SEPTEMBER 18, 2014
POLICY ADVISORY
GROUP
MEETING
![Page 2: 1 PROJECT UPDATES - AlexandriaVA.Gov · 9/18/2014 · Winter 2014 Spring 2014 Fall 2014 Winter 2015 Spring 2015 PLANNING PROCESS PUBLIC PROCESS Project Kick-Off Existing Conditions](https://reader035.vdocuments.us/reader035/viewer/2022071407/60ff0924c6bf591da571d983/html5/thumbnails/2.jpg)
MEETING AGENDA
• Project Updates
• Study Alternatives
• Evaluation Measures
• Next Steps
2
1
2
3
4
![Page 3: 1 PROJECT UPDATES - AlexandriaVA.Gov · 9/18/2014 · Winter 2014 Spring 2014 Fall 2014 Winter 2015 Spring 2015 PLANNING PROCESS PUBLIC PROCESS Project Kick-Off Existing Conditions](https://reader035.vdocuments.us/reader035/viewer/2022071407/60ff0924c6bf591da571d983/html5/thumbnails/3.jpg)
PROJECT UPDATES 1
3
![Page 4: 1 PROJECT UPDATES - AlexandriaVA.Gov · 9/18/2014 · Winter 2014 Spring 2014 Fall 2014 Winter 2015 Spring 2015 PLANNING PROCESS PUBLIC PROCESS Project Kick-Off Existing Conditions](https://reader035.vdocuments.us/reader035/viewer/2022071407/60ff0924c6bf591da571d983/html5/thumbnails/4.jpg)
AA and EA | Timeline
4
1
Winter 2014 Spring 2014 Fall 2014 Winter 2015 Spring 2015
PLANNING PROCESS
PUBLIC PROCESS
Project Kick-Off
Existing Conditions
Definition of Alternatives
May 22 4:00 – 8:00 PM Public Kick-off Meeting Landmark Mall
October 22 6:30 – 8:30 PM Transitway Options Pavillion at Mark Center
Public Meeting to Comment on Study Recommendations
Public Meeting to Review Environmental Document
Purpose and Need
Existing Conditions Assessment
Preliminary Screening of Alternatives
Definition of Evaluation Measures
Results of Evaluation
Draft Environmental Assessment
Preferred Alternative
Final Environmental Assessment
18 Months WE ARE
HERE
Evaluation of Alternatives
Environmental Assessment
![Page 5: 1 PROJECT UPDATES - AlexandriaVA.Gov · 9/18/2014 · Winter 2014 Spring 2014 Fall 2014 Winter 2015 Spring 2015 PLANNING PROCESS PUBLIC PROCESS Project Kick-Off Existing Conditions](https://reader035.vdocuments.us/reader035/viewer/2022071407/60ff0924c6bf591da571d983/html5/thumbnails/5.jpg)
Public Workshop – October 22, 2014
• Location: Pavilion at Mark Center
• Time: 6:30 to 8:30 p.m.
Agenda
• Study Overview and Progress to Date
• Work Groups
oReview Alternatives
oReview Evaluation Approach and Preliminary Outcomes
• Work Group Report-out and Discussion
5
![Page 6: 1 PROJECT UPDATES - AlexandriaVA.Gov · 9/18/2014 · Winter 2014 Spring 2014 Fall 2014 Winter 2015 Spring 2015 PLANNING PROCESS PUBLIC PROCESS Project Kick-Off Existing Conditions](https://reader035.vdocuments.us/reader035/viewer/2022071407/60ff0924c6bf591da571d983/html5/thumbnails/6.jpg)
Additional Public Outreach
• Pop-Up Meetings
• Queen of the Apostle
• Mark Center Transit
Station
• Van Dorn Metro
Station
• Help us get the
word out
• Seminary Towers
• Mark Center
• Others
suggestions?
6
![Page 7: 1 PROJECT UPDATES - AlexandriaVA.Gov · 9/18/2014 · Winter 2014 Spring 2014 Fall 2014 Winter 2015 Spring 2015 PLANNING PROCESS PUBLIC PROCESS Project Kick-Off Existing Conditions](https://reader035.vdocuments.us/reader035/viewer/2022071407/60ff0924c6bf591da571d983/html5/thumbnails/7.jpg)
STUDY ALTERNATIVES 2
7
![Page 8: 1 PROJECT UPDATES - AlexandriaVA.Gov · 9/18/2014 · Winter 2014 Spring 2014 Fall 2014 Winter 2015 Spring 2015 PLANNING PROCESS PUBLIC PROCESS Project Kick-Off Existing Conditions](https://reader035.vdocuments.us/reader035/viewer/2022071407/60ff0924c6bf591da571d983/html5/thumbnails/8.jpg)
Study
Corridor
2
8
![Page 9: 1 PROJECT UPDATES - AlexandriaVA.Gov · 9/18/2014 · Winter 2014 Spring 2014 Fall 2014 Winter 2015 Spring 2015 PLANNING PROCESS PUBLIC PROCESS Project Kick-Off Existing Conditions](https://reader035.vdocuments.us/reader035/viewer/2022071407/60ff0924c6bf591da571d983/html5/thumbnails/9.jpg)
AA Study Alternatives
• Build Alternative
o Frequent, continuous transit service along Van Dorn and Beauregard Streets
o Dedicated transit lanes along significant portions of corridor
o Infrastructure and operational elements to enhance transit operations
• Transportation Systems Management (TSM) Alternative
o Frequent, continuous transit service along Van Dorn and Beauregard Streets
o New, limited-stop bus service along the entirety of the corridor
o Some traffic operational enhancements
o No major capital investment in new infrastructure for dedicated transit lanes
• No Build Alternative
o Transit services in shared lanes similar to current conditions
o Includes already planned and programmed infrastructure, traffic operational and
transit service improvements
2
9
![Page 10: 1 PROJECT UPDATES - AlexandriaVA.Gov · 9/18/2014 · Winter 2014 Spring 2014 Fall 2014 Winter 2015 Spring 2015 PLANNING PROCESS PUBLIC PROCESS Project Kick-Off Existing Conditions](https://reader035.vdocuments.us/reader035/viewer/2022071407/60ff0924c6bf591da571d983/html5/thumbnails/10.jpg)
Elements of the Alternatives
• Systems Operations
• Infrastructure
• Service
2
10
![Page 11: 1 PROJECT UPDATES - AlexandriaVA.Gov · 9/18/2014 · Winter 2014 Spring 2014 Fall 2014 Winter 2015 Spring 2015 PLANNING PROCESS PUBLIC PROCESS Project Kick-Off Existing Conditions](https://reader035.vdocuments.us/reader035/viewer/2022071407/60ff0924c6bf591da571d983/html5/thumbnails/11.jpg)
System Operations
Element No Build Alternative TSM Alternative Build Alternative
Transit Signal Priority Up to 9 locations Up to 13 locations All corridor signalized
intersections
Queue Jump Lanes 1 location 1 location None
Increased Service Some Significant Significant
Transit-Dedicated
Lanes None None
Dedicated Lanes: 2.3 Miles
(42% of Alexandria portion)
+
I-395 HOV Peak Direction
(Mark Center to Pentagon – 5.4
Miles
Shirlington to Pentagon – 3.4 Miles)
Stop or Station
Improvements
Maintain existing transit
stop locations;
Stop improvements at 2
locations
Stop consolidation to
match Build Alternative
station locations;
Stop improvements at 2
locations
Significant stations at all
transitway stops defined
Vehicles Same as agency fleet Same as agency fleet Build Alternative-specific
2
11
![Page 12: 1 PROJECT UPDATES - AlexandriaVA.Gov · 9/18/2014 · Winter 2014 Spring 2014 Fall 2014 Winter 2015 Spring 2015 PLANNING PROCESS PUBLIC PROCESS Project Kick-Off Existing Conditions](https://reader035.vdocuments.us/reader035/viewer/2022071407/60ff0924c6bf591da571d983/html5/thumbnails/12.jpg)
Build Alternative Stations
• Up to two vehicles
• Shelters
• Level or near-level
boarding
• Off-board fare
collection system
• Service-specific
branding
• Real-time service
information display
2
US 1 Metroway station, Source: www.flickr.com/BeyondDC
12
![Page 13: 1 PROJECT UPDATES - AlexandriaVA.Gov · 9/18/2014 · Winter 2014 Spring 2014 Fall 2014 Winter 2015 Spring 2015 PLANNING PROCESS PUBLIC PROCESS Project Kick-Off Existing Conditions](https://reader035.vdocuments.us/reader035/viewer/2022071407/60ff0924c6bf591da571d983/html5/thumbnails/13.jpg)
TSM & Build Alternative Station Locations 2
Van Dorn St Metrorail
Edsall Rd
Landmark Mall
Holmes Run Pkwy S.
Van Dorn/Sanger Ave
Beauregard/ Sanger Ave
Mark Center
Rayburn Ave Southern Towers
Fillmore Ave
W. Braddock Rd S. King St
Shirlington Transit Center
Pentagon Bus Center
13
![Page 14: 1 PROJECT UPDATES - AlexandriaVA.Gov · 9/18/2014 · Winter 2014 Spring 2014 Fall 2014 Winter 2015 Spring 2015 PLANNING PROCESS PUBLIC PROCESS Project Kick-Off Existing Conditions](https://reader035.vdocuments.us/reader035/viewer/2022071407/60ff0924c6bf591da571d983/html5/thumbnails/14.jpg)
Build Alternative Vehicles
• Service-specific low-floor BRT buses with specific branding
2
US 1 Metroway vehicle, Source: www.wmata.com
14
![Page 15: 1 PROJECT UPDATES - AlexandriaVA.Gov · 9/18/2014 · Winter 2014 Spring 2014 Fall 2014 Winter 2015 Spring 2015 PLANNING PROCESS PUBLIC PROCESS Project Kick-Off Existing Conditions](https://reader035.vdocuments.us/reader035/viewer/2022071407/60ff0924c6bf591da571d983/html5/thumbnails/15.jpg)
Infrastructure
Element No Build
Alternative
TSM
Alternative Build Alternative
Modifications by
Others
• Right turn lane westbound Edsall Road at South Van Dorn Street
• Right turn lane northbound South Van Dorn Street at Pickett Street
• I-395 widening and shoulder improvements
• Intersection reconstruction at North Beauregard Street and Seminary Road
Transit Runningway
Modifications None None
• Dedicated Lanes: 2.3 Miles (42% of
Alexandria portion)
• Curbside dedicated lanes: 0.8 miles
• Median dedicated lanes: 1.5 miles
Other Modifications None None
• Shared use bicycle/pedestrian path and
streetscape improvements: 6 locations
• Widen sidewalks: 3 locations
2
15
![Page 16: 1 PROJECT UPDATES - AlexandriaVA.Gov · 9/18/2014 · Winter 2014 Spring 2014 Fall 2014 Winter 2015 Spring 2015 PLANNING PROCESS PUBLIC PROCESS Project Kick-Off Existing Conditions](https://reader035.vdocuments.us/reader035/viewer/2022071407/60ff0924c6bf591da571d983/html5/thumbnails/16.jpg)
Build
Alternative
Runningway
2
16
![Page 17: 1 PROJECT UPDATES - AlexandriaVA.Gov · 9/18/2014 · Winter 2014 Spring 2014 Fall 2014 Winter 2015 Spring 2015 PLANNING PROCESS PUBLIC PROCESS Project Kick-Off Existing Conditions](https://reader035.vdocuments.us/reader035/viewer/2022071407/60ff0924c6bf591da571d983/html5/thumbnails/17.jpg)
Build Alternative Cross Sections 2
Curbside dedicated transit lanes
Median dedicated transit lanes 17
![Page 18: 1 PROJECT UPDATES - AlexandriaVA.Gov · 9/18/2014 · Winter 2014 Spring 2014 Fall 2014 Winter 2015 Spring 2015 PLANNING PROCESS PUBLIC PROCESS Project Kick-Off Existing Conditions](https://reader035.vdocuments.us/reader035/viewer/2022071407/60ff0924c6bf591da571d983/html5/thumbnails/18.jpg)
Median Dedicated Transit – US 1 Metroway
Source: www.flickr.com/BeyondDC
18
![Page 19: 1 PROJECT UPDATES - AlexandriaVA.Gov · 9/18/2014 · Winter 2014 Spring 2014 Fall 2014 Winter 2015 Spring 2015 PLANNING PROCESS PUBLIC PROCESS Project Kick-Off Existing Conditions](https://reader035.vdocuments.us/reader035/viewer/2022071407/60ff0924c6bf591da571d983/html5/thumbnails/19.jpg)
Median Dedicated Transit – US 1 Metroway
Source: www.flickr.com/BeyondDC
19
![Page 20: 1 PROJECT UPDATES - AlexandriaVA.Gov · 9/18/2014 · Winter 2014 Spring 2014 Fall 2014 Winter 2015 Spring 2015 PLANNING PROCESS PUBLIC PROCESS Project Kick-Off Existing Conditions](https://reader035.vdocuments.us/reader035/viewer/2022071407/60ff0924c6bf591da571d983/html5/thumbnails/20.jpg)
2015 Service
Element No Build Alternative TSM Alternative Build Alternative
Transitway
Corridor
Service
• Improved headway: 2 routes
• Change in route: 2 routes
• New Service: 1 route
• Eliminate Service: 2 routes
• Other adjustments: 6 routes
• New service: 1 route
• Eliminate Service: 2 routes
• Other adjustments: 6 routes
Service
Span • Existing service
• Weekdays: 19 daily hours
• Weekends: 17 daily hours
• Weekdays: 19 daily hours
• Weekends: 17 daily hours
Travel Time
Estimate • Existing service • 33 to 40 minutes • 29 to 35 minutes
Vehicles
Required
• Existing service
requirements
• 24-26 peak vehicles on
weekdays
• 8 peak vehicles on
weekends
• 21-24 peak vehicles on
weekdays
• 8 peak vehicles on
weekends
Supporting
Bus Service
• New Service: 1 route
• Decrease headway: 4
routes
• Improve headway: 1 route
• Change in route: 1 route
• No Build changes, plus:
• New service: 1 route
• Eliminate service: 1 route
• Change in route: 1 route
• No Build changes, plus:
• New service: 1 route
• Eliminate service: 1 route
• Change in route: 1 route
2
20
![Page 21: 1 PROJECT UPDATES - AlexandriaVA.Gov · 9/18/2014 · Winter 2014 Spring 2014 Fall 2014 Winter 2015 Spring 2015 PLANNING PROCESS PUBLIC PROCESS Project Kick-Off Existing Conditions](https://reader035.vdocuments.us/reader035/viewer/2022071407/60ff0924c6bf591da571d983/html5/thumbnails/21.jpg)
Transitway Service Options 2
Proposed Weekday Headways:
Van Dorn to Pentagon:
Green Route – 15 peak/30 midday
Blue Route – 15 peak/30 midday
Combined – 7.5 peak/15 midday
Pentagon
21
Proposed Weekday Headways:
Van Dorn Metro-Mark Center:
Red Route – 15 peak/15 midday
Green Route – 7.5 peak/15 midday
Combined – 5 peak/7.5 midday
Mark Center-Shirlington:
Red Route – 15 peak/15 midday
Blue Route – 7.5 peak/15 midday
Combined – 5 peak/7.5 midday
Service to Pentagon:
Green Route – 7.5 peak/15 midday
Blue Route – 7.5 peak/15 midday
![Page 22: 1 PROJECT UPDATES - AlexandriaVA.Gov · 9/18/2014 · Winter 2014 Spring 2014 Fall 2014 Winter 2015 Spring 2015 PLANNING PROCESS PUBLIC PROCESS Project Kick-Off Existing Conditions](https://reader035.vdocuments.us/reader035/viewer/2022071407/60ff0924c6bf591da571d983/html5/thumbnails/22.jpg)
2015 No Build
Transit Service
2
22
![Page 23: 1 PROJECT UPDATES - AlexandriaVA.Gov · 9/18/2014 · Winter 2014 Spring 2014 Fall 2014 Winter 2015 Spring 2015 PLANNING PROCESS PUBLIC PROCESS Project Kick-Off Existing Conditions](https://reader035.vdocuments.us/reader035/viewer/2022071407/60ff0924c6bf591da571d983/html5/thumbnails/23.jpg)
2035 No Build
Transit Service
2
23
![Page 24: 1 PROJECT UPDATES - AlexandriaVA.Gov · 9/18/2014 · Winter 2014 Spring 2014 Fall 2014 Winter 2015 Spring 2015 PLANNING PROCESS PUBLIC PROCESS Project Kick-Off Existing Conditions](https://reader035.vdocuments.us/reader035/viewer/2022071407/60ff0924c6bf591da571d983/html5/thumbnails/24.jpg)
2 2015 and 2035
TSM and Build
Transit Service
24
![Page 25: 1 PROJECT UPDATES - AlexandriaVA.Gov · 9/18/2014 · Winter 2014 Spring 2014 Fall 2014 Winter 2015 Spring 2015 PLANNING PROCESS PUBLIC PROCESS Project Kick-Off Existing Conditions](https://reader035.vdocuments.us/reader035/viewer/2022071407/60ff0924c6bf591da571d983/html5/thumbnails/25.jpg)
EVALUATION MEASURES 3
25
![Page 26: 1 PROJECT UPDATES - AlexandriaVA.Gov · 9/18/2014 · Winter 2014 Spring 2014 Fall 2014 Winter 2015 Spring 2015 PLANNING PROCESS PUBLIC PROCESS Project Kick-Off Existing Conditions](https://reader035.vdocuments.us/reader035/viewer/2022071407/60ff0924c6bf591da571d983/html5/thumbnails/26.jpg)
EVALUATION PROCESS
• Evaluation measures
needed to determine
performance of alternatives
• Performance of alternatives
will determine Locally
Preferred Alternative
• Effects of Locally Preferred
Alternative will be
documented in the
Environmental Assessment
3
26
WE ARE HERE
![Page 27: 1 PROJECT UPDATES - AlexandriaVA.Gov · 9/18/2014 · Winter 2014 Spring 2014 Fall 2014 Winter 2015 Spring 2015 PLANNING PROCESS PUBLIC PROCESS Project Kick-Off Existing Conditions](https://reader035.vdocuments.us/reader035/viewer/2022071407/60ff0924c6bf591da571d983/html5/thumbnails/27.jpg)
DRAFT EVALUATION MEASURES
Transit
• Ridership
• Coverage
• Transit Connectivity
• Transit Operations
Traffic Operations
• Intersection LOS/Delay
• Intersection Queuing
• Vehicular Travel Time
Bicycles and Pedestrians
Land Use
Financial
Environmental
3
27
![Page 28: 1 PROJECT UPDATES - AlexandriaVA.Gov · 9/18/2014 · Winter 2014 Spring 2014 Fall 2014 Winter 2015 Spring 2015 PLANNING PROCESS PUBLIC PROCESS Project Kick-Off Existing Conditions](https://reader035.vdocuments.us/reader035/viewer/2022071407/60ff0924c6bf591da571d983/html5/thumbnails/28.jpg)
NEXT STEPS 4
28
![Page 29: 1 PROJECT UPDATES - AlexandriaVA.Gov · 9/18/2014 · Winter 2014 Spring 2014 Fall 2014 Winter 2015 Spring 2015 PLANNING PROCESS PUBLIC PROCESS Project Kick-Off Existing Conditions](https://reader035.vdocuments.us/reader035/viewer/2022071407/60ff0924c6bf591da571d983/html5/thumbnails/29.jpg)
AA and EA | NEXT STEPS
October 2014
• Evaluation of Alternatives and Revised Definition of Alternatives
• Public Meeting October 22, 2014 at 6:30 p.m.
• PAG Meeting October 23, 2014 at 7:00 p.m.
November 2014
• Build Alternative Concept Engineering
• PAG Meeting Date TBD
December 2014
• Alternatives Analysis Report
• Request to Enter Project Development
4
29
Thank you!