1 management report on bradley west project boac meeting october 5, 2009
TRANSCRIPT
1
Management Report on Bradley West Project
BOAC Meeting
October 5, 2009
2
• Upcoming Decisions
- Bradley West Gates
- Bradley West Core
• How CMAR Works
• Program Budget Overview
• Board Action - October 19, 2009
AGENDA
3
UPCOMING DECISIONS
Exercise Bradley West Gates Project Construction Option
• Approve the contract amendment with an upper limit of $545.5M
• Approve a Budgeted Owner’s Contingency of $61.4M
• Delegate Signature Authority for Change Orders
• Appropriate Capital Funds in an amount of $14.7M
► Gates
4
UPCOMING DECISIONS
Award Core Construction Manager at Risk (CMAR) Contract and Authorize Preconstruction Services
• Award contract with upper limit of $584.2M
• Approve a Budgeted Owner’s Contingency of $66.7M
• Appropriate Capital Funds in an amount of $25.1M
• Delegate Signature Authority for Change Orders
► Core
5
HOW CMAR WORKS
$545.5M
Passenger Boarding Bridges
Preconstruction
Bus Gates and TPAR Equipment Procurement
Core Emergency Egress
Site Enabling
Foundations/Steel/Utilities
Exterior Skin and Systems
Interior Architecture and Finishes
West Apron Work
North and South Concourse Demolition
• LAWA provides CMAR with work packages
• CMAR commits to complete each package for a Component Guaranteed Maximum Price (CGMP)
• Each CGMP will be presented to BOAC for approval and appropriation of funds
• CMAR must competitively bid 90% of Scope of Work from minimum of 3 bidders
• CMAR cannot perform more than 10% of Scope of Work
• Each CGMP will be additive resulting in an “aggregate” Guaranteed Maximum Price for all Scope of Work appropriated to date within the contract amount of $545.5M
Bradley West Gates CGMPs
6
PROGRAM BUDGET OVERVIEW
Total Program Cost Summary ReportPROGRAM BUDGET
7
PROGRAM BUDGET OVERVIEW
Bradley West ElementELEMENT BUDGET
8
PROGRAM BUDGET OVERVIEW
Bradley West GatesPROJECT BUDGET
(dollars in millions)
Bradley West Gates
ITEM No. ITEM/DESCRIPTION AMOUNT
1. Construction 501.40
2. Program Management 20.13
3. Design 52.40
4. Construction Support 28.65
5. LAWA / City Support 34.10
SUBTOTAL BUDGET 636.68
Contingency 54.98
TOTAL PROJECT BUDGET 691.66
9
BOARD ACTION – OCTOBER 19, 2009
10
BOARD ACTION – OCTOBER 19, 2009
Bradley West Gates Project Construction Option
Bradley West Gates
1. Airside Element – Concourse Demolition / West Aprons 42.90
2. Bradley West – Concourses 501.40
3. Utilities & Infrastructure – TPAR 1.25
Total Cost 545.55
11
Process• Administrative Requirements
• Technical Requirements (Quality Points)
• Interview (Quality Points)
• Fee
• Fee x Budget / Total Quality Points = Ultimate Cost
Award Core Construction Manager at Risk (CMAR) Contract and Authorize Preconstruction Services
Selection Process Results
• Received seven proposals
• Interviewed all seven firms
• Walsh Austin Joint Venture Proposed Lowest Ultimate Cost
BOARD ACTION – OCTOBER 19, 2009
12
BOARD ACTION – OCTOBER 19, 2009
Bradley West Core Improvements
• Award contract with upper limit of $584.2M
• West Apron $2.2M
• Core $569.0M
• Temporary Power and Relocation $13.0M
$584.2M
• Approve a Budgeted Owner’s Contingency of $66.7M
• Appropriate Capital Funds in an amount of $25.1M
• Pre-Construction Services $6.0M
• Public Art Allowance $5.4M
• LAWA Support $6.2M
• City Services $7.5M
$25.1M
13
BOARD ACTION – OCTOBER 19, 2009
Bradley West Core Improvements
Bradley West Core Improvements
1. Airside – Apron Strip 2.20
2. Bradley West – Core 569.00
3. Utilities & Infrastructure – TPAR 13.00
Total Cost 584.20
14
BOARD ACTION – OCTOBER 19, 2009
Signature Authority
• Exercise authority pursuant to Charter Section 376
• Authorize Executive Director to execute change orders up to $1M
• Limit accumulative amount of change orders to no more than 10% of the BOAC approved aggregate guaranteed maximum price
• Report monthly to BOAC on all change orders executed throughout the term of the contract