1 presto rollout update board of directors - metrolinx april 28, 2011
TRANSCRIPT
1
PRESTO Rollout UpdateBoard of Directors -
Metrolinx
April 28, 2011
In productionIn production
• Burlington Transit• Oakville Transit• All Lakeshore West, Milton, Georgetown, Barrie and
Lakeshore East GO Rail Stations (except Pickering and Brampton GO Station)
• Kennedy, Oriole, Old Cummer, Langstaff and Centennial GO Rail Stations
• MiWay (Mississauga Transit) Route 32, Route 62, Route 64• 12 TTC Subway Stations
Coming upComing up
Spring 2011• GO Transit’s Richmond Hill Station and Stouffville Rail Line,
Hamilton Street Railway, York Region Transit, Durham Region Transit, Brampton Transit, Mississauga Transit
Summer 2011• GO Transit Bus ServiceSpring 2012• OC Transpo (Ottawa)
Project StatusProject Status
Total Cards Issued: 36 500
Total Cards Registered: 25 000 (68%)
Total ePurse Value Loaded to date: $17.7 million
Total Fare Payment Value to date: $15.8 million
Total Fare Payments to date: 2.9 million +
Card and Revenue Stats (As of April 17, 2011)
Roll-out, GO TransitRoll-out, GO TransitGO Station Date Comments
Centennial April 18 Stouffville Line
Richmond Hill April 19 Final station on Richmond Hill line
Pickering April 20 Final station on Lakeshore East
Agincourt April 20 Stouffville Line
Lincolnville April 27 Stouffville Line
Stouffville April 29 Stouffville Line
Mount Joy May 4 Stouffville Line
Markham May 6 Stouffville Line
Unionville May 11 Stouffville Line
Milliken May 13 Stouffville Line
Niagara Falls May 18 Niagara Falls GO Rail Line
St Catharines May 18 Niagara Falls GO Rail Line
Brampton Week of May 23 Final station on Brampton Line