1. program background and introduction to specifications.pptconcrete bridge decks july 19, 2011...
TRANSCRIPT
![Page 1: 1. Program Background and Introduction to Specifications.pptConcrete Bridge Decks July 19, 2011 Kansas City, MO Outline Overview of LC-HPC Specifications and their application Where](https://reader036.vdocuments.us/reader036/viewer/2022071115/5ff7aa6c1a21346186202c9d/html5/thumbnails/1.jpg)
1
Program Background and Introduction to Specifications
9th Annual Meeting - Construction of Crack-Free
Concrete Bridge Decks July 19, 2011
Kansas City, MO
OutlineOverview of LC-HPCSpecifications and their applicationWhere we stand
Scope of Work
Low-Cracking High Performance Concrete (LC-HPC) Bridge Decks
23 LC-HPC decks (28 placements) ( p )completed through 2010
1 LC-HPC deck to be constructed this year
More to be let in MN
Bridges
Primarily composite steel girder bridges
Full-depth slabsRemovable formsMatching bridges to serve as a control where possible (Phase I)
Why LC-HPC?
Cracks
Why LC-HPC?
Negative impact of cracks on concrete in the decks.
Negative impact of cracks on corrosionNegative impact of cracks on corrosion performance of both conventional and epoxy-coated reinforcement.
![Page 2: 1. Program Background and Introduction to Specifications.pptConcrete Bridge Decks July 19, 2011 Kansas City, MO Outline Overview of LC-HPC Specifications and their application Where](https://reader036.vdocuments.us/reader036/viewer/2022071115/5ff7aa6c1a21346186202c9d/html5/thumbnails/2.jpg)
2
Our goalEliminate cracking in bridge decks
To do this, we need to minimize cracking due tocracking due to
Plastic shrinkageSettlement over reinforcing barsThermal contractionDrying shrinkage
Factors that affect crackingAgeDeck typeCement paste contentCompressive strengthAir contentAir contentSlumpTemperatureConstruction dateCuringConstruction techniques
Age
0.60
0.80
1.00
1.20
ensi
ty, m
/m2
Monolithic
0.00
0.20
0.40
0 25 50 75 100 125 150 175 200 225 250 275
Cra
ck D
e
Bridge Age, months
Bridge Deck Type
0.51 0.490.44
0.33
0 200.300.400.500.600.700.800.90
ck D
ensi
ty, m
/m2
Age
Cor
rect
ed
0.000.100.20
7% SFO 5% SFO CO MONO
Bridge Deck Type
Cra
Number of Bridges
(9) (18) (30) (16)
Number of Surveys
(9) (36) (52) (32)
Paste Content
0.19 0.16
0.680.73
0.200.300.400.500.600.700.800.90
ack
Den
sity
, m/m
2
Age
Cor
rect
ed
0.000.10
26 27 28 29
Percent Volume of Water and Cement, %
Cra
Number of Placements
Number of Surveys
(8) (16) (4) (5)
(16) (31) (8) (11)
Monolithic
0.18
0.31
0.51
0.87
0 150.19 0.22
0 200.300.400.500.600.700.800.90
ack
Den
sity
, m/m
2
Age
Cor
rect
ed
Uncorrected
Adjusted for Water Content
Slump
0.11 0.15
0.000.100.20
38 (1.5) 51 (2.0) 64 (2.5) 76 (3.0)
Slump, mm (in.)
Cra
Number of Placements
Number of Surveys
(5) (20) (5) (1)
(10) (40) (11) (3)
Monolithic
![Page 3: 1. Program Background and Introduction to Specifications.pptConcrete Bridge Decks July 19, 2011 Kansas City, MO Outline Overview of LC-HPC Specifications and their application Where](https://reader036.vdocuments.us/reader036/viewer/2022071115/5ff7aa6c1a21346186202c9d/html5/thumbnails/3.jpg)
3
Compressive Strength
0.160.26
0.49
0 200.300.400.500.600.700.800.90
ack
Den
sity
, m/m
2
Age
Cor
rect
ed
0.000.100.20
31 (4500) 38 (5500) 45 (6500)
Compressive Strength, MPa (psi)
Cra
Number of Placements
Number of Surveys
(7) (12) (10)
(13) (24) (23)
Monolithic
0.37 0.38
0.300.400.500.600.700.800.90
ck D
ensi
ty, m
/m2
Age
Cor
rect
ed
Air Content
0.13
0.000.100.20
4.5 5.5 6.5
Air Content, %
Cra
c
Number of Placements
Number of Surveys
(7) (19) (5)
(14) (40) (10)
Monolithic
0.19
0.330.37
0.44
0 20
0.30
0.40
0.50
0.60
0.70
0.80
0.90
ack
Den
sity
, m/m
2
Age
Cor
rect
ed
High Air Temperature
0.00
0.10
0.20
5 (41) 15 (59) 25 (77) 35 (95)
High Air Temperature, C (F)
Cra
Number of Placements
Number of Surveys
(4) (15) (9) (4)
(8) (31) (17) (9)
Monolithic
0.50
0.300.400.500.600.700.800.90
ck D
ensi
ty, m
/m2
Age
-Cor
rect
ed
Date of Construction - Monolithic
0.16
0.000.100.20
1984-1987 1990-1993
Date of Construction
Cra
c
Number of Bridges
(6) (7)
Number of Surveys
(12) (16)
0.24
0.53
0.81
0.300.400.500.600.700.800.90
ack
Den
sity
, m/m
2
Age
Cor
rect
ed
Date of Construction - Conventional Overlays
0.000.100.20
1985-1987 1990-1992 1993-1995
Date of Construction
Cra
(6) (36) (6)
(6) (17) (3)Number of BridgesNumber of Surveys
![Page 4: 1. Program Background and Introduction to Specifications.pptConcrete Bridge Decks July 19, 2011 Kansas City, MO Outline Overview of LC-HPC Specifications and their application Where](https://reader036.vdocuments.us/reader036/viewer/2022071115/5ff7aa6c1a21346186202c9d/html5/thumbnails/4.jpg)
4
0.87
0.55
0.420.48
0.300.400.500.600.700.800.90
ck D
ensi
ty, m
/m2
Age
Cor
rect
ed
Date of Construction - Silica Fume Overlays
0.000.100.20
1990-1991 1995-1996 1997-1998 2000-2002
Date of Construction
Cra
c
(6) (20) (16) (10)
(2) (10) (8) (10)Number of BridgesNumber of Surveys
Control of early evaporation and improved curing
0.87
0.58 0.61
0.390.48
0 300.400.500.600.700.800.90
kD
ensi
ty, m
/m2
Age
Cor
rect
ed
Control of early evaporation and improved curing -Silica Fume Overlays
0.000.100.200.30
NONE R1, R2 R3 R4, R5, R6 R8, R9
Special Provision, (R#)
Cra
ck
Ag
(6) (8) (10) (18) (10)
(2) (4) (5) (9) (10)Number of BridgesNumber of Surveys
4
5
6
7lu
mp,
in.
MONO
CO Subdecks
5% SFO Subdecks
7% SFO Subdecks
1
2
3
1984 1986 1988 1990 1992 1994 1996 1998 2000 2002 2004
Sl
Placement Date
5
6
7
8
9
10
ump,
in.
MONO
CO Subdecks
5% SFO Subdecks
7% SFO Subdecks
1
2
3
4
1984 1986 1988 1990 1992 1994 1996 1998 2000 2002 2004 2006 2008
Slu
Placement Date
Overall ApproachWork to reduce plastic, settlement, thermal
and drying shrinkage cracking
Low cement & water contentsLow slumpLow slumpHigh strength is not goodLow evaporation rateConstruction methods and materials matterMore early cracking means more total
cracking
![Page 5: 1. Program Background and Introduction to Specifications.pptConcrete Bridge Decks July 19, 2011 Kansas City, MO Outline Overview of LC-HPC Specifications and their application Where](https://reader036.vdocuments.us/reader036/viewer/2022071115/5ff7aa6c1a21346186202c9d/html5/thumbnails/5.jpg)
5
LC-HPC SpecificationsOptimized Aggregate GradationLow-absorption Aggregate1 inch Max Size AggregateCement Content ≤ 540 lb/yd3
w/c ratio = 0.43 – 0.45Air Content of 8 ±1½%Designated slump 1½ – 3 in. (4 3½ in. max)Controlled temperatureImproved curing
Concrete temperature control
55 – 70°F 50 – 75°F if approved by Engineer pp y g
Cold-weather concreting
Maintain temperature of both girders and deck.
Alternatives to Pumping
Concrete BucketsConveyor Belts
![Page 6: 1. Program Background and Introduction to Specifications.pptConcrete Bridge Decks July 19, 2011 Kansas City, MO Outline Overview of LC-HPC Specifications and their application Where](https://reader036.vdocuments.us/reader036/viewer/2022071115/5ff7aa6c1a21346186202c9d/html5/thumbnails/6.jpg)
6
Placing
Air cuff/bladder valve on pump or limit drop with conveyorFilling end walls and diaphragms ahead of slab
Consolidation RequirementsVertically mounted internal gang vibrators
Concrete Finishing
General Rule:Less is More
Pan or burlap dragBullfloating only if neededneededWater is not a finishing aid!
Curing
Presoaked burlapTimely placementConstantly wetConstantly wet
Spray hosesSoaker hoses14 days
Three work bridges. Four rolls of pre-cut, pre-soaked burlap, two on each side
Cost effectivenessCost of equipment: approximately $5000Cuts work crew to handle burlap on day of placement from 11 to 5 Contractor added power to move the work bridges between first and second deck
![Page 7: 1. Program Background and Introduction to Specifications.pptConcrete Bridge Decks July 19, 2011 Kansas City, MO Outline Overview of LC-HPC Specifications and their application Where](https://reader036.vdocuments.us/reader036/viewer/2022071115/5ff7aa6c1a21346186202c9d/html5/thumbnails/7.jpg)
7
Curing
Followed by curing compound to slow the rate of evaporation
Qualification Batch & Slab
Construction Schedule
Bridge Construction
Concrete Testing & Acceptance
Clearly define testing schedule ahead of timeC i tCommunicate how out-of-spec concrete will be handled
Specifications
07-PS0167 Construction07-PS0166 Concrete07 PS0165 Aggregates07-PS0165 Aggregates
![Page 8: 1. Program Background and Introduction to Specifications.pptConcrete Bridge Decks July 19, 2011 Kansas City, MO Outline Overview of LC-HPC Specifications and their application Where](https://reader036.vdocuments.us/reader036/viewer/2022071115/5ff7aa6c1a21346186202c9d/html5/thumbnails/8.jpg)
8
Where we standLC-HPC decks are workingCurrent provisions, however, don’t encompass all of the technologies that can be brought to barecan be brought to bareWe chose not to propose those technologies until we were assured that they posed no durability problems
We’ve now evaluated those technologies for durability and are prepared to recommend their adoptionReady for some more decks!
This year’s crack surveysAdherence to the rules...
Questions
The University of Kansas
David Darwin, Ph.D., P.E.Deane E. Ackers Distinguished Professor Director, Structural Engineering & Materials Laboratory
Dept. of Civil, Environmental & Architectural Engineering2142 Learned HallLawrence, Kansas, 66045-7609(785) 864-3827 Fax: (785) 864-5631
The University of Kansas
JoAnn Browning, Ph.D., P.E.Professor
Dept. of Civil, Environmental & Architectural Engineering2142 Learned HallLawrence, Kansas, 66045-7609(785) 864-3723 Fax: (785) 864-5631