fan during LDO firing or starting LDO firing without running

ID fan of DRI kilns. Inter locking ID fan running with LDO firing can prevent this kind

of mishap.

Page 10: 1) THE EXISTING AND PROPOSED FACILITIES AND CAPACITIES

Jobs in confined space

If proper air circulation in not ensured in side confined vessels and electrical jobs like

welding/cutting is taken up resistance of skin of human being decreases, hence only

24V lamps or welding hand sets to be used.

Burn injuries

For prevention of burn injuries asbestos or leather hand gloves are to be used.

Handling gas cylinders

Gas cylinders shall not be lifted on bare slings. For lifting the cylinders, cage of suitable

size shall be used and all cylinders shall be horizontally positioned in it. Such cage shall

have fencing in such a way that there is no possibility of fall of cylinders from this cage

5) CRITERIA FOR SELECTION OF SAMPLING LOCATIONS AND THE

PARAMETERS SELECTED FOR ANALYSIS OF AIR, WATER AND SOIL

SAMPLE.

Air Environment:

The air quality in two locations in core zone and ambient air quality in six locations in

impact (Buffer) zone i.e. 10 Km radius of the study area around the proposed site

formed the baseline information over which the predicted impacts has been

superimposed to find out the net impacts on the air quality of the surrounding

environment. The location of the network of ambient air quality monitoring stations in

the study area was based on the following criteria.

Meteorological conditions like downward prevailing wind direction

Representation of the site like sensitive areas, village roads

Influence of the existing sources like urban & Industrial area, infrastructures

Major human settlements in the study area

Air pollution in the project area is minimal despite of the presence of industries in the

surrounding. The prominent sources of air pollution in the study area are due to

emission from industries, vehicular movement, mining activities and utilization of

domestic fuel.

The pollutants of concerned area are Particulate Matter (PM10 and PM2.5), SO2 and NOX.

Ambient air quality monitoring in the study area was carried for the pollutants as per

the project requirement. The selected sampling locations for air quality study are shown

in Figure below Air quality monitoring stations were selected using simulation models

within the study area keeping in view the topographical and the meteorological

conditions. All the ambient air quality monitoring stations were installed on flat roof, at

Page 11: 1) THE EXISTING AND PROPOSED FACILITIES AND CAPACITIES

least 3m above the ground level with no obstructions and ensuring free flow of the

wind.

Details of Ambient Air Quality Monitoring Locations

Station

Code

Location Distance(

Km)

Directio

n

Latitude &

Longitude of the

site

Location Selection Criteria

CA1 Main gate 21050’17.03”N

840 55’ 37.76” E

-

CA2 Admin

Building

- - 210 50’ 19.08” N

840 55’ 49.51” E

-

BA1 Banei 2.7 E 210 49’ 24.73” N

840 57’ 11.18” E

Location having settlement &

road infrastructure with urban

type settlement (Criteria 4)

BA2 Baidpali 3.3 SW 21048’53.43”N

840 54’ 26.59” E

Rural village with access road

(Criteria 2)

BA3 Pandua 5.29 NW 21047’17.25”N

840 53’ 57.62” E

Rural village with access road

(Criteria 2)

BA4 Jibika 5.67 W 21050’23.04”N

840 52’ 24.34”E

A junction village between

Banei and Satakuta along the

River.

(Criteria 2)

BA5 Lahunipara 5.99 SE 21052’55.10”N

840 56’ 06.72” E

Point of the area mostly due to

industrial activities and a north

reference point on the Leeward

side of the wind direction

(Criteria 1 & 3)

BA6 Katupada 6.6 SW 21052’16.68”N

840 56’ 40.13”E

Village below Banei in Topo-

sheet with traverse Road.

(Criteria 2)

BA7 Sibnathpur 7.23 SW 21047’52.14”N

840 52’ 03.40” E

Location is near the Porhagoth

RF.

(Criteria 2)

BA8 Kenaveta 9.23 N 210 45’ 21.93”N

840 54’ 38.01” E

Location near to NH-23

(Criteria 3)

CA : Core zone BA : Buffer zone

Page 12: 1) THE EXISTING AND PROPOSED FACILITIES AND CAPACITIES

Map Showing the Sampling Locations:

The parameters measured for the proposed project is as follows:

Techniques used for Ambient Air Quality Analysis

Sl. No. Parameter Technique Technical Protocol

1 Particulate Matter (PM10)

Respirable Dust Sampler (Gravimetric Method)

IS: 5182 Part IV

2 Particulate Matter (PM2.5 )

FP Sampler (Gravimetric Method) IS: 5182 Part IV

3 Sulphur Dioxide Modified West and Gaeke method IS: 5182 Part II

4 Oxides of Nitrogen Jacob & Hochheiser method IS: 5182 Part VI

5 Carbon Monoxide Gas Chromatography IS: 5182 Part X

Page 13: 1) THE EXISTING AND PROPOSED FACILITIES AND CAPACITIES

WATER ENVIRONMENT

Selection of Sampling Locations

Some general criteria for selecting appropriate sampling sites are summarized under

the following points:

Reference station up-stream of all possible discharge points. The usual purpose

of a monitoring exercise is to determine the degree of man induced pollution,

and the damage that is caused. The reference station serves to assess the situation

with respect to background water quality and biological aspects,

The project site is by the side of River Brahmani which does not have polluted

stretch as identified by CPCB/MoEFCC. No waste water from the project is

discharged to river Brahmani or any other water bodies hence, sampling from

100m upstream or downstream were not envisaged

Protocols and Standards followed

Water Samples were collected from 8 locations. These samples were taken as grab

samples and were analyzed for various parameters to compare with the standards for

drinking water as per IS: 10500 for ground water sources and IS: 2296 for Surface water

sources. The water Sampling Locations are identified as per drainage pattern. The

selection of parameters as per respective IS specifications.

Surface water monitoring

A number of water samples from river, nala, pond, dug well & bore well were collected

from different locations within study area. The water samples were collected and

analyzed for physical, chemical and microbiological characteristics as per CPCB

guidelines and approved methods.

Sampling locations for surface water

Locatio

n

Code

Location Distanc

e (Km)

Direction Latitude &

Longitude of

the site

Location Selection Criteria

SW1 Up Stream of

Brahmani river

3.59 W 21050’18.68”N

840 53’ 34.10” E

Referential point for

pollution load estimation.

SW2 Down Stream of

Brahmani river

2.11 E 21050’18.30”N

840 56’ 58.05” E

Measurable point for all

discharge facts

Page 14: 1) THE EXISTING AND PROPOSED FACILITIES AND CAPACITIES

SW3 Barahpanda Jor

nala

4.04 NE 210 51’ 00.19” N

840 57’ 51.84” E

Actual conditions & water

quality

SW4 Rukuna nala 8.05 SWW 210 49’ 39.44” N

840 51’ 01.34” E

Type and behavior of the

nala on a typical factor

SW5 Pond Water of

Pandua

6.37 SW 210 47’ 08.22” N

840 54’ 07.11” E

Near settlement having

pond

SW6 Pond Water of

Pandrisila

4.91 S 210 47’ 37.22” N

840 55’ 36.61” E

Near settlement having

pond

SW7 Pond Water of

Bhaldungri

9 NW 210 51’ 22.55” N

840 50’ 30.87” E

Having an industrial

township and related

discharge

SW8 Pond Water of

Saradhapur

2.28 N 210 51’ 30.59” N

840 55’ 47.43” E

A transitory pathway of

natural flow of water

Ground water Sampling Location

Location

Code

Location Distance(Km) Direction Latitude &

Longitude of the

site

Location Selection

Criteria

GW1 Pandua 5.65 SW 210 47’ 07.94” N

840 54’ 06.99” E

Nearer to pond being

used as washing &

bathing purposes

GW2 Pandrisila 4.07 S 210 47’ 37.22” N

840 55’ 36.61” E

Public Pond Nearby

GW3 Sibnathpur 8.10 SW 210 48’ 07.91” N

840 51’ 21.82” E

Reference Sample

GW4 Baneigarh 3.11 SE 210 49’ 21.82” N

840 57’ 25.15” E

Thickly populated area

GW5 Rajamunda 3.89 N 210 51’ 57.71” N Thickly populated area

Page 15: 1) THE EXISTING AND PROPOSED FACILITIES AND CAPACITIES

840 55’ 28.16” E

GW6 Kenapali 2.77 NE 210 50’ 55.51” N

840 56’ 46.39” E

Nearer to plant site

GW7 Bad- Turamera 5.00 W 210 50’ 02.43” N

840 52’ 46.95” E

Settlement and public

pond

GW8 Jharbeda 6.12 SW 210 48’ 41.16” N

840 52’ 20.34” E

Reference Sample

SOIL ENVIRONMENT

The primary objective of soil sampling are to determine the average nutrient status and

degree of variability in a field so as to decide the nutrients needed for development of

agriculture.

One grab sample from the villages were taken. For Studying Soil profile of the region,

sampling locations were selected to assess the existing soil conditions in and around the

project area representing various land use conditions. The Physical, Chemical and

heavy metal concentrations were determined. The samples were collected by ramming

a core – cutter in to the soil up to a depth of 90 cm.

Six locations within 10 km radius of the plant site were selected for soil sampling. At

each location, soil samples were collected from three different depths viz. 30 cm, 60 cm

and 90 cm below the surface and are homogenized. The Homogenized Samples were

analyzed for physical and chemical characteristics. The soil samples were collected once

during pre – monsoon season. These samples were taken as grab samples and were

analyzed for various parameters to compare with the standards as per IS: 2720 &

methods of analysis part-1st , 2nd edition 1986, American society of Agronomy

Soil Sampling locations

Location Distance(

Km) Direction

Latitude &

Longitude of the

site

Location Selection Criteria

Banei 2.7 E 21049’24.73”N

840 57’ 11.18” E

Barren land with urban type

settlement

Page 16: 1) THE EXISTING AND PROPOSED FACILITIES AND CAPACITIES

Baidpali 3.3 SW 21048’53.43”N

840 54’ 26.59” E

Agriculture land

Pandua 5.29 NW 21047’17.25”N

840 53’ 57.62” E

Rural village with access road

Jibika 5.67 W 21050’23.04”N

840 52’ 24.34”E

A junction village between

Banei and Satakuta along the

River.

Lahunipara 5.99 SE 21052’55.10”N

840 56’ 06.72” E

Point of the area mostly due to

industrial activities

Katupada 6.6 SW 21052’16.68”N

840 56’ 40.13”E

Village below Banei in Topo-

sheet with traverse Road.

Kenaveta 9.23 N 21045’21.93”N

840 54’ 38.01” E

Location near to NH-23

6) REVISED WATER BALANCE ADDRESSING THE MAKEUP WATER,

GROUND WATER EXTRACTION AND RECHARGE PROPOSED.

COMMITMENT THAT NO ADDITIONAL WATER SHALL BE DRAWN

BEYOND THE PERMITTED QUANTITY OF 2976 M3/DAY

The total amount of fresh water required for the total project is 2976 m3/day.

Sl

no Facilities

Total

Circulating

water in

m3/hr

Fresh

Makeup

water in

m3/hr

Treated

water

recycled in

m3/hr

Waste

Water

generated

in m3/hr

Water

Loss with

material

in m3/hr

Evaporation

Loss in

m3/hr

1

2x100 TPD

DRI Kiln 9.4 0.65 8.75 0.05 Nil 0.6

2

Iron Ore

Beneficiation

cum 134 50 114 Nil 28 22

Page 17: 1) THE EXISTING AND PROPOSED FACILITIES AND CAPACITIES

Pelletization

3 2x12 T IF 510 7.65 502.35 Nil Nil 7.65

4 CCM 218 3.6 214.4 Nil Nil 3.6

5

30 TPH

Rolling Mill 459 9 450 Nil Nil 9

6

10 MW

Power Plant 134 45 109 20 Nil 25

7

Domestic &

AC

ventilation 8 8

Total 1464.4 123.9 1398.5 20.05 28 75.85

Total fresh water requirement = 124*24 = 2976 m3/day

Water loss with material = 20.05 = 481.2 m3/day will be utilized for dust suppression,

watering green belt and vehicle washing purposes.

Requirement of fresh water will be met from Surface and Ground water resources as

permission for drawl of surface water is 2304 m3/day and requirement is 2976 m3/day.

So, about 672 m3/day ground water will be required. However, with utilization of

harvested rain water ground water drawl will be reduced.

a) Industrial Promotion and Investment Corporation of Odisha Ltd (IPICOL) has

recommended to Add Secretary water department , Bhubaneswar for drawl of 96

m3/hr of water from River Brahmani by Vikram Pvt Ltd.

b) The company has obtained permission to draw 990 m3/day water which does

not need NOC as per CGWA

Both the letter annexed.

M/s VPL has proposed for harvesting 62,720 m3/yr of water through rain water

harvesting plan.

Page 18: 1) THE EXISTING AND PROPOSED FACILITIES AND CAPACITIES

7) COMMITMENT FOR MAINTAINING WORK ZONE ENVIRONMENT AS

PER THE REQUIREMENT OF FACTORY OF ACT.

M/s VPL commits to provide Environmentally safe work zone to its work men as per

Factory Act 1948 (Act No. 63 of 1948), as amended by the Factories (Amendment) Act,

1987 (Act 20 of 1987) and amendments thereafter to come.

The definition of workplace pollution is the presence of hazardous materials or noises

within a workplace that may affect people while performing their job. Such workplace

pollutants may affect workers' health, especially if exposure continues over longer

periods of time even at low levels. The presence of hazardous substances in the

workplace indoor air either as gases or as particulate matter dispersed in the air make

working zone environmentally unsafe.

Work zone in project of M/s Vikram Private Ltd are Iron ore Beneficiation cum

pelletization area, Induction Furnace area, Rolling mill and FBC area. FBC and Pellet

Plant will have closed control room for operating people, to be provided with air

conditioning facilities. In IF and Rolling mill work zone is distributed in open areas.

In work zone adequate ventilation is to be done by the circulation of fresh air using ID

or FD fans as per the prevailing situation. Effective measures shall be taken to prevent

dust inhalation and accumulation in any workroom, and if any exhaust appliance is

necessary for this purpose, it shall be applied as near as possible to the point of origin of

the dust, fume or other impurity, and such point shall be enclosed so far as possible.

There will be in every workroom at least 14.2 cubic meters of space for every worker

employed therein, and for the purposes no account shall be taken of any space which is

more than 4.2 meters above the level of the floor of the room.

Threshold Limit Value of gases for working 8hr a day are CO2=5,000ppm, CO= 25ppm,

Nitric Oxide= 25ppm, Nitrogen Dioxide =3, Nitrous Oxide =50 ppm and SO2 = 2ppm

and Chemical asphyxiants like CO or Hydrogen sulphide prevent oxygen transport and

the normal oxygenation of blood or prevent normal oxygenation of tissues. Hence

Oxygen concentration in air should never be below 19.5% by volume. Hence work zone

air monitoring to be done every shift and accordingly ventilation to be increased.

Low NOx burners & low Sulphur Coal to be used in FBC. PM10 level in work zone to be

maintained <50µgm/m3, preferable <20µgm/m3 of air. All the drains are to be fully

covered at least at work zone. Dust mask to be provided to work men for working in

dusty atmosphere.

Page 19: 1) THE EXISTING AND PROPOSED FACILITIES AND CAPACITIES

In every part of a factory where workers are working or passing, there shall be

provided and maintained sufficient and suitable lighting, natural or artificial, or both.

Induction Furnaces involve high temperature; such adequate measures as are

practicable shall be taken to protect the workers therefrom, so that workmen get

reasonable conditions of comfort from heat radiation.

Workplace noise is also another example of workplace pollution. Noise is considered as

any unwanted sound that may adversely affect the health and well-being of

individuals. Aspects of noise hazards include total energy of the sound, frequency

distribution, duration of exposure and impulsive noise. Hearing acuity is generally

affected first with a loss or dip at 4000 Hz followed by losses in the frequency range

from 2000 to 6000 Hz. Noise might result in acute effects like communication problems,

decreased concentration, sleepiness and as a consequence interference with job

performance. The noise level in no case shall exceed limit of 115 dBA over the period of

a quarter of an hour.

It is commitment of M/s VPL to keep noise level below 85 dB(A) at one-meter distance

from noise generating machines. Care to be taken at design stage to procure machine

generating noise at low level, silent type generator, periodic lubrication of moving

parts.

Arrangements shall be made to provide and maintain at suitable points conveniently

situated for all workers employed therein a sufficient supply of wholesome drinking

water and all such points shall be legibly marked "drinking water" in a language

understood by a majority of the workers employed in the factory and such points

should not be located within six meters of any washing place, urinal, latrine, spittoon or

open drain carrying sullage.

8) TIME SCHEDULE FOR THE COMPLETION AND COMMISSIONING OF

THE FACILITIES FOR WHICH EC WAS GRANTED ON 2ND DECEMBER

2012

Page 20: 1) THE EXISTING AND PROPOSED FACILITIES AND CAPACITIES
Page 21: 1) THE EXISTING AND PROPOSED FACILITIES AND CAPACITIES
Page 22: 1) THE EXISTING AND PROPOSED FACILITIES AND CAPACITIES

9) Details of Corporate Environment Responsibility addressing the issues raised

during the PH and issues emerged in SIA along with time bound action plan and

budgetary requirement

With Office memorandum issued by MoEF F.No 22-65/2017-IA.III dt 01.05.18 the

allocation of budget under Corporate Environment Responsibility (CER) cost is

estimated be about 1.5 % of the capital cost invested.

As the facilities of existing EC have not been completed the total capital cost has been

estimated to be Rs 275 Crores ( Rs 207 Crore for existing + Rs 68 Crore for expansion).

Therefore, the CER cost is estimated to be Rs 4.125 Crore. The detailed breakup and

time schedule is as follows :

Sl. No.

Description of Social Need

Budget (Rs. Crore) Time Schedule

Budget for existing

plant

Budget for expansion

plant

Total Budget

Target Start Date

Target Finish Date

1 Drinking water facility at Lahunipara tehsil office

-

0.01 0.01 01-10-18 01-11-18

2 Borewell for drinking water in the villages of Rajamunda panchayat

-

0.1 0.1 01-01-19 01-04-19

3 Ambulance for Rajamunda panchayat

-

0.15 0.15 01-05-19 01-08-19

4 Plantation near Saleibahal village

-

0.06 0.06 15-06-19 15-07-19

5 Plantation near Arkeikala village

-

0.06 0.06 15-06-19 15-07-19

6 Public utility & rest house at Luthurba village

-

0.06 0.06 01-09-19 30-09-20

7 Vocational training to unemployed youth of Rajamunda panchayat/block

-

0.18 0.18 01-09-19 30-09-20

8 Medical checkup camp in the villages of Rajamunda panchayat/block

-

0.1 0.1 01-01-19 30-09-20

9 Support to village school at Shardhapali

-

0.01 0.01 01-08-18 30-09-20

10 Support for girl child education & vocational training

-

0.2 0.2 01-09-18 30-09-19

11 Development of children parks in the villages of Rajamunda

-

0.12 0.12 01-01-19 30-09-19

Page 23: 1) THE EXISTING AND PROPOSED FACILITIES AND CAPACITIES

gram panchayat

12 Vocational training to unemployed youth of Rajamunda panchayat/block

0.5 - 0.5 15-02-20 15-12-22

13 Medical checkup camp in the villages of Rajamunda panchayat/block

0.2 - 0.2 01-03-20 30-03-22

14 Borewell for drinking water in the villages of Rajamunda panchayat

0.2 - 0.2 15-04-20 15-04-22

15 Development of children's park at Bonai

0.16 - 0.16 01-01-14 15-01-20

16 Public utility & rest house at Badtumkela, Gomlei & other villages

0.25 - 0.25 01-01-12 30-12-22

17 Support to village school at Shardhapali

0.035 - 0.035 01-04-12 31-12-22

18 Payment of electricity bill for Badtumkela village water supply

0.06 - 0.06 01-04-12 01-01-22

19 Support for cultural activities in the locality

0.12 - 0.06 01-01-12 30-12-22

20 Support to Gramya Vikash Samiti/Surakhya Manch, Badtumkela

0.06 - 0.06 01-01-12 30-12-22

21 Plantation in villages of Rajamunda panchayat except Saleibahal & Arkeikala

0.25 - 0.25 01-02-20 30-12-22

22 Support for girl child education & vocational training

0.55 0.55 01-01-20 30-12-22

23 Support to village students for higher education

0.6 - 0.6 01-03-20 30-12-22

24 Development of children parks in the villages of Rajamunda gram panchayat

0.15 0.15 15-04-20 30-12-22

Total 3.135 1.050 4.125