1 tae joon lee nuclear training & education center training for the introduction of nuclear...
TRANSCRIPT
1
Tae Joon LEE
Nuclear Training & Education Center
Trainingfor the Introduction
of Nuclear Power Plant
Trainingfor the Introduction
of Nuclear Power Plant
Atomexpo2013 June 28,
St. Petersburg, Russia
22
Table of ContentsTable of Contents
IAEA Approach
Conclusion
Korea/KAERI Approach
Korea, KAERI & NTC
1. Nuclear Power Plants in Korea
Wolseong (#1,2,3,4) Shin-Wolseong (#1) Shin-Wolseong (#2)
Uljin (#1,2,3,4,5,6)Shin-Uljin (#1,2)
Gori (#1,2,3,4)Shin-Gori (#1,2)Shin-Gori (#3,4)
Yonggwang(#1,2,3,4,5,6)
Under Construction− OPR1000 : Shin-Gori (#2)− APR1400 : Shin-Gori (#3,4), Shin-Uljin (#1,2)
Site
Gori
Wolseong
Yonggwang
Uljin
Total
In Operation
6 (5,137)
5 (3,779)
6 (5,900)
6 (5,900)
23 (20,716)
UnderConstruction
2 (2,800)
1 (1,000)
-
2 (2,800)
5 (6,600)
Total(2016)
8 (7,937)
6 (4,779)
6 (5,900)
8 (8,700)
28 (27,316)
As of Mar., 2013
Source : www. khnp.co.kr
Radioactive Waste Disposal Facility (Under construction)
1. KAERI, Cradle of Nuclear Organizations in Korea since 1959
AERI : Atomic Energy Research Institute
RRI : Radiomedical Research Institute
KCCH : Korea Cancer Center Hospital
RRIA : Radiation Research Institute in Agriculture
KNFDI : Korea Nuclear Fuel Development Institute
KOPEC : Korea Power Engineering Co., Inc. (renamed as KEPCO E&C)
KINS : Korea Institute of Nuclear Safety
KNFC : Korea Nuclear Fuel Company (renamed as KEPCO NF)
KINAC : Korea Institute of Nuclear Nonproliferation and Control
KIRAMS : Korea Institute of Radiological and Medical Sciences
KHNP : Korea Hydro & Nuclear Power Co., Ltd.
NETEC: Nuclear Environment Technology Institute
Technology Transfer- NSSS design → KOPEC
- Fuel design → KNFC- Radwaste → KHNP/NETEC
Dec. 1996
1960s1960s 1970s1970s 1980s1980s 1990s1990s 2000s2000s
RRI KCCH
KNFDIRRIA
KOPEC
Oct. 1975
KNFC
Nov. 1982
KINS
Feb. 1990
KINAC
Dec. 2004
KCCH
Apr. 2007
Feb. 1959
Dec. 1963
Nov. 1969
Feb. 1973
Dec. 1976
Feb. 1968
KAERI
KAERI
AERI
KAERI
KAERI
1967 KAERI/NTC• NTC: Nuclear Education & Training Center
2004 KINS/NSS*NSS: Nuclear Safety School
1979 KHNP/KNPEI*KNPEI: KHNP Nuclear Power Education Institute
1959 KAERI, Nuclear Eng. Dept. in Univ.
1. KAERI/NTC: Cradle of Nuclear E&T in Korea since 1967
2. IAEA Infrastructure Development Program
Milestones in the Development of a National , Nuclear Energy Series, No. NG-G-3.1, p. 7, IAEA, 2007
2. IAEA HRD Approach for 1st Nuclear Power Programs
Training for recognition & assessment of environment
Milestones in the Development of a National , Nuclear Energy Series, No. NG-G-3.1, IAEA, 2007
NPPPhase
HRDRequire-ments
MILESTONE 1
Phase 1 Phase 2 Phase 3 Phase 4Pre-project Project Decision Making Construction Operation / decommissioning
MILESTONE 2 MILESTONE 3
Preparatory work to the construction of a nuclear power plant after a policy decision has been taken
Considerations before a decision to launch a nuclear power program is taken
HRDTarget
NEPIO
Project Managers Manufacturing personnel O/M Personnel Regulator
Decision makers Business/Technical Experts
Activities toimplement a firstnuclear power plant
Operation of the firstnuclear power plant
Knowledge and skills needed to support a nuclear programme identified by NEPIO
Plan to develop and maintain the human resource base developed
Sufficient human resources to issue bid request are in place
Initial education and training for remaining human resources
All human resources to commission and operate the first nuclear power plant
Educational and training programmes for continuing flow of qualified people are underway
2. IAEA 19 Infrastructure Issues for 1st NPP (2008)
Infrastructure issues by the IAEA, 2008
1 National Position 2 Nuclear Safety
3 Management 4 Funding and Financing
5 Legislative Framework 6 Safeguards
7 Regulatory Framework 8 Radiation Protection
9 Electrical Grid 10 Human Resources Development
11 Stakeholders Involvement 12 Site and Supporting Facilities
13 Environmental Protection 14 Emergency Planning
15Security and Physical Protec-tion
16 Nuclear Fuel Cycle
17 Radioactive Waste 18 Industrial Involvement
19 Procurement
3. KAERI Training Programs by Course
Training for recognition & assessment of environment
MILESTONE 1
Phase 1 Phase 2 Phase 3 Phase 4
Pre-project Project Decision Making Construction Operation / decommissioning
MILESTONE 2 MILESTONE 3
KAERINuclearTrainingCenterProgram
Capacity Building of Emerging Countries (Bilateral)
Interregional Training on Evaluation of Sustainable Energy Strategies for Addressing Climate Change Issues, Using IAEA’s Model Massage
KOICA/KAERI/IAEA/ Interregional Training Course on Nuclear Energy Policy, Planning and Project Management
Nuclear Energy Policy and Nuclear Power Project Management for High-level Decision –makers in emerging countries(Bilateral)
IAEA Inter-regional Training Course on Fundamentals of Pressurized Water reactors with PC-Based Simulators
Training Course on Nuclear Power Planning and Project Management for Middle-level Managers in Developing countries
IAEA Regional Training Course on Safety Assessment for Nuclear Reactor(EBP)
IAEA Regional workshop on Asian network for education in Nuclear Technology
WNU Course on “Key issue in the world nuclear Industry today”
Interregional training on natural circulation and passive safety systems in advanced water cooled reactor
NPPPhase
※ KHNP Courses
- Civil engineering- Architecture engineering- Electrical engineering- I&C engineering etc- QA & QC
※ KHNP Courses
- Operation training- Mechanical engineering- Electrical engineering- I&C engineering- Maintenance
KHNP training programs for project management, construction, operation nuclear power plant
Training for recognition & assessment of environment
MILESTONE 1
Phase 1 Phase 2 Phase 3 Phase 4
Pre-project Project Decision Making Construction
MILESTONE 2 MILESTONE 3
KAERIProgram
The IAEA assistance programme to member
states embarking on nuclear power
Economics of NPP
Korea’s N E policies
IAEA milestones approach
Siting aspects Legal and regulatory
Financing NPP PJT
Public acceptance
Nuclear safety infrastructure
Energy resources Dev’t
Radiation protection
Environmental aspects
International cooperation considering introduction
of nuclear program
Risk Mgt of NPP PJT
Nuclear HRD
Pre-project phase for NPP PJT management
Non- proliferation regime
Research reactor
Next generation nuclear reactors
NPPPhase
Decontamin’g & Dec.
Waste management
Back-end NFC
3. KAERI Training Programs by Subject
Strategic Planning of NPP
NPP & Sustainable Dev’t
NPP and Fuel
SMR & SMART
Further needs of NE
M&ONPP
in Korea
APR1400 & OPR1000
Korea experience of localization and innovation in nuclear industry
QA & QC in NPP
Project management of NPP program
Licensing of NPP
HRD in NPP
Construction & Manufacturing of NPP
4. Conclusion: E&T Programs for 1st NPP in Korea
Professional programs
KAERI/NTC: Pre-project and Project Decision Making
KHNP/KHRDI: Project Management, Construction, O&M
Academic Programs
BS Degree : Universities, KAIST
MS Degree : Universities, KAIST, KAERI-UST, KINS-KAIST,
K-INGS(KEPCO),
PhD Degree : Universities, KAIST, KAERI-UST