1 renewable energy in california brian c prusnek deputy cabinet secretary governor arnold...
TRANSCRIPT
1
Renewable Energy in Renewable Energy in CaliforniaCalifornia
Brian C Prusnek
Deputy Cabinet Secretary
Governor Arnold Schwarzenegger
The views and opinions discussed in this presentation are my own and not representative of the Schwarzenegger Administration
2
Background Background By law established in 2002, California
Investor Owned Utilities must procure 20% of their power from renewable resources by 2010.
3
The Major Criticism…The Major Criticism…
“The framework and process for implementing California's policy bears little resemblance to…other states and has…taken longer than…processes used in most states. Indeed, we are unaware of any state RPS process that comes close to approximating the detail, complexity, and duration of the process in California.”[1]
[1] http://www.energy.ca.gov/2005publications/CEC-300-2005-011/CEC-300-2005-011.PDF
4
Detail, Complexity and DurationDetail, Complexity and Duration Unnecessary oversight and process
Utilities go through renewable solicitations AND general solicitations. Solution: Set goal and allow renewables to be treated like other resources
under an Integrated Resource Planning approach. Early fears of above-market costs created additional
process To remedy this, a cost socialization element was created whereby an
administratively established market price, the Market Price Referent (MPR), is set annually.
Renewable projects above the MPR, require that utilities have “above market prices” socialized over entire system rather than from its customers. These above market costs are called Supplemental Energy Payments.
Kill one bird with two stones? The RPS is further complicated because the Public Utilities Commission
determines the MPR and approves renewable contracts whether they are above or below the MPR. But because of existing law, if the cost of the approved project is above the MPR, the utility applies to the Energy Commission for approval to gain access to SEPs.
5
Other ChallengesOther Challenges Only hydro (less than 30MWs) counts Transmission, transmission, transmission
Transmission Lines Planned
300
1,200
400
400
2,400
3,800
3,000
up to 12,000
900
0 2000 4000 6000 8000 10000 12000
Otay Mesa (2007)
Tehachapi (Seg. 1) (2009)
Devers-Palo Verde (2009)
Trans Bay Cable (2010)
Tehachapi (Seg. 2-3) (2010)
Green Path/Sunrise (2010)
Frontier Multi-State (2011)
Tehachapi (Seg. 4-11) (2011)
Trans West Express (2012)
Sea Breeze Cable (2013)
MW
6
Focus on the PositiveFocus on the Positive
RPS based on energy, not capacitySignificant renewable resource opportunitiesFERC decision allows renewable
transmission to be recovered in the Transmission Access Charge
Million Solar Roofs Initiative and world leading energy efficiency programs
Climate change law makes the RPS the floor rather than the ceiling
7
IOU Actual and Forecasted RPS Generation
0
5,000
10,000
15,000
20,000
25,000
30,000
35,000
40,000
45,000
50,00020
03
2004
2005
2006
2007
2008
2009
2010
2011
2012
2013
GW
h
Pre-2002 Contracts 2002 Contracts 2003 Contracts 2004 Contracts 2005 Contracts
2006 Contracts Pending Approval Short-listed Bids Expired Contracts RPS Target
9
Existing California Renewable Generationand Possible Additions to meet the 20% RPS Goal by 2010*
1,977
765
2513
465
1,214
228
4,577
1,300
-
1,000
2,000
3,000
4,000
5,000
6,000
7,000
8,000
Geothermal Biomass Wind Solar
MW Additional
Existing3,191 MW
993 MW
7,090 MW
1,765 MW
* Data on additional renewable resource is based on a current CEC studies on renewables. Potential retirements of existing resources and repowering projects are not included.
13,039 MW Total 7,319 MW Additonal 5,720 MW Existing