1 june 15 / slide 1 / title of document top 10 things your project manager should be telling you a...
Post on 19-Dec-2015
213 views
TRANSCRIPT
Apr 18, 2023 / Slide 1 / Title of Document
1
Top 10 Things Top 10 Things YourYour
Project Manager Project Manager Should Should
Be Telling YouBe Telling YouA TUSC PMO Presentation
Apr 18, 2023 / Slide 2 / Title of Document
2
Top Ten Things you need to knowTop Ten Things you need to know
85% of a Project Manager’s time is spent
COMMUNICATING
Apr 18, 2023 / Slide 3 / Title of Document
3
Top Ten Things you need to knowTop Ten Things you need to know
Communication Quality Not enough Information Too much Information Timeliness of Information
Communication Plan Setting Expectations Who gets what and when do they get it What are the key things you should know each week What key things should be monitored monthly How much should the delivery team know How much should the management team know Is it in writing?
Apr 18, 2023 / Slide 4 / Title of Document
4
Typical vs CriticalTypical vs Critical
What is Typical to hear?
What is Critical to hear?
Analyze the types of communication in key project areas
Scope Risks Issues Cross Project Dependencies Budget Project Team Organizational Readiness
Apr 18, 2023 / Slide 5 / Title of Document
5
Scope ManagementScope Management
Typical Scope Management Plan
What is in scope What is out of scope Log of scope changes
Critical#1 How much push back are you receiving on
scope?
#2 What is the overall impact on the original budget?
Apr 18, 2023 / Slide 6 / Title of Document
6
Risk ManagementRisk Management
Typical Risk Management Plan
Quantification of risk Qualification of risk Mitigation plans Monitoring for new risks
Critical#3 How effective have the Risk Management &
Mitigation strategies been?
Apr 18, 2023 / Slide 7 / Title of Document
7
Issue ManagementIssue Management
Typical Issue management process defined
Type, Owner, Status, Resolution Issue escalation process Weekly review of issues
Critical#4 How effective is the escalation process ?
What issues have been escalated Did escalation process help to resolve the issue Are there patterns to the types of issues needing escalation What types of issues are not being resolved
Apr 18, 2023 / Slide 8 / Title of Document
8
Project DependenciesProject Dependencies
Typical Identify the dependencies within the project Project level - Critical Path awareness
Critical#5 What other projects have the ability to impact
this project’s success What is the critical path for the entire organization How are cross project dependencies tracked Who has the ability to resolve grid lock How are dependency-level conflicts resolved Is there an organizational level steering committee
Apr 18, 2023 / Slide 9 / Title of Document
9
Budget ManagementBudget Management
Typical Overall Budget Weekly burn-rate (Actuals)
Critical#6 Budgetary view of Project progression
Actuals vs Budget – to –date Estimate at completion Earned Value
• Can it really be calculated• What level makes sense
Apr 18, 2023 / Slide 10 / Title of Document
10
Team ManagementTeam Management
Typical Team roster Team turnover
Critical#7 How effective is the team
Internal Factors that contribute• Skill Sets, Personality Conflicts, Attitude, Stress Levels• Unrealistic deadlines• Frequent changes to requirements
External Factors that contribute• Travel & commuting issues• The right Tool for the job• Team Space & Meeting facilities
Apr 18, 2023 / Slide 11 / Title of Document
11
QualityQuality
Typical Number of defects found in testing Number of defects found once in production
Critical#8 Quality of Deliverables
What is the Quality Management Plan• How is quality measured• How frequently is it measured• Are there patterns that identify quality issues
Apr 18, 2023 / Slide 12 / Title of Document
12
Organizational ReadinessOrganizational Readiness
Typical Change Management Plan
Critical#9 How accepting is the organization to change
• How Effective is the Change Management Team• How much push-back is the organization providing
○ Excessive number of Scope changes○ High-levels of absenteeism ○ Delays in User Acceptance○ High-level of turnover
Change
Is a
Good
Thing
I
Love
Change
Apr 18, 2023 / Slide 13 / Title of Document
13
Organizational ReadinessOrganizational Readiness
#10 How ready is the organization to support the program once it is in production
• Operational processes and monitoring○ Who will monitor process○ Who will monitor data○ What is the process for logging post-production issues
• Ongoing Maintenance○ Who will address post-production issues○ Who will be able to enhance application when business
rules change
Apr 18, 2023 / Slide 14 / Title of Document
14
The Top The Top 10 10 in reviewin review
Critical Review Point
Project Initiation
* Project Execution
Project Closure
Scope Containment w/in Org Once Monthly
Scope Impact to Project Monthly Once
Risk Mitigation Effectiveness Once Monthly
Issue Escalation Effectiveness Monthly
Cross Project Dependencies Once Monthly Once
Project Cost Progression Monthly
Team Effectiveness Quarterly
Quality of Deliverables Once Monthly Monthly
Organizational Change Acceptance Monthly
Organizational Readiness Once Monthly Weekly
* Assumes a project timeline of 6 months or more.
Apr 18, 2023 / Slide 15 / Title of Document
15
A TUSC PMO PresentationA TUSC PMO Presentation
Top 10 Things
Your Project Manager
Should Be Telling You
References: A guide to the Project Management Body of Knowledge, (PMBOK Guide). 3rd
Edition, Nov 2004. Project Management Institute, Pennsylvania, USA
Just Enough Project Management, Curtis R. Cook, McGraw-Hill, 2004