1-s2.0-s0950423012001702-main
TRANSCRIPT
![Page 1: 1-s2.0-S0950423012001702-main](https://reader038.vdocuments.us/reader038/viewer/2022100505/577cd1271a28ab9e7893bef5/html5/thumbnails/1.jpg)
8132019 1-s20-S0950423012001702-main
httpslidepdfcomreaderfull1-s20-s0950423012001702-main 19
Application of a multi-plant QRA A case study investigating the riskimpact of the construction of a new plant on an existing chemicalplantrsquos risk levels
Shahabaldin Baesi a Bahman Abdolhamidzadeh a Che Rosmani Che Hassan aMahar Diana Hamid a Genserik Reniers bc
a Department of Chemical Engineering Faculty of Engineering University of Malaya 50603 Kuala Lumpur Malaysiab Antwerp Research Group on Safety and Security (ARGoSS) University of Antwerp Prinsstraat 13 2000 Antwerpen Belgiumc Hogeschool-UniversiteitBrusselKULeuven Belgium
a r t i c l e i n f o
Article history
Received 10 April 2012
Received in revised form
25 October 2012
Accepted 6 November 2012
Keywords
Quantitative Risk assessment
Individual risk
Societal risk
Domino accidents
Chemical cluster
Process industries
a b s t r a c t
The construction of chemical clusters whereby a variety of chemical plants are located next to each other
provides great economic bene1047297ts However in such clusters due to the mere scale on which hazardous
materials are processed stored and handled the potential of various accidents is much higher than in
single companies Furthermore the close proximity of process installations and storage tanks in such
areas gives rise to the risk of domino effects Therefore land use planning and layout design has always
been a challenge within such clusters
In this paper a Quantitative Risk Assessment (QRA) is carried out and used as a decision making tool to
evaluate the acceptability of constructing a new chemical plant adjacent to an existing one For this
purpose standard parameters such as individual risk and societal risk were quanti1047297ed before and after
the new plant would come into operation Given the experience of past accidents in the process
industries the likelihood of domino accidents in the two neighboring plants has also been analyzed
2012 Elsevier Ltd All rights reserved
1 Introduction
Due to the 1047298ammable and toxic nature of substances which are
being handled in the oil- gas- and petrochemical industries
installations within chemical plants have a high potential to cause
substantial damages in terms of fatalities serious injuries property
damages and environmental degradation In addition large
inventories of hydrocarbons intense temperature and pressure
conditions and inherent congestion in process installations
whereby process equipment is often situated in close proximity to
one another increases the probability of catastrophic accidents andampli1047297es their potential consequences (Abdolhamidzadeh Abbasi
Rashtchian amp Abbasi 2010 Khan amp Abbasi 1999a 1999b Reniers
2010) For example in Toulouse France 30 people were killed and
2242 injured in 2001 dueto an ammonium nitrate explosion and in
Texas city USA 15 persons lost their lives and 170 others were
injured in 2005 due to a re1047297nery disaster (Dechy Bourdeaux
Ayrault Kordek amp Le Coze 2004 Kalantarnia Khan amp Hawboldt
2010) We refer eg to Lees (1996) Wells (1997) Kletz (1999a
2003) and Atherton and Gil (2008) for many other examples of
major accidents in the chemical industries Such catastrophic
events also happen in developing countries and especially in the
Middle East (Khan amp Abbasi1999a) This may be related to the ever
growing number of chemical clusters in this particular region due
to the existence of massive sources of energy in the Persian Gulf In
chemical clusters upstream activities such as production and
separation are increasingly carried out in chemical plants being
physically located nearby chemical companies with downstream
activities such as re1047297neries
One of the important issues in the construction of chemicalclusters is so-called land use planning Land use planning is in1047298u-
enced by economic operational and safety aspects The high
number of hazardous activities and substances in chemical clusters
in combination with high levelsof congestion demand an adequate
and solid decision making process for situating new plants in the
area whereby individual and group risks are taken into account
Usually so-called Quantitative Risk Assessment or abbreviated
QRA is used for this purpose Previous studies indicate that QRA is
a useful tool forlanduse planninglayout designand modi1047297cation in
the process industries Khan and Abbasi (1999b) have estimated the
overall individual risk posed by a chemical cluster to adjacent Corresponding author
E-mail address abdolhamidzadehumedumy (B Abdolhamidzadeh)
Contents lists available at SciVerse ScienceDirect
Journal of Loss Prevention in the Process Industries
j o u r n a l h o m e p a g e w w w e l s e v i e r c om l o c a t e j l p
0950-4230$ e see front matter 2012 Elsevier Ltd All rights reserved
httpdxdoiorg101016jjlp201211005
Journal of Loss Prevention in the Process Industries 26 (2013) 895e903
8132019 1-s20-S0950423012001702-main
httpslidepdfcomreaderfull1-s20-s0950423012001702-main 29
residential areas in order to compare the result with safety
criteria and eventually recommendations were given to make
modi1047297cations in the plants since the criteria were not met Jo and
Crowl (2008) speci1047297ed the minimum safety distances between
a high pressure gas pipeline and residential areas Risk and conse-
quence analyses of toxic chemicals in certain warehouses to the
nearby villages were analyzed by Rigas and Sklavounos (2002) to
investigate the extent of compliance to exposure threshold limits
The study by Papazoglou Nivolianitou Aneziris Christou and
Bonanos (1999) demonstrated that a high level of risk is exposed
to passengers crossing the highway adjacent to a speci1047297c re1047297nery
and thereforea new trajectory withthe safety distancecalculated by
QRAshould be constructed These area limited numberof examples
showing that land use planning is vital forlocating process facilities
near to public areas and a QRA could be an effective technique for
this purpose In this method in addition to identifying the hazards
also their associated consequences and the frequencies of occur-
rences are quantitatively estimated (Kletz 1999b) Furthermore
parameters such as lsquoindividual riskrsquo and lsquogroup riskrsquo (the latter also
being called lsquosocietal riskrsquo) are parameters which support the deci-
sion making process for land use planning Several other relevant
studies can be found elsewhere (Bubbico Maschio Mazzarotta
Milazzo amp Parisi 2006 Gharabagh et al 2009 Milazzo et al2002 Yet-Pole Chi-Min amp Ching-Hong 2009)
The proliferation of chain accidents suggests that the probability
of domino effects should also be considered as an important
parameterin land useplanning forchemical clusters A recent study
on past domino events indicated that the number of cascading
accidents in the process industries has increased globally in recent
decades (Abdolhamidzadeh Abbasi Rashtchian amp Abbasi 2011) In
the same study there are some accidents mentioned in which an
initiating event in a single plant has led to a catastrophe within
a clusterof chemical plants A recentexample couldbe Shazand Iran
in which 30 peoplewere killedand 38 others were seriously injured
in 2008due to an initial explosion that ledto other majorexplosions
and 1047297res in the neighboring plants The dominant accident
that caused the majority of fatalities was the major explosions thatwere triggered by the initial blast (Abdolhamidzadeh et al 2011)
As already mentioned in land use planning possible scenarios
are reviewed from different points of view one being the safety
perspective In many cases different chemical plants in a chemical
industrial area do not come into operation at the same point in
time Forexample it is common practice to build plants to consume
the product(s) of an existing plant It is obvious that the construc-
tion of new plant(s) adjacent to existing one(s) will affect the
overall risk of the industrial area regardless of the fact whether risk
assessments have been performed for individual plants
In the remainder of this article QRA has been applied to eval-
uate the risk-based effects of constructing a new chemical plant
(which is called BSPC in this article) adjacent to an existing one
(called AKPC in this paper) These two plants forming our case-study are located in one of the largest energy zones in the world
in southern Iran (called lsquoPETZONErsquo) Parameters such as the indi-
vidualrisk and the societal risk have been assessedbefore and after
the new plant came into operation Furthermore the possibility
and the likelihood of domino events in the two neighboring plants
were investigated We mainly focus on safety aspects in our article
as the feasibility of the planning from both an economic and an
operational perspective has been carried out in an earlier stage of
the land-use planning decision process
2 Quantitative Risk Assessment (QRA)
QRA along with other techniques have been used in one way or
another in the process industries for loss prevention from 1970
onwards (Abbasi Krishnakumari amp Khan 1998 Khan amp Abbasi
1998) QRA is a method that provides quanti1047297ed estimation for
the risk posed by a group of hazards (Kletz 1999) Hence this
technique enables risk mitigation methods to be evaluated in order
to bring the risk to tolerable levels without resorting to too costly
protective systems (Pula Khan Veitch amp Amyotte 2006) Although
QRAhas itsweaknesses anddrawbacksit is often theonlyapproach
to get grip on possible risks and to tame complexity as indicated by
Pasman Jung Prem Rogers and Yang (2009) QRA involves the
following main steps scenario selection frequency estimation
consequence assessment and risk quanti1047297cation (CCPS 2000
Khan Sadiq amp Husain 2002) We will discuss these steps hereafter
21 Scenario selection
Possible scenarios in the process industries may be different
modes of 1047297re explosion and toxic dispersion (Arunraj amp Maiti
2009 Markowski 2007) Neglecting any possible scenario can
lead to a risk underestimation and eventually affect the overall risk
values (Van Sciver 1990) Scenario selection is usually based on
expertrsquos opinion history of past accidents and safety reviews For
our study after selecting the credible scenarios based on a combi-
nation of mentioned methods Event Tree Analysis (ETA) wasapplied for scenario development The quantitative feature of ETA
was then used for incident frequency calculation
22 Frequency estimation
Once the 1047297nal outcomes and their sequences are predicted for
each scenario the scenario frequency should be determined For
this purpose the failure frequency of each initiating event and the
probability of every intermediate event such as immediate ignition
delayed ignition vapor cloud 1047297re etc are used The frequency
values which can be found in literature are mostly based on
historical data of previous incidents (Beerens Post amp Uijt de Haag
2006) The frequency of a scenario speci1047297es the number of occur-
rences of that scenario in a speci1047297ed timeframe (which is usuallyone year) The probability of an intermediate event is a dimension-
less value between0 and 1 which indicates the possibility of
occurrence of that event in a speci1047297c period of time For this paper
the failure frequencies for the initiating events and the intermediate
values were obtained from the Purple Book (CPR 1999) Application
of failure frequenciesin thePurple Book andthe BEVI Manualduring
the past years wasindustry standard Also softwaresuch as ARIPAR-
GIS (Spadoni Egidi amp Contini 2000) or DomPrevPlanning (Reniers
amp Dullaert 2007) use these values The following equation shows
how the initiating event frequency intermediate probabilities and
1047297nal outcome frequency are related to each other (CCPS 2000)
f i frac14 F I P oiP oci (1)
where f i is the frequency of the 1047297nal outcome of scenario i arising
from incident I (1yr)F I is the frequency of incident I which causes
different outcomes (1yr)P oi is probability of occurrence for an
intermediate outcome of incident I which causes a number of i 1047297nal
outcomes and P oci is the probability of occurrence for a 1047297nal
outcome which is a subset of outcomes arising from incident I
23 Consequences assessment
During the consequence assessment the effects and magnitude
of the 1047297nal outcome of each scenario should be estimated The
consequences of potential scenarios could be classi1047297ed as follows
(Lees 1996) 1047297re thermal radiation explosion overpressure and
fragment projection and toxic dispersion and exposure
S Baesi et al Journal of Loss Prevention in the Process Industries 26 (2013) 895e903896
8132019 1-s20-S0950423012001702-main
httpslidepdfcomreaderfull1-s20-s0950423012001702-main 39
Besides serious physical human harm and eventually casualties
property damage and environmental effects are other conse-
quences among the overall potential loss (Pintaric 2007)
The measure of damage in QRA is fatality since other types of loss
are more complex to assess in comparison to human casualties
(Pula et al 2006)
A chain of rigorous calculations is needed to estimate the
intensity of the physical harm posed by the mentioned scenario
outcomes in a chemical cluster Software packages for the proce-
dure of consequence assessment are used to estimate the numer-
ical value of thermal heat load explosion overpressure and toxic
concentration at various spots around the release point For this
study the well-known PHAST (Process Hazard Analysis Safety Tool)
software was used for consequence assessment Once the appro-
priate failure frequencies are given this particular software con-
taining 1047297ne discharge dispersion evaporation and rainout models
is a powerful tool for the prediction of effect zones (Pintaric 2007)
In addition to the results of consequence modeling fatality probit
equations were used to quantify the expected percentage of
lethality for the exposed population
24 Risk quanti 1047297cation
The frequency and severity (rate of fatality) of every speci1047297c
scenario are combined to obtain a measure of the corresponding
risk Risk quanti1047297cation results are presented in two conventional
categories which are known as lsquoindividual riskrsquo and lsquogroup riskrsquo
(also called lsquosocietal riskrsquo)
The frequency at which a particular individual being fatally
harmed when standing at a certain distance from a potential
hazard is known as ldquoindividual riskrdquo (Gooijer Cornil amp Lenoble
2012) The overall individual risk at any location ( x y) inside or
outside the industrial plant is the summation of all individual risks
at that speci1047297c point The individual risk at any location ( x y) is
calculated by the following equation (CCPS 200 0)
IR x y frac14Xn
ifrac141
IR x yi (2)
In other words the risk of any identi1047297ed scenario will be indi-
vidually calculated at a speci1047297c location ( x y) and subsequently all
risks are summed to estimate the overall risk at that speci1047297c point
To calculate the individual risk at location ( x y) arising from
scenario i the following equation is applied (CCPS 200 0)
IR x yi frac14 f iP f i (3)
where f i is the frequency of the 1047297nal outcome of scenario i arising
from an incident (1yr) andP f iis the fatality probability of the 1047297nal
outcome of scenario i at the geographical location ( x y) Individualrisk contours represent the 1047297nal results of this step The individual
risk value in every position when compared to universally or
regionally accepted values is one of the criteria in risk-based
decision making for land use planning
Societal risk provides a risk evaluation for a group of people
located in the vicinity of the accident location In other words the
number of people affected by all 1047297nal outcomes is estimated
(Renjith amp Madhu 2010) Similar to the individual risk the societal
risk is a function of frequency of occurrence and rate of fatality
Another important and determinant factor for calculating the
societal risk is the population density around the incident location
Thesocietal riskis presented in form of FeN (FrequencyeNumber
of fatalities) curves where the cumulative frequency of 1047297nal
outcomes is plotted against the number of fatalities arising from anoutcome in a logarithmic scale To calculate the number of fatalities
of each 1047297nal outcome the following equation is used (CCPS 2000)
N i frac14X
x y
P x y p f i (4)
whereN irepresents the number of fatalities of the 1047297nal outcome of
scenario i P x yis the number of individuals at the geographical
location ( x y) and p f i is the probability that the 1047297nal outcome of
scenario i causes death at the geographical location ( x y)
The results obtained above are used in Equation (5) to calculate
the ultimate data required for plotting the FeN curve This equation
which is known as the cumulative frequency equation is expressed
as below (CCPS 2000)
F N frac14X
i
F i for all final outcome case I which N i gt N (5)
where F N is the cumulative frequency for all 1047297nal outcomes which
result in fatalities of more than N personsF i is the frequency of the
Fig 1 Layout of the study area (case-study) showing the two neighboring plants AKPC and BSPC
S Baesi et al Journal of Loss Prevention in the Process Industries 26 (2013) 895e903 897
8132019 1-s20-S0950423012001702-main
httpslidepdfcomreaderfull1-s20-s0950423012001702-main 49
1047297nal outcome of scenario i and N i is the number of fatalities for the
1047297nal outcome of scenario i Finally having the quantities of F N and
N the cumulative frequency of 1047297nal outcomes is plotted against the
number of fatalities The obtained FeN curved will be compared
against the intended criteria to evaluate the acceptability of the
potential societal risk
3 Case study
ldquoAKPCrdquo and ldquoBSPCrdquo are two neighboring complexes located in
the so-called PETZONE In this industrial region 15 petrochemical
plants are situated in 5 distinct sites within an area of approxi-mately 20 km2 and therefore it is known to be one of the biggest
energy zones in the world The PETZONE lies in the northern coast
of the Persian Gulf and expands to the southwestern city of Mah-
shahr in southern Iran
Before and during the construction of many plants in the PET-
ZONE until present only economic and operational factors have
been taken into account leaving safety aspects to be largely
neglected in the layout design of those plants This was also the
case for our case study of the two plants AKPC and BSPC The ole1047297n
unit of AKPC produces ethylene and propylene and these
substances are later used in the polymerization unit to produce
high density polyethylene low density polyethylene and poly-
propylene Regarding BSPC its main products are naphtha p-
xylene and acetic acid
These two plants present an interesting case study due to their
high number of storage tanks and huge inventory of chemicals As
one of these plants provides a portion of the other one rsquos feed
constructing them close together seemed a wise choice from an
economic and operational point of view However the compliance
of risk criteria had not been an item of consideration After occur-
rence of some minor process accidents with limited consequences
in these plants the risk of accident escalation from one plant to
another was highlighted more than ever Therefore the idea of
constructing AKPC and BSPC in proximity of each other which
seemed a defendable choice once has been challenged In the
present study the two adjacent chemical complexes AKPC and
BSPC are both subjected to one QRA (treating both plants as one
plant) allowing us to analyze the effects of the construction of a
petrochemical plant adjacent to an existing one on the overall riskThe purpose was to verify whether it was indeed a wise choice to
construct these two plants this close to each other (for production
purposes) or not (for safety reasons) Fig 1 represents the layout of
the two petrochemical plants
Based on a safety review and on a safety screening carried out
as a preliminary step the major hazard sources of the study area
(as displayed in Fig 1) appear to be the storage tanks of these two
plants Although there are obviously other sources of hazards
within this area their contribution in the overall risk could be
regarded negligible (compared with the present storage tanks)
AKPC houses 5 major operational storage tanks containing
ethylene and propylene while BSPC contains 10 major atmo-spheric storage tanks containing naphtha p-xylene and acetic
acid Tables 1 and 2 provide a list of the chemical substance
inventories in AKPC and BSPC Although there were some other
storage tanks or process equipment no one passed the screening
step for scenario selection due to their low inventory of hazardous
materials and due to the lesser inherent hazardousness of the
materials
The atmosphericdata used in this study were established by the
Iranian Meteorological Organization (IMO) for the Mahshahr port
from 1988 to 2006 (IRIMO 2006) The result of the meteorological
data analysis indicates that two prevailing weather conditions (hot
season and cold season) can be intended for the QRA study during
daytime and nighttime to cover almost all of the probable condi-
tions Table 3 summarizes the average meteorological data whichare used for the consequence analysis
31 Accident scenarios
As stated previously the storage tanks have been identi1047297ed to
lead to the most hazardous scenarios in the case under study
Table 1
List of AKPC storages in this study
TK-item Compound Type Temperature
(C)
Pressure
(barg)
Volume
(m3)
Inventory
(tonne)
TK-101 Propylene Spherical 40 25 2200 1044
TK-102 Propylene Spherical 40 25 2200 1044
TK-103 Propylene Spherical 40 25 2200 1044
TK-104 Propylene Spherical 40 25 2200 1044
TK-105 Ethylene Cylindrical
104 Atm 14000 7968
Table 2
List of BSPC storages in this study
TK-item Compound Type Temperature
(C)
Pressure
(barg)
Volume
(m3)
Inventory
(tonne)
TK-201 Naphtha Cy lindrical 30 001 331188 24839
TK-202 Naphtha Cy lindrical 30 001 331188 24839
TK-203 Naphtha Cy lindrical 30 001 331188 24839
TK-204 Naphtha Cylindrical 30 001 16272 12204
TK-205 Naphtha Cylindrical 30 Atm 16272 12204TK-206 P -Xylene Cy lindrical 30 At m 170856 14693
TK-207 P -Xylene Cy lindrical 30 At m 170856 14693
TK-208 P-Xylene Cylindrical 40 0003 1500 1267
TK-209 Acetic acid Cylindrical 45 0014 1500 1554
TK-210 Acetic acid Cylindrical 45 0014 1500 1554
Table 3
Prevailing weather conditions
Category Atmospheric stability Average wind
speed (ms)
Average ambient
temp (C)
Average relative
humidity ()
Hot season (daytime) Neutral (D class) 5 40 50
Hot season (nighttime) Stable (F class) 15 25 60
Cold season (daytime) Neutral (D class) 5 20 80
Cold season (nighttime) Stable (F class) 15 10 90
Table 4
Accident scenarios and the relevant failure frequencies
Scenario
no
TK -i tem n o C ontai nmen t Scena ri o typ e Frequency
(1yr)
1e4 TK-101102103104 Propylene Leakage 1 105
5e8 TK-101102103104 Propylene Rupture 5 107
9 TK-105 Ethylene Leakage 1 105
10e14 TK-201202203
204205
Naphtha Leakage 1 105
15e17 TK-206207208 P-Xylene Leakage 1 105
18e19 TK-209 210 Acetic acid Leakage 1 105
S Baesi et al Journal of Loss Prevention in the Process Industries 26 (2013) 895e903898
8132019 1-s20-S0950423012001702-main
httpslidepdfcomreaderfull1-s20-s0950423012001702-main 59
8132019 1-s20-S0950423012001702-main
httpslidepdfcomreaderfull1-s20-s0950423012001702-main 69
Fig 4 A B individual risk contours before (for AKPC) and after (for cluster composed of AKPC and BSPC) constructing the new plant
8132019 1-s20-S0950423012001702-main
httpslidepdfcomreaderfull1-s20-s0950423012001702-main 79
the leakage case and in the rupture case Moreover based on the
plant layout review and due to the low level of equipment
congestion in this particular area under study the probability of
a 1047298ash 1047297re is higher than that of a Vapor Cloud Explosion (VCE)
since higher congestion is known to increase the probability of
a VCE rather than that of a 1047298ash 1047297re
4 Result and discussion
In order to evaluate the risk-based effects of constructing BSPC
adjacent to AKPC calculations were made for both individual risk
and societal risk before and after the new plant came under oper-
ation adjacent to the existing one The quanti1047297ed risk can then be
Fig 5 A B societal risk (Fe
N curve) before (A) and after (B) constructing the new plant
S Baesi et al Journal of Loss Prevention in the Process Industries 26 (2013) 895e903 901
8132019 1-s20-S0950423012001702-main
httpslidepdfcomreaderfull1-s20-s0950423012001702-main 89
compared against the criteria to assess the acceptability of the risk
levels The likelihood of domino effects needs to be assessed as
well
41 Calculation of individual risk
Using the results of frequency estimation and a detailed
consequence assessment for all the possible scenarios the indi-
vidual risk contours were obtained and are shown on a satellite
view of the study area Key outputs of the consequence modeling
are presented in Table 5 to give more insight in the two selected
scenarios Fig 4A and B demonstrate the individual risk levels
before (A) and after (B) the second plant came operational The
numerical value of each risk contour represents the frequency at
which a particular individual is fatally harmed when standing
within the contour boundary
The results of individual risk calculations reveal that inside the
chemical cluster composed of both plants (AKPC and BSPC) as well
as within the single plant AKPC the individual risk values do not
exceed the tolerable magnitude of 105yr before and after the new
plant came under operation Fig 3A and B also demonstrate that for
public areas (such as the main roads around AKPC and BSPC) the
risk level does not exceed the magnitude of 106yr except fora short interval of 100 m at the southern main road of AKPC
Nevertheless this issue was already present even before the
construction of BSPC In general we can state that in terms of
individual risk constructing the new plant adjacent to the existing
one did not affect the acceptability of risk levels
42 Calculation of societal risk
Although the previous section indicates that individual risk
levels do not exceed the tolerable levels the impact of any potential
accident on operators and public should also be investigated
Fig 4A and B provide the societal risk calculation results before and
after the new plant came into operation respectively As it can be
seen in Fig 5A the societal risk posed by AKPC individually falls inthe ALARP (As Low As Reasonably Practicable) region as de1047297ned by
HSE (UK)Fig 5Bshows that after constructing the new plant the
societal risk curve gets closer to the maximum risk criteria but still
remains in the ALARP region Therefore constructing the new plant
BSPC adjacent to the existing one AKPC seems to have only limited
impact upon the change of tolerability of the societal risk in our
case study
43 Domino effects assessment
The distance from the storage tanks located in AKPC to the
closest operational storage tank in BSPC is about 800 m Based on
the values reported by Cozzani Gubinelli and Salzano (2006) this
distance suggests that potential cascading accidents between theneighboring plants caused by thermal radiation are highly
improbable Therefore the only factor that can trigger a secondary
accident in the other neighboring plant is the overpressure caused
by an uncon1047297ned Vapor Cloud Explosion Considering the volatility
of the materials involved the operational conditions of storage the
average ambient temperature and the prevailing wind direction
(west) we may conclude that only materials stored in AKPCrsquos
storages are capable of forming an effective vapor cloud
There are different values reported for damage threshold due to
overpressure in literature but the overpressure of 1bar would
surely destroy any target equipment (Salzano amp Cozzani 2005)
This threshold has been chosen to evaluate the possibility of
domino accidents on the storage tanks in BSPC Table 6 provides
the magnitude of overpressure caused by different AKPC scenarios
(1e9) at the location of BSPCrsquos storage tanks These values are
based on performing a detailed consequence modeling
As it can be seen in Table 6 the closest storage tanks to AKPC
(TK-201 and TK-202) are possibly damaged due to overpressurecaused by a propylene explosion after a leakage or tank rupture
eventually triggering secondary accidents In other words the
accidental release of propylene in AKPC either continuous
(scenarios 1e4) or instantaneous (scenarios 5e8) has the capa-
bility of causing cascading accidents in BSPC This suggests that if
decision-makers insist on not changing the new plantrsquos layout (eg
due to large economic and operational bene1047297ts) countermeasures
should be taken into consideration in order to minimize the
heightened risk of domino accidents
Both choices for the Purple Book and the UK risk tolerance
criteria are individual choices for this study and they should be
seen and respected as such We are aware that failure frequencies
are subject to constant optimization and that the Purple Book has
its limitations (Pasman 2011) Nonetheless for this study of twoplants situated in Iran using the frequencies reported in this well-
known and much-used work was a justi1047297able choice
5 Conclusions
The risk-based effects of constructing a new chemical plant
adjacent to an existing one forming a chemical cluster is analyzed
and discussed in this paper For this purpose a QRA was carried out
to assess different parameters of risk Individual and societal risks
were evaluated before and after the new plant came under oper-
ation The results indicate that the new plant did not have a major
impact on the risk levels since the risk levels stay within the
tolerability limits Although no major impact was observed there
was a signi1047297cant increase in the societal risk Moreover a dominoeffect analysis indicates that some storage tanks in the new plant
entail a high potential of being affected by events originating in the
existing plant
This research and this case study illustrate that in order to make
an objective plant lay out decision for a chemical cluster with
regard to operational risks not only conventional risk assessments
should be carried out but a domino effects analysis should be
performed as well since otherwise some risks may be under-
estimated and overlooked
It is undoubtedly true that themore accurateinformationis used
(eg concerning probabilities) the more accurate risk calculations
can be made However one should always remember that basically
calculated risks arerelativerisks andthat absolute valuesare prone
to variability and uncertainty As referencedby Pasman et al(2009)
Table 6
Target equipment affected by domino accident (due to overpressure)
scenario
Magnitude of overpressure caused by different AKPC scenarios at
target equipment (bar)
T K - 2 0 1
T K - 2 0 2
T K - 2 0 3
T K - 2 0 4
T K - 2 0 5
T K - 2 0 6
T K - 2 0 7
T K - 2 0 8
T K - 2 0 9
T K - 2 1 0
1-4 02 01 01 008 008 017 015 015
5-8 1 04 02 02 014 014 025 023 022
9 005 005 005 005 005 005 005 005 005 005
Affected by Dominoaccident
Not Affected by Dominoaccident
1 1
1
S Baesi et al Journal of Loss Prevention in the Process Industries 26 (2013) 895e903902
8132019 1-s20-S0950423012001702-main
httpslidepdfcomreaderfull1-s20-s0950423012001702-main 99
EU-studies have shown that a factor of 10e100 both ways in risk
results is not uncommon Hence future research might include risk
distributions and con1047297dence limits allowing risk analysts to even
better understand the uncertainties accompanying the results
References
Abbasi S A Krishnakumari P amp Khan F I (1998) Hot topics Global warming acidrain ozone hole hazardous waste industrial disasters disinfection New DelhiOxford University Press
Abdolhamidzadeh B Abbasi T Rashtchian D amp Abbasi S A (2010) A newmethod for assessing domino effect in chemical process industry Journal of Hazardous Materials 182(1e3) 416e426
Abdolhamidzadeh B Abbasi T Rashtchian D amp Abbasi S A (2011) Dominoeffect in process-industry accidents e an inventory of past events and identi-1047297cation of some patterns Journal of Loss Prevention in the Process Industries
24(5) 575e593Arunraj N S amp Maiti J (2009) A methodology for overall consequence modeling
in chemical industry Journal of Hazardous Materials 169 556e574Atherton J amp Gil F (2008) Incidents that de 1047297ne process safety Hoboken New
Jersey USA WileyBeerens H I Post J G amp Uijt de Haag P A M (2006) The use of generic failure
frequencies in QRA the quality and use of failure frequencies and how to bringthem up-to-date Journal of Hazardous Materials 130 265e270
Bubbico R Maschio G Mazzarotta B Milazzo M amp Parisi E (2006) Riskmanagement of road and rail transport of hazardous materials in Sicily Journalof Loss Prevention in the Process Industries 19(1) 32e38
Center for Chemical Process Safety (CCPS) (2000) Guidelines for chemical processquantitative risk analysis (2nd ed) New York American Institute of ChemicalEngineering
CozzaniV GubinelliG amp SalzanoE (2006)Escalationthresholds inthe assessmentof domino accidental events Journal of Hazardous Materials 129(1e3)1e21
CPR 18E (1999) lsquo Purple bookrsquo guidelines for quantitative risk assessment Part oneEstablishments The Hague RVIM
Dechy N Bourdeaux T Ayrault N Kordek M A amp Le Coze J C (2004) Firstlessons of the Toulouse ammonium nitrate disaster 21st September 2001 AZFplant France Journal of Hazardous Materials 111(1e3) 131e138
Gharabagh M J Asilian H Mortasavi S B Mogaddam A Z Hajizadeh E ampKhavanin A (2009) Comprehensive risk assessment and management of petrochemical feed and product transportation pipelines Journal of LossPrevention in the Process Industries 22(4) 533e539
Gooijer L Cornil N amp Lenoble C L (2012) An international comparison of fourquantitative risk assessment approaches e a benchmark study based on a 1047297cti-tious LPG plant Process Safety and Environmental Protection 90(2) 101e107
IRIMO (2006) Climatologically normal for the period 1987 e
2006 Mahshahr TehranIR of Iran Meteorological Organization Data Processing Center
Jo Y amp Crowl D (2008) Individual risk analysis of high-pressure natural gaspipelines Journal of Loss Prevention in the Process Industries 21 (6) 589e595
Kalantarnia M Khan F amp Hawboldt K (2010) Modelling of BP Texas City re1047297neryaccident using dynamic risk assessment approach Process Safety and Environ-mental Protection 88(3) 191e199 (Institution of Chemical Engineers)
Khan F I amp Abbasi S A (1998) Techniques and methodologies for risk analysis inchemical process industries Journal of Loss Prevention in the Process Industries11 261e277
Khan F I amp Abbasi S A (1999a) Major accidents in process industries and ananalysis of causes and consequences Journal of Loss Prevention in the ProcessIndustries 12 361e378
Khan F I amp Abbasi S A (1999b) Assessment of risks posed by chemical indus-triesdapplication of a new computer automated tool MAXCRED-III Journal of Loss Prevention in the Process Industries 12(6) 455e469
Khan F I Sadiq R amp Husain T (2002) Risk-based process safety assessment andcontrol measures design for offshore process facilities Journal of HazardousMaterials 94(1) 1e36
Kletz T A (1999b) The origins and history of loss prevention Transaction IChemE77 109e116
Kletz T A (1999a) What went wrong Case histories of process plant disasters andhow they could have been avoided Houston USA Gulf Professional Publishing
Kletz T A (2003) Still going wrong Case histories of process plant disasters and howthey could have been avoided Houston USA Gulf Professional Publishing
Lees F P (1996) Loss prevention in the process industries (2nd ed) Oxford LondonButterworth Heinemann
Markowski A S (2007) exLOPA for explosion risks assessment Journal of Hazardous Materials 142(3) 669e676
Milazzo M F Lisi R Maschio G Antonioni G Bonvicini S amp Spadoni G (2002)HazMat transport through Messina town from risk analysis suggestions forimproving territorial safety Journal of Loss Prevention in the Process Industries15(5) 347e356
Papazoglou I A Nivolianitou Z Aneziris O Christou M D amp Bonanos G (1999)Risk-informed selection of a highway trajectory in the neighborhood of an oil-re1047297nery Journal of Hazardous Materials 67 (2) 111e144
Pasman H J (2011) History of Dutch process equipment failure frequencies and thepurple book Journal of Loss Prevention in the Process Industries 24 208e213
Pasman H J Jung S Prem K Rogers W J amp Yang X (2009) Is risk analysisa useful tool for improving process safety Journal of Loss Prevention in theProcess Industries 22(6) 769e777
Pintaric Z (2007) Assessment of the consequences of accident scenariosinvolving dangerous substances Process Safety and Environmental Protection85(1) 23e38
Pula R Khan F I Veitch B amp Amyotte P (2006) A grid based approach for 1047297reand explosion consequence analysis Process Safety and Environmental Protec-tion 84(2) 79e91
Reniers G L L (2010) An external domino effects investment approach to improvecross-plant safety within chemical clusters Journal of Hazardous Materials 177 167e174
Reniers G L L amp Dullaert W (2007) DomPrevPlanning user-friendly software forplanning domino effects prevention Safety Science 45(10) 1060e1081
Renjith V R amp Madhu G (2010) Individual and societal risk analysis and mappingof human vulnerability to chemical accidents in the vicinity of an industrialarea International Journal of Applied Engineering Research Dindigul 1 135e148
Rigas F amp Sklavounos S (2002) Risk and consequence analyses of hazardouschemicals in marshalling yards and warehouses at IkonioPiraeus harbourGreece Journal of Loss Prevention in the Process Industries 15(6) 531e544
Salzano Eamp Cozzani V (2005)The analysis of dominoaccidents triggered byvaporcloud explosions Reliability Engineering amp System Safety 90(2e3) 271e284
Spadoni G Egidi D amp Contini S (2000) Through ARIPAR-GIS the quanti 1047297ed arearisk analysis supports land-use planning activities Journal of Hazardous Mate-rials 71(1e3) 423e437
Van Sciver G R (1990) Quantitative risk analysis in the chemical process indus-tries Reliability Engineering amp System Safety 29 55e68
Viacutelchez J A Espejo V amp Casal J (2011) Generic event trees and probabilities forthe release of different types of hazardous materials Journal of Loss Preventionin the Process Industries 24(3) 281e287
Wells G (1997) Major hazards and their management Rugby UK Institution of Chemical Engineers
Yet-Pole IChi-MinS amp Ching-Hong C (2009)Applicationsof 3D QRAtechnique tothe 1047297reexplosion simulation and hazard mitigation within a naphtha-crackingplant Journal of Loss Prevention in the Process Industries 22 (4) 506e515
S Baesi et al Journal of Loss Prevention in the Process Industries 26 (2013) 895e903 903
![Page 2: 1-s2.0-S0950423012001702-main](https://reader038.vdocuments.us/reader038/viewer/2022100505/577cd1271a28ab9e7893bef5/html5/thumbnails/2.jpg)
8132019 1-s20-S0950423012001702-main
httpslidepdfcomreaderfull1-s20-s0950423012001702-main 29
residential areas in order to compare the result with safety
criteria and eventually recommendations were given to make
modi1047297cations in the plants since the criteria were not met Jo and
Crowl (2008) speci1047297ed the minimum safety distances between
a high pressure gas pipeline and residential areas Risk and conse-
quence analyses of toxic chemicals in certain warehouses to the
nearby villages were analyzed by Rigas and Sklavounos (2002) to
investigate the extent of compliance to exposure threshold limits
The study by Papazoglou Nivolianitou Aneziris Christou and
Bonanos (1999) demonstrated that a high level of risk is exposed
to passengers crossing the highway adjacent to a speci1047297c re1047297nery
and thereforea new trajectory withthe safety distancecalculated by
QRAshould be constructed These area limited numberof examples
showing that land use planning is vital forlocating process facilities
near to public areas and a QRA could be an effective technique for
this purpose In this method in addition to identifying the hazards
also their associated consequences and the frequencies of occur-
rences are quantitatively estimated (Kletz 1999b) Furthermore
parameters such as lsquoindividual riskrsquo and lsquogroup riskrsquo (the latter also
being called lsquosocietal riskrsquo) are parameters which support the deci-
sion making process for land use planning Several other relevant
studies can be found elsewhere (Bubbico Maschio Mazzarotta
Milazzo amp Parisi 2006 Gharabagh et al 2009 Milazzo et al2002 Yet-Pole Chi-Min amp Ching-Hong 2009)
The proliferation of chain accidents suggests that the probability
of domino effects should also be considered as an important
parameterin land useplanning forchemical clusters A recent study
on past domino events indicated that the number of cascading
accidents in the process industries has increased globally in recent
decades (Abdolhamidzadeh Abbasi Rashtchian amp Abbasi 2011) In
the same study there are some accidents mentioned in which an
initiating event in a single plant has led to a catastrophe within
a clusterof chemical plants A recentexample couldbe Shazand Iran
in which 30 peoplewere killedand 38 others were seriously injured
in 2008due to an initial explosion that ledto other majorexplosions
and 1047297res in the neighboring plants The dominant accident
that caused the majority of fatalities was the major explosions thatwere triggered by the initial blast (Abdolhamidzadeh et al 2011)
As already mentioned in land use planning possible scenarios
are reviewed from different points of view one being the safety
perspective In many cases different chemical plants in a chemical
industrial area do not come into operation at the same point in
time Forexample it is common practice to build plants to consume
the product(s) of an existing plant It is obvious that the construc-
tion of new plant(s) adjacent to existing one(s) will affect the
overall risk of the industrial area regardless of the fact whether risk
assessments have been performed for individual plants
In the remainder of this article QRA has been applied to eval-
uate the risk-based effects of constructing a new chemical plant
(which is called BSPC in this article) adjacent to an existing one
(called AKPC in this paper) These two plants forming our case-study are located in one of the largest energy zones in the world
in southern Iran (called lsquoPETZONErsquo) Parameters such as the indi-
vidualrisk and the societal risk have been assessedbefore and after
the new plant came into operation Furthermore the possibility
and the likelihood of domino events in the two neighboring plants
were investigated We mainly focus on safety aspects in our article
as the feasibility of the planning from both an economic and an
operational perspective has been carried out in an earlier stage of
the land-use planning decision process
2 Quantitative Risk Assessment (QRA)
QRA along with other techniques have been used in one way or
another in the process industries for loss prevention from 1970
onwards (Abbasi Krishnakumari amp Khan 1998 Khan amp Abbasi
1998) QRA is a method that provides quanti1047297ed estimation for
the risk posed by a group of hazards (Kletz 1999) Hence this
technique enables risk mitigation methods to be evaluated in order
to bring the risk to tolerable levels without resorting to too costly
protective systems (Pula Khan Veitch amp Amyotte 2006) Although
QRAhas itsweaknesses anddrawbacksit is often theonlyapproach
to get grip on possible risks and to tame complexity as indicated by
Pasman Jung Prem Rogers and Yang (2009) QRA involves the
following main steps scenario selection frequency estimation
consequence assessment and risk quanti1047297cation (CCPS 2000
Khan Sadiq amp Husain 2002) We will discuss these steps hereafter
21 Scenario selection
Possible scenarios in the process industries may be different
modes of 1047297re explosion and toxic dispersion (Arunraj amp Maiti
2009 Markowski 2007) Neglecting any possible scenario can
lead to a risk underestimation and eventually affect the overall risk
values (Van Sciver 1990) Scenario selection is usually based on
expertrsquos opinion history of past accidents and safety reviews For
our study after selecting the credible scenarios based on a combi-
nation of mentioned methods Event Tree Analysis (ETA) wasapplied for scenario development The quantitative feature of ETA
was then used for incident frequency calculation
22 Frequency estimation
Once the 1047297nal outcomes and their sequences are predicted for
each scenario the scenario frequency should be determined For
this purpose the failure frequency of each initiating event and the
probability of every intermediate event such as immediate ignition
delayed ignition vapor cloud 1047297re etc are used The frequency
values which can be found in literature are mostly based on
historical data of previous incidents (Beerens Post amp Uijt de Haag
2006) The frequency of a scenario speci1047297es the number of occur-
rences of that scenario in a speci1047297ed timeframe (which is usuallyone year) The probability of an intermediate event is a dimension-
less value between0 and 1 which indicates the possibility of
occurrence of that event in a speci1047297c period of time For this paper
the failure frequencies for the initiating events and the intermediate
values were obtained from the Purple Book (CPR 1999) Application
of failure frequenciesin thePurple Book andthe BEVI Manualduring
the past years wasindustry standard Also softwaresuch as ARIPAR-
GIS (Spadoni Egidi amp Contini 2000) or DomPrevPlanning (Reniers
amp Dullaert 2007) use these values The following equation shows
how the initiating event frequency intermediate probabilities and
1047297nal outcome frequency are related to each other (CCPS 2000)
f i frac14 F I P oiP oci (1)
where f i is the frequency of the 1047297nal outcome of scenario i arising
from incident I (1yr)F I is the frequency of incident I which causes
different outcomes (1yr)P oi is probability of occurrence for an
intermediate outcome of incident I which causes a number of i 1047297nal
outcomes and P oci is the probability of occurrence for a 1047297nal
outcome which is a subset of outcomes arising from incident I
23 Consequences assessment
During the consequence assessment the effects and magnitude
of the 1047297nal outcome of each scenario should be estimated The
consequences of potential scenarios could be classi1047297ed as follows
(Lees 1996) 1047297re thermal radiation explosion overpressure and
fragment projection and toxic dispersion and exposure
S Baesi et al Journal of Loss Prevention in the Process Industries 26 (2013) 895e903896
8132019 1-s20-S0950423012001702-main
httpslidepdfcomreaderfull1-s20-s0950423012001702-main 39
Besides serious physical human harm and eventually casualties
property damage and environmental effects are other conse-
quences among the overall potential loss (Pintaric 2007)
The measure of damage in QRA is fatality since other types of loss
are more complex to assess in comparison to human casualties
(Pula et al 2006)
A chain of rigorous calculations is needed to estimate the
intensity of the physical harm posed by the mentioned scenario
outcomes in a chemical cluster Software packages for the proce-
dure of consequence assessment are used to estimate the numer-
ical value of thermal heat load explosion overpressure and toxic
concentration at various spots around the release point For this
study the well-known PHAST (Process Hazard Analysis Safety Tool)
software was used for consequence assessment Once the appro-
priate failure frequencies are given this particular software con-
taining 1047297ne discharge dispersion evaporation and rainout models
is a powerful tool for the prediction of effect zones (Pintaric 2007)
In addition to the results of consequence modeling fatality probit
equations were used to quantify the expected percentage of
lethality for the exposed population
24 Risk quanti 1047297cation
The frequency and severity (rate of fatality) of every speci1047297c
scenario are combined to obtain a measure of the corresponding
risk Risk quanti1047297cation results are presented in two conventional
categories which are known as lsquoindividual riskrsquo and lsquogroup riskrsquo
(also called lsquosocietal riskrsquo)
The frequency at which a particular individual being fatally
harmed when standing at a certain distance from a potential
hazard is known as ldquoindividual riskrdquo (Gooijer Cornil amp Lenoble
2012) The overall individual risk at any location ( x y) inside or
outside the industrial plant is the summation of all individual risks
at that speci1047297c point The individual risk at any location ( x y) is
calculated by the following equation (CCPS 200 0)
IR x y frac14Xn
ifrac141
IR x yi (2)
In other words the risk of any identi1047297ed scenario will be indi-
vidually calculated at a speci1047297c location ( x y) and subsequently all
risks are summed to estimate the overall risk at that speci1047297c point
To calculate the individual risk at location ( x y) arising from
scenario i the following equation is applied (CCPS 200 0)
IR x yi frac14 f iP f i (3)
where f i is the frequency of the 1047297nal outcome of scenario i arising
from an incident (1yr) andP f iis the fatality probability of the 1047297nal
outcome of scenario i at the geographical location ( x y) Individualrisk contours represent the 1047297nal results of this step The individual
risk value in every position when compared to universally or
regionally accepted values is one of the criteria in risk-based
decision making for land use planning
Societal risk provides a risk evaluation for a group of people
located in the vicinity of the accident location In other words the
number of people affected by all 1047297nal outcomes is estimated
(Renjith amp Madhu 2010) Similar to the individual risk the societal
risk is a function of frequency of occurrence and rate of fatality
Another important and determinant factor for calculating the
societal risk is the population density around the incident location
Thesocietal riskis presented in form of FeN (FrequencyeNumber
of fatalities) curves where the cumulative frequency of 1047297nal
outcomes is plotted against the number of fatalities arising from anoutcome in a logarithmic scale To calculate the number of fatalities
of each 1047297nal outcome the following equation is used (CCPS 2000)
N i frac14X
x y
P x y p f i (4)
whereN irepresents the number of fatalities of the 1047297nal outcome of
scenario i P x yis the number of individuals at the geographical
location ( x y) and p f i is the probability that the 1047297nal outcome of
scenario i causes death at the geographical location ( x y)
The results obtained above are used in Equation (5) to calculate
the ultimate data required for plotting the FeN curve This equation
which is known as the cumulative frequency equation is expressed
as below (CCPS 2000)
F N frac14X
i
F i for all final outcome case I which N i gt N (5)
where F N is the cumulative frequency for all 1047297nal outcomes which
result in fatalities of more than N personsF i is the frequency of the
Fig 1 Layout of the study area (case-study) showing the two neighboring plants AKPC and BSPC
S Baesi et al Journal of Loss Prevention in the Process Industries 26 (2013) 895e903 897
8132019 1-s20-S0950423012001702-main
httpslidepdfcomreaderfull1-s20-s0950423012001702-main 49
1047297nal outcome of scenario i and N i is the number of fatalities for the
1047297nal outcome of scenario i Finally having the quantities of F N and
N the cumulative frequency of 1047297nal outcomes is plotted against the
number of fatalities The obtained FeN curved will be compared
against the intended criteria to evaluate the acceptability of the
potential societal risk
3 Case study
ldquoAKPCrdquo and ldquoBSPCrdquo are two neighboring complexes located in
the so-called PETZONE In this industrial region 15 petrochemical
plants are situated in 5 distinct sites within an area of approxi-mately 20 km2 and therefore it is known to be one of the biggest
energy zones in the world The PETZONE lies in the northern coast
of the Persian Gulf and expands to the southwestern city of Mah-
shahr in southern Iran
Before and during the construction of many plants in the PET-
ZONE until present only economic and operational factors have
been taken into account leaving safety aspects to be largely
neglected in the layout design of those plants This was also the
case for our case study of the two plants AKPC and BSPC The ole1047297n
unit of AKPC produces ethylene and propylene and these
substances are later used in the polymerization unit to produce
high density polyethylene low density polyethylene and poly-
propylene Regarding BSPC its main products are naphtha p-
xylene and acetic acid
These two plants present an interesting case study due to their
high number of storage tanks and huge inventory of chemicals As
one of these plants provides a portion of the other one rsquos feed
constructing them close together seemed a wise choice from an
economic and operational point of view However the compliance
of risk criteria had not been an item of consideration After occur-
rence of some minor process accidents with limited consequences
in these plants the risk of accident escalation from one plant to
another was highlighted more than ever Therefore the idea of
constructing AKPC and BSPC in proximity of each other which
seemed a defendable choice once has been challenged In the
present study the two adjacent chemical complexes AKPC and
BSPC are both subjected to one QRA (treating both plants as one
plant) allowing us to analyze the effects of the construction of a
petrochemical plant adjacent to an existing one on the overall riskThe purpose was to verify whether it was indeed a wise choice to
construct these two plants this close to each other (for production
purposes) or not (for safety reasons) Fig 1 represents the layout of
the two petrochemical plants
Based on a safety review and on a safety screening carried out
as a preliminary step the major hazard sources of the study area
(as displayed in Fig 1) appear to be the storage tanks of these two
plants Although there are obviously other sources of hazards
within this area their contribution in the overall risk could be
regarded negligible (compared with the present storage tanks)
AKPC houses 5 major operational storage tanks containing
ethylene and propylene while BSPC contains 10 major atmo-spheric storage tanks containing naphtha p-xylene and acetic
acid Tables 1 and 2 provide a list of the chemical substance
inventories in AKPC and BSPC Although there were some other
storage tanks or process equipment no one passed the screening
step for scenario selection due to their low inventory of hazardous
materials and due to the lesser inherent hazardousness of the
materials
The atmosphericdata used in this study were established by the
Iranian Meteorological Organization (IMO) for the Mahshahr port
from 1988 to 2006 (IRIMO 2006) The result of the meteorological
data analysis indicates that two prevailing weather conditions (hot
season and cold season) can be intended for the QRA study during
daytime and nighttime to cover almost all of the probable condi-
tions Table 3 summarizes the average meteorological data whichare used for the consequence analysis
31 Accident scenarios
As stated previously the storage tanks have been identi1047297ed to
lead to the most hazardous scenarios in the case under study
Table 1
List of AKPC storages in this study
TK-item Compound Type Temperature
(C)
Pressure
(barg)
Volume
(m3)
Inventory
(tonne)
TK-101 Propylene Spherical 40 25 2200 1044
TK-102 Propylene Spherical 40 25 2200 1044
TK-103 Propylene Spherical 40 25 2200 1044
TK-104 Propylene Spherical 40 25 2200 1044
TK-105 Ethylene Cylindrical
104 Atm 14000 7968
Table 2
List of BSPC storages in this study
TK-item Compound Type Temperature
(C)
Pressure
(barg)
Volume
(m3)
Inventory
(tonne)
TK-201 Naphtha Cy lindrical 30 001 331188 24839
TK-202 Naphtha Cy lindrical 30 001 331188 24839
TK-203 Naphtha Cy lindrical 30 001 331188 24839
TK-204 Naphtha Cylindrical 30 001 16272 12204
TK-205 Naphtha Cylindrical 30 Atm 16272 12204TK-206 P -Xylene Cy lindrical 30 At m 170856 14693
TK-207 P -Xylene Cy lindrical 30 At m 170856 14693
TK-208 P-Xylene Cylindrical 40 0003 1500 1267
TK-209 Acetic acid Cylindrical 45 0014 1500 1554
TK-210 Acetic acid Cylindrical 45 0014 1500 1554
Table 3
Prevailing weather conditions
Category Atmospheric stability Average wind
speed (ms)
Average ambient
temp (C)
Average relative
humidity ()
Hot season (daytime) Neutral (D class) 5 40 50
Hot season (nighttime) Stable (F class) 15 25 60
Cold season (daytime) Neutral (D class) 5 20 80
Cold season (nighttime) Stable (F class) 15 10 90
Table 4
Accident scenarios and the relevant failure frequencies
Scenario
no
TK -i tem n o C ontai nmen t Scena ri o typ e Frequency
(1yr)
1e4 TK-101102103104 Propylene Leakage 1 105
5e8 TK-101102103104 Propylene Rupture 5 107
9 TK-105 Ethylene Leakage 1 105
10e14 TK-201202203
204205
Naphtha Leakage 1 105
15e17 TK-206207208 P-Xylene Leakage 1 105
18e19 TK-209 210 Acetic acid Leakage 1 105
S Baesi et al Journal of Loss Prevention in the Process Industries 26 (2013) 895e903898
8132019 1-s20-S0950423012001702-main
httpslidepdfcomreaderfull1-s20-s0950423012001702-main 59
8132019 1-s20-S0950423012001702-main
httpslidepdfcomreaderfull1-s20-s0950423012001702-main 69
Fig 4 A B individual risk contours before (for AKPC) and after (for cluster composed of AKPC and BSPC) constructing the new plant
8132019 1-s20-S0950423012001702-main
httpslidepdfcomreaderfull1-s20-s0950423012001702-main 79
the leakage case and in the rupture case Moreover based on the
plant layout review and due to the low level of equipment
congestion in this particular area under study the probability of
a 1047298ash 1047297re is higher than that of a Vapor Cloud Explosion (VCE)
since higher congestion is known to increase the probability of
a VCE rather than that of a 1047298ash 1047297re
4 Result and discussion
In order to evaluate the risk-based effects of constructing BSPC
adjacent to AKPC calculations were made for both individual risk
and societal risk before and after the new plant came under oper-
ation adjacent to the existing one The quanti1047297ed risk can then be
Fig 5 A B societal risk (Fe
N curve) before (A) and after (B) constructing the new plant
S Baesi et al Journal of Loss Prevention in the Process Industries 26 (2013) 895e903 901
8132019 1-s20-S0950423012001702-main
httpslidepdfcomreaderfull1-s20-s0950423012001702-main 89
compared against the criteria to assess the acceptability of the risk
levels The likelihood of domino effects needs to be assessed as
well
41 Calculation of individual risk
Using the results of frequency estimation and a detailed
consequence assessment for all the possible scenarios the indi-
vidual risk contours were obtained and are shown on a satellite
view of the study area Key outputs of the consequence modeling
are presented in Table 5 to give more insight in the two selected
scenarios Fig 4A and B demonstrate the individual risk levels
before (A) and after (B) the second plant came operational The
numerical value of each risk contour represents the frequency at
which a particular individual is fatally harmed when standing
within the contour boundary
The results of individual risk calculations reveal that inside the
chemical cluster composed of both plants (AKPC and BSPC) as well
as within the single plant AKPC the individual risk values do not
exceed the tolerable magnitude of 105yr before and after the new
plant came under operation Fig 3A and B also demonstrate that for
public areas (such as the main roads around AKPC and BSPC) the
risk level does not exceed the magnitude of 106yr except fora short interval of 100 m at the southern main road of AKPC
Nevertheless this issue was already present even before the
construction of BSPC In general we can state that in terms of
individual risk constructing the new plant adjacent to the existing
one did not affect the acceptability of risk levels
42 Calculation of societal risk
Although the previous section indicates that individual risk
levels do not exceed the tolerable levels the impact of any potential
accident on operators and public should also be investigated
Fig 4A and B provide the societal risk calculation results before and
after the new plant came into operation respectively As it can be
seen in Fig 5A the societal risk posed by AKPC individually falls inthe ALARP (As Low As Reasonably Practicable) region as de1047297ned by
HSE (UK)Fig 5Bshows that after constructing the new plant the
societal risk curve gets closer to the maximum risk criteria but still
remains in the ALARP region Therefore constructing the new plant
BSPC adjacent to the existing one AKPC seems to have only limited
impact upon the change of tolerability of the societal risk in our
case study
43 Domino effects assessment
The distance from the storage tanks located in AKPC to the
closest operational storage tank in BSPC is about 800 m Based on
the values reported by Cozzani Gubinelli and Salzano (2006) this
distance suggests that potential cascading accidents between theneighboring plants caused by thermal radiation are highly
improbable Therefore the only factor that can trigger a secondary
accident in the other neighboring plant is the overpressure caused
by an uncon1047297ned Vapor Cloud Explosion Considering the volatility
of the materials involved the operational conditions of storage the
average ambient temperature and the prevailing wind direction
(west) we may conclude that only materials stored in AKPCrsquos
storages are capable of forming an effective vapor cloud
There are different values reported for damage threshold due to
overpressure in literature but the overpressure of 1bar would
surely destroy any target equipment (Salzano amp Cozzani 2005)
This threshold has been chosen to evaluate the possibility of
domino accidents on the storage tanks in BSPC Table 6 provides
the magnitude of overpressure caused by different AKPC scenarios
(1e9) at the location of BSPCrsquos storage tanks These values are
based on performing a detailed consequence modeling
As it can be seen in Table 6 the closest storage tanks to AKPC
(TK-201 and TK-202) are possibly damaged due to overpressurecaused by a propylene explosion after a leakage or tank rupture
eventually triggering secondary accidents In other words the
accidental release of propylene in AKPC either continuous
(scenarios 1e4) or instantaneous (scenarios 5e8) has the capa-
bility of causing cascading accidents in BSPC This suggests that if
decision-makers insist on not changing the new plantrsquos layout (eg
due to large economic and operational bene1047297ts) countermeasures
should be taken into consideration in order to minimize the
heightened risk of domino accidents
Both choices for the Purple Book and the UK risk tolerance
criteria are individual choices for this study and they should be
seen and respected as such We are aware that failure frequencies
are subject to constant optimization and that the Purple Book has
its limitations (Pasman 2011) Nonetheless for this study of twoplants situated in Iran using the frequencies reported in this well-
known and much-used work was a justi1047297able choice
5 Conclusions
The risk-based effects of constructing a new chemical plant
adjacent to an existing one forming a chemical cluster is analyzed
and discussed in this paper For this purpose a QRA was carried out
to assess different parameters of risk Individual and societal risks
were evaluated before and after the new plant came under oper-
ation The results indicate that the new plant did not have a major
impact on the risk levels since the risk levels stay within the
tolerability limits Although no major impact was observed there
was a signi1047297cant increase in the societal risk Moreover a dominoeffect analysis indicates that some storage tanks in the new plant
entail a high potential of being affected by events originating in the
existing plant
This research and this case study illustrate that in order to make
an objective plant lay out decision for a chemical cluster with
regard to operational risks not only conventional risk assessments
should be carried out but a domino effects analysis should be
performed as well since otherwise some risks may be under-
estimated and overlooked
It is undoubtedly true that themore accurateinformationis used
(eg concerning probabilities) the more accurate risk calculations
can be made However one should always remember that basically
calculated risks arerelativerisks andthat absolute valuesare prone
to variability and uncertainty As referencedby Pasman et al(2009)
Table 6
Target equipment affected by domino accident (due to overpressure)
scenario
Magnitude of overpressure caused by different AKPC scenarios at
target equipment (bar)
T K - 2 0 1
T K - 2 0 2
T K - 2 0 3
T K - 2 0 4
T K - 2 0 5
T K - 2 0 6
T K - 2 0 7
T K - 2 0 8
T K - 2 0 9
T K - 2 1 0
1-4 02 01 01 008 008 017 015 015
5-8 1 04 02 02 014 014 025 023 022
9 005 005 005 005 005 005 005 005 005 005
Affected by Dominoaccident
Not Affected by Dominoaccident
1 1
1
S Baesi et al Journal of Loss Prevention in the Process Industries 26 (2013) 895e903902
8132019 1-s20-S0950423012001702-main
httpslidepdfcomreaderfull1-s20-s0950423012001702-main 99
EU-studies have shown that a factor of 10e100 both ways in risk
results is not uncommon Hence future research might include risk
distributions and con1047297dence limits allowing risk analysts to even
better understand the uncertainties accompanying the results
References
Abbasi S A Krishnakumari P amp Khan F I (1998) Hot topics Global warming acidrain ozone hole hazardous waste industrial disasters disinfection New DelhiOxford University Press
Abdolhamidzadeh B Abbasi T Rashtchian D amp Abbasi S A (2010) A newmethod for assessing domino effect in chemical process industry Journal of Hazardous Materials 182(1e3) 416e426
Abdolhamidzadeh B Abbasi T Rashtchian D amp Abbasi S A (2011) Dominoeffect in process-industry accidents e an inventory of past events and identi-1047297cation of some patterns Journal of Loss Prevention in the Process Industries
24(5) 575e593Arunraj N S amp Maiti J (2009) A methodology for overall consequence modeling
in chemical industry Journal of Hazardous Materials 169 556e574Atherton J amp Gil F (2008) Incidents that de 1047297ne process safety Hoboken New
Jersey USA WileyBeerens H I Post J G amp Uijt de Haag P A M (2006) The use of generic failure
frequencies in QRA the quality and use of failure frequencies and how to bringthem up-to-date Journal of Hazardous Materials 130 265e270
Bubbico R Maschio G Mazzarotta B Milazzo M amp Parisi E (2006) Riskmanagement of road and rail transport of hazardous materials in Sicily Journalof Loss Prevention in the Process Industries 19(1) 32e38
Center for Chemical Process Safety (CCPS) (2000) Guidelines for chemical processquantitative risk analysis (2nd ed) New York American Institute of ChemicalEngineering
CozzaniV GubinelliG amp SalzanoE (2006)Escalationthresholds inthe assessmentof domino accidental events Journal of Hazardous Materials 129(1e3)1e21
CPR 18E (1999) lsquo Purple bookrsquo guidelines for quantitative risk assessment Part oneEstablishments The Hague RVIM
Dechy N Bourdeaux T Ayrault N Kordek M A amp Le Coze J C (2004) Firstlessons of the Toulouse ammonium nitrate disaster 21st September 2001 AZFplant France Journal of Hazardous Materials 111(1e3) 131e138
Gharabagh M J Asilian H Mortasavi S B Mogaddam A Z Hajizadeh E ampKhavanin A (2009) Comprehensive risk assessment and management of petrochemical feed and product transportation pipelines Journal of LossPrevention in the Process Industries 22(4) 533e539
Gooijer L Cornil N amp Lenoble C L (2012) An international comparison of fourquantitative risk assessment approaches e a benchmark study based on a 1047297cti-tious LPG plant Process Safety and Environmental Protection 90(2) 101e107
IRIMO (2006) Climatologically normal for the period 1987 e
2006 Mahshahr TehranIR of Iran Meteorological Organization Data Processing Center
Jo Y amp Crowl D (2008) Individual risk analysis of high-pressure natural gaspipelines Journal of Loss Prevention in the Process Industries 21 (6) 589e595
Kalantarnia M Khan F amp Hawboldt K (2010) Modelling of BP Texas City re1047297neryaccident using dynamic risk assessment approach Process Safety and Environ-mental Protection 88(3) 191e199 (Institution of Chemical Engineers)
Khan F I amp Abbasi S A (1998) Techniques and methodologies for risk analysis inchemical process industries Journal of Loss Prevention in the Process Industries11 261e277
Khan F I amp Abbasi S A (1999a) Major accidents in process industries and ananalysis of causes and consequences Journal of Loss Prevention in the ProcessIndustries 12 361e378
Khan F I amp Abbasi S A (1999b) Assessment of risks posed by chemical indus-triesdapplication of a new computer automated tool MAXCRED-III Journal of Loss Prevention in the Process Industries 12(6) 455e469
Khan F I Sadiq R amp Husain T (2002) Risk-based process safety assessment andcontrol measures design for offshore process facilities Journal of HazardousMaterials 94(1) 1e36
Kletz T A (1999b) The origins and history of loss prevention Transaction IChemE77 109e116
Kletz T A (1999a) What went wrong Case histories of process plant disasters andhow they could have been avoided Houston USA Gulf Professional Publishing
Kletz T A (2003) Still going wrong Case histories of process plant disasters and howthey could have been avoided Houston USA Gulf Professional Publishing
Lees F P (1996) Loss prevention in the process industries (2nd ed) Oxford LondonButterworth Heinemann
Markowski A S (2007) exLOPA for explosion risks assessment Journal of Hazardous Materials 142(3) 669e676
Milazzo M F Lisi R Maschio G Antonioni G Bonvicini S amp Spadoni G (2002)HazMat transport through Messina town from risk analysis suggestions forimproving territorial safety Journal of Loss Prevention in the Process Industries15(5) 347e356
Papazoglou I A Nivolianitou Z Aneziris O Christou M D amp Bonanos G (1999)Risk-informed selection of a highway trajectory in the neighborhood of an oil-re1047297nery Journal of Hazardous Materials 67 (2) 111e144
Pasman H J (2011) History of Dutch process equipment failure frequencies and thepurple book Journal of Loss Prevention in the Process Industries 24 208e213
Pasman H J Jung S Prem K Rogers W J amp Yang X (2009) Is risk analysisa useful tool for improving process safety Journal of Loss Prevention in theProcess Industries 22(6) 769e777
Pintaric Z (2007) Assessment of the consequences of accident scenariosinvolving dangerous substances Process Safety and Environmental Protection85(1) 23e38
Pula R Khan F I Veitch B amp Amyotte P (2006) A grid based approach for 1047297reand explosion consequence analysis Process Safety and Environmental Protec-tion 84(2) 79e91
Reniers G L L (2010) An external domino effects investment approach to improvecross-plant safety within chemical clusters Journal of Hazardous Materials 177 167e174
Reniers G L L amp Dullaert W (2007) DomPrevPlanning user-friendly software forplanning domino effects prevention Safety Science 45(10) 1060e1081
Renjith V R amp Madhu G (2010) Individual and societal risk analysis and mappingof human vulnerability to chemical accidents in the vicinity of an industrialarea International Journal of Applied Engineering Research Dindigul 1 135e148
Rigas F amp Sklavounos S (2002) Risk and consequence analyses of hazardouschemicals in marshalling yards and warehouses at IkonioPiraeus harbourGreece Journal of Loss Prevention in the Process Industries 15(6) 531e544
Salzano Eamp Cozzani V (2005)The analysis of dominoaccidents triggered byvaporcloud explosions Reliability Engineering amp System Safety 90(2e3) 271e284
Spadoni G Egidi D amp Contini S (2000) Through ARIPAR-GIS the quanti 1047297ed arearisk analysis supports land-use planning activities Journal of Hazardous Mate-rials 71(1e3) 423e437
Van Sciver G R (1990) Quantitative risk analysis in the chemical process indus-tries Reliability Engineering amp System Safety 29 55e68
Viacutelchez J A Espejo V amp Casal J (2011) Generic event trees and probabilities forthe release of different types of hazardous materials Journal of Loss Preventionin the Process Industries 24(3) 281e287
Wells G (1997) Major hazards and their management Rugby UK Institution of Chemical Engineers
Yet-Pole IChi-MinS amp Ching-Hong C (2009)Applicationsof 3D QRAtechnique tothe 1047297reexplosion simulation and hazard mitigation within a naphtha-crackingplant Journal of Loss Prevention in the Process Industries 22 (4) 506e515
S Baesi et al Journal of Loss Prevention in the Process Industries 26 (2013) 895e903 903
![Page 3: 1-s2.0-S0950423012001702-main](https://reader038.vdocuments.us/reader038/viewer/2022100505/577cd1271a28ab9e7893bef5/html5/thumbnails/3.jpg)
8132019 1-s20-S0950423012001702-main
httpslidepdfcomreaderfull1-s20-s0950423012001702-main 39
Besides serious physical human harm and eventually casualties
property damage and environmental effects are other conse-
quences among the overall potential loss (Pintaric 2007)
The measure of damage in QRA is fatality since other types of loss
are more complex to assess in comparison to human casualties
(Pula et al 2006)
A chain of rigorous calculations is needed to estimate the
intensity of the physical harm posed by the mentioned scenario
outcomes in a chemical cluster Software packages for the proce-
dure of consequence assessment are used to estimate the numer-
ical value of thermal heat load explosion overpressure and toxic
concentration at various spots around the release point For this
study the well-known PHAST (Process Hazard Analysis Safety Tool)
software was used for consequence assessment Once the appro-
priate failure frequencies are given this particular software con-
taining 1047297ne discharge dispersion evaporation and rainout models
is a powerful tool for the prediction of effect zones (Pintaric 2007)
In addition to the results of consequence modeling fatality probit
equations were used to quantify the expected percentage of
lethality for the exposed population
24 Risk quanti 1047297cation
The frequency and severity (rate of fatality) of every speci1047297c
scenario are combined to obtain a measure of the corresponding
risk Risk quanti1047297cation results are presented in two conventional
categories which are known as lsquoindividual riskrsquo and lsquogroup riskrsquo
(also called lsquosocietal riskrsquo)
The frequency at which a particular individual being fatally
harmed when standing at a certain distance from a potential
hazard is known as ldquoindividual riskrdquo (Gooijer Cornil amp Lenoble
2012) The overall individual risk at any location ( x y) inside or
outside the industrial plant is the summation of all individual risks
at that speci1047297c point The individual risk at any location ( x y) is
calculated by the following equation (CCPS 200 0)
IR x y frac14Xn
ifrac141
IR x yi (2)
In other words the risk of any identi1047297ed scenario will be indi-
vidually calculated at a speci1047297c location ( x y) and subsequently all
risks are summed to estimate the overall risk at that speci1047297c point
To calculate the individual risk at location ( x y) arising from
scenario i the following equation is applied (CCPS 200 0)
IR x yi frac14 f iP f i (3)
where f i is the frequency of the 1047297nal outcome of scenario i arising
from an incident (1yr) andP f iis the fatality probability of the 1047297nal
outcome of scenario i at the geographical location ( x y) Individualrisk contours represent the 1047297nal results of this step The individual
risk value in every position when compared to universally or
regionally accepted values is one of the criteria in risk-based
decision making for land use planning
Societal risk provides a risk evaluation for a group of people
located in the vicinity of the accident location In other words the
number of people affected by all 1047297nal outcomes is estimated
(Renjith amp Madhu 2010) Similar to the individual risk the societal
risk is a function of frequency of occurrence and rate of fatality
Another important and determinant factor for calculating the
societal risk is the population density around the incident location
Thesocietal riskis presented in form of FeN (FrequencyeNumber
of fatalities) curves where the cumulative frequency of 1047297nal
outcomes is plotted against the number of fatalities arising from anoutcome in a logarithmic scale To calculate the number of fatalities
of each 1047297nal outcome the following equation is used (CCPS 2000)
N i frac14X
x y
P x y p f i (4)
whereN irepresents the number of fatalities of the 1047297nal outcome of
scenario i P x yis the number of individuals at the geographical
location ( x y) and p f i is the probability that the 1047297nal outcome of
scenario i causes death at the geographical location ( x y)
The results obtained above are used in Equation (5) to calculate
the ultimate data required for plotting the FeN curve This equation
which is known as the cumulative frequency equation is expressed
as below (CCPS 2000)
F N frac14X
i
F i for all final outcome case I which N i gt N (5)
where F N is the cumulative frequency for all 1047297nal outcomes which
result in fatalities of more than N personsF i is the frequency of the
Fig 1 Layout of the study area (case-study) showing the two neighboring plants AKPC and BSPC
S Baesi et al Journal of Loss Prevention in the Process Industries 26 (2013) 895e903 897
8132019 1-s20-S0950423012001702-main
httpslidepdfcomreaderfull1-s20-s0950423012001702-main 49
1047297nal outcome of scenario i and N i is the number of fatalities for the
1047297nal outcome of scenario i Finally having the quantities of F N and
N the cumulative frequency of 1047297nal outcomes is plotted against the
number of fatalities The obtained FeN curved will be compared
against the intended criteria to evaluate the acceptability of the
potential societal risk
3 Case study
ldquoAKPCrdquo and ldquoBSPCrdquo are two neighboring complexes located in
the so-called PETZONE In this industrial region 15 petrochemical
plants are situated in 5 distinct sites within an area of approxi-mately 20 km2 and therefore it is known to be one of the biggest
energy zones in the world The PETZONE lies in the northern coast
of the Persian Gulf and expands to the southwestern city of Mah-
shahr in southern Iran
Before and during the construction of many plants in the PET-
ZONE until present only economic and operational factors have
been taken into account leaving safety aspects to be largely
neglected in the layout design of those plants This was also the
case for our case study of the two plants AKPC and BSPC The ole1047297n
unit of AKPC produces ethylene and propylene and these
substances are later used in the polymerization unit to produce
high density polyethylene low density polyethylene and poly-
propylene Regarding BSPC its main products are naphtha p-
xylene and acetic acid
These two plants present an interesting case study due to their
high number of storage tanks and huge inventory of chemicals As
one of these plants provides a portion of the other one rsquos feed
constructing them close together seemed a wise choice from an
economic and operational point of view However the compliance
of risk criteria had not been an item of consideration After occur-
rence of some minor process accidents with limited consequences
in these plants the risk of accident escalation from one plant to
another was highlighted more than ever Therefore the idea of
constructing AKPC and BSPC in proximity of each other which
seemed a defendable choice once has been challenged In the
present study the two adjacent chemical complexes AKPC and
BSPC are both subjected to one QRA (treating both plants as one
plant) allowing us to analyze the effects of the construction of a
petrochemical plant adjacent to an existing one on the overall riskThe purpose was to verify whether it was indeed a wise choice to
construct these two plants this close to each other (for production
purposes) or not (for safety reasons) Fig 1 represents the layout of
the two petrochemical plants
Based on a safety review and on a safety screening carried out
as a preliminary step the major hazard sources of the study area
(as displayed in Fig 1) appear to be the storage tanks of these two
plants Although there are obviously other sources of hazards
within this area their contribution in the overall risk could be
regarded negligible (compared with the present storage tanks)
AKPC houses 5 major operational storage tanks containing
ethylene and propylene while BSPC contains 10 major atmo-spheric storage tanks containing naphtha p-xylene and acetic
acid Tables 1 and 2 provide a list of the chemical substance
inventories in AKPC and BSPC Although there were some other
storage tanks or process equipment no one passed the screening
step for scenario selection due to their low inventory of hazardous
materials and due to the lesser inherent hazardousness of the
materials
The atmosphericdata used in this study were established by the
Iranian Meteorological Organization (IMO) for the Mahshahr port
from 1988 to 2006 (IRIMO 2006) The result of the meteorological
data analysis indicates that two prevailing weather conditions (hot
season and cold season) can be intended for the QRA study during
daytime and nighttime to cover almost all of the probable condi-
tions Table 3 summarizes the average meteorological data whichare used for the consequence analysis
31 Accident scenarios
As stated previously the storage tanks have been identi1047297ed to
lead to the most hazardous scenarios in the case under study
Table 1
List of AKPC storages in this study
TK-item Compound Type Temperature
(C)
Pressure
(barg)
Volume
(m3)
Inventory
(tonne)
TK-101 Propylene Spherical 40 25 2200 1044
TK-102 Propylene Spherical 40 25 2200 1044
TK-103 Propylene Spherical 40 25 2200 1044
TK-104 Propylene Spherical 40 25 2200 1044
TK-105 Ethylene Cylindrical
104 Atm 14000 7968
Table 2
List of BSPC storages in this study
TK-item Compound Type Temperature
(C)
Pressure
(barg)
Volume
(m3)
Inventory
(tonne)
TK-201 Naphtha Cy lindrical 30 001 331188 24839
TK-202 Naphtha Cy lindrical 30 001 331188 24839
TK-203 Naphtha Cy lindrical 30 001 331188 24839
TK-204 Naphtha Cylindrical 30 001 16272 12204
TK-205 Naphtha Cylindrical 30 Atm 16272 12204TK-206 P -Xylene Cy lindrical 30 At m 170856 14693
TK-207 P -Xylene Cy lindrical 30 At m 170856 14693
TK-208 P-Xylene Cylindrical 40 0003 1500 1267
TK-209 Acetic acid Cylindrical 45 0014 1500 1554
TK-210 Acetic acid Cylindrical 45 0014 1500 1554
Table 3
Prevailing weather conditions
Category Atmospheric stability Average wind
speed (ms)
Average ambient
temp (C)
Average relative
humidity ()
Hot season (daytime) Neutral (D class) 5 40 50
Hot season (nighttime) Stable (F class) 15 25 60
Cold season (daytime) Neutral (D class) 5 20 80
Cold season (nighttime) Stable (F class) 15 10 90
Table 4
Accident scenarios and the relevant failure frequencies
Scenario
no
TK -i tem n o C ontai nmen t Scena ri o typ e Frequency
(1yr)
1e4 TK-101102103104 Propylene Leakage 1 105
5e8 TK-101102103104 Propylene Rupture 5 107
9 TK-105 Ethylene Leakage 1 105
10e14 TK-201202203
204205
Naphtha Leakage 1 105
15e17 TK-206207208 P-Xylene Leakage 1 105
18e19 TK-209 210 Acetic acid Leakage 1 105
S Baesi et al Journal of Loss Prevention in the Process Industries 26 (2013) 895e903898
8132019 1-s20-S0950423012001702-main
httpslidepdfcomreaderfull1-s20-s0950423012001702-main 59
8132019 1-s20-S0950423012001702-main
httpslidepdfcomreaderfull1-s20-s0950423012001702-main 69
Fig 4 A B individual risk contours before (for AKPC) and after (for cluster composed of AKPC and BSPC) constructing the new plant
8132019 1-s20-S0950423012001702-main
httpslidepdfcomreaderfull1-s20-s0950423012001702-main 79
the leakage case and in the rupture case Moreover based on the
plant layout review and due to the low level of equipment
congestion in this particular area under study the probability of
a 1047298ash 1047297re is higher than that of a Vapor Cloud Explosion (VCE)
since higher congestion is known to increase the probability of
a VCE rather than that of a 1047298ash 1047297re
4 Result and discussion
In order to evaluate the risk-based effects of constructing BSPC
adjacent to AKPC calculations were made for both individual risk
and societal risk before and after the new plant came under oper-
ation adjacent to the existing one The quanti1047297ed risk can then be
Fig 5 A B societal risk (Fe
N curve) before (A) and after (B) constructing the new plant
S Baesi et al Journal of Loss Prevention in the Process Industries 26 (2013) 895e903 901
8132019 1-s20-S0950423012001702-main
httpslidepdfcomreaderfull1-s20-s0950423012001702-main 89
compared against the criteria to assess the acceptability of the risk
levels The likelihood of domino effects needs to be assessed as
well
41 Calculation of individual risk
Using the results of frequency estimation and a detailed
consequence assessment for all the possible scenarios the indi-
vidual risk contours were obtained and are shown on a satellite
view of the study area Key outputs of the consequence modeling
are presented in Table 5 to give more insight in the two selected
scenarios Fig 4A and B demonstrate the individual risk levels
before (A) and after (B) the second plant came operational The
numerical value of each risk contour represents the frequency at
which a particular individual is fatally harmed when standing
within the contour boundary
The results of individual risk calculations reveal that inside the
chemical cluster composed of both plants (AKPC and BSPC) as well
as within the single plant AKPC the individual risk values do not
exceed the tolerable magnitude of 105yr before and after the new
plant came under operation Fig 3A and B also demonstrate that for
public areas (such as the main roads around AKPC and BSPC) the
risk level does not exceed the magnitude of 106yr except fora short interval of 100 m at the southern main road of AKPC
Nevertheless this issue was already present even before the
construction of BSPC In general we can state that in terms of
individual risk constructing the new plant adjacent to the existing
one did not affect the acceptability of risk levels
42 Calculation of societal risk
Although the previous section indicates that individual risk
levels do not exceed the tolerable levels the impact of any potential
accident on operators and public should also be investigated
Fig 4A and B provide the societal risk calculation results before and
after the new plant came into operation respectively As it can be
seen in Fig 5A the societal risk posed by AKPC individually falls inthe ALARP (As Low As Reasonably Practicable) region as de1047297ned by
HSE (UK)Fig 5Bshows that after constructing the new plant the
societal risk curve gets closer to the maximum risk criteria but still
remains in the ALARP region Therefore constructing the new plant
BSPC adjacent to the existing one AKPC seems to have only limited
impact upon the change of tolerability of the societal risk in our
case study
43 Domino effects assessment
The distance from the storage tanks located in AKPC to the
closest operational storage tank in BSPC is about 800 m Based on
the values reported by Cozzani Gubinelli and Salzano (2006) this
distance suggests that potential cascading accidents between theneighboring plants caused by thermal radiation are highly
improbable Therefore the only factor that can trigger a secondary
accident in the other neighboring plant is the overpressure caused
by an uncon1047297ned Vapor Cloud Explosion Considering the volatility
of the materials involved the operational conditions of storage the
average ambient temperature and the prevailing wind direction
(west) we may conclude that only materials stored in AKPCrsquos
storages are capable of forming an effective vapor cloud
There are different values reported for damage threshold due to
overpressure in literature but the overpressure of 1bar would
surely destroy any target equipment (Salzano amp Cozzani 2005)
This threshold has been chosen to evaluate the possibility of
domino accidents on the storage tanks in BSPC Table 6 provides
the magnitude of overpressure caused by different AKPC scenarios
(1e9) at the location of BSPCrsquos storage tanks These values are
based on performing a detailed consequence modeling
As it can be seen in Table 6 the closest storage tanks to AKPC
(TK-201 and TK-202) are possibly damaged due to overpressurecaused by a propylene explosion after a leakage or tank rupture
eventually triggering secondary accidents In other words the
accidental release of propylene in AKPC either continuous
(scenarios 1e4) or instantaneous (scenarios 5e8) has the capa-
bility of causing cascading accidents in BSPC This suggests that if
decision-makers insist on not changing the new plantrsquos layout (eg
due to large economic and operational bene1047297ts) countermeasures
should be taken into consideration in order to minimize the
heightened risk of domino accidents
Both choices for the Purple Book and the UK risk tolerance
criteria are individual choices for this study and they should be
seen and respected as such We are aware that failure frequencies
are subject to constant optimization and that the Purple Book has
its limitations (Pasman 2011) Nonetheless for this study of twoplants situated in Iran using the frequencies reported in this well-
known and much-used work was a justi1047297able choice
5 Conclusions
The risk-based effects of constructing a new chemical plant
adjacent to an existing one forming a chemical cluster is analyzed
and discussed in this paper For this purpose a QRA was carried out
to assess different parameters of risk Individual and societal risks
were evaluated before and after the new plant came under oper-
ation The results indicate that the new plant did not have a major
impact on the risk levels since the risk levels stay within the
tolerability limits Although no major impact was observed there
was a signi1047297cant increase in the societal risk Moreover a dominoeffect analysis indicates that some storage tanks in the new plant
entail a high potential of being affected by events originating in the
existing plant
This research and this case study illustrate that in order to make
an objective plant lay out decision for a chemical cluster with
regard to operational risks not only conventional risk assessments
should be carried out but a domino effects analysis should be
performed as well since otherwise some risks may be under-
estimated and overlooked
It is undoubtedly true that themore accurateinformationis used
(eg concerning probabilities) the more accurate risk calculations
can be made However one should always remember that basically
calculated risks arerelativerisks andthat absolute valuesare prone
to variability and uncertainty As referencedby Pasman et al(2009)
Table 6
Target equipment affected by domino accident (due to overpressure)
scenario
Magnitude of overpressure caused by different AKPC scenarios at
target equipment (bar)
T K - 2 0 1
T K - 2 0 2
T K - 2 0 3
T K - 2 0 4
T K - 2 0 5
T K - 2 0 6
T K - 2 0 7
T K - 2 0 8
T K - 2 0 9
T K - 2 1 0
1-4 02 01 01 008 008 017 015 015
5-8 1 04 02 02 014 014 025 023 022
9 005 005 005 005 005 005 005 005 005 005
Affected by Dominoaccident
Not Affected by Dominoaccident
1 1
1
S Baesi et al Journal of Loss Prevention in the Process Industries 26 (2013) 895e903902
8132019 1-s20-S0950423012001702-main
httpslidepdfcomreaderfull1-s20-s0950423012001702-main 99
EU-studies have shown that a factor of 10e100 both ways in risk
results is not uncommon Hence future research might include risk
distributions and con1047297dence limits allowing risk analysts to even
better understand the uncertainties accompanying the results
References
Abbasi S A Krishnakumari P amp Khan F I (1998) Hot topics Global warming acidrain ozone hole hazardous waste industrial disasters disinfection New DelhiOxford University Press
Abdolhamidzadeh B Abbasi T Rashtchian D amp Abbasi S A (2010) A newmethod for assessing domino effect in chemical process industry Journal of Hazardous Materials 182(1e3) 416e426
Abdolhamidzadeh B Abbasi T Rashtchian D amp Abbasi S A (2011) Dominoeffect in process-industry accidents e an inventory of past events and identi-1047297cation of some patterns Journal of Loss Prevention in the Process Industries
24(5) 575e593Arunraj N S amp Maiti J (2009) A methodology for overall consequence modeling
in chemical industry Journal of Hazardous Materials 169 556e574Atherton J amp Gil F (2008) Incidents that de 1047297ne process safety Hoboken New
Jersey USA WileyBeerens H I Post J G amp Uijt de Haag P A M (2006) The use of generic failure
frequencies in QRA the quality and use of failure frequencies and how to bringthem up-to-date Journal of Hazardous Materials 130 265e270
Bubbico R Maschio G Mazzarotta B Milazzo M amp Parisi E (2006) Riskmanagement of road and rail transport of hazardous materials in Sicily Journalof Loss Prevention in the Process Industries 19(1) 32e38
Center for Chemical Process Safety (CCPS) (2000) Guidelines for chemical processquantitative risk analysis (2nd ed) New York American Institute of ChemicalEngineering
CozzaniV GubinelliG amp SalzanoE (2006)Escalationthresholds inthe assessmentof domino accidental events Journal of Hazardous Materials 129(1e3)1e21
CPR 18E (1999) lsquo Purple bookrsquo guidelines for quantitative risk assessment Part oneEstablishments The Hague RVIM
Dechy N Bourdeaux T Ayrault N Kordek M A amp Le Coze J C (2004) Firstlessons of the Toulouse ammonium nitrate disaster 21st September 2001 AZFplant France Journal of Hazardous Materials 111(1e3) 131e138
Gharabagh M J Asilian H Mortasavi S B Mogaddam A Z Hajizadeh E ampKhavanin A (2009) Comprehensive risk assessment and management of petrochemical feed and product transportation pipelines Journal of LossPrevention in the Process Industries 22(4) 533e539
Gooijer L Cornil N amp Lenoble C L (2012) An international comparison of fourquantitative risk assessment approaches e a benchmark study based on a 1047297cti-tious LPG plant Process Safety and Environmental Protection 90(2) 101e107
IRIMO (2006) Climatologically normal for the period 1987 e
2006 Mahshahr TehranIR of Iran Meteorological Organization Data Processing Center
Jo Y amp Crowl D (2008) Individual risk analysis of high-pressure natural gaspipelines Journal of Loss Prevention in the Process Industries 21 (6) 589e595
Kalantarnia M Khan F amp Hawboldt K (2010) Modelling of BP Texas City re1047297neryaccident using dynamic risk assessment approach Process Safety and Environ-mental Protection 88(3) 191e199 (Institution of Chemical Engineers)
Khan F I amp Abbasi S A (1998) Techniques and methodologies for risk analysis inchemical process industries Journal of Loss Prevention in the Process Industries11 261e277
Khan F I amp Abbasi S A (1999a) Major accidents in process industries and ananalysis of causes and consequences Journal of Loss Prevention in the ProcessIndustries 12 361e378
Khan F I amp Abbasi S A (1999b) Assessment of risks posed by chemical indus-triesdapplication of a new computer automated tool MAXCRED-III Journal of Loss Prevention in the Process Industries 12(6) 455e469
Khan F I Sadiq R amp Husain T (2002) Risk-based process safety assessment andcontrol measures design for offshore process facilities Journal of HazardousMaterials 94(1) 1e36
Kletz T A (1999b) The origins and history of loss prevention Transaction IChemE77 109e116
Kletz T A (1999a) What went wrong Case histories of process plant disasters andhow they could have been avoided Houston USA Gulf Professional Publishing
Kletz T A (2003) Still going wrong Case histories of process plant disasters and howthey could have been avoided Houston USA Gulf Professional Publishing
Lees F P (1996) Loss prevention in the process industries (2nd ed) Oxford LondonButterworth Heinemann
Markowski A S (2007) exLOPA for explosion risks assessment Journal of Hazardous Materials 142(3) 669e676
Milazzo M F Lisi R Maschio G Antonioni G Bonvicini S amp Spadoni G (2002)HazMat transport through Messina town from risk analysis suggestions forimproving territorial safety Journal of Loss Prevention in the Process Industries15(5) 347e356
Papazoglou I A Nivolianitou Z Aneziris O Christou M D amp Bonanos G (1999)Risk-informed selection of a highway trajectory in the neighborhood of an oil-re1047297nery Journal of Hazardous Materials 67 (2) 111e144
Pasman H J (2011) History of Dutch process equipment failure frequencies and thepurple book Journal of Loss Prevention in the Process Industries 24 208e213
Pasman H J Jung S Prem K Rogers W J amp Yang X (2009) Is risk analysisa useful tool for improving process safety Journal of Loss Prevention in theProcess Industries 22(6) 769e777
Pintaric Z (2007) Assessment of the consequences of accident scenariosinvolving dangerous substances Process Safety and Environmental Protection85(1) 23e38
Pula R Khan F I Veitch B amp Amyotte P (2006) A grid based approach for 1047297reand explosion consequence analysis Process Safety and Environmental Protec-tion 84(2) 79e91
Reniers G L L (2010) An external domino effects investment approach to improvecross-plant safety within chemical clusters Journal of Hazardous Materials 177 167e174
Reniers G L L amp Dullaert W (2007) DomPrevPlanning user-friendly software forplanning domino effects prevention Safety Science 45(10) 1060e1081
Renjith V R amp Madhu G (2010) Individual and societal risk analysis and mappingof human vulnerability to chemical accidents in the vicinity of an industrialarea International Journal of Applied Engineering Research Dindigul 1 135e148
Rigas F amp Sklavounos S (2002) Risk and consequence analyses of hazardouschemicals in marshalling yards and warehouses at IkonioPiraeus harbourGreece Journal of Loss Prevention in the Process Industries 15(6) 531e544
Salzano Eamp Cozzani V (2005)The analysis of dominoaccidents triggered byvaporcloud explosions Reliability Engineering amp System Safety 90(2e3) 271e284
Spadoni G Egidi D amp Contini S (2000) Through ARIPAR-GIS the quanti 1047297ed arearisk analysis supports land-use planning activities Journal of Hazardous Mate-rials 71(1e3) 423e437
Van Sciver G R (1990) Quantitative risk analysis in the chemical process indus-tries Reliability Engineering amp System Safety 29 55e68
Viacutelchez J A Espejo V amp Casal J (2011) Generic event trees and probabilities forthe release of different types of hazardous materials Journal of Loss Preventionin the Process Industries 24(3) 281e287
Wells G (1997) Major hazards and their management Rugby UK Institution of Chemical Engineers
Yet-Pole IChi-MinS amp Ching-Hong C (2009)Applicationsof 3D QRAtechnique tothe 1047297reexplosion simulation and hazard mitigation within a naphtha-crackingplant Journal of Loss Prevention in the Process Industries 22 (4) 506e515
S Baesi et al Journal of Loss Prevention in the Process Industries 26 (2013) 895e903 903
![Page 4: 1-s2.0-S0950423012001702-main](https://reader038.vdocuments.us/reader038/viewer/2022100505/577cd1271a28ab9e7893bef5/html5/thumbnails/4.jpg)
8132019 1-s20-S0950423012001702-main
httpslidepdfcomreaderfull1-s20-s0950423012001702-main 49
1047297nal outcome of scenario i and N i is the number of fatalities for the
1047297nal outcome of scenario i Finally having the quantities of F N and
N the cumulative frequency of 1047297nal outcomes is plotted against the
number of fatalities The obtained FeN curved will be compared
against the intended criteria to evaluate the acceptability of the
potential societal risk
3 Case study
ldquoAKPCrdquo and ldquoBSPCrdquo are two neighboring complexes located in
the so-called PETZONE In this industrial region 15 petrochemical
plants are situated in 5 distinct sites within an area of approxi-mately 20 km2 and therefore it is known to be one of the biggest
energy zones in the world The PETZONE lies in the northern coast
of the Persian Gulf and expands to the southwestern city of Mah-
shahr in southern Iran
Before and during the construction of many plants in the PET-
ZONE until present only economic and operational factors have
been taken into account leaving safety aspects to be largely
neglected in the layout design of those plants This was also the
case for our case study of the two plants AKPC and BSPC The ole1047297n
unit of AKPC produces ethylene and propylene and these
substances are later used in the polymerization unit to produce
high density polyethylene low density polyethylene and poly-
propylene Regarding BSPC its main products are naphtha p-
xylene and acetic acid
These two plants present an interesting case study due to their
high number of storage tanks and huge inventory of chemicals As
one of these plants provides a portion of the other one rsquos feed
constructing them close together seemed a wise choice from an
economic and operational point of view However the compliance
of risk criteria had not been an item of consideration After occur-
rence of some minor process accidents with limited consequences
in these plants the risk of accident escalation from one plant to
another was highlighted more than ever Therefore the idea of
constructing AKPC and BSPC in proximity of each other which
seemed a defendable choice once has been challenged In the
present study the two adjacent chemical complexes AKPC and
BSPC are both subjected to one QRA (treating both plants as one
plant) allowing us to analyze the effects of the construction of a
petrochemical plant adjacent to an existing one on the overall riskThe purpose was to verify whether it was indeed a wise choice to
construct these two plants this close to each other (for production
purposes) or not (for safety reasons) Fig 1 represents the layout of
the two petrochemical plants
Based on a safety review and on a safety screening carried out
as a preliminary step the major hazard sources of the study area
(as displayed in Fig 1) appear to be the storage tanks of these two
plants Although there are obviously other sources of hazards
within this area their contribution in the overall risk could be
regarded negligible (compared with the present storage tanks)
AKPC houses 5 major operational storage tanks containing
ethylene and propylene while BSPC contains 10 major atmo-spheric storage tanks containing naphtha p-xylene and acetic
acid Tables 1 and 2 provide a list of the chemical substance
inventories in AKPC and BSPC Although there were some other
storage tanks or process equipment no one passed the screening
step for scenario selection due to their low inventory of hazardous
materials and due to the lesser inherent hazardousness of the
materials
The atmosphericdata used in this study were established by the
Iranian Meteorological Organization (IMO) for the Mahshahr port
from 1988 to 2006 (IRIMO 2006) The result of the meteorological
data analysis indicates that two prevailing weather conditions (hot
season and cold season) can be intended for the QRA study during
daytime and nighttime to cover almost all of the probable condi-
tions Table 3 summarizes the average meteorological data whichare used for the consequence analysis
31 Accident scenarios
As stated previously the storage tanks have been identi1047297ed to
lead to the most hazardous scenarios in the case under study
Table 1
List of AKPC storages in this study
TK-item Compound Type Temperature
(C)
Pressure
(barg)
Volume
(m3)
Inventory
(tonne)
TK-101 Propylene Spherical 40 25 2200 1044
TK-102 Propylene Spherical 40 25 2200 1044
TK-103 Propylene Spherical 40 25 2200 1044
TK-104 Propylene Spherical 40 25 2200 1044
TK-105 Ethylene Cylindrical
104 Atm 14000 7968
Table 2
List of BSPC storages in this study
TK-item Compound Type Temperature
(C)
Pressure
(barg)
Volume
(m3)
Inventory
(tonne)
TK-201 Naphtha Cy lindrical 30 001 331188 24839
TK-202 Naphtha Cy lindrical 30 001 331188 24839
TK-203 Naphtha Cy lindrical 30 001 331188 24839
TK-204 Naphtha Cylindrical 30 001 16272 12204
TK-205 Naphtha Cylindrical 30 Atm 16272 12204TK-206 P -Xylene Cy lindrical 30 At m 170856 14693
TK-207 P -Xylene Cy lindrical 30 At m 170856 14693
TK-208 P-Xylene Cylindrical 40 0003 1500 1267
TK-209 Acetic acid Cylindrical 45 0014 1500 1554
TK-210 Acetic acid Cylindrical 45 0014 1500 1554
Table 3
Prevailing weather conditions
Category Atmospheric stability Average wind
speed (ms)
Average ambient
temp (C)
Average relative
humidity ()
Hot season (daytime) Neutral (D class) 5 40 50
Hot season (nighttime) Stable (F class) 15 25 60
Cold season (daytime) Neutral (D class) 5 20 80
Cold season (nighttime) Stable (F class) 15 10 90
Table 4
Accident scenarios and the relevant failure frequencies
Scenario
no
TK -i tem n o C ontai nmen t Scena ri o typ e Frequency
(1yr)
1e4 TK-101102103104 Propylene Leakage 1 105
5e8 TK-101102103104 Propylene Rupture 5 107
9 TK-105 Ethylene Leakage 1 105
10e14 TK-201202203
204205
Naphtha Leakage 1 105
15e17 TK-206207208 P-Xylene Leakage 1 105
18e19 TK-209 210 Acetic acid Leakage 1 105
S Baesi et al Journal of Loss Prevention in the Process Industries 26 (2013) 895e903898
8132019 1-s20-S0950423012001702-main
httpslidepdfcomreaderfull1-s20-s0950423012001702-main 59
8132019 1-s20-S0950423012001702-main
httpslidepdfcomreaderfull1-s20-s0950423012001702-main 69
Fig 4 A B individual risk contours before (for AKPC) and after (for cluster composed of AKPC and BSPC) constructing the new plant
8132019 1-s20-S0950423012001702-main
httpslidepdfcomreaderfull1-s20-s0950423012001702-main 79
the leakage case and in the rupture case Moreover based on the
plant layout review and due to the low level of equipment
congestion in this particular area under study the probability of
a 1047298ash 1047297re is higher than that of a Vapor Cloud Explosion (VCE)
since higher congestion is known to increase the probability of
a VCE rather than that of a 1047298ash 1047297re
4 Result and discussion
In order to evaluate the risk-based effects of constructing BSPC
adjacent to AKPC calculations were made for both individual risk
and societal risk before and after the new plant came under oper-
ation adjacent to the existing one The quanti1047297ed risk can then be
Fig 5 A B societal risk (Fe
N curve) before (A) and after (B) constructing the new plant
S Baesi et al Journal of Loss Prevention in the Process Industries 26 (2013) 895e903 901
8132019 1-s20-S0950423012001702-main
httpslidepdfcomreaderfull1-s20-s0950423012001702-main 89
compared against the criteria to assess the acceptability of the risk
levels The likelihood of domino effects needs to be assessed as
well
41 Calculation of individual risk
Using the results of frequency estimation and a detailed
consequence assessment for all the possible scenarios the indi-
vidual risk contours were obtained and are shown on a satellite
view of the study area Key outputs of the consequence modeling
are presented in Table 5 to give more insight in the two selected
scenarios Fig 4A and B demonstrate the individual risk levels
before (A) and after (B) the second plant came operational The
numerical value of each risk contour represents the frequency at
which a particular individual is fatally harmed when standing
within the contour boundary
The results of individual risk calculations reveal that inside the
chemical cluster composed of both plants (AKPC and BSPC) as well
as within the single plant AKPC the individual risk values do not
exceed the tolerable magnitude of 105yr before and after the new
plant came under operation Fig 3A and B also demonstrate that for
public areas (such as the main roads around AKPC and BSPC) the
risk level does not exceed the magnitude of 106yr except fora short interval of 100 m at the southern main road of AKPC
Nevertheless this issue was already present even before the
construction of BSPC In general we can state that in terms of
individual risk constructing the new plant adjacent to the existing
one did not affect the acceptability of risk levels
42 Calculation of societal risk
Although the previous section indicates that individual risk
levels do not exceed the tolerable levels the impact of any potential
accident on operators and public should also be investigated
Fig 4A and B provide the societal risk calculation results before and
after the new plant came into operation respectively As it can be
seen in Fig 5A the societal risk posed by AKPC individually falls inthe ALARP (As Low As Reasonably Practicable) region as de1047297ned by
HSE (UK)Fig 5Bshows that after constructing the new plant the
societal risk curve gets closer to the maximum risk criteria but still
remains in the ALARP region Therefore constructing the new plant
BSPC adjacent to the existing one AKPC seems to have only limited
impact upon the change of tolerability of the societal risk in our
case study
43 Domino effects assessment
The distance from the storage tanks located in AKPC to the
closest operational storage tank in BSPC is about 800 m Based on
the values reported by Cozzani Gubinelli and Salzano (2006) this
distance suggests that potential cascading accidents between theneighboring plants caused by thermal radiation are highly
improbable Therefore the only factor that can trigger a secondary
accident in the other neighboring plant is the overpressure caused
by an uncon1047297ned Vapor Cloud Explosion Considering the volatility
of the materials involved the operational conditions of storage the
average ambient temperature and the prevailing wind direction
(west) we may conclude that only materials stored in AKPCrsquos
storages are capable of forming an effective vapor cloud
There are different values reported for damage threshold due to
overpressure in literature but the overpressure of 1bar would
surely destroy any target equipment (Salzano amp Cozzani 2005)
This threshold has been chosen to evaluate the possibility of
domino accidents on the storage tanks in BSPC Table 6 provides
the magnitude of overpressure caused by different AKPC scenarios
(1e9) at the location of BSPCrsquos storage tanks These values are
based on performing a detailed consequence modeling
As it can be seen in Table 6 the closest storage tanks to AKPC
(TK-201 and TK-202) are possibly damaged due to overpressurecaused by a propylene explosion after a leakage or tank rupture
eventually triggering secondary accidents In other words the
accidental release of propylene in AKPC either continuous
(scenarios 1e4) or instantaneous (scenarios 5e8) has the capa-
bility of causing cascading accidents in BSPC This suggests that if
decision-makers insist on not changing the new plantrsquos layout (eg
due to large economic and operational bene1047297ts) countermeasures
should be taken into consideration in order to minimize the
heightened risk of domino accidents
Both choices for the Purple Book and the UK risk tolerance
criteria are individual choices for this study and they should be
seen and respected as such We are aware that failure frequencies
are subject to constant optimization and that the Purple Book has
its limitations (Pasman 2011) Nonetheless for this study of twoplants situated in Iran using the frequencies reported in this well-
known and much-used work was a justi1047297able choice
5 Conclusions
The risk-based effects of constructing a new chemical plant
adjacent to an existing one forming a chemical cluster is analyzed
and discussed in this paper For this purpose a QRA was carried out
to assess different parameters of risk Individual and societal risks
were evaluated before and after the new plant came under oper-
ation The results indicate that the new plant did not have a major
impact on the risk levels since the risk levels stay within the
tolerability limits Although no major impact was observed there
was a signi1047297cant increase in the societal risk Moreover a dominoeffect analysis indicates that some storage tanks in the new plant
entail a high potential of being affected by events originating in the
existing plant
This research and this case study illustrate that in order to make
an objective plant lay out decision for a chemical cluster with
regard to operational risks not only conventional risk assessments
should be carried out but a domino effects analysis should be
performed as well since otherwise some risks may be under-
estimated and overlooked
It is undoubtedly true that themore accurateinformationis used
(eg concerning probabilities) the more accurate risk calculations
can be made However one should always remember that basically
calculated risks arerelativerisks andthat absolute valuesare prone
to variability and uncertainty As referencedby Pasman et al(2009)
Table 6
Target equipment affected by domino accident (due to overpressure)
scenario
Magnitude of overpressure caused by different AKPC scenarios at
target equipment (bar)
T K - 2 0 1
T K - 2 0 2
T K - 2 0 3
T K - 2 0 4
T K - 2 0 5
T K - 2 0 6
T K - 2 0 7
T K - 2 0 8
T K - 2 0 9
T K - 2 1 0
1-4 02 01 01 008 008 017 015 015
5-8 1 04 02 02 014 014 025 023 022
9 005 005 005 005 005 005 005 005 005 005
Affected by Dominoaccident
Not Affected by Dominoaccident
1 1
1
S Baesi et al Journal of Loss Prevention in the Process Industries 26 (2013) 895e903902
8132019 1-s20-S0950423012001702-main
httpslidepdfcomreaderfull1-s20-s0950423012001702-main 99
EU-studies have shown that a factor of 10e100 both ways in risk
results is not uncommon Hence future research might include risk
distributions and con1047297dence limits allowing risk analysts to even
better understand the uncertainties accompanying the results
References
Abbasi S A Krishnakumari P amp Khan F I (1998) Hot topics Global warming acidrain ozone hole hazardous waste industrial disasters disinfection New DelhiOxford University Press
Abdolhamidzadeh B Abbasi T Rashtchian D amp Abbasi S A (2010) A newmethod for assessing domino effect in chemical process industry Journal of Hazardous Materials 182(1e3) 416e426
Abdolhamidzadeh B Abbasi T Rashtchian D amp Abbasi S A (2011) Dominoeffect in process-industry accidents e an inventory of past events and identi-1047297cation of some patterns Journal of Loss Prevention in the Process Industries
24(5) 575e593Arunraj N S amp Maiti J (2009) A methodology for overall consequence modeling
in chemical industry Journal of Hazardous Materials 169 556e574Atherton J amp Gil F (2008) Incidents that de 1047297ne process safety Hoboken New
Jersey USA WileyBeerens H I Post J G amp Uijt de Haag P A M (2006) The use of generic failure
frequencies in QRA the quality and use of failure frequencies and how to bringthem up-to-date Journal of Hazardous Materials 130 265e270
Bubbico R Maschio G Mazzarotta B Milazzo M amp Parisi E (2006) Riskmanagement of road and rail transport of hazardous materials in Sicily Journalof Loss Prevention in the Process Industries 19(1) 32e38
Center for Chemical Process Safety (CCPS) (2000) Guidelines for chemical processquantitative risk analysis (2nd ed) New York American Institute of ChemicalEngineering
CozzaniV GubinelliG amp SalzanoE (2006)Escalationthresholds inthe assessmentof domino accidental events Journal of Hazardous Materials 129(1e3)1e21
CPR 18E (1999) lsquo Purple bookrsquo guidelines for quantitative risk assessment Part oneEstablishments The Hague RVIM
Dechy N Bourdeaux T Ayrault N Kordek M A amp Le Coze J C (2004) Firstlessons of the Toulouse ammonium nitrate disaster 21st September 2001 AZFplant France Journal of Hazardous Materials 111(1e3) 131e138
Gharabagh M J Asilian H Mortasavi S B Mogaddam A Z Hajizadeh E ampKhavanin A (2009) Comprehensive risk assessment and management of petrochemical feed and product transportation pipelines Journal of LossPrevention in the Process Industries 22(4) 533e539
Gooijer L Cornil N amp Lenoble C L (2012) An international comparison of fourquantitative risk assessment approaches e a benchmark study based on a 1047297cti-tious LPG plant Process Safety and Environmental Protection 90(2) 101e107
IRIMO (2006) Climatologically normal for the period 1987 e
2006 Mahshahr TehranIR of Iran Meteorological Organization Data Processing Center
Jo Y amp Crowl D (2008) Individual risk analysis of high-pressure natural gaspipelines Journal of Loss Prevention in the Process Industries 21 (6) 589e595
Kalantarnia M Khan F amp Hawboldt K (2010) Modelling of BP Texas City re1047297neryaccident using dynamic risk assessment approach Process Safety and Environ-mental Protection 88(3) 191e199 (Institution of Chemical Engineers)
Khan F I amp Abbasi S A (1998) Techniques and methodologies for risk analysis inchemical process industries Journal of Loss Prevention in the Process Industries11 261e277
Khan F I amp Abbasi S A (1999a) Major accidents in process industries and ananalysis of causes and consequences Journal of Loss Prevention in the ProcessIndustries 12 361e378
Khan F I amp Abbasi S A (1999b) Assessment of risks posed by chemical indus-triesdapplication of a new computer automated tool MAXCRED-III Journal of Loss Prevention in the Process Industries 12(6) 455e469
Khan F I Sadiq R amp Husain T (2002) Risk-based process safety assessment andcontrol measures design for offshore process facilities Journal of HazardousMaterials 94(1) 1e36
Kletz T A (1999b) The origins and history of loss prevention Transaction IChemE77 109e116
Kletz T A (1999a) What went wrong Case histories of process plant disasters andhow they could have been avoided Houston USA Gulf Professional Publishing
Kletz T A (2003) Still going wrong Case histories of process plant disasters and howthey could have been avoided Houston USA Gulf Professional Publishing
Lees F P (1996) Loss prevention in the process industries (2nd ed) Oxford LondonButterworth Heinemann
Markowski A S (2007) exLOPA for explosion risks assessment Journal of Hazardous Materials 142(3) 669e676
Milazzo M F Lisi R Maschio G Antonioni G Bonvicini S amp Spadoni G (2002)HazMat transport through Messina town from risk analysis suggestions forimproving territorial safety Journal of Loss Prevention in the Process Industries15(5) 347e356
Papazoglou I A Nivolianitou Z Aneziris O Christou M D amp Bonanos G (1999)Risk-informed selection of a highway trajectory in the neighborhood of an oil-re1047297nery Journal of Hazardous Materials 67 (2) 111e144
Pasman H J (2011) History of Dutch process equipment failure frequencies and thepurple book Journal of Loss Prevention in the Process Industries 24 208e213
Pasman H J Jung S Prem K Rogers W J amp Yang X (2009) Is risk analysisa useful tool for improving process safety Journal of Loss Prevention in theProcess Industries 22(6) 769e777
Pintaric Z (2007) Assessment of the consequences of accident scenariosinvolving dangerous substances Process Safety and Environmental Protection85(1) 23e38
Pula R Khan F I Veitch B amp Amyotte P (2006) A grid based approach for 1047297reand explosion consequence analysis Process Safety and Environmental Protec-tion 84(2) 79e91
Reniers G L L (2010) An external domino effects investment approach to improvecross-plant safety within chemical clusters Journal of Hazardous Materials 177 167e174
Reniers G L L amp Dullaert W (2007) DomPrevPlanning user-friendly software forplanning domino effects prevention Safety Science 45(10) 1060e1081
Renjith V R amp Madhu G (2010) Individual and societal risk analysis and mappingof human vulnerability to chemical accidents in the vicinity of an industrialarea International Journal of Applied Engineering Research Dindigul 1 135e148
Rigas F amp Sklavounos S (2002) Risk and consequence analyses of hazardouschemicals in marshalling yards and warehouses at IkonioPiraeus harbourGreece Journal of Loss Prevention in the Process Industries 15(6) 531e544
Salzano Eamp Cozzani V (2005)The analysis of dominoaccidents triggered byvaporcloud explosions Reliability Engineering amp System Safety 90(2e3) 271e284
Spadoni G Egidi D amp Contini S (2000) Through ARIPAR-GIS the quanti 1047297ed arearisk analysis supports land-use planning activities Journal of Hazardous Mate-rials 71(1e3) 423e437
Van Sciver G R (1990) Quantitative risk analysis in the chemical process indus-tries Reliability Engineering amp System Safety 29 55e68
Viacutelchez J A Espejo V amp Casal J (2011) Generic event trees and probabilities forthe release of different types of hazardous materials Journal of Loss Preventionin the Process Industries 24(3) 281e287
Wells G (1997) Major hazards and their management Rugby UK Institution of Chemical Engineers
Yet-Pole IChi-MinS amp Ching-Hong C (2009)Applicationsof 3D QRAtechnique tothe 1047297reexplosion simulation and hazard mitigation within a naphtha-crackingplant Journal of Loss Prevention in the Process Industries 22 (4) 506e515
S Baesi et al Journal of Loss Prevention in the Process Industries 26 (2013) 895e903 903
![Page 5: 1-s2.0-S0950423012001702-main](https://reader038.vdocuments.us/reader038/viewer/2022100505/577cd1271a28ab9e7893bef5/html5/thumbnails/5.jpg)
8132019 1-s20-S0950423012001702-main
httpslidepdfcomreaderfull1-s20-s0950423012001702-main 59
8132019 1-s20-S0950423012001702-main
httpslidepdfcomreaderfull1-s20-s0950423012001702-main 69
Fig 4 A B individual risk contours before (for AKPC) and after (for cluster composed of AKPC and BSPC) constructing the new plant
8132019 1-s20-S0950423012001702-main
httpslidepdfcomreaderfull1-s20-s0950423012001702-main 79
the leakage case and in the rupture case Moreover based on the
plant layout review and due to the low level of equipment
congestion in this particular area under study the probability of
a 1047298ash 1047297re is higher than that of a Vapor Cloud Explosion (VCE)
since higher congestion is known to increase the probability of
a VCE rather than that of a 1047298ash 1047297re
4 Result and discussion
In order to evaluate the risk-based effects of constructing BSPC
adjacent to AKPC calculations were made for both individual risk
and societal risk before and after the new plant came under oper-
ation adjacent to the existing one The quanti1047297ed risk can then be
Fig 5 A B societal risk (Fe
N curve) before (A) and after (B) constructing the new plant
S Baesi et al Journal of Loss Prevention in the Process Industries 26 (2013) 895e903 901
8132019 1-s20-S0950423012001702-main
httpslidepdfcomreaderfull1-s20-s0950423012001702-main 89
compared against the criteria to assess the acceptability of the risk
levels The likelihood of domino effects needs to be assessed as
well
41 Calculation of individual risk
Using the results of frequency estimation and a detailed
consequence assessment for all the possible scenarios the indi-
vidual risk contours were obtained and are shown on a satellite
view of the study area Key outputs of the consequence modeling
are presented in Table 5 to give more insight in the two selected
scenarios Fig 4A and B demonstrate the individual risk levels
before (A) and after (B) the second plant came operational The
numerical value of each risk contour represents the frequency at
which a particular individual is fatally harmed when standing
within the contour boundary
The results of individual risk calculations reveal that inside the
chemical cluster composed of both plants (AKPC and BSPC) as well
as within the single plant AKPC the individual risk values do not
exceed the tolerable magnitude of 105yr before and after the new
plant came under operation Fig 3A and B also demonstrate that for
public areas (such as the main roads around AKPC and BSPC) the
risk level does not exceed the magnitude of 106yr except fora short interval of 100 m at the southern main road of AKPC
Nevertheless this issue was already present even before the
construction of BSPC In general we can state that in terms of
individual risk constructing the new plant adjacent to the existing
one did not affect the acceptability of risk levels
42 Calculation of societal risk
Although the previous section indicates that individual risk
levels do not exceed the tolerable levels the impact of any potential
accident on operators and public should also be investigated
Fig 4A and B provide the societal risk calculation results before and
after the new plant came into operation respectively As it can be
seen in Fig 5A the societal risk posed by AKPC individually falls inthe ALARP (As Low As Reasonably Practicable) region as de1047297ned by
HSE (UK)Fig 5Bshows that after constructing the new plant the
societal risk curve gets closer to the maximum risk criteria but still
remains in the ALARP region Therefore constructing the new plant
BSPC adjacent to the existing one AKPC seems to have only limited
impact upon the change of tolerability of the societal risk in our
case study
43 Domino effects assessment
The distance from the storage tanks located in AKPC to the
closest operational storage tank in BSPC is about 800 m Based on
the values reported by Cozzani Gubinelli and Salzano (2006) this
distance suggests that potential cascading accidents between theneighboring plants caused by thermal radiation are highly
improbable Therefore the only factor that can trigger a secondary
accident in the other neighboring plant is the overpressure caused
by an uncon1047297ned Vapor Cloud Explosion Considering the volatility
of the materials involved the operational conditions of storage the
average ambient temperature and the prevailing wind direction
(west) we may conclude that only materials stored in AKPCrsquos
storages are capable of forming an effective vapor cloud
There are different values reported for damage threshold due to
overpressure in literature but the overpressure of 1bar would
surely destroy any target equipment (Salzano amp Cozzani 2005)
This threshold has been chosen to evaluate the possibility of
domino accidents on the storage tanks in BSPC Table 6 provides
the magnitude of overpressure caused by different AKPC scenarios
(1e9) at the location of BSPCrsquos storage tanks These values are
based on performing a detailed consequence modeling
As it can be seen in Table 6 the closest storage tanks to AKPC
(TK-201 and TK-202) are possibly damaged due to overpressurecaused by a propylene explosion after a leakage or tank rupture
eventually triggering secondary accidents In other words the
accidental release of propylene in AKPC either continuous
(scenarios 1e4) or instantaneous (scenarios 5e8) has the capa-
bility of causing cascading accidents in BSPC This suggests that if
decision-makers insist on not changing the new plantrsquos layout (eg
due to large economic and operational bene1047297ts) countermeasures
should be taken into consideration in order to minimize the
heightened risk of domino accidents
Both choices for the Purple Book and the UK risk tolerance
criteria are individual choices for this study and they should be
seen and respected as such We are aware that failure frequencies
are subject to constant optimization and that the Purple Book has
its limitations (Pasman 2011) Nonetheless for this study of twoplants situated in Iran using the frequencies reported in this well-
known and much-used work was a justi1047297able choice
5 Conclusions
The risk-based effects of constructing a new chemical plant
adjacent to an existing one forming a chemical cluster is analyzed
and discussed in this paper For this purpose a QRA was carried out
to assess different parameters of risk Individual and societal risks
were evaluated before and after the new plant came under oper-
ation The results indicate that the new plant did not have a major
impact on the risk levels since the risk levels stay within the
tolerability limits Although no major impact was observed there
was a signi1047297cant increase in the societal risk Moreover a dominoeffect analysis indicates that some storage tanks in the new plant
entail a high potential of being affected by events originating in the
existing plant
This research and this case study illustrate that in order to make
an objective plant lay out decision for a chemical cluster with
regard to operational risks not only conventional risk assessments
should be carried out but a domino effects analysis should be
performed as well since otherwise some risks may be under-
estimated and overlooked
It is undoubtedly true that themore accurateinformationis used
(eg concerning probabilities) the more accurate risk calculations
can be made However one should always remember that basically
calculated risks arerelativerisks andthat absolute valuesare prone
to variability and uncertainty As referencedby Pasman et al(2009)
Table 6
Target equipment affected by domino accident (due to overpressure)
scenario
Magnitude of overpressure caused by different AKPC scenarios at
target equipment (bar)
T K - 2 0 1
T K - 2 0 2
T K - 2 0 3
T K - 2 0 4
T K - 2 0 5
T K - 2 0 6
T K - 2 0 7
T K - 2 0 8
T K - 2 0 9
T K - 2 1 0
1-4 02 01 01 008 008 017 015 015
5-8 1 04 02 02 014 014 025 023 022
9 005 005 005 005 005 005 005 005 005 005
Affected by Dominoaccident
Not Affected by Dominoaccident
1 1
1
S Baesi et al Journal of Loss Prevention in the Process Industries 26 (2013) 895e903902
8132019 1-s20-S0950423012001702-main
httpslidepdfcomreaderfull1-s20-s0950423012001702-main 99
EU-studies have shown that a factor of 10e100 both ways in risk
results is not uncommon Hence future research might include risk
distributions and con1047297dence limits allowing risk analysts to even
better understand the uncertainties accompanying the results
References
Abbasi S A Krishnakumari P amp Khan F I (1998) Hot topics Global warming acidrain ozone hole hazardous waste industrial disasters disinfection New DelhiOxford University Press
Abdolhamidzadeh B Abbasi T Rashtchian D amp Abbasi S A (2010) A newmethod for assessing domino effect in chemical process industry Journal of Hazardous Materials 182(1e3) 416e426
Abdolhamidzadeh B Abbasi T Rashtchian D amp Abbasi S A (2011) Dominoeffect in process-industry accidents e an inventory of past events and identi-1047297cation of some patterns Journal of Loss Prevention in the Process Industries
24(5) 575e593Arunraj N S amp Maiti J (2009) A methodology for overall consequence modeling
in chemical industry Journal of Hazardous Materials 169 556e574Atherton J amp Gil F (2008) Incidents that de 1047297ne process safety Hoboken New
Jersey USA WileyBeerens H I Post J G amp Uijt de Haag P A M (2006) The use of generic failure
frequencies in QRA the quality and use of failure frequencies and how to bringthem up-to-date Journal of Hazardous Materials 130 265e270
Bubbico R Maschio G Mazzarotta B Milazzo M amp Parisi E (2006) Riskmanagement of road and rail transport of hazardous materials in Sicily Journalof Loss Prevention in the Process Industries 19(1) 32e38
Center for Chemical Process Safety (CCPS) (2000) Guidelines for chemical processquantitative risk analysis (2nd ed) New York American Institute of ChemicalEngineering
CozzaniV GubinelliG amp SalzanoE (2006)Escalationthresholds inthe assessmentof domino accidental events Journal of Hazardous Materials 129(1e3)1e21
CPR 18E (1999) lsquo Purple bookrsquo guidelines for quantitative risk assessment Part oneEstablishments The Hague RVIM
Dechy N Bourdeaux T Ayrault N Kordek M A amp Le Coze J C (2004) Firstlessons of the Toulouse ammonium nitrate disaster 21st September 2001 AZFplant France Journal of Hazardous Materials 111(1e3) 131e138
Gharabagh M J Asilian H Mortasavi S B Mogaddam A Z Hajizadeh E ampKhavanin A (2009) Comprehensive risk assessment and management of petrochemical feed and product transportation pipelines Journal of LossPrevention in the Process Industries 22(4) 533e539
Gooijer L Cornil N amp Lenoble C L (2012) An international comparison of fourquantitative risk assessment approaches e a benchmark study based on a 1047297cti-tious LPG plant Process Safety and Environmental Protection 90(2) 101e107
IRIMO (2006) Climatologically normal for the period 1987 e
2006 Mahshahr TehranIR of Iran Meteorological Organization Data Processing Center
Jo Y amp Crowl D (2008) Individual risk analysis of high-pressure natural gaspipelines Journal of Loss Prevention in the Process Industries 21 (6) 589e595
Kalantarnia M Khan F amp Hawboldt K (2010) Modelling of BP Texas City re1047297neryaccident using dynamic risk assessment approach Process Safety and Environ-mental Protection 88(3) 191e199 (Institution of Chemical Engineers)
Khan F I amp Abbasi S A (1998) Techniques and methodologies for risk analysis inchemical process industries Journal of Loss Prevention in the Process Industries11 261e277
Khan F I amp Abbasi S A (1999a) Major accidents in process industries and ananalysis of causes and consequences Journal of Loss Prevention in the ProcessIndustries 12 361e378
Khan F I amp Abbasi S A (1999b) Assessment of risks posed by chemical indus-triesdapplication of a new computer automated tool MAXCRED-III Journal of Loss Prevention in the Process Industries 12(6) 455e469
Khan F I Sadiq R amp Husain T (2002) Risk-based process safety assessment andcontrol measures design for offshore process facilities Journal of HazardousMaterials 94(1) 1e36
Kletz T A (1999b) The origins and history of loss prevention Transaction IChemE77 109e116
Kletz T A (1999a) What went wrong Case histories of process plant disasters andhow they could have been avoided Houston USA Gulf Professional Publishing
Kletz T A (2003) Still going wrong Case histories of process plant disasters and howthey could have been avoided Houston USA Gulf Professional Publishing
Lees F P (1996) Loss prevention in the process industries (2nd ed) Oxford LondonButterworth Heinemann
Markowski A S (2007) exLOPA for explosion risks assessment Journal of Hazardous Materials 142(3) 669e676
Milazzo M F Lisi R Maschio G Antonioni G Bonvicini S amp Spadoni G (2002)HazMat transport through Messina town from risk analysis suggestions forimproving territorial safety Journal of Loss Prevention in the Process Industries15(5) 347e356
Papazoglou I A Nivolianitou Z Aneziris O Christou M D amp Bonanos G (1999)Risk-informed selection of a highway trajectory in the neighborhood of an oil-re1047297nery Journal of Hazardous Materials 67 (2) 111e144
Pasman H J (2011) History of Dutch process equipment failure frequencies and thepurple book Journal of Loss Prevention in the Process Industries 24 208e213
Pasman H J Jung S Prem K Rogers W J amp Yang X (2009) Is risk analysisa useful tool for improving process safety Journal of Loss Prevention in theProcess Industries 22(6) 769e777
Pintaric Z (2007) Assessment of the consequences of accident scenariosinvolving dangerous substances Process Safety and Environmental Protection85(1) 23e38
Pula R Khan F I Veitch B amp Amyotte P (2006) A grid based approach for 1047297reand explosion consequence analysis Process Safety and Environmental Protec-tion 84(2) 79e91
Reniers G L L (2010) An external domino effects investment approach to improvecross-plant safety within chemical clusters Journal of Hazardous Materials 177 167e174
Reniers G L L amp Dullaert W (2007) DomPrevPlanning user-friendly software forplanning domino effects prevention Safety Science 45(10) 1060e1081
Renjith V R amp Madhu G (2010) Individual and societal risk analysis and mappingof human vulnerability to chemical accidents in the vicinity of an industrialarea International Journal of Applied Engineering Research Dindigul 1 135e148
Rigas F amp Sklavounos S (2002) Risk and consequence analyses of hazardouschemicals in marshalling yards and warehouses at IkonioPiraeus harbourGreece Journal of Loss Prevention in the Process Industries 15(6) 531e544
Salzano Eamp Cozzani V (2005)The analysis of dominoaccidents triggered byvaporcloud explosions Reliability Engineering amp System Safety 90(2e3) 271e284
Spadoni G Egidi D amp Contini S (2000) Through ARIPAR-GIS the quanti 1047297ed arearisk analysis supports land-use planning activities Journal of Hazardous Mate-rials 71(1e3) 423e437
Van Sciver G R (1990) Quantitative risk analysis in the chemical process indus-tries Reliability Engineering amp System Safety 29 55e68
Viacutelchez J A Espejo V amp Casal J (2011) Generic event trees and probabilities forthe release of different types of hazardous materials Journal of Loss Preventionin the Process Industries 24(3) 281e287
Wells G (1997) Major hazards and their management Rugby UK Institution of Chemical Engineers
Yet-Pole IChi-MinS amp Ching-Hong C (2009)Applicationsof 3D QRAtechnique tothe 1047297reexplosion simulation and hazard mitigation within a naphtha-crackingplant Journal of Loss Prevention in the Process Industries 22 (4) 506e515
S Baesi et al Journal of Loss Prevention in the Process Industries 26 (2013) 895e903 903
![Page 6: 1-s2.0-S0950423012001702-main](https://reader038.vdocuments.us/reader038/viewer/2022100505/577cd1271a28ab9e7893bef5/html5/thumbnails/6.jpg)
8132019 1-s20-S0950423012001702-main
httpslidepdfcomreaderfull1-s20-s0950423012001702-main 69
Fig 4 A B individual risk contours before (for AKPC) and after (for cluster composed of AKPC and BSPC) constructing the new plant
8132019 1-s20-S0950423012001702-main
httpslidepdfcomreaderfull1-s20-s0950423012001702-main 79
the leakage case and in the rupture case Moreover based on the
plant layout review and due to the low level of equipment
congestion in this particular area under study the probability of
a 1047298ash 1047297re is higher than that of a Vapor Cloud Explosion (VCE)
since higher congestion is known to increase the probability of
a VCE rather than that of a 1047298ash 1047297re
4 Result and discussion
In order to evaluate the risk-based effects of constructing BSPC
adjacent to AKPC calculations were made for both individual risk
and societal risk before and after the new plant came under oper-
ation adjacent to the existing one The quanti1047297ed risk can then be
Fig 5 A B societal risk (Fe
N curve) before (A) and after (B) constructing the new plant
S Baesi et al Journal of Loss Prevention in the Process Industries 26 (2013) 895e903 901
8132019 1-s20-S0950423012001702-main
httpslidepdfcomreaderfull1-s20-s0950423012001702-main 89
compared against the criteria to assess the acceptability of the risk
levels The likelihood of domino effects needs to be assessed as
well
41 Calculation of individual risk
Using the results of frequency estimation and a detailed
consequence assessment for all the possible scenarios the indi-
vidual risk contours were obtained and are shown on a satellite
view of the study area Key outputs of the consequence modeling
are presented in Table 5 to give more insight in the two selected
scenarios Fig 4A and B demonstrate the individual risk levels
before (A) and after (B) the second plant came operational The
numerical value of each risk contour represents the frequency at
which a particular individual is fatally harmed when standing
within the contour boundary
The results of individual risk calculations reveal that inside the
chemical cluster composed of both plants (AKPC and BSPC) as well
as within the single plant AKPC the individual risk values do not
exceed the tolerable magnitude of 105yr before and after the new
plant came under operation Fig 3A and B also demonstrate that for
public areas (such as the main roads around AKPC and BSPC) the
risk level does not exceed the magnitude of 106yr except fora short interval of 100 m at the southern main road of AKPC
Nevertheless this issue was already present even before the
construction of BSPC In general we can state that in terms of
individual risk constructing the new plant adjacent to the existing
one did not affect the acceptability of risk levels
42 Calculation of societal risk
Although the previous section indicates that individual risk
levels do not exceed the tolerable levels the impact of any potential
accident on operators and public should also be investigated
Fig 4A and B provide the societal risk calculation results before and
after the new plant came into operation respectively As it can be
seen in Fig 5A the societal risk posed by AKPC individually falls inthe ALARP (As Low As Reasonably Practicable) region as de1047297ned by
HSE (UK)Fig 5Bshows that after constructing the new plant the
societal risk curve gets closer to the maximum risk criteria but still
remains in the ALARP region Therefore constructing the new plant
BSPC adjacent to the existing one AKPC seems to have only limited
impact upon the change of tolerability of the societal risk in our
case study
43 Domino effects assessment
The distance from the storage tanks located in AKPC to the
closest operational storage tank in BSPC is about 800 m Based on
the values reported by Cozzani Gubinelli and Salzano (2006) this
distance suggests that potential cascading accidents between theneighboring plants caused by thermal radiation are highly
improbable Therefore the only factor that can trigger a secondary
accident in the other neighboring plant is the overpressure caused
by an uncon1047297ned Vapor Cloud Explosion Considering the volatility
of the materials involved the operational conditions of storage the
average ambient temperature and the prevailing wind direction
(west) we may conclude that only materials stored in AKPCrsquos
storages are capable of forming an effective vapor cloud
There are different values reported for damage threshold due to
overpressure in literature but the overpressure of 1bar would
surely destroy any target equipment (Salzano amp Cozzani 2005)
This threshold has been chosen to evaluate the possibility of
domino accidents on the storage tanks in BSPC Table 6 provides
the magnitude of overpressure caused by different AKPC scenarios
(1e9) at the location of BSPCrsquos storage tanks These values are
based on performing a detailed consequence modeling
As it can be seen in Table 6 the closest storage tanks to AKPC
(TK-201 and TK-202) are possibly damaged due to overpressurecaused by a propylene explosion after a leakage or tank rupture
eventually triggering secondary accidents In other words the
accidental release of propylene in AKPC either continuous
(scenarios 1e4) or instantaneous (scenarios 5e8) has the capa-
bility of causing cascading accidents in BSPC This suggests that if
decision-makers insist on not changing the new plantrsquos layout (eg
due to large economic and operational bene1047297ts) countermeasures
should be taken into consideration in order to minimize the
heightened risk of domino accidents
Both choices for the Purple Book and the UK risk tolerance
criteria are individual choices for this study and they should be
seen and respected as such We are aware that failure frequencies
are subject to constant optimization and that the Purple Book has
its limitations (Pasman 2011) Nonetheless for this study of twoplants situated in Iran using the frequencies reported in this well-
known and much-used work was a justi1047297able choice
5 Conclusions
The risk-based effects of constructing a new chemical plant
adjacent to an existing one forming a chemical cluster is analyzed
and discussed in this paper For this purpose a QRA was carried out
to assess different parameters of risk Individual and societal risks
were evaluated before and after the new plant came under oper-
ation The results indicate that the new plant did not have a major
impact on the risk levels since the risk levels stay within the
tolerability limits Although no major impact was observed there
was a signi1047297cant increase in the societal risk Moreover a dominoeffect analysis indicates that some storage tanks in the new plant
entail a high potential of being affected by events originating in the
existing plant
This research and this case study illustrate that in order to make
an objective plant lay out decision for a chemical cluster with
regard to operational risks not only conventional risk assessments
should be carried out but a domino effects analysis should be
performed as well since otherwise some risks may be under-
estimated and overlooked
It is undoubtedly true that themore accurateinformationis used
(eg concerning probabilities) the more accurate risk calculations
can be made However one should always remember that basically
calculated risks arerelativerisks andthat absolute valuesare prone
to variability and uncertainty As referencedby Pasman et al(2009)
Table 6
Target equipment affected by domino accident (due to overpressure)
scenario
Magnitude of overpressure caused by different AKPC scenarios at
target equipment (bar)
T K - 2 0 1
T K - 2 0 2
T K - 2 0 3
T K - 2 0 4
T K - 2 0 5
T K - 2 0 6
T K - 2 0 7
T K - 2 0 8
T K - 2 0 9
T K - 2 1 0
1-4 02 01 01 008 008 017 015 015
5-8 1 04 02 02 014 014 025 023 022
9 005 005 005 005 005 005 005 005 005 005
Affected by Dominoaccident
Not Affected by Dominoaccident
1 1
1
S Baesi et al Journal of Loss Prevention in the Process Industries 26 (2013) 895e903902
8132019 1-s20-S0950423012001702-main
httpslidepdfcomreaderfull1-s20-s0950423012001702-main 99
EU-studies have shown that a factor of 10e100 both ways in risk
results is not uncommon Hence future research might include risk
distributions and con1047297dence limits allowing risk analysts to even
better understand the uncertainties accompanying the results
References
Abbasi S A Krishnakumari P amp Khan F I (1998) Hot topics Global warming acidrain ozone hole hazardous waste industrial disasters disinfection New DelhiOxford University Press
Abdolhamidzadeh B Abbasi T Rashtchian D amp Abbasi S A (2010) A newmethod for assessing domino effect in chemical process industry Journal of Hazardous Materials 182(1e3) 416e426
Abdolhamidzadeh B Abbasi T Rashtchian D amp Abbasi S A (2011) Dominoeffect in process-industry accidents e an inventory of past events and identi-1047297cation of some patterns Journal of Loss Prevention in the Process Industries
24(5) 575e593Arunraj N S amp Maiti J (2009) A methodology for overall consequence modeling
in chemical industry Journal of Hazardous Materials 169 556e574Atherton J amp Gil F (2008) Incidents that de 1047297ne process safety Hoboken New
Jersey USA WileyBeerens H I Post J G amp Uijt de Haag P A M (2006) The use of generic failure
frequencies in QRA the quality and use of failure frequencies and how to bringthem up-to-date Journal of Hazardous Materials 130 265e270
Bubbico R Maschio G Mazzarotta B Milazzo M amp Parisi E (2006) Riskmanagement of road and rail transport of hazardous materials in Sicily Journalof Loss Prevention in the Process Industries 19(1) 32e38
Center for Chemical Process Safety (CCPS) (2000) Guidelines for chemical processquantitative risk analysis (2nd ed) New York American Institute of ChemicalEngineering
CozzaniV GubinelliG amp SalzanoE (2006)Escalationthresholds inthe assessmentof domino accidental events Journal of Hazardous Materials 129(1e3)1e21
CPR 18E (1999) lsquo Purple bookrsquo guidelines for quantitative risk assessment Part oneEstablishments The Hague RVIM
Dechy N Bourdeaux T Ayrault N Kordek M A amp Le Coze J C (2004) Firstlessons of the Toulouse ammonium nitrate disaster 21st September 2001 AZFplant France Journal of Hazardous Materials 111(1e3) 131e138
Gharabagh M J Asilian H Mortasavi S B Mogaddam A Z Hajizadeh E ampKhavanin A (2009) Comprehensive risk assessment and management of petrochemical feed and product transportation pipelines Journal of LossPrevention in the Process Industries 22(4) 533e539
Gooijer L Cornil N amp Lenoble C L (2012) An international comparison of fourquantitative risk assessment approaches e a benchmark study based on a 1047297cti-tious LPG plant Process Safety and Environmental Protection 90(2) 101e107
IRIMO (2006) Climatologically normal for the period 1987 e
2006 Mahshahr TehranIR of Iran Meteorological Organization Data Processing Center
Jo Y amp Crowl D (2008) Individual risk analysis of high-pressure natural gaspipelines Journal of Loss Prevention in the Process Industries 21 (6) 589e595
Kalantarnia M Khan F amp Hawboldt K (2010) Modelling of BP Texas City re1047297neryaccident using dynamic risk assessment approach Process Safety and Environ-mental Protection 88(3) 191e199 (Institution of Chemical Engineers)
Khan F I amp Abbasi S A (1998) Techniques and methodologies for risk analysis inchemical process industries Journal of Loss Prevention in the Process Industries11 261e277
Khan F I amp Abbasi S A (1999a) Major accidents in process industries and ananalysis of causes and consequences Journal of Loss Prevention in the ProcessIndustries 12 361e378
Khan F I amp Abbasi S A (1999b) Assessment of risks posed by chemical indus-triesdapplication of a new computer automated tool MAXCRED-III Journal of Loss Prevention in the Process Industries 12(6) 455e469
Khan F I Sadiq R amp Husain T (2002) Risk-based process safety assessment andcontrol measures design for offshore process facilities Journal of HazardousMaterials 94(1) 1e36
Kletz T A (1999b) The origins and history of loss prevention Transaction IChemE77 109e116
Kletz T A (1999a) What went wrong Case histories of process plant disasters andhow they could have been avoided Houston USA Gulf Professional Publishing
Kletz T A (2003) Still going wrong Case histories of process plant disasters and howthey could have been avoided Houston USA Gulf Professional Publishing
Lees F P (1996) Loss prevention in the process industries (2nd ed) Oxford LondonButterworth Heinemann
Markowski A S (2007) exLOPA for explosion risks assessment Journal of Hazardous Materials 142(3) 669e676
Milazzo M F Lisi R Maschio G Antonioni G Bonvicini S amp Spadoni G (2002)HazMat transport through Messina town from risk analysis suggestions forimproving territorial safety Journal of Loss Prevention in the Process Industries15(5) 347e356
Papazoglou I A Nivolianitou Z Aneziris O Christou M D amp Bonanos G (1999)Risk-informed selection of a highway trajectory in the neighborhood of an oil-re1047297nery Journal of Hazardous Materials 67 (2) 111e144
Pasman H J (2011) History of Dutch process equipment failure frequencies and thepurple book Journal of Loss Prevention in the Process Industries 24 208e213
Pasman H J Jung S Prem K Rogers W J amp Yang X (2009) Is risk analysisa useful tool for improving process safety Journal of Loss Prevention in theProcess Industries 22(6) 769e777
Pintaric Z (2007) Assessment of the consequences of accident scenariosinvolving dangerous substances Process Safety and Environmental Protection85(1) 23e38
Pula R Khan F I Veitch B amp Amyotte P (2006) A grid based approach for 1047297reand explosion consequence analysis Process Safety and Environmental Protec-tion 84(2) 79e91
Reniers G L L (2010) An external domino effects investment approach to improvecross-plant safety within chemical clusters Journal of Hazardous Materials 177 167e174
Reniers G L L amp Dullaert W (2007) DomPrevPlanning user-friendly software forplanning domino effects prevention Safety Science 45(10) 1060e1081
Renjith V R amp Madhu G (2010) Individual and societal risk analysis and mappingof human vulnerability to chemical accidents in the vicinity of an industrialarea International Journal of Applied Engineering Research Dindigul 1 135e148
Rigas F amp Sklavounos S (2002) Risk and consequence analyses of hazardouschemicals in marshalling yards and warehouses at IkonioPiraeus harbourGreece Journal of Loss Prevention in the Process Industries 15(6) 531e544
Salzano Eamp Cozzani V (2005)The analysis of dominoaccidents triggered byvaporcloud explosions Reliability Engineering amp System Safety 90(2e3) 271e284
Spadoni G Egidi D amp Contini S (2000) Through ARIPAR-GIS the quanti 1047297ed arearisk analysis supports land-use planning activities Journal of Hazardous Mate-rials 71(1e3) 423e437
Van Sciver G R (1990) Quantitative risk analysis in the chemical process indus-tries Reliability Engineering amp System Safety 29 55e68
Viacutelchez J A Espejo V amp Casal J (2011) Generic event trees and probabilities forthe release of different types of hazardous materials Journal of Loss Preventionin the Process Industries 24(3) 281e287
Wells G (1997) Major hazards and their management Rugby UK Institution of Chemical Engineers
Yet-Pole IChi-MinS amp Ching-Hong C (2009)Applicationsof 3D QRAtechnique tothe 1047297reexplosion simulation and hazard mitigation within a naphtha-crackingplant Journal of Loss Prevention in the Process Industries 22 (4) 506e515
S Baesi et al Journal of Loss Prevention in the Process Industries 26 (2013) 895e903 903
![Page 7: 1-s2.0-S0950423012001702-main](https://reader038.vdocuments.us/reader038/viewer/2022100505/577cd1271a28ab9e7893bef5/html5/thumbnails/7.jpg)
8132019 1-s20-S0950423012001702-main
httpslidepdfcomreaderfull1-s20-s0950423012001702-main 79
the leakage case and in the rupture case Moreover based on the
plant layout review and due to the low level of equipment
congestion in this particular area under study the probability of
a 1047298ash 1047297re is higher than that of a Vapor Cloud Explosion (VCE)
since higher congestion is known to increase the probability of
a VCE rather than that of a 1047298ash 1047297re
4 Result and discussion
In order to evaluate the risk-based effects of constructing BSPC
adjacent to AKPC calculations were made for both individual risk
and societal risk before and after the new plant came under oper-
ation adjacent to the existing one The quanti1047297ed risk can then be
Fig 5 A B societal risk (Fe
N curve) before (A) and after (B) constructing the new plant
S Baesi et al Journal of Loss Prevention in the Process Industries 26 (2013) 895e903 901
8132019 1-s20-S0950423012001702-main
httpslidepdfcomreaderfull1-s20-s0950423012001702-main 89
compared against the criteria to assess the acceptability of the risk
levels The likelihood of domino effects needs to be assessed as
well
41 Calculation of individual risk
Using the results of frequency estimation and a detailed
consequence assessment for all the possible scenarios the indi-
vidual risk contours were obtained and are shown on a satellite
view of the study area Key outputs of the consequence modeling
are presented in Table 5 to give more insight in the two selected
scenarios Fig 4A and B demonstrate the individual risk levels
before (A) and after (B) the second plant came operational The
numerical value of each risk contour represents the frequency at
which a particular individual is fatally harmed when standing
within the contour boundary
The results of individual risk calculations reveal that inside the
chemical cluster composed of both plants (AKPC and BSPC) as well
as within the single plant AKPC the individual risk values do not
exceed the tolerable magnitude of 105yr before and after the new
plant came under operation Fig 3A and B also demonstrate that for
public areas (such as the main roads around AKPC and BSPC) the
risk level does not exceed the magnitude of 106yr except fora short interval of 100 m at the southern main road of AKPC
Nevertheless this issue was already present even before the
construction of BSPC In general we can state that in terms of
individual risk constructing the new plant adjacent to the existing
one did not affect the acceptability of risk levels
42 Calculation of societal risk
Although the previous section indicates that individual risk
levels do not exceed the tolerable levels the impact of any potential
accident on operators and public should also be investigated
Fig 4A and B provide the societal risk calculation results before and
after the new plant came into operation respectively As it can be
seen in Fig 5A the societal risk posed by AKPC individually falls inthe ALARP (As Low As Reasonably Practicable) region as de1047297ned by
HSE (UK)Fig 5Bshows that after constructing the new plant the
societal risk curve gets closer to the maximum risk criteria but still
remains in the ALARP region Therefore constructing the new plant
BSPC adjacent to the existing one AKPC seems to have only limited
impact upon the change of tolerability of the societal risk in our
case study
43 Domino effects assessment
The distance from the storage tanks located in AKPC to the
closest operational storage tank in BSPC is about 800 m Based on
the values reported by Cozzani Gubinelli and Salzano (2006) this
distance suggests that potential cascading accidents between theneighboring plants caused by thermal radiation are highly
improbable Therefore the only factor that can trigger a secondary
accident in the other neighboring plant is the overpressure caused
by an uncon1047297ned Vapor Cloud Explosion Considering the volatility
of the materials involved the operational conditions of storage the
average ambient temperature and the prevailing wind direction
(west) we may conclude that only materials stored in AKPCrsquos
storages are capable of forming an effective vapor cloud
There are different values reported for damage threshold due to
overpressure in literature but the overpressure of 1bar would
surely destroy any target equipment (Salzano amp Cozzani 2005)
This threshold has been chosen to evaluate the possibility of
domino accidents on the storage tanks in BSPC Table 6 provides
the magnitude of overpressure caused by different AKPC scenarios
(1e9) at the location of BSPCrsquos storage tanks These values are
based on performing a detailed consequence modeling
As it can be seen in Table 6 the closest storage tanks to AKPC
(TK-201 and TK-202) are possibly damaged due to overpressurecaused by a propylene explosion after a leakage or tank rupture
eventually triggering secondary accidents In other words the
accidental release of propylene in AKPC either continuous
(scenarios 1e4) or instantaneous (scenarios 5e8) has the capa-
bility of causing cascading accidents in BSPC This suggests that if
decision-makers insist on not changing the new plantrsquos layout (eg
due to large economic and operational bene1047297ts) countermeasures
should be taken into consideration in order to minimize the
heightened risk of domino accidents
Both choices for the Purple Book and the UK risk tolerance
criteria are individual choices for this study and they should be
seen and respected as such We are aware that failure frequencies
are subject to constant optimization and that the Purple Book has
its limitations (Pasman 2011) Nonetheless for this study of twoplants situated in Iran using the frequencies reported in this well-
known and much-used work was a justi1047297able choice
5 Conclusions
The risk-based effects of constructing a new chemical plant
adjacent to an existing one forming a chemical cluster is analyzed
and discussed in this paper For this purpose a QRA was carried out
to assess different parameters of risk Individual and societal risks
were evaluated before and after the new plant came under oper-
ation The results indicate that the new plant did not have a major
impact on the risk levels since the risk levels stay within the
tolerability limits Although no major impact was observed there
was a signi1047297cant increase in the societal risk Moreover a dominoeffect analysis indicates that some storage tanks in the new plant
entail a high potential of being affected by events originating in the
existing plant
This research and this case study illustrate that in order to make
an objective plant lay out decision for a chemical cluster with
regard to operational risks not only conventional risk assessments
should be carried out but a domino effects analysis should be
performed as well since otherwise some risks may be under-
estimated and overlooked
It is undoubtedly true that themore accurateinformationis used
(eg concerning probabilities) the more accurate risk calculations
can be made However one should always remember that basically
calculated risks arerelativerisks andthat absolute valuesare prone
to variability and uncertainty As referencedby Pasman et al(2009)
Table 6
Target equipment affected by domino accident (due to overpressure)
scenario
Magnitude of overpressure caused by different AKPC scenarios at
target equipment (bar)
T K - 2 0 1
T K - 2 0 2
T K - 2 0 3
T K - 2 0 4
T K - 2 0 5
T K - 2 0 6
T K - 2 0 7
T K - 2 0 8
T K - 2 0 9
T K - 2 1 0
1-4 02 01 01 008 008 017 015 015
5-8 1 04 02 02 014 014 025 023 022
9 005 005 005 005 005 005 005 005 005 005
Affected by Dominoaccident
Not Affected by Dominoaccident
1 1
1
S Baesi et al Journal of Loss Prevention in the Process Industries 26 (2013) 895e903902
8132019 1-s20-S0950423012001702-main
httpslidepdfcomreaderfull1-s20-s0950423012001702-main 99
EU-studies have shown that a factor of 10e100 both ways in risk
results is not uncommon Hence future research might include risk
distributions and con1047297dence limits allowing risk analysts to even
better understand the uncertainties accompanying the results
References
Abbasi S A Krishnakumari P amp Khan F I (1998) Hot topics Global warming acidrain ozone hole hazardous waste industrial disasters disinfection New DelhiOxford University Press
Abdolhamidzadeh B Abbasi T Rashtchian D amp Abbasi S A (2010) A newmethod for assessing domino effect in chemical process industry Journal of Hazardous Materials 182(1e3) 416e426
Abdolhamidzadeh B Abbasi T Rashtchian D amp Abbasi S A (2011) Dominoeffect in process-industry accidents e an inventory of past events and identi-1047297cation of some patterns Journal of Loss Prevention in the Process Industries
24(5) 575e593Arunraj N S amp Maiti J (2009) A methodology for overall consequence modeling
in chemical industry Journal of Hazardous Materials 169 556e574Atherton J amp Gil F (2008) Incidents that de 1047297ne process safety Hoboken New
Jersey USA WileyBeerens H I Post J G amp Uijt de Haag P A M (2006) The use of generic failure
frequencies in QRA the quality and use of failure frequencies and how to bringthem up-to-date Journal of Hazardous Materials 130 265e270
Bubbico R Maschio G Mazzarotta B Milazzo M amp Parisi E (2006) Riskmanagement of road and rail transport of hazardous materials in Sicily Journalof Loss Prevention in the Process Industries 19(1) 32e38
Center for Chemical Process Safety (CCPS) (2000) Guidelines for chemical processquantitative risk analysis (2nd ed) New York American Institute of ChemicalEngineering
CozzaniV GubinelliG amp SalzanoE (2006)Escalationthresholds inthe assessmentof domino accidental events Journal of Hazardous Materials 129(1e3)1e21
CPR 18E (1999) lsquo Purple bookrsquo guidelines for quantitative risk assessment Part oneEstablishments The Hague RVIM
Dechy N Bourdeaux T Ayrault N Kordek M A amp Le Coze J C (2004) Firstlessons of the Toulouse ammonium nitrate disaster 21st September 2001 AZFplant France Journal of Hazardous Materials 111(1e3) 131e138
Gharabagh M J Asilian H Mortasavi S B Mogaddam A Z Hajizadeh E ampKhavanin A (2009) Comprehensive risk assessment and management of petrochemical feed and product transportation pipelines Journal of LossPrevention in the Process Industries 22(4) 533e539
Gooijer L Cornil N amp Lenoble C L (2012) An international comparison of fourquantitative risk assessment approaches e a benchmark study based on a 1047297cti-tious LPG plant Process Safety and Environmental Protection 90(2) 101e107
IRIMO (2006) Climatologically normal for the period 1987 e
2006 Mahshahr TehranIR of Iran Meteorological Organization Data Processing Center
Jo Y amp Crowl D (2008) Individual risk analysis of high-pressure natural gaspipelines Journal of Loss Prevention in the Process Industries 21 (6) 589e595
Kalantarnia M Khan F amp Hawboldt K (2010) Modelling of BP Texas City re1047297neryaccident using dynamic risk assessment approach Process Safety and Environ-mental Protection 88(3) 191e199 (Institution of Chemical Engineers)
Khan F I amp Abbasi S A (1998) Techniques and methodologies for risk analysis inchemical process industries Journal of Loss Prevention in the Process Industries11 261e277
Khan F I amp Abbasi S A (1999a) Major accidents in process industries and ananalysis of causes and consequences Journal of Loss Prevention in the ProcessIndustries 12 361e378
Khan F I amp Abbasi S A (1999b) Assessment of risks posed by chemical indus-triesdapplication of a new computer automated tool MAXCRED-III Journal of Loss Prevention in the Process Industries 12(6) 455e469
Khan F I Sadiq R amp Husain T (2002) Risk-based process safety assessment andcontrol measures design for offshore process facilities Journal of HazardousMaterials 94(1) 1e36
Kletz T A (1999b) The origins and history of loss prevention Transaction IChemE77 109e116
Kletz T A (1999a) What went wrong Case histories of process plant disasters andhow they could have been avoided Houston USA Gulf Professional Publishing
Kletz T A (2003) Still going wrong Case histories of process plant disasters and howthey could have been avoided Houston USA Gulf Professional Publishing
Lees F P (1996) Loss prevention in the process industries (2nd ed) Oxford LondonButterworth Heinemann
Markowski A S (2007) exLOPA for explosion risks assessment Journal of Hazardous Materials 142(3) 669e676
Milazzo M F Lisi R Maschio G Antonioni G Bonvicini S amp Spadoni G (2002)HazMat transport through Messina town from risk analysis suggestions forimproving territorial safety Journal of Loss Prevention in the Process Industries15(5) 347e356
Papazoglou I A Nivolianitou Z Aneziris O Christou M D amp Bonanos G (1999)Risk-informed selection of a highway trajectory in the neighborhood of an oil-re1047297nery Journal of Hazardous Materials 67 (2) 111e144
Pasman H J (2011) History of Dutch process equipment failure frequencies and thepurple book Journal of Loss Prevention in the Process Industries 24 208e213
Pasman H J Jung S Prem K Rogers W J amp Yang X (2009) Is risk analysisa useful tool for improving process safety Journal of Loss Prevention in theProcess Industries 22(6) 769e777
Pintaric Z (2007) Assessment of the consequences of accident scenariosinvolving dangerous substances Process Safety and Environmental Protection85(1) 23e38
Pula R Khan F I Veitch B amp Amyotte P (2006) A grid based approach for 1047297reand explosion consequence analysis Process Safety and Environmental Protec-tion 84(2) 79e91
Reniers G L L (2010) An external domino effects investment approach to improvecross-plant safety within chemical clusters Journal of Hazardous Materials 177 167e174
Reniers G L L amp Dullaert W (2007) DomPrevPlanning user-friendly software forplanning domino effects prevention Safety Science 45(10) 1060e1081
Renjith V R amp Madhu G (2010) Individual and societal risk analysis and mappingof human vulnerability to chemical accidents in the vicinity of an industrialarea International Journal of Applied Engineering Research Dindigul 1 135e148
Rigas F amp Sklavounos S (2002) Risk and consequence analyses of hazardouschemicals in marshalling yards and warehouses at IkonioPiraeus harbourGreece Journal of Loss Prevention in the Process Industries 15(6) 531e544
Salzano Eamp Cozzani V (2005)The analysis of dominoaccidents triggered byvaporcloud explosions Reliability Engineering amp System Safety 90(2e3) 271e284
Spadoni G Egidi D amp Contini S (2000) Through ARIPAR-GIS the quanti 1047297ed arearisk analysis supports land-use planning activities Journal of Hazardous Mate-rials 71(1e3) 423e437
Van Sciver G R (1990) Quantitative risk analysis in the chemical process indus-tries Reliability Engineering amp System Safety 29 55e68
Viacutelchez J A Espejo V amp Casal J (2011) Generic event trees and probabilities forthe release of different types of hazardous materials Journal of Loss Preventionin the Process Industries 24(3) 281e287
Wells G (1997) Major hazards and their management Rugby UK Institution of Chemical Engineers
Yet-Pole IChi-MinS amp Ching-Hong C (2009)Applicationsof 3D QRAtechnique tothe 1047297reexplosion simulation and hazard mitigation within a naphtha-crackingplant Journal of Loss Prevention in the Process Industries 22 (4) 506e515
S Baesi et al Journal of Loss Prevention in the Process Industries 26 (2013) 895e903 903
![Page 8: 1-s2.0-S0950423012001702-main](https://reader038.vdocuments.us/reader038/viewer/2022100505/577cd1271a28ab9e7893bef5/html5/thumbnails/8.jpg)
8132019 1-s20-S0950423012001702-main
httpslidepdfcomreaderfull1-s20-s0950423012001702-main 89
compared against the criteria to assess the acceptability of the risk
levels The likelihood of domino effects needs to be assessed as
well
41 Calculation of individual risk
Using the results of frequency estimation and a detailed
consequence assessment for all the possible scenarios the indi-
vidual risk contours were obtained and are shown on a satellite
view of the study area Key outputs of the consequence modeling
are presented in Table 5 to give more insight in the two selected
scenarios Fig 4A and B demonstrate the individual risk levels
before (A) and after (B) the second plant came operational The
numerical value of each risk contour represents the frequency at
which a particular individual is fatally harmed when standing
within the contour boundary
The results of individual risk calculations reveal that inside the
chemical cluster composed of both plants (AKPC and BSPC) as well
as within the single plant AKPC the individual risk values do not
exceed the tolerable magnitude of 105yr before and after the new
plant came under operation Fig 3A and B also demonstrate that for
public areas (such as the main roads around AKPC and BSPC) the
risk level does not exceed the magnitude of 106yr except fora short interval of 100 m at the southern main road of AKPC
Nevertheless this issue was already present even before the
construction of BSPC In general we can state that in terms of
individual risk constructing the new plant adjacent to the existing
one did not affect the acceptability of risk levels
42 Calculation of societal risk
Although the previous section indicates that individual risk
levels do not exceed the tolerable levels the impact of any potential
accident on operators and public should also be investigated
Fig 4A and B provide the societal risk calculation results before and
after the new plant came into operation respectively As it can be
seen in Fig 5A the societal risk posed by AKPC individually falls inthe ALARP (As Low As Reasonably Practicable) region as de1047297ned by
HSE (UK)Fig 5Bshows that after constructing the new plant the
societal risk curve gets closer to the maximum risk criteria but still
remains in the ALARP region Therefore constructing the new plant
BSPC adjacent to the existing one AKPC seems to have only limited
impact upon the change of tolerability of the societal risk in our
case study
43 Domino effects assessment
The distance from the storage tanks located in AKPC to the
closest operational storage tank in BSPC is about 800 m Based on
the values reported by Cozzani Gubinelli and Salzano (2006) this
distance suggests that potential cascading accidents between theneighboring plants caused by thermal radiation are highly
improbable Therefore the only factor that can trigger a secondary
accident in the other neighboring plant is the overpressure caused
by an uncon1047297ned Vapor Cloud Explosion Considering the volatility
of the materials involved the operational conditions of storage the
average ambient temperature and the prevailing wind direction
(west) we may conclude that only materials stored in AKPCrsquos
storages are capable of forming an effective vapor cloud
There are different values reported for damage threshold due to
overpressure in literature but the overpressure of 1bar would
surely destroy any target equipment (Salzano amp Cozzani 2005)
This threshold has been chosen to evaluate the possibility of
domino accidents on the storage tanks in BSPC Table 6 provides
the magnitude of overpressure caused by different AKPC scenarios
(1e9) at the location of BSPCrsquos storage tanks These values are
based on performing a detailed consequence modeling
As it can be seen in Table 6 the closest storage tanks to AKPC
(TK-201 and TK-202) are possibly damaged due to overpressurecaused by a propylene explosion after a leakage or tank rupture
eventually triggering secondary accidents In other words the
accidental release of propylene in AKPC either continuous
(scenarios 1e4) or instantaneous (scenarios 5e8) has the capa-
bility of causing cascading accidents in BSPC This suggests that if
decision-makers insist on not changing the new plantrsquos layout (eg
due to large economic and operational bene1047297ts) countermeasures
should be taken into consideration in order to minimize the
heightened risk of domino accidents
Both choices for the Purple Book and the UK risk tolerance
criteria are individual choices for this study and they should be
seen and respected as such We are aware that failure frequencies
are subject to constant optimization and that the Purple Book has
its limitations (Pasman 2011) Nonetheless for this study of twoplants situated in Iran using the frequencies reported in this well-
known and much-used work was a justi1047297able choice
5 Conclusions
The risk-based effects of constructing a new chemical plant
adjacent to an existing one forming a chemical cluster is analyzed
and discussed in this paper For this purpose a QRA was carried out
to assess different parameters of risk Individual and societal risks
were evaluated before and after the new plant came under oper-
ation The results indicate that the new plant did not have a major
impact on the risk levels since the risk levels stay within the
tolerability limits Although no major impact was observed there
was a signi1047297cant increase in the societal risk Moreover a dominoeffect analysis indicates that some storage tanks in the new plant
entail a high potential of being affected by events originating in the
existing plant
This research and this case study illustrate that in order to make
an objective plant lay out decision for a chemical cluster with
regard to operational risks not only conventional risk assessments
should be carried out but a domino effects analysis should be
performed as well since otherwise some risks may be under-
estimated and overlooked
It is undoubtedly true that themore accurateinformationis used
(eg concerning probabilities) the more accurate risk calculations
can be made However one should always remember that basically
calculated risks arerelativerisks andthat absolute valuesare prone
to variability and uncertainty As referencedby Pasman et al(2009)
Table 6
Target equipment affected by domino accident (due to overpressure)
scenario
Magnitude of overpressure caused by different AKPC scenarios at
target equipment (bar)
T K - 2 0 1
T K - 2 0 2
T K - 2 0 3
T K - 2 0 4
T K - 2 0 5
T K - 2 0 6
T K - 2 0 7
T K - 2 0 8
T K - 2 0 9
T K - 2 1 0
1-4 02 01 01 008 008 017 015 015
5-8 1 04 02 02 014 014 025 023 022
9 005 005 005 005 005 005 005 005 005 005
Affected by Dominoaccident
Not Affected by Dominoaccident
1 1
1
S Baesi et al Journal of Loss Prevention in the Process Industries 26 (2013) 895e903902
8132019 1-s20-S0950423012001702-main
httpslidepdfcomreaderfull1-s20-s0950423012001702-main 99
EU-studies have shown that a factor of 10e100 both ways in risk
results is not uncommon Hence future research might include risk
distributions and con1047297dence limits allowing risk analysts to even
better understand the uncertainties accompanying the results
References
Abbasi S A Krishnakumari P amp Khan F I (1998) Hot topics Global warming acidrain ozone hole hazardous waste industrial disasters disinfection New DelhiOxford University Press
Abdolhamidzadeh B Abbasi T Rashtchian D amp Abbasi S A (2010) A newmethod for assessing domino effect in chemical process industry Journal of Hazardous Materials 182(1e3) 416e426
Abdolhamidzadeh B Abbasi T Rashtchian D amp Abbasi S A (2011) Dominoeffect in process-industry accidents e an inventory of past events and identi-1047297cation of some patterns Journal of Loss Prevention in the Process Industries
24(5) 575e593Arunraj N S amp Maiti J (2009) A methodology for overall consequence modeling
in chemical industry Journal of Hazardous Materials 169 556e574Atherton J amp Gil F (2008) Incidents that de 1047297ne process safety Hoboken New
Jersey USA WileyBeerens H I Post J G amp Uijt de Haag P A M (2006) The use of generic failure
frequencies in QRA the quality and use of failure frequencies and how to bringthem up-to-date Journal of Hazardous Materials 130 265e270
Bubbico R Maschio G Mazzarotta B Milazzo M amp Parisi E (2006) Riskmanagement of road and rail transport of hazardous materials in Sicily Journalof Loss Prevention in the Process Industries 19(1) 32e38
Center for Chemical Process Safety (CCPS) (2000) Guidelines for chemical processquantitative risk analysis (2nd ed) New York American Institute of ChemicalEngineering
CozzaniV GubinelliG amp SalzanoE (2006)Escalationthresholds inthe assessmentof domino accidental events Journal of Hazardous Materials 129(1e3)1e21
CPR 18E (1999) lsquo Purple bookrsquo guidelines for quantitative risk assessment Part oneEstablishments The Hague RVIM
Dechy N Bourdeaux T Ayrault N Kordek M A amp Le Coze J C (2004) Firstlessons of the Toulouse ammonium nitrate disaster 21st September 2001 AZFplant France Journal of Hazardous Materials 111(1e3) 131e138
Gharabagh M J Asilian H Mortasavi S B Mogaddam A Z Hajizadeh E ampKhavanin A (2009) Comprehensive risk assessment and management of petrochemical feed and product transportation pipelines Journal of LossPrevention in the Process Industries 22(4) 533e539
Gooijer L Cornil N amp Lenoble C L (2012) An international comparison of fourquantitative risk assessment approaches e a benchmark study based on a 1047297cti-tious LPG plant Process Safety and Environmental Protection 90(2) 101e107
IRIMO (2006) Climatologically normal for the period 1987 e
2006 Mahshahr TehranIR of Iran Meteorological Organization Data Processing Center
Jo Y amp Crowl D (2008) Individual risk analysis of high-pressure natural gaspipelines Journal of Loss Prevention in the Process Industries 21 (6) 589e595
Kalantarnia M Khan F amp Hawboldt K (2010) Modelling of BP Texas City re1047297neryaccident using dynamic risk assessment approach Process Safety and Environ-mental Protection 88(3) 191e199 (Institution of Chemical Engineers)
Khan F I amp Abbasi S A (1998) Techniques and methodologies for risk analysis inchemical process industries Journal of Loss Prevention in the Process Industries11 261e277
Khan F I amp Abbasi S A (1999a) Major accidents in process industries and ananalysis of causes and consequences Journal of Loss Prevention in the ProcessIndustries 12 361e378
Khan F I amp Abbasi S A (1999b) Assessment of risks posed by chemical indus-triesdapplication of a new computer automated tool MAXCRED-III Journal of Loss Prevention in the Process Industries 12(6) 455e469
Khan F I Sadiq R amp Husain T (2002) Risk-based process safety assessment andcontrol measures design for offshore process facilities Journal of HazardousMaterials 94(1) 1e36
Kletz T A (1999b) The origins and history of loss prevention Transaction IChemE77 109e116
Kletz T A (1999a) What went wrong Case histories of process plant disasters andhow they could have been avoided Houston USA Gulf Professional Publishing
Kletz T A (2003) Still going wrong Case histories of process plant disasters and howthey could have been avoided Houston USA Gulf Professional Publishing
Lees F P (1996) Loss prevention in the process industries (2nd ed) Oxford LondonButterworth Heinemann
Markowski A S (2007) exLOPA for explosion risks assessment Journal of Hazardous Materials 142(3) 669e676
Milazzo M F Lisi R Maschio G Antonioni G Bonvicini S amp Spadoni G (2002)HazMat transport through Messina town from risk analysis suggestions forimproving territorial safety Journal of Loss Prevention in the Process Industries15(5) 347e356
Papazoglou I A Nivolianitou Z Aneziris O Christou M D amp Bonanos G (1999)Risk-informed selection of a highway trajectory in the neighborhood of an oil-re1047297nery Journal of Hazardous Materials 67 (2) 111e144
Pasman H J (2011) History of Dutch process equipment failure frequencies and thepurple book Journal of Loss Prevention in the Process Industries 24 208e213
Pasman H J Jung S Prem K Rogers W J amp Yang X (2009) Is risk analysisa useful tool for improving process safety Journal of Loss Prevention in theProcess Industries 22(6) 769e777
Pintaric Z (2007) Assessment of the consequences of accident scenariosinvolving dangerous substances Process Safety and Environmental Protection85(1) 23e38
Pula R Khan F I Veitch B amp Amyotte P (2006) A grid based approach for 1047297reand explosion consequence analysis Process Safety and Environmental Protec-tion 84(2) 79e91
Reniers G L L (2010) An external domino effects investment approach to improvecross-plant safety within chemical clusters Journal of Hazardous Materials 177 167e174
Reniers G L L amp Dullaert W (2007) DomPrevPlanning user-friendly software forplanning domino effects prevention Safety Science 45(10) 1060e1081
Renjith V R amp Madhu G (2010) Individual and societal risk analysis and mappingof human vulnerability to chemical accidents in the vicinity of an industrialarea International Journal of Applied Engineering Research Dindigul 1 135e148
Rigas F amp Sklavounos S (2002) Risk and consequence analyses of hazardouschemicals in marshalling yards and warehouses at IkonioPiraeus harbourGreece Journal of Loss Prevention in the Process Industries 15(6) 531e544
Salzano Eamp Cozzani V (2005)The analysis of dominoaccidents triggered byvaporcloud explosions Reliability Engineering amp System Safety 90(2e3) 271e284
Spadoni G Egidi D amp Contini S (2000) Through ARIPAR-GIS the quanti 1047297ed arearisk analysis supports land-use planning activities Journal of Hazardous Mate-rials 71(1e3) 423e437
Van Sciver G R (1990) Quantitative risk analysis in the chemical process indus-tries Reliability Engineering amp System Safety 29 55e68
Viacutelchez J A Espejo V amp Casal J (2011) Generic event trees and probabilities forthe release of different types of hazardous materials Journal of Loss Preventionin the Process Industries 24(3) 281e287
Wells G (1997) Major hazards and their management Rugby UK Institution of Chemical Engineers
Yet-Pole IChi-MinS amp Ching-Hong C (2009)Applicationsof 3D QRAtechnique tothe 1047297reexplosion simulation and hazard mitigation within a naphtha-crackingplant Journal of Loss Prevention in the Process Industries 22 (4) 506e515
S Baesi et al Journal of Loss Prevention in the Process Industries 26 (2013) 895e903 903
![Page 9: 1-s2.0-S0950423012001702-main](https://reader038.vdocuments.us/reader038/viewer/2022100505/577cd1271a28ab9e7893bef5/html5/thumbnails/9.jpg)
8132019 1-s20-S0950423012001702-main
httpslidepdfcomreaderfull1-s20-s0950423012001702-main 99
EU-studies have shown that a factor of 10e100 both ways in risk
results is not uncommon Hence future research might include risk
distributions and con1047297dence limits allowing risk analysts to even
better understand the uncertainties accompanying the results
References
Abbasi S A Krishnakumari P amp Khan F I (1998) Hot topics Global warming acidrain ozone hole hazardous waste industrial disasters disinfection New DelhiOxford University Press
Abdolhamidzadeh B Abbasi T Rashtchian D amp Abbasi S A (2010) A newmethod for assessing domino effect in chemical process industry Journal of Hazardous Materials 182(1e3) 416e426
Abdolhamidzadeh B Abbasi T Rashtchian D amp Abbasi S A (2011) Dominoeffect in process-industry accidents e an inventory of past events and identi-1047297cation of some patterns Journal of Loss Prevention in the Process Industries
24(5) 575e593Arunraj N S amp Maiti J (2009) A methodology for overall consequence modeling
in chemical industry Journal of Hazardous Materials 169 556e574Atherton J amp Gil F (2008) Incidents that de 1047297ne process safety Hoboken New
Jersey USA WileyBeerens H I Post J G amp Uijt de Haag P A M (2006) The use of generic failure
frequencies in QRA the quality and use of failure frequencies and how to bringthem up-to-date Journal of Hazardous Materials 130 265e270
Bubbico R Maschio G Mazzarotta B Milazzo M amp Parisi E (2006) Riskmanagement of road and rail transport of hazardous materials in Sicily Journalof Loss Prevention in the Process Industries 19(1) 32e38
Center for Chemical Process Safety (CCPS) (2000) Guidelines for chemical processquantitative risk analysis (2nd ed) New York American Institute of ChemicalEngineering
CozzaniV GubinelliG amp SalzanoE (2006)Escalationthresholds inthe assessmentof domino accidental events Journal of Hazardous Materials 129(1e3)1e21
CPR 18E (1999) lsquo Purple bookrsquo guidelines for quantitative risk assessment Part oneEstablishments The Hague RVIM
Dechy N Bourdeaux T Ayrault N Kordek M A amp Le Coze J C (2004) Firstlessons of the Toulouse ammonium nitrate disaster 21st September 2001 AZFplant France Journal of Hazardous Materials 111(1e3) 131e138
Gharabagh M J Asilian H Mortasavi S B Mogaddam A Z Hajizadeh E ampKhavanin A (2009) Comprehensive risk assessment and management of petrochemical feed and product transportation pipelines Journal of LossPrevention in the Process Industries 22(4) 533e539
Gooijer L Cornil N amp Lenoble C L (2012) An international comparison of fourquantitative risk assessment approaches e a benchmark study based on a 1047297cti-tious LPG plant Process Safety and Environmental Protection 90(2) 101e107
IRIMO (2006) Climatologically normal for the period 1987 e
2006 Mahshahr TehranIR of Iran Meteorological Organization Data Processing Center
Jo Y amp Crowl D (2008) Individual risk analysis of high-pressure natural gaspipelines Journal of Loss Prevention in the Process Industries 21 (6) 589e595
Kalantarnia M Khan F amp Hawboldt K (2010) Modelling of BP Texas City re1047297neryaccident using dynamic risk assessment approach Process Safety and Environ-mental Protection 88(3) 191e199 (Institution of Chemical Engineers)
Khan F I amp Abbasi S A (1998) Techniques and methodologies for risk analysis inchemical process industries Journal of Loss Prevention in the Process Industries11 261e277
Khan F I amp Abbasi S A (1999a) Major accidents in process industries and ananalysis of causes and consequences Journal of Loss Prevention in the ProcessIndustries 12 361e378
Khan F I amp Abbasi S A (1999b) Assessment of risks posed by chemical indus-triesdapplication of a new computer automated tool MAXCRED-III Journal of Loss Prevention in the Process Industries 12(6) 455e469
Khan F I Sadiq R amp Husain T (2002) Risk-based process safety assessment andcontrol measures design for offshore process facilities Journal of HazardousMaterials 94(1) 1e36
Kletz T A (1999b) The origins and history of loss prevention Transaction IChemE77 109e116
Kletz T A (1999a) What went wrong Case histories of process plant disasters andhow they could have been avoided Houston USA Gulf Professional Publishing
Kletz T A (2003) Still going wrong Case histories of process plant disasters and howthey could have been avoided Houston USA Gulf Professional Publishing
Lees F P (1996) Loss prevention in the process industries (2nd ed) Oxford LondonButterworth Heinemann
Markowski A S (2007) exLOPA for explosion risks assessment Journal of Hazardous Materials 142(3) 669e676
Milazzo M F Lisi R Maschio G Antonioni G Bonvicini S amp Spadoni G (2002)HazMat transport through Messina town from risk analysis suggestions forimproving territorial safety Journal of Loss Prevention in the Process Industries15(5) 347e356
Papazoglou I A Nivolianitou Z Aneziris O Christou M D amp Bonanos G (1999)Risk-informed selection of a highway trajectory in the neighborhood of an oil-re1047297nery Journal of Hazardous Materials 67 (2) 111e144
Pasman H J (2011) History of Dutch process equipment failure frequencies and thepurple book Journal of Loss Prevention in the Process Industries 24 208e213
Pasman H J Jung S Prem K Rogers W J amp Yang X (2009) Is risk analysisa useful tool for improving process safety Journal of Loss Prevention in theProcess Industries 22(6) 769e777
Pintaric Z (2007) Assessment of the consequences of accident scenariosinvolving dangerous substances Process Safety and Environmental Protection85(1) 23e38
Pula R Khan F I Veitch B amp Amyotte P (2006) A grid based approach for 1047297reand explosion consequence analysis Process Safety and Environmental Protec-tion 84(2) 79e91
Reniers G L L (2010) An external domino effects investment approach to improvecross-plant safety within chemical clusters Journal of Hazardous Materials 177 167e174
Reniers G L L amp Dullaert W (2007) DomPrevPlanning user-friendly software forplanning domino effects prevention Safety Science 45(10) 1060e1081
Renjith V R amp Madhu G (2010) Individual and societal risk analysis and mappingof human vulnerability to chemical accidents in the vicinity of an industrialarea International Journal of Applied Engineering Research Dindigul 1 135e148
Rigas F amp Sklavounos S (2002) Risk and consequence analyses of hazardouschemicals in marshalling yards and warehouses at IkonioPiraeus harbourGreece Journal of Loss Prevention in the Process Industries 15(6) 531e544
Salzano Eamp Cozzani V (2005)The analysis of dominoaccidents triggered byvaporcloud explosions Reliability Engineering amp System Safety 90(2e3) 271e284
Spadoni G Egidi D amp Contini S (2000) Through ARIPAR-GIS the quanti 1047297ed arearisk analysis supports land-use planning activities Journal of Hazardous Mate-rials 71(1e3) 423e437
Van Sciver G R (1990) Quantitative risk analysis in the chemical process indus-tries Reliability Engineering amp System Safety 29 55e68
Viacutelchez J A Espejo V amp Casal J (2011) Generic event trees and probabilities forthe release of different types of hazardous materials Journal of Loss Preventionin the Process Industries 24(3) 281e287
Wells G (1997) Major hazards and their management Rugby UK Institution of Chemical Engineers
Yet-Pole IChi-MinS amp Ching-Hong C (2009)Applicationsof 3D QRAtechnique tothe 1047297reexplosion simulation and hazard mitigation within a naphtha-crackingplant Journal of Loss Prevention in the Process Industries 22 (4) 506e515
S Baesi et al Journal of Loss Prevention in the Process Industries 26 (2013) 895e903 903