Page 1: 1 Service panels run from detector end to end of support tube X-section through service panels 3-D view of panels PP0 region. All services break here Patch

1

Service panels run from detector end to end of support tube

X-section through service panels

3-D view of panels

PP0 region. All services break here

Patch Panel 0(PP0)

Page 2: 1 Service panels run from detector end to end of support tube X-section through service panels 3-D view of panels PP0 region. All services break here Patch

2

Detector end of service panel

PPO Flex Boards connectElectrical cables from modules toOptical & electrical services

Optoboards

PP0 Region

Type 0 cables plug into PP0

Page 3: 1 Service panels run from detector end to end of support tube X-section through service panels 3-D view of panels PP0 region. All services break here Patch

3

PP0 and Opto-Board Prototype

“Loop-back testthrough opto-board

Page 4: 1 Service panels run from detector end to end of support tube X-section through service panels 3-D view of panels PP0 region. All services break here Patch

4

First Mechanical Prototype• Service panel mockup

Page 5: 1 Service panels run from detector end to end of support tube X-section through service panels 3-D view of panels PP0 region. All services break here Patch

5

PP0 Status• PP0 prototype v2 flex has been fabricated.• In use for prototype opto-board test.• Single PP0 flex will be laminated to PCB for initial system tests.

This will largely validate electrical design.• Many flexes will be laminated to composite panel as part of full

service panel prototype. Composite panel under fabrication, lamination in January.

• Full service panel prototype will include soldering of Type I cables to PP0 prototypes. This will be completed by summer 2003.

• By summer 2003 should also have results from system tests.• PP0 FDR in June 2003(along with service panels). PRR a few

months later.