1 mndot metro district proposed 2007-2010 transportation improvement program (tip) amendment...

15
1 MnDOT Metro District Proposed 2007-2010 Transportation Improvement Program (TIP) Amendment Metropolitan Council January 17, 2007

Upload: rafe-payne

Post on 17-Jan-2016

212 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 1 MnDOT Metro District Proposed 2007-2010 Transportation Improvement Program (TIP) Amendment Metropolitan Council January 17, 2007

1

MnDOT Metro District Proposed 2007-2010

Transportation Improvement Program (TIP) Amendment

Metropolitan CouncilJanuary 17, 2007

Page 2: 1 MnDOT Metro District Proposed 2007-2010 Transportation Improvement Program (TIP) Amendment Metropolitan Council January 17, 2007

2

Purpose Present background information on I-

35W/ Crosstown project Present information on proposed 2007-

2010 TIP amendment that will come to the Metropolitan Council for action January 24

Answer questions

Page 3: 1 MnDOT Metro District Proposed 2007-2010 Transportation Improvement Program (TIP) Amendment Metropolitan Council January 17, 2007

3

I-35W/Crosstown Project Background Project limits: On I-35W from 66th St

(Richfield) to 42nd St. (Minneapolis). On TH 62 from Portland Ave to Penn Ave.

Description: Reconstruct 4 miles of I-35W and 2 miles of TH 62. Eliminate the forced weaving in the commons area

by separating the two roadways. Expand I-35W from 3 lanes in each direction north of

TH 62 to 4 general purpose lanes plus 1 HOV/Bus Rapid Transit lane each direction.

Build an on-line transit station at 46th St.

Page 4: 1 MnDOT Metro District Proposed 2007-2010 Transportation Improvement Program (TIP) Amendment Metropolitan Council January 17, 2007

4

Project Background (continued) Project Need:

Common Section and adjacent highway segments constructed in middle to late 1960’s; design was criticized shortly after opening.

Crosstown Commons interchange carries an average of 240,000 vehicles per day.

Crash rates are up to 5 times higher than the average for metropolitan urban freeways.

Bridges are deteriorated. Congestion extends through most hours of

the day.

Page 5: 1 MnDOT Metro District Proposed 2007-2010 Transportation Improvement Program (TIP) Amendment Metropolitan Council January 17, 2007

5

Project Background (continued) Project Priority

Interchange area has been identified as a major deficiency in the Metropolitan Council’s Transportation Plan since 1983

Project has been under development by MnDOT since mid-1980’s

Identified as a recommended project by the Metropolitan Council in the Transportation Policy Plan since 1989.

Page 6: 1 MnDOT Metro District Proposed 2007-2010 Transportation Improvement Program (TIP) Amendment Metropolitan Council January 17, 2007

6

Project Background (continued)

In 2001, MnDOT was preparing to begin construction of a redesigned interchange.

The Minnesota Legislature placed a moratorium on the project, and required MnDOT to study other designs that added more capacity and did not result in long closures during construction.

The current design responds to those concerns.

Page 7: 1 MnDOT Metro District Proposed 2007-2010 Transportation Improvement Program (TIP) Amendment Metropolitan Council January 17, 2007

7

Current Project The I-35W Crosstown project was

advertised in April 2006 but received no bids.

Comments from prospective bidders as to why no bids: Cost estimate appeared too low Proposal would have required contractor to

work in advance of payment availability over course of 4-year project.

Page 8: 1 MnDOT Metro District Proposed 2007-2010 Transportation Improvement Program (TIP) Amendment Metropolitan Council January 17, 2007

8

Revised Cost Estimate

FHWA asked MnDOT to perform a risk analysis to identify where costs are likely to be at risk for increase over previous estimate. These areas are considered to be:

Structural concrete, traffic control, mobilization, inflation, segmental bridges, traditional bridges, single bidder, disincentives, financing.

A revised payout curve eliminated the need for contractor to finance work to meet proposed schedule.

Revised cost estimate is now $285M (from previous $251M)

Page 9: 1 MnDOT Metro District Proposed 2007-2010 Transportation Improvement Program (TIP) Amendment Metropolitan Council January 17, 2007

9

Need for TIP Amendment In order for the project to move forward

toward federal authorization, federal rules require a TIP/STIP amendment to identify the additional funds necessary for this project, and to maintain fiscal balance within the 2007-2010 TIP.

Additional cost increases for Phase 2 of TH 12 near Long Lake are also included in this amendment.

Page 10: 1 MnDOT Metro District Proposed 2007-2010 Transportation Improvement Program (TIP) Amendment Metropolitan Council January 17, 2007

10

Fiscal Balance Both increased funds and project

deferral are needed to maintain fiscal balance. Use of Bond Accelerated Program

Transit Advantage funds Additional State Trunk Highway funds Temporary deferral of TH 169/CR 81

interchange in Brooklyn Park from SFY 2008 to SFY 2010

Page 11: 1 MnDOT Metro District Proposed 2007-2010 Transportation Improvement Program (TIP) Amendment Metropolitan Council January 17, 2007

11

Fiscal Balance

Project YearCurrent TIP/STIP

Amount

Revised Cost

Estimate

Additional Amount Needed

How Funded Amount

I-35W/ Crosstown

SFY 07(Mar 07 letting)

$251.0BAPTA $10.0

$261.0

$285.0M $24.0M Remaining BAPTA

Defer TH 169/CSAH 81 from SFY 08 to SFY 10

Additional State TH Funds

$5.0M

$21.0M

6.5M

TH 12 Wayzata Blvd to CR 6 near Long Lake

SFY 08 (May 07 letting)

$27.5M $36.0M $8.5M

TOTAL $288.5M $321.0M $32.5M $32.5M

Page 12: 1 MnDOT Metro District Proposed 2007-2010 Transportation Improvement Program (TIP) Amendment Metropolitan Council January 17, 2007

12

Program Impacts

Proposed TIP amendment : Continues to fund Metro preservation and

safety project under construction and in the program

Allows I-35W/Crosstown project to move forward to a March 30, 2007 letting

Temporarily defers TH 169/CR 81 interchange from spring 2007 to spring 2009.

Page 13: 1 MnDOT Metro District Proposed 2007-2010 Transportation Improvement Program (TIP) Amendment Metropolitan Council January 17, 2007

13

Other Considerations MnDOT remains committed to

delivering the TH 169/CR 81 project.

Plan development, project approvals and municipal consent process will continue as scheduled.

This project is positioned to be constructed earlier should new or additional funding be available.

Page 14: 1 MnDOT Metro District Proposed 2007-2010 Transportation Improvement Program (TIP) Amendment Metropolitan Council January 17, 2007

14

Next Steps (as anticipated) Metropolian Council Transportation Committee

recommendation Jan 22 Metropolitan Council adoption Jan 24 MnDOT STIP amendment approval Jan 25 FHWA STIP amendment approval Jan 26 FHWA project authorization Jan 26 Project advertised for bidding Feb 2 Bid opening March 30 Contract award April 30 Contract approval May 21 Contract start May 29

Page 15: 1 MnDOT Metro District Proposed 2007-2010 Transportation Improvement Program (TIP) Amendment Metropolitan Council January 17, 2007

15

Questions?