1 power quality mary santori, p.e. senior engineer september 12, 2013
TRANSCRIPT
1
Power QualityPower Quality
Mary Santori, P.E.
Senior Engineer
September 12, 2013
2
Topics discussed
Causes of Disturbances
Normal utility operations that can cause problems with sensitive equipment
How Xcel Energy works with customers on power quality issues
Reliability Key Indices and Outage Causes
Preventive Maintenance
3
Causes of disturbances
On-site interference Caused by loads inside a facility affecting the power in such a way
as to cause other loads to malfunction
Neighboring interference Caused by loads outside a facility affecting the power in such a
ways as to cause other loads to malfunction
Natural phenomena and accidents Events such as lightning, storms, cars hitting power poles and
dig-ins to underground cable
Utility operations and problems Normal utility operations or malfunctioning utility equipment
4
Normal utility operations that can cause problems with sensitive equipment
Protective devices operating under fault (i.e. breakers, fuses, reclosers)
Normal equipment operation (i.e. capacitor bank switching)
Single phase events (one phase of a three phase service is out) – Recommend phase protection
Xcel Energy RMS voltage guideline: + 5% secondary, + 10% primary and transmission
5
Typical Electric Utility Distribution Layout
Customer X
Customer Y
Customer Z
Breaker BreakerBreakerBreaker
Feeder A Feeder B
Feeder C
Feeder D
From Transmission System
Fuse 1
Fuse 3
Fuse 2
Recloser
Fuse 4
XX
6
Typical Electric Utility Capacitor Bank Switching Waveform at Customer
7
Process for power quality issues
Gather background information from customer
Try and correlate disturbance to utility events
Set Recording Meters if Needed
Review Findings and Discuss Mitigations
8
Step 1: Review Issue With Customer
What happened?
Dates and times (important to keep log)
Note anything else that happened in facility at the same time
Discuss customer’s electrical layout
If customer has monitoring, note location of meters (service entrance ideal)
9
Step 2: Correlate Disturbance to Xcel Energy Electrical System
If 0 volt condition, review outage logs
If voltage sag condition, review outages on transmission system and neighboring taps and feeders
If voltage sag or surge condition, review distribution lines device operation (i.e. capacitor banks and voltage regulators)
10
Step 3: Set Recording Meters if Needed
Monitor current and voltage at customer’s transformer or service entrance
Possibly monitor at neighboring customers
11
Step 4: Review Findings and Discuss Mitigations
After reviewing monitoring data, may need to repeat Step 2
Note current and voltage relationship Utility mitigation may include investigating
malfunctioning equipment (cap bank, voltage regulator, etc..)
Customer mitigation may include installing ride through equipment, soft start on motors, etc..
12
Reliability Indices Reported to the MN PUC (many different formats)
SAIFI – System Average Interruption Frequency Index Total Number of Sustained Customer Interruptions
Total Number of Customers
CAIDI – Customer Average Interruption Duration Index Total Customer Minutes of Sustained Outages
Total Number of Sustained Customers Interruptions
SAIDI – System Average Interruption Duration Index Total Customer Minutes of Sustained Outages
Total Number of Customers
MAIFI – Momentary Average Interruption Frequency Index Total Number of Customer Momentary Interruption Events
Total Number of Customers
13
Outages Causes (by customer minutes)
Minnesota YTD December 2012, Internal Normalization Method
Includes Partial Restoration
0
2,000,000
4,000,000
6,000,000
8,000,000
10,000,000
12,000,000
14,000,000
16,000,000
18,000,000
Cu
sto
mer
Min
ute
s
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Cu
mu
lati
ve %
Customer Minutes
Cumulative %n = 80,714,261
14
Preventive Maintenance Efforts
Vegetation Management – Continual Condition Assessment/5-Year Maintenance Cycle
Infrared Testing – Semiannual Condition Assessment Substation Transformers Circuit Breakers Surge Arrestors Bushings Regulators
Animal Control – Ongoing/Condition Based
Capacitor Banks – Annual Condition Assessment (Metro Areas) Upgrading with Centralized Controls
15
Customer Reliability Opportunities
Customer owned back-up generation
UPS
Auto or Manual Transfer
Phase Loss Protection
Transient Voltage Surge Suppression
16
Power Quality Consultants(Note: Xcel Energy does not recommend any one consultant)
EPRI, Mark Stephens, 865-218-8022
Hunt Electric, 651-646-2911
OlympiaTech, 763-559-1900
Parsons Electric, 763-571-8000
ColliSys, 763-535-6000
Hypertect, 651-631-0172
17