Page 1: 1 OSD Assessment of the Performance of the DoD Supply Chain Using the Strategic Distribution Database (SDDB) November 14, 2013

1

OSD Assessment of the Performance of the DoD Supply Chain

Using the Strategic Distribution Database (SDDB)

November 14, 2013

Page 2: 1 OSD Assessment of the Performance of the DoD Supply Chain Using the Strategic Distribution Database (SDDB) November 14, 2013

2

OSD Supply Chain Performance Assessment

Health of the

Supply Chain

Materiel Readiness

Responsiveness

ReliabilityCost

Planning and

Precision

Is the mission capability of weapon systems degraded due to declining supply chain

support?Is the supply

chain supporting readiness and satisfying its

customers in a timely manner?

Is the supply chain providing

consistent support to its

customers and sustaining or

improving readiness?

Is inventory management within the supply chain improving?

Is the supply chain providing cost-effective support to its customers and managing inventory in a cost-

effective manner?

Pipeline measurement is key to assessing the responsiveness and reliability of the DoD supply chain.

Outcome/Attribute ConstructHypothesis: The health of the supply chain involves doing well in four critical performance areas while supporting the readiness outcome.Hypothesis: For an outcome or attribute to be “healthy”, its associated metrics must perform as expected.

AssessmentApproach: A metric is performing as expected if it is meeting its goal or is performing at an acceptable level.

Page 3: 1 OSD Assessment of the Performance of the DoD Supply Chain Using the Strategic Distribution Database (SDDB) November 14, 2013

3

LMARS and Responsiveness and Reliability Metrics

LMARS

Responsiveness:

Logistics Response Time

Reliability:

Perfect Order Fulfillment

SDDBReliability:

TDD Compliance

• Logistics response time and perfect order fulfillment measurements are based solely on LMARS data.

• SDDB uses LMARS data as a starting pointing but does some record filtering, data supplementing, and re-computing of pipeline segment times.

• TDD compliance measurements are based on SDDB data.

Page 4: 1 OSD Assessment of the Performance of the DoD Supply Chain Using the Strategic Distribution Database (SDDB) November 14, 2013

4

How the Assessment is Conducted

Monthly Data Update

Review of Metrics for Trends and

Anomalies

Deep Data Dives

Monthly Metrics PMR

Component Consultations

• Besides the metrics themselves, LMARS supports deep dive capability in the online LRT tool.

• The tool allows us to look at LRT over different times, to use dimensions to focus on specific sets of orders, and to collect statistics beyond mean times.

• In addition, the LRT tool allows us to work with LMARS data or SDDB data.

Page 5: 1 OSD Assessment of the Performance of the DoD Supply Chain Using the Strategic Distribution Database (SDDB) November 14, 2013

5

SDDB Plays a Key Role in the LRT Tool

We get SDDB from DORRA along with an “allsvc” file, which we use to include the customer’s country based on its DoDAAC.

We combine SDDB records with LMARS to get: Joint LMARS/SDDB records LMARS only records SDDB only records

LMARS Monthly Feed

SDDB Monthly Feed

DLIS/DORRA Feeds

LMARS Enhanced File

LRT-LMARS Cubes

Combined LMARS/SDDB

File

LRT-SDDB Cubes

LRT Tool

37%

62%

1%

Joint LMARS/SDDB LMARS OnlySDDB Only

FY2013

Page 6: 1 OSD Assessment of the Performance of the DoD Supply Chain Using the Strategic Distribution Database (SDDB) November 14, 2013

6

Joint LMARS/SDDB Records

• For joint records, we use SDDB segment times.

• Most of the segment time changes are in these OCONUS segments

• Port of Embarkation (POE) processing time

• In-transit from POE to POD time

• Port of Debarkation (POD) processing time

• In-theater in-transit time

• The next highest changes is in requisition submission times.

Page 7: 1 OSD Assessment of the Performance of the DoD Supply Chain Using the Strategic Distribution Database (SDDB) November 14, 2013

7

LMARS Only Records

Includes Perishable records (54.9%) Prime Medical Vendor records (26.6%) Local Clothing Issues (5.4%) Maintenance, Repair, and Operations records (0.8%) Initial Outfitting records (0.3%) [excluded from LRT computations] Local issues to maintenance (0.0%)

The other 11.1% Orders placed on USSOCOM Orders placed by civilian agencies (not DoD) Subsistence orders not part of an LMARS special feed Unshipped records Other SDDB exclusions

Page 8: 1 OSD Assessment of the Performance of the DoD Supply Chain Using the Strategic Distribution Database (SDDB) November 14, 2013

8

SDDB Orders Only

SDDB closes records the LMARS has open (Army data).

Page 9: 1 OSD Assessment of the Performance of the DoD Supply Chain Using the Strategic Distribution Database (SDDB) November 14, 2013

9

In Summary

We use SDDB to drill down into

Pipeline segment data.

Customer command, base, country/state

Type of shipment (Air, surface, inter-theater, CONUS)