1 m-150 / botts rd interchange modot project no. j4p2251 pre-bid meeting june 24 th, 2010

16
1 M-150 / Botts Rd Interchange MoDOT Project No. J4P2251 Pre-Bid Meeting June 24 th , 2010

Upload: jerome-creamer

Post on 28-Mar-2015

213 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 1 M-150 / Botts Rd Interchange MoDOT Project No. J4P2251 Pre-Bid Meeting June 24 th, 2010

1

M-150 / Botts Rd InterchangeMoDOT Project No. J4P2251

Pre-Bid MeetingJune 24th, 2010

Page 2: 1 M-150 / Botts Rd Interchange MoDOT Project No. J4P2251 Pre-Bid Meeting June 24 th, 2010

Agenda

Project Description

Project Schedule

Project Coordination with Adjacent Projects

Traffic Control Phases

Special Features Q&A

2

Page 3: 1 M-150 / Botts Rd Interchange MoDOT Project No. J4P2251 Pre-Bid Meeting June 24 th, 2010

Botts Road and M150 Interchange

Existing Conditions• At-grade

intersections• Development in NW

Quadrant and South of M-150. National Security Campus and Centerpoint Development

• Development south of M-150: Kansas City Southern Intermodal Facility

• New Interchange construction at US 71

3

Page 4: 1 M-150 / Botts Rd Interchange MoDOT Project No. J4P2251 Pre-Bid Meeting June 24 th, 2010

Botts Road at M150: Two Components

4

Botts Road North of M-150

Interchange at Botts Road and M-150 (Includes Auxiliary Lanes)

Page 5: 1 M-150 / Botts Rd Interchange MoDOT Project No. J4P2251 Pre-Bid Meeting June 24 th, 2010

Project Description

• Interchange Construction of NEW Diverging Diamond

Interchange Botts Road over M150 Auxillary lanes from Botts to US 71

• Botts Rd Reconstruction of existing 2 lane. M-150 north ½ mile to Grandview city limits. M-150 south to tie in to existing Botts Rd.

5

Page 6: 1 M-150 / Botts Rd Interchange MoDOT Project No. J4P2251 Pre-Bid Meeting June 24 th, 2010

What is a Diverging Diamond Interchange (DDI)?

6

Page 7: 1 M-150 / Botts Rd Interchange MoDOT Project No. J4P2251 Pre-Bid Meeting June 24 th, 2010

The Botts Road and M-150 DDI

7

Page 8: 1 M-150 / Botts Rd Interchange MoDOT Project No. J4P2251 Pre-Bid Meeting June 24 th, 2010

Project Schedule

Advertisement July 15, 2010

Contract Letting August 20, 2010

Construction Notice to Proceed October 4,2010

Construction Complete by October 2012

8

Page 9: 1 M-150 / Botts Rd Interchange MoDOT Project No. J4P2251 Pre-Bid Meeting June 24 th, 2010

Coordination with Adjacent Projects

National Security Campus• Development in NW quadrant

JE Dunn is contractor Coordinate access between projects Coordinate construction activities

US 71/M-150 Interchange• Clarkson Construction is contractor

M-150/Thunderbird Rd Half Diamond Interchange • Partnership between KCS and MoDOT

Currently in Negotiations

9

Page 10: 1 M-150 / Botts Rd Interchange MoDOT Project No. J4P2251 Pre-Bid Meeting June 24 th, 2010

Traffic Control Phases

Phase I• Construct Botts Rd

Existing Botts Rd to be closed to public ½ mile corridor 4 access drives Signal at South Access Drive Ditches instead of standard curb & gutter

• Interchange North bridge abutment South bridge abutment Ramps Retaining wall Auxiliary lanes from M-150 to US 71 Median treatment between Andrews and Colorado

10

Page 11: 1 M-150 / Botts Rd Interchange MoDOT Project No. J4P2251 Pre-Bid Meeting June 24 th, 2010

Traffic Control Phases

Phase 2• Interchange

Divert traffic to ramps to build center pier Complete bridges

Phase 3• Close Thunderbird Rd (to remain open until end

of project)• Interchange median islands

11

Page 12: 1 M-150 / Botts Rd Interchange MoDOT Project No. J4P2251 Pre-Bid Meeting June 24 th, 2010

Special Features

Walkway Down Center of Bridge to Allow Pedestrian Access

12

Page 13: 1 M-150 / Botts Rd Interchange MoDOT Project No. J4P2251 Pre-Bid Meeting June 24 th, 2010

Special Features

Green Solutions

• Dry detention basins:

Note the controlled fill

Review spillway structure details

• Topsoil removal and placement incidental to Excavation, Embankment and Compaction

• Extra care required to avoid or mitigate compaction in all planted areas (BMP’s)

• Note the check dams in selected swales

13

Page 14: 1 M-150 / Botts Rd Interchange MoDOT Project No. J4P2251 Pre-Bid Meeting June 24 th, 2010

Special Features

Green Solutions

• Some vegetated areas will be planted with plugs (basins, swale bottoms)

• Bonded fiber matrix mulch for slopes greater than 6:1

• Note the 2-year establishment period for native plantings

• Note the Geocell reinforcement stormwater basin maintenance paths

• Review erosion and sediment control plan

• Temporary cover plantings required if planting seasonal periods missed

14

Page 15: 1 M-150 / Botts Rd Interchange MoDOT Project No. J4P2251 Pre-Bid Meeting June 24 th, 2010

Special Features

Hardscape

• Review architectural elements within the interchange islands (recycled glass surface, etc.)

• Note architectural elements in Botts Road median

• Note amended fill for plantings in medians

15

Page 16: 1 M-150 / Botts Rd Interchange MoDOT Project No. J4P2251 Pre-Bid Meeting June 24 th, 2010

16

Questions?

Barbara Friedman, PESenior Project Manager

HNTB [email protected]