1 project scheduling faculty of applied engineering and urban planning civil engineering department...
TRANSCRIPT
![Page 1: 1 Project Scheduling Faculty of Applied Engineering and Urban Planning Civil Engineering Department Week ( 6 + 7 ) Lec. ( 11 + 12 + 13 + 14 ) 2 nd Semester](https://reader035.vdocuments.us/reader035/viewer/2022081519/56649ea05503460f94ba3c83/html5/thumbnails/1.jpg)
11
Project Scheduling
Faculty of Applied Engineering and Urban Planning
Civil Engineering Department
Week ( 6 + 7 )
Lec. ( 11 + 12 + 13 + 14 )
2nd Semester 2008/2009
UP Copyrights 2008
Const
ruct
ion P
roje
ct
Managem
ent
Eng: Eyad Haddad
![Page 2: 1 Project Scheduling Faculty of Applied Engineering and Urban Planning Civil Engineering Department Week ( 6 + 7 ) Lec. ( 11 + 12 + 13 + 14 ) 2 nd Semester](https://reader035.vdocuments.us/reader035/viewer/2022081519/56649ea05503460f94ba3c83/html5/thumbnails/2.jpg)
22
CH4: Project SchedulingCH4: Project Scheduling
Construction Project management functions:Construction Project management functions:
Scheduling = Planning + TimeScheduling = Planning + Time
SchedulingScheduling is the determination of the timing of the activities comprising
the project to enable managers to execute the project in a timely manner.
1. Planningتخطيط
2. Organizationتنظيم
3. Supervisionمراقبه
4. Controlتحكم
1. Timeالوقت
2. Costالتكلفة
3. Qualityالجودة
4. Performanceاالنجاز
Scheduling
![Page 3: 1 Project Scheduling Faculty of Applied Engineering and Urban Planning Civil Engineering Department Week ( 6 + 7 ) Lec. ( 11 + 12 + 13 + 14 ) 2 nd Semester](https://reader035.vdocuments.us/reader035/viewer/2022081519/56649ea05503460f94ba3c83/html5/thumbnails/3.jpg)
33
CH4: Project SchedulingCH4: Project Scheduling
The project scheduling is used for:
1. Knowing the activities timing and the project completion time.
2. Having resources available on site in the correct time.
3. Making correction actions if schedule shows that the plan will result in
late completion.
4. Assessing the value of penalties on project late completion.
5. Determining the project cash flow.
6. Evaluating the effect of change orders on the project completion time.
7. Determining the value of project delay and the responsible parties.
![Page 4: 1 Project Scheduling Faculty of Applied Engineering and Urban Planning Civil Engineering Department Week ( 6 + 7 ) Lec. ( 11 + 12 + 13 + 14 ) 2 nd Semester](https://reader035.vdocuments.us/reader035/viewer/2022081519/56649ea05503460f94ba3c83/html5/thumbnails/4.jpg)
44
4.2 The Critical Path Method (CPM)4.2 The Critical Path Method (CPM)
The critical path can be defined as
the longest possible path through the "network" of project activities.
(CPM)(CPM) is the most widely technique used for scheduling, it calculates the
minimum completion time for a project along with the possible start and
finish times for the project activities.
![Page 5: 1 Project Scheduling Faculty of Applied Engineering and Urban Planning Civil Engineering Department Week ( 6 + 7 ) Lec. ( 11 + 12 + 13 + 14 ) 2 nd Semester](https://reader035.vdocuments.us/reader035/viewer/2022081519/56649ea05503460f94ba3c83/html5/thumbnails/5.jpg)
55
4.2 The Critical Path Method (CPM)4.2 The Critical Path Method (CPM)
The critical path itself represents the set or sequence of activities
which will take the longest time to complete.
The duration of the critical path is the sum of the activities'
durations along the path.
Duration of the critical path represents the minimum timeminimum time required
to complete a project.
Any delays along the critical path would delay the project.
More than one critical path may be among all the project activities,
so completion of the entire project could be delayed by delaying
activities along any one of the critical paths.
![Page 6: 1 Project Scheduling Faculty of Applied Engineering and Urban Planning Civil Engineering Department Week ( 6 + 7 ) Lec. ( 11 + 12 + 13 + 14 ) 2 nd Semester](https://reader035.vdocuments.us/reader035/viewer/2022081519/56649ea05503460f94ba3c83/html5/thumbnails/6.jpg)
66
4.2 The Critical Path Method (CPM)4.2 The Critical Path Method (CPM)
For example,
a project consisting of two activities performed in parallel that each
requires three days would have each activity critical for a completion in
three days.
Critical path scheduling assumes that a project has been divided into
activities of fixed duration and well defined predecessor relationships.
A predecessor relationship implies that one activity must come
before another in the schedule
![Page 7: 1 Project Scheduling Faculty of Applied Engineering and Urban Planning Civil Engineering Department Week ( 6 + 7 ) Lec. ( 11 + 12 + 13 + 14 ) 2 nd Semester](https://reader035.vdocuments.us/reader035/viewer/2022081519/56649ea05503460f94ba3c83/html5/thumbnails/7.jpg)
77
The CPM is a systematic scheduling method for a project network and involves
four main steps:
1. A forward path to determine activities early-start timesearly-start times;
2. A backward path to determine activities late-finish timeslate-finish times;
3. Float calculations ( Free & Total ) float; and
4. Identifying critical activities.
![Page 8: 1 Project Scheduling Faculty of Applied Engineering and Urban Planning Civil Engineering Department Week ( 6 + 7 ) Lec. ( 11 + 12 + 13 + 14 ) 2 nd Semester](https://reader035.vdocuments.us/reader035/viewer/2022081519/56649ea05503460f94ba3c83/html5/thumbnails/8.jpg)
88
4.3.1 Activity-on-node networks calculations
The objective of arrow network analysis is to compute each event in the
network its early and late timings. These times are defined as
Early event time (ET)Early event time (ET) is the earliest time at which an event can occur,
considering the duration of preceding activities.
Late event time (LT)Late event time (LT) Is the latest time at which an event can occur if the
project is to be completed on schedule.
i jx
ETj LTjETi LTi
dx
11 . .Forward PathForward Path::
ETj = ETi + dxETj = ETi + dx
![Page 9: 1 Project Scheduling Faculty of Applied Engineering and Urban Planning Civil Engineering Department Week ( 6 + 7 ) Lec. ( 11 + 12 + 13 + 14 ) 2 nd Semester](https://reader035.vdocuments.us/reader035/viewer/2022081519/56649ea05503460f94ba3c83/html5/thumbnails/9.jpg)
99
11 . .Forward PathForward Path::
1 3
5
7
9 11
0
ProjectStart=0
Ad=3
C4
E5
B3
D
6 d2
d13
Es+d=EF
6
3+3=6
0+3=3
9
6+0=63+4=79+0=9
14
9+5=14
9
3+6=9
1A
ProjectStart=0
1A
![Page 10: 1 Project Scheduling Faculty of Applied Engineering and Urban Planning Civil Engineering Department Week ( 6 + 7 ) Lec. ( 11 + 12 + 13 + 14 ) 2 nd Semester](https://reader035.vdocuments.us/reader035/viewer/2022081519/56649ea05503460f94ba3c83/html5/thumbnails/10.jpg)
1010
22 . .Backward PathBackward Path LS = LF – dLS = LF – d
1 3
5
7
9 11
0 0
3-3=0
A3
C4
E5
B3
D
6 d2
d13 3
9-4=5
6 9
9-0=9
9-6=3
9 9
14-5=9LF-d=LS
14 14
9 9
9-0=9
9-3=6
![Page 11: 1 Project Scheduling Faculty of Applied Engineering and Urban Planning Civil Engineering Department Week ( 6 + 7 ) Lec. ( 11 + 12 + 13 + 14 ) 2 nd Semester](https://reader035.vdocuments.us/reader035/viewer/2022081519/56649ea05503460f94ba3c83/html5/thumbnails/11.jpg)
1111
3. Float Calculations:
First, let's tabulate the information we have as shown in next Table
One important aspect is Total-Float (TF) calculations, which determine the
flexibility of an activity to be delayed.
Total Float (TF) = LF – EF
= LS – ES
.TFمالحظة : الواحد للنشاط يستخدم دوما
Free Float (FF) = ETj – ETi – d
or FF = smallest ES (of succeeding activities) – EF (of current activity)
.FFمالحظة : والالحق السابق للنشاطين يستخدم دوما
![Page 12: 1 Project Scheduling Faculty of Applied Engineering and Urban Planning Civil Engineering Department Week ( 6 + 7 ) Lec. ( 11 + 12 + 13 + 14 ) 2 nd Semester](https://reader035.vdocuments.us/reader035/viewer/2022081519/56649ea05503460f94ba3c83/html5/thumbnails/12.jpg)
1212
3. Float Calculations:
Total Float (TF) = LF – EF
= LS – ES
.TFمالحظة : الواحد للنشاط يستخدم دوما
Free Float (FF) = ETj – ETi – d
or FF = smallest ES (of succeeding activities) – EF (of current activity)
.FFمالحظة : والالحق السابق للنشاطين يستخدم دوما
i j
ES EF
A
LS LF
AOA
ES EF
ES EF
A
B
LS LF
LS LF
ES EF
A
LS LF
AON
TF
i j
ES EF
A
LS LF
AOA
i j
ES EF
B
LS LF
AOA
![Page 13: 1 Project Scheduling Faculty of Applied Engineering and Urban Planning Civil Engineering Department Week ( 6 + 7 ) Lec. ( 11 + 12 + 13 + 14 ) 2 nd Semester](https://reader035.vdocuments.us/reader035/viewer/2022081519/56649ea05503460f94ba3c83/html5/thumbnails/13.jpg)
1313
Total Float (TF) = LF – EF = LS – ES
Free Float (FF) = ETj – ETi – d
or FF = smallest ES (of succeeding activities) – EF (of current
activity)
ActivityDurationEarly Start
)ES(
Late Start
)LS(
Early Finish
)EF(
Late Finish
)LF(
Total Float
)TF(
CriticalActivity
AA3300003300YesYes
BB3333666933NoNo
CC4433557922NoNo
DD6633339900YesYes
EE559999141400YesYes
![Page 14: 1 Project Scheduling Faculty of Applied Engineering and Urban Planning Civil Engineering Department Week ( 6 + 7 ) Lec. ( 11 + 12 + 13 + 14 ) 2 nd Semester](https://reader035.vdocuments.us/reader035/viewer/2022081519/56649ea05503460f94ba3c83/html5/thumbnails/14.jpg)
1414
4.3.2 Precedence Diagram Method (PDM):
Precedence Diagram Method (PDM) is the CPM scheduling method used for AON
networks and it follows the same four steps of the CPM for AOA method.
Forward PathForward Path
Forward path can proceed from one activity to the other; the process is as
follow .3 6
B(3)
3 7
C(4)
3 9
D(6)
0 3
A(3)
9 14
E(5)
Early start
Name (duration)
Early finish
Late start
Late finish
6,7,or 9
Fig. 4.8: Forward Path in PDM Analysis
![Page 15: 1 Project Scheduling Faculty of Applied Engineering and Urban Planning Civil Engineering Department Week ( 6 + 7 ) Lec. ( 11 + 12 + 13 + 14 ) 2 nd Semester](https://reader035.vdocuments.us/reader035/viewer/2022081519/56649ea05503460f94ba3c83/html5/thumbnails/15.jpg)
1515
Backward PathBackward Path::
3 6
B(3)
3 7
C(4)
3 9
D(6)
0 3
A(3)
9 14
E(5)
Early start
Name (duration)
Early finish
Late start
Late finish
6,5 ,or 3
149
96
95
93
30
![Page 16: 1 Project Scheduling Faculty of Applied Engineering and Urban Planning Civil Engineering Department Week ( 6 + 7 ) Lec. ( 11 + 12 + 13 + 14 ) 2 nd Semester](https://reader035.vdocuments.us/reader035/viewer/2022081519/56649ea05503460f94ba3c83/html5/thumbnails/16.jpg)
1616
FloatsFloats
Activity A7 days
Activity B13 days
Activity C4 days
Start CompletionProject duration = 24 days
CASE 1: All activities are critical: total float and free floats for all activities = 0
Activity A7 days
Activity B13 days
Activity C4 days
Start CompletionTotal Float = 5Free Float = 5
CASE 2: Activity sequence in which one activity has total and free float
Activity D8 days
Activity A7 days
Activity B13 days
Activity C4 days
Start Completion
Total Float of D = 5 Total Float of E = 5Free Float of D = 0 Free Float = 5
CASE 3: Activity sequence illustrating total and free float
Activity D5 days
Activity E3 days
![Page 17: 1 Project Scheduling Faculty of Applied Engineering and Urban Planning Civil Engineering Department Week ( 6 + 7 ) Lec. ( 11 + 12 + 13 + 14 ) 2 nd Semester](https://reader035.vdocuments.us/reader035/viewer/2022081519/56649ea05503460f94ba3c83/html5/thumbnails/17.jpg)
1717
Floats - 2Floats - 2
Areas of shared float
Activity duration Total Float
Start Event Finish Event
TLi TEjTEi TLj
Activity duration Free Float
Activity duration Independent Float
![Page 18: 1 Project Scheduling Faculty of Applied Engineering and Urban Planning Civil Engineering Department Week ( 6 + 7 ) Lec. ( 11 + 12 + 13 + 14 ) 2 nd Semester](https://reader035.vdocuments.us/reader035/viewer/2022081519/56649ea05503460f94ba3c83/html5/thumbnails/18.jpg)
1818
Float CalculationsFloat Calculations::
Total Float (TF) = LF – EF = LS – ES
Free Float (FF) = ETj – ETi – d
Duration
3
3
4
65
ES
0
3
3
39
LF
3
9
9
914
LS
0
6
5
39
EF
3
6
7
914
TF
0
3
2
00
Activity
A
B
C
DE
Critical Act.
Yes
No
No
YesYes
![Page 19: 1 Project Scheduling Faculty of Applied Engineering and Urban Planning Civil Engineering Department Week ( 6 + 7 ) Lec. ( 11 + 12 + 13 + 14 ) 2 nd Semester](https://reader035.vdocuments.us/reader035/viewer/2022081519/56649ea05503460f94ba3c83/html5/thumbnails/19.jpg)
1919
A3
B3
C5
D7
E4
F6
G4
I9
H6
J8
Fn
12 20
10 166 10
6 12
8 12
10 19
3 6
3 8
3 10
0 3
12 20
14 208 12
6 12
8 12
11 20
3 6
3 8
4 11
0 3
ActDur
ES EF
LS LF
TF/FF
PDM Calculations PDM Calculations (PDM = (PDM = PPrecedence recedence DDiagram iagram MMethod)ethod) ExampleExample
0/0
0/ 0
0/ 0
1/ 0
2/ 0
0/ 0
0/0
1/1
4/4
0/0
TF/FFTFi = LFi - EFi
Free Float (FF) = ETj – ETi – d
or FF = smallest ES (of succeeding activities) – EF (of current
activity)
![Page 20: 1 Project Scheduling Faculty of Applied Engineering and Urban Planning Civil Engineering Department Week ( 6 + 7 ) Lec. ( 11 + 12 + 13 + 14 ) 2 nd Semester](https://reader035.vdocuments.us/reader035/viewer/2022081519/56649ea05503460f94ba3c83/html5/thumbnails/20.jpg)
2020
PPrecedence recedence RRelationships - Lead & Lagelationships - Lead & Lag
FFij Lag time for a finish-to-finish relationship. (The succeeding activity finishes this amount of time after the completion of the preceding activity.)
SSij Lead time for a start-to-start relationship. (The preceding activity starts this much earlier than the start of the succeeding activity.)
FSij Lag time for a finish-to-finish relationship. (The succeeding activity starts this amount of time after the completion of the preceding activity.)
SFij Lead time for a start-to-finish relationship. (The preceding activity starts this much earlier than the completion of the succeeding activity.)
![Page 21: 1 Project Scheduling Faculty of Applied Engineering and Urban Planning Civil Engineering Department Week ( 6 + 7 ) Lec. ( 11 + 12 + 13 + 14 ) 2 nd Semester](https://reader035.vdocuments.us/reader035/viewer/2022081519/56649ea05503460f94ba3c83/html5/thumbnails/21.jpg)
2121
PRECEDENCE LOGICPRECEDENCE LOGIC1. Preceding Activities. السابقة الفعاليات
Which activities must be finished before this activity may begin ?
What is the time lag? (finish to start.)
Which activities must be started before this activity may begin?
What is the lead time (start to start.)
Which activities must be finished before this activity may be completed?
What is the lag time? (Finish to finish)
Which activities must be started before this activity is completed?
What is the lead time ? (start to finish.)
![Page 22: 1 Project Scheduling Faculty of Applied Engineering and Urban Planning Civil Engineering Department Week ( 6 + 7 ) Lec. ( 11 + 12 + 13 + 14 ) 2 nd Semester](https://reader035.vdocuments.us/reader035/viewer/2022081519/56649ea05503460f94ba3c83/html5/thumbnails/22.jpg)
R. RUSTOMR. RUSTOM 2222
Follow: PRECEDENCE LOGICFollow: PRECEDENCE LOGIC
2. Succeeding Activities الالحقة الفعاليات
Which activities can begin after the finish of this activity?
What is the time lag? (finish to start.)
Which activities can begin after the start of this activity?
What is the lead time? ( Start to start )
Which activities can be completed after the finish of this activity?
What is the lag time? (Finish to finish.)
Which activities can finish after the start of this activity? What is the lead time? (Start to finish.)
3. Concurrent Activities.
Which activities can be carried out at the same time?
(Start to start equals zero, that is, SS = 0 in this case.)
![Page 23: 1 Project Scheduling Faculty of Applied Engineering and Urban Planning Civil Engineering Department Week ( 6 + 7 ) Lec. ( 11 + 12 + 13 + 14 ) 2 nd Semester](https://reader035.vdocuments.us/reader035/viewer/2022081519/56649ea05503460f94ba3c83/html5/thumbnails/23.jpg)
2323
Lead/Lag RelationshipsLead/Lag Relationships
ES DESC. EF ES DESC. EF
FF ij
FS ij
SS ij
SF ij
Forward Pass
Backward Pass
i Dij Dj
LS DESC. LF LS DESC. LF
FF jk
FS jk
SS jk
SF jk
j Djk Dk
![Page 24: 1 Project Scheduling Faculty of Applied Engineering and Urban Planning Civil Engineering Department Week ( 6 + 7 ) Lec. ( 11 + 12 + 13 + 14 ) 2 nd Semester](https://reader035.vdocuments.us/reader035/viewer/2022081519/56649ea05503460f94ba3c83/html5/thumbnails/24.jpg)
2424
PDM Activity Diagramming MethodsPDM Activity Diagramming Methods
Activity No.
Duration RESP.
Star
t Sid
e
Fini
sh S
ide
METHOD 1METHOD 1METHOD 1METHOD 1
Activity No.
Duration RESP.
Star
t Sid
e
Fini
sh S
ide
METHOD 2METHOD 2METHOD 2METHOD 2
DESCRIPTION DESCRIPTION
ES
LS
EF
LF
Activity No.
LS LF
Star
t Sid
e
Fini
sh S
ide
METHOD 3METHOD 3METHOD 3METHOD 3
Activity No.
Star
t Sid
e
Fini
sh S
ide
METHOD 4METHOD 4METHOD 4METHOD 4
DESCRIPTION DESCRIPTION
ES
LS
EF
LF
DUR TF
ES EFDuration RESP.
![Page 25: 1 Project Scheduling Faculty of Applied Engineering and Urban Planning Civil Engineering Department Week ( 6 + 7 ) Lec. ( 11 + 12 + 13 + 14 ) 2 nd Semester](https://reader035.vdocuments.us/reader035/viewer/2022081519/56649ea05503460f94ba3c83/html5/thumbnails/25.jpg)
2525
Logical Relationships of PDMLogical Relationships of PDM
12
FINISH - TO - STARTFINISH - TO - STARTFINISH - TO - STARTFINISH - TO - START
Layout & Excavate
2 GO
12Install exterior
Conduit & piping
5 EL
20
FINISH - TO - FINISHFINISH - TO - FINISHFINISH - TO - FINISHFINISH - TO - FINISH
Install fuel tanks
2 GO
12Install exterior
Conduit & piping
5 EL
10
Contract Award
2 GO
10
Layout & Excavate
2 GO
START - TO - FINISHSTART - TO - FINISHSTART - TO - FINISHSTART - TO - FINISH
12
Layout & Excavate
2 GO
18
Install fuel tanks
2 ME
START - TO - STARTSTART - TO - STARTSTART - TO - STARTSTART - TO - START
12
Layout & Excavate
2 GO
12Install exterior
Conduit & piping
5 EL
Relationship with LagRelationship with LagRelationship with LagRelationship with Lag
1
![Page 26: 1 Project Scheduling Faculty of Applied Engineering and Urban Planning Civil Engineering Department Week ( 6 + 7 ) Lec. ( 11 + 12 + 13 + 14 ) 2 nd Semester](https://reader035.vdocuments.us/reader035/viewer/2022081519/56649ea05503460f94ba3c83/html5/thumbnails/26.jpg)
PDM Calculation ProcedurePDM Calculation Procedure(Assumes no splitting of activity is allowed)(Assumes no splitting of activity is allowed)
F O R W A R D P A T H
S t e p 1
jiji
jiji
iji
iji
j
DSFES
DFFEF
SSES
FSEF
MaxES
1
S t e p 2
jjj DESEF
![Page 27: 1 Project Scheduling Faculty of Applied Engineering and Urban Planning Civil Engineering Department Week ( 6 + 7 ) Lec. ( 11 + 12 + 13 + 14 ) 2 nd Semester](https://reader035.vdocuments.us/reader035/viewer/2022081519/56649ea05503460f94ba3c83/html5/thumbnails/27.jpg)
2727
Follow PDM Calculation ProcedureFollow PDM Calculation Procedure
B A C K W A R D P A T H
S t e p 1
iijj
iijj
ijj
ijj
i
DSFLF
DSSLS
FFLF
FSLS
alTimeTer
MinLF
min
S t e p 2
iii DLFLS
![Page 28: 1 Project Scheduling Faculty of Applied Engineering and Urban Planning Civil Engineering Department Week ( 6 + 7 ) Lec. ( 11 + 12 + 13 + 14 ) 2 nd Semester](https://reader035.vdocuments.us/reader035/viewer/2022081519/56649ea05503460f94ba3c83/html5/thumbnails/28.jpg)
2828
Calculation of Total Float and Free FloatCalculation of Total Float and Free Float
Total Float
iii EFLFTF Free Float
iijj
iijj
iijj
iijj
ESSFEF
EFFFEF
ESSSES
EFFSES
![Page 29: 1 Project Scheduling Faculty of Applied Engineering and Urban Planning Civil Engineering Department Week ( 6 + 7 ) Lec. ( 11 + 12 + 13 + 14 ) 2 nd Semester](https://reader035.vdocuments.us/reader035/viewer/2022081519/56649ea05503460f94ba3c83/html5/thumbnails/29.jpg)
2929
A10
B7
C10
D10
E4
F3
G10
H15
I7
K5
L5
J3
M6
N8
SS5
FS2
FF2
SS5
FF1
FS5
FS3
SF7
SS2
SS10, FF2
FS2
SS3
FF2, SS1
FS1
FF0
1 11
6 13
11 21
11 21
7 11
15 18
21 31
16 31
16 23
23 28
28 33
11 14
31 37
38 46
38 46
ESi + SSij1 +5 = 6
EFi + FFi - Di11 + 0 - 4
FS0
FS0
EFi + FSij13 + 2
ESi + SFij - Dj15 + 7 -5
EFi + FFij - Dj28 + 2 - 8
ESi + SSij 23 + 1
EFi + FFij-Dj 13 + 2 -10
FS0ESi +SSij11 + 5
EFi + FFij - Dj21 + 1 - 7
EFi + FSij11 +5
ESi + SSij21 + 2
ESi + SSij16 + 10
EFi + FFij - Dj31 + 2 - 5
EFi+FSij23 + 2
FS0
EFi + FSij14 + 3
ESi+SSij28+3
EFij+FSij37+1
FORWARD PASS
![Page 30: 1 Project Scheduling Faculty of Applied Engineering and Urban Planning Civil Engineering Department Week ( 6 + 7 ) Lec. ( 11 + 12 + 13 + 14 ) 2 nd Semester](https://reader035.vdocuments.us/reader035/viewer/2022081519/56649ea05503460f94ba3c83/html5/thumbnails/30.jpg)
3030
A10
B7
C10
D10
E4
F3
G10
H15
I7
K5
L5
J3
M6
N8
SS5
FS2
FF2
SS5
FF1
FS5
FS3
SF7
SS2
SS10, FF2
FS2
SS3
FF2, SS1
FS1
FF0
38 46
38 4631 37
31 37
23 28
37 42
28 33
28 33
11 14
25 28
15 18
35 38
21 31
35 45
16 31
16 3116 23
19 26
6 13
26 3311 21
11 21
11 21
15 25
7 11
11 14
1 11
1 11
LFj - FFij46 - 2
LSj - SSj - Di38 - 1 + 5
LSj - FSij38 - 1
LSj - SSij + Di31 - 3 + 5
LSj - FSij31 - 3
LFj - Sfij + Di42 - 7 + 3
LSj - SSij + Di 37 - 2 + 10
LFi - FFij33 - 2
LSj - SSij + Di28 - 10 + 15
LSj - FSij28 - 2
LSj - FSij19 - 5
LFj - FFij26 - 1
LSj - SSij + Di 16 - 5 + 10
FS0
LSj - FSij35 - 2
LSj - SSij + Di26 - 5 + 10
SF0
SF0
SF0
LFj - FFij45 - 2
BACKWARD PASS
![Page 31: 1 Project Scheduling Faculty of Applied Engineering and Urban Planning Civil Engineering Department Week ( 6 + 7 ) Lec. ( 11 + 12 + 13 + 14 ) 2 nd Semester](https://reader035.vdocuments.us/reader035/viewer/2022081519/56649ea05503460f94ba3c83/html5/thumbnails/31.jpg)
3131
A10
B7
C10
D10
E4
F3
aG10
H15
I7
K5
L5
J3
M6
N8
SS5
FS2
FF2
SS5
FF1
FS5
FS3
SF7
SS2
SS10, FF2
FS2
SS3
FF2, SS1
FS1
FF0
38 46
38 4631 37
31 37
28 33
28 33
11 14
25 28
23 28
37 42
15 18
35 38
21 31
35 45
16 31
16 31
16 23
19 26
6 13
26 33
11 21
11 21
11 21
15 25
7 11
11 14
1 11
1 11
ESj - SSij - ESi6-5-1
ESj - FSij - EFi15 - 2-13
ESj - Sfij - ESi28 - 7 - 15 ESj - SSij - ESi
38 - 1 - 23
EFj - FFij - EFi46 - 2 - 28
ESj - FSij - EFi38 - 1 - 37
ESj - FSij - EFi31 - 3 - 14
ESj - FSij - EFi11 - 0 - 11
ESj - FFij -EFi11 - 0 - 11
EFj - FFij - EFi31 - 2 - 13
ESj - SSij - ESi16 - 5 - 11
ESj - FSij -EFi21 - 0 - 21
FS0
ESj - FFij - EFi23 - 1 - 21
ESj - FSij - EFi16 - 5 - 11
FS0
ESj - SSij - ESi23 - 2 - 21
ESj - FSij - EFi28 - 2 - 23
EFj - FFij - EFi33 - 2 - 31
ESj - SSij - ESi28 - 10 - 16
ESj - SSij - ESi31 - 3 28
0/0
20/0
0/0
4/1
3/0
20/0
14/0
0/0
3/3
14/14
0/0
14/14
0/0
0/0FS0
FS0
ESj - FSij - ESj11 - 0 - 1
ESj - FSij - Efi11 - 0 - 11
TF/FFTFi = LFi - EFi
![Page 32: 1 Project Scheduling Faculty of Applied Engineering and Urban Planning Civil Engineering Department Week ( 6 + 7 ) Lec. ( 11 + 12 + 13 + 14 ) 2 nd Semester](https://reader035.vdocuments.us/reader035/viewer/2022081519/56649ea05503460f94ba3c83/html5/thumbnails/32.jpg)
3232
4.4 Time-Scaled Diagrams:Time-scaled diagrams are used extensively in the construction industry. Such diagrams enable one to determine immediately which activities are scheduled to proceed at any point in time . to monitor field progress. it can be used to determine resources need. The time scale used in time-scaled diagrams can be either the calendar dates or the working periods (ordinary dates), or using both at the same time.Its disadvantage is that it needs a great effort to be modified or updated. Also, it can not be used torepresent overlapping activities.
A3
C4
B3
D6
E5
3
2
Time-scaled diagram
1 2 3 4 5 6 7 8 9 10 11 12 13 14
![Page 33: 1 Project Scheduling Faculty of Applied Engineering and Urban Planning Civil Engineering Department Week ( 6 + 7 ) Lec. ( 11 + 12 + 13 + 14 ) 2 nd Semester](https://reader035.vdocuments.us/reader035/viewer/2022081519/56649ea05503460f94ba3c83/html5/thumbnails/33.jpg)
3333
The TF for activity A equals the smallest of the sum of the floats along all paths from the end of activity A to the end of the project. The float on path ABE = 3, path ACE = 2 and path ADE = 0, then the TF of activity A = 0. The calculations are shown in Table 4.2.
Table 4.2 Time-scaled diagram calculations
![Page 34: 1 Project Scheduling Faculty of Applied Engineering and Urban Planning Civil Engineering Department Week ( 6 + 7 ) Lec. ( 11 + 12 + 13 + 14 ) 2 nd Semester](https://reader035.vdocuments.us/reader035/viewer/2022081519/56649ea05503460f94ba3c83/html5/thumbnails/34.jpg)
3434
4.54.5 Schedule PresentationSchedule Presentation::
After the AOA and AON calculations are made, it is important to present their results in a format that is clear and understandable to all the parties involved in the project. The simplest form is the Bar chart or Gantt chart, named after the person who first used it. A bar chart is a time versus activity chart in which activities are plotted using their early or late times .
a) Early bar chat
b) Late bar chart
![Page 35: 1 Project Scheduling Faculty of Applied Engineering and Urban Planning Civil Engineering Department Week ( 6 + 7 ) Lec. ( 11 + 12 + 13 + 14 ) 2 nd Semester](https://reader035.vdocuments.us/reader035/viewer/2022081519/56649ea05503460f94ba3c83/html5/thumbnails/35.jpg)
3535
The bar chart representationThe bar chart representation::
It shows various details. Float times of activities, critical activities can be shown in a different color, or bold borders, as shown in Figure 4.12. The bar chart can also be used for accumulating total daily resources and / or costs, as shown at the bottom part of Figure 6.13. In this figure, the numbers on each activity represent the number of labors needed.
Figure 4.13: Using bar chart to accumulate resources
![Page 36: 1 Project Scheduling Faculty of Applied Engineering and Urban Planning Civil Engineering Department Week ( 6 + 7 ) Lec. ( 11 + 12 + 13 + 14 ) 2 nd Semester](https://reader035.vdocuments.us/reader035/viewer/2022081519/56649ea05503460f94ba3c83/html5/thumbnails/36.jpg)
3636
4.6 Criticisms to Network Techniques:4.6 Criticisms to Network Techniques:
1- Assume all required resources are available: The CPM calculations do not incorporate resources into their formulation. Also, as they deal with activity durations only, it can result in large resource fluctuations. Dealing with limited resources and resource leveling, therefore, has to be done separately after the analysis.
2- Ignore project deadline: The formulations of CPM and PDM methods do not incorporate مندمجةغير a deadline duration to constrain project duration.
3- Ignore project costs: Since CPM and PDM methods deal mainly with activities durations, they do not deal with any aspects related to minimize project cost.
4- Use deterministic durations: The basic assumption in CPM and PDM formulations is that activity durations are deterministic. In reality, however, activity durations take certain probability distribution that reflect the effect of project conditions on resource productivity and the level of uncertainty involved in the project.
![Page 37: 1 Project Scheduling Faculty of Applied Engineering and Urban Planning Civil Engineering Department Week ( 6 + 7 ) Lec. ( 11 + 12 + 13 + 14 ) 2 nd Semester](https://reader035.vdocuments.us/reader035/viewer/2022081519/56649ea05503460f94ba3c83/html5/thumbnails/37.jpg)
3737
4.74.7 Solved ExamplesSolved Examples
Example 3.1Example 3.1For the project data in Table 4.3, answer the following questions:
a) Draw an AOA network of the project?
b) Perform forward path and backward path calculations c) What is the effect of delaying activity D by 3 days?
![Page 38: 1 Project Scheduling Faculty of Applied Engineering and Urban Planning Civil Engineering Department Week ( 6 + 7 ) Lec. ( 11 + 12 + 13 + 14 ) 2 nd Semester](https://reader035.vdocuments.us/reader035/viewer/2022081519/56649ea05503460f94ba3c83/html5/thumbnails/38.jpg)
3838
Solution:
a, b
0
1A
2
3
5 6
0
2
4
2 2
8 8
14 14 16 16
9 11
B
6
E
6
C
3 F
3
G
21D
8,or10
14,or122,or 8
9,or 5
c) Total float of activity D = LF – ES – d = 11 – 8 – 1 = 2.
![Page 39: 1 Project Scheduling Faculty of Applied Engineering and Urban Planning Civil Engineering Department Week ( 6 + 7 ) Lec. ( 11 + 12 + 13 + 14 ) 2 nd Semester](https://reader035.vdocuments.us/reader035/viewer/2022081519/56649ea05503460f94ba3c83/html5/thumbnails/39.jpg)
3939
Example 3.2Example 3.2Perform PDM calculations for the small project below and determine activity times. Durations are shown on the activities.
![Page 40: 1 Project Scheduling Faculty of Applied Engineering and Urban Planning Civil Engineering Department Week ( 6 + 7 ) Lec. ( 11 + 12 + 13 + 14 ) 2 nd Semester](https://reader035.vdocuments.us/reader035/viewer/2022081519/56649ea05503460f94ba3c83/html5/thumbnails/40.jpg)
4040
Solution:
1 5
B(4)
1 5
5 6
D(1)
5 6
6 7
G(1)
6 7
7 14
J(7)
7 14
14 16
L(2)
14 16
1 2
C(1)
6 7
2 4
E(2)
7 9
4 5
H(1)
9 10
2 4
F(2)
8 10
5 9
K(4)
10 14
0 1
A(1)
0 1
7 9
I(2)
12 14
7or85or4
9or9or14
1or6
12or7
![Page 41: 1 Project Scheduling Faculty of Applied Engineering and Urban Planning Civil Engineering Department Week ( 6 + 7 ) Lec. ( 11 + 12 + 13 + 14 ) 2 nd Semester](https://reader035.vdocuments.us/reader035/viewer/2022081519/56649ea05503460f94ba3c83/html5/thumbnails/41.jpg)
4141
Example 3.3Example 3.3For the activities listed in the table below, draw the time-scaled diagram and mark the critical path. Determine the completion time for the project. Tabulate activities times and floats.
![Page 42: 1 Project Scheduling Faculty of Applied Engineering and Urban Planning Civil Engineering Department Week ( 6 + 7 ) Lec. ( 11 + 12 + 13 + 14 ) 2 nd Semester](https://reader035.vdocuments.us/reader035/viewer/2022081519/56649ea05503460f94ba3c83/html5/thumbnails/42.jpg)
4242
Solution:
![Page 43: 1 Project Scheduling Faculty of Applied Engineering and Urban Planning Civil Engineering Department Week ( 6 + 7 ) Lec. ( 11 + 12 + 13 + 14 ) 2 nd Semester](https://reader035.vdocuments.us/reader035/viewer/2022081519/56649ea05503460f94ba3c83/html5/thumbnails/43.jpg)
4343
Example 3.4Example 3.4Perform PDM calculations for the small AoN network shown here. Pay special attention to the different relationships and the lag times shown on them.
Solution:
0 3
A(3)
0 3
2 5
B(3)
4 7
3 7
C(4)
3 7
3 9
D(6)
4 10
7 12
E(5)
7 12
SS2
FF2
8
5 or 7 or 2=9-2-5
12-2=10
4 or 3 or 5=4-2+3
![Page 44: 1 Project Scheduling Faculty of Applied Engineering and Urban Planning Civil Engineering Department Week ( 6 + 7 ) Lec. ( 11 + 12 + 13 + 14 ) 2 nd Semester](https://reader035.vdocuments.us/reader035/viewer/2022081519/56649ea05503460f94ba3c83/html5/thumbnails/44.jpg)
4444
Exercise 4Exercise 4
![Page 45: 1 Project Scheduling Faculty of Applied Engineering and Urban Planning Civil Engineering Department Week ( 6 + 7 ) Lec. ( 11 + 12 + 13 + 14 ) 2 nd Semester](https://reader035.vdocuments.us/reader035/viewer/2022081519/56649ea05503460f94ba3c83/html5/thumbnails/45.jpg)
4545
Exercise 4 Exercise 4 (Cont.)(Cont.)
![Page 46: 1 Project Scheduling Faculty of Applied Engineering and Urban Planning Civil Engineering Department Week ( 6 + 7 ) Lec. ( 11 + 12 + 13 + 14 ) 2 nd Semester](https://reader035.vdocuments.us/reader035/viewer/2022081519/56649ea05503460f94ba3c83/html5/thumbnails/46.jpg)
4646
Exercise 4 Exercise 4 (Cont.)(Cont.)
![Page 47: 1 Project Scheduling Faculty of Applied Engineering and Urban Planning Civil Engineering Department Week ( 6 + 7 ) Lec. ( 11 + 12 + 13 + 14 ) 2 nd Semester](https://reader035.vdocuments.us/reader035/viewer/2022081519/56649ea05503460f94ba3c83/html5/thumbnails/47.jpg)
4747
Exercise 4 Exercise 4 (Cont.)(Cont.)
![Page 48: 1 Project Scheduling Faculty of Applied Engineering and Urban Planning Civil Engineering Department Week ( 6 + 7 ) Lec. ( 11 + 12 + 13 + 14 ) 2 nd Semester](https://reader035.vdocuments.us/reader035/viewer/2022081519/56649ea05503460f94ba3c83/html5/thumbnails/48.jpg)
4848
Exercise 4 Exercise 4 (Cont.)(Cont.)
![Page 49: 1 Project Scheduling Faculty of Applied Engineering and Urban Planning Civil Engineering Department Week ( 6 + 7 ) Lec. ( 11 + 12 + 13 + 14 ) 2 nd Semester](https://reader035.vdocuments.us/reader035/viewer/2022081519/56649ea05503460f94ba3c83/html5/thumbnails/49.jpg)
4949
Exercise 4 Exercise 4 (Cont.)(Cont.)
![Page 50: 1 Project Scheduling Faculty of Applied Engineering and Urban Planning Civil Engineering Department Week ( 6 + 7 ) Lec. ( 11 + 12 + 13 + 14 ) 2 nd Semester](https://reader035.vdocuments.us/reader035/viewer/2022081519/56649ea05503460f94ba3c83/html5/thumbnails/50.jpg)
5050
Exercise 4 Exercise 4 (Cont.)(Cont.)