1 july 2004 european commission: second international workshop on ppps 5 july 2004
Post on 22-Dec-2015
215 views
TRANSCRIPT
1
July 2004
European Commission: Second International Workshop on PPPs
5 July 2004
2
July 2004
Who is Skanska ?
• Multinational Construction Company• Total annual revenues of 18 Billion USD in
2003.• Over 81% of revenue is international.• Over 69 000 employees.• Consistently named to Forbes' A-List of
World's Best companies. • Ranked #1 in Fortune Magazine's
2002 World's Most Admired Companies listing in Engineering, Construction category.
3
July 2004
Skanska BOT Business Sectors
Skanska BOT AB, a development and investment company specializing in private infrastructure projects in following business sectors.
UK PFI:s – the concept being spread to rest of Europe
Roads – number of cars/inhabitants increase
Power – energy capacity increase necessary for development
Ports – Seaborne traffic grows 2*GNP
Airports –similar pattern as ports
4
July 2004
What does the private sector expect from
PPPs?
5
July 2004
The Industry requires, in order to invest in BOT/PPP projects.
• A viable investment that stands alone
• Generate construction works and service
• Gaining operational knowledge in interesting sectors
• Long term stable revenue flow – interesting for long-term owners
• Stock market appreciation
Expectations
6
July 2004
Political/administrative decisions
• general project scope – size and content• tolling or not / cash, electronic or free flow • rate regulation or not• interoperability of tolling systems• other performance criteria• traffic risk sharing mechanism• financial risk sharing mechanism• concession period and transfer mechanism• legal framework• financial award critera• the political commitment to follow through
Expectations
7
July 2004
Skanska’s different roles in BOT/PPP projects
• Developer
• Contractor - normally a 33-100% stake
• Investor - normally a 20-50% stake
• Facilities manager
Expectations
8
July 2004
BOT/PPP is relationship management
• Contractual
• Partner
• Client
• Service providers
• Lenders and lawyers
• Economic and financial
If we do it well we mitigate risks- We create
Value for Money
Expectations
9
July 2004
Expectations that we perceive Governments have on the investor/contractor
Fixed price, time certain. PPP is not a claim business
We are not just a builder any longer
In PPP construction is only one element out of several
We sell a service/solution – not a building or a road
We must understand the clients needs and objective
We take complete responsibility for cost, quantities and time with penalties should we fail to deliver
We must look at our work from a lifecycle perspective
We must develop our industry and design with Life Cycle Thinking
Expectations
10
July 2004
Expectation of procurement Pre Qualification – Reasonable number of bidders
Performance specification of a service – not a quantity specification of an asset.
Transparency in the procurement
Confidentiality and intellectual property
Balanced Bidding costs
Openings for unsolicited proposals
Expectations
11
July 2004
What are the lessons learned in PPPs by Skanska?
12
July 2004
The perfect financing option
• There is NO ONE solution
• Project specific features are important
• You will be caught if you make a short-cut
• Optimize rather than maximize
• A robust structure is better than rocket science
• Approximately right rather than exactly wrong
Lessons Learned
13
July 2004
Why BOT/PPP/PFI is a success
• Save money when looking at LCC
• Possible to realize earlier
• Easier procurement – international tender
• Faster execution
• Known maximum cost, no cost overruns
• Access to investments earlier will boost economy
• Off Balance sheet
• Alternative to conventional way
Lessons Learned
14
July 2004
Keys Reasons for Failure
• Project not commercially viable if the state does not make it feasible for the investor
“Value for money”
• Government abandons the Project
• Failure in the Consortium- Disagreement between parties- Changed priorities- Economy
• Public disapproval
• Mismatch in expectations between public and private sector
• Wrong risk allocation – right part to carry the risk. Don´t push all risk down excessively - not financiable
Lessons Learned
15
July 2004
UK’s National Audit Office published a report on PFI on 5 February 2003
Improved
Project
Delivery
Non PPP Procurement (1999 Survey)
PPP Procurement (2002 Survey)
Price
Overruns
73% 22% (mostly client changes)
Time
Overruns
70% 24% (only 8% > 2 months)
Lessons Learned
16
July 2004
Where are the obstacles in the public sector?
17
July 2004
Opponent opinions on BOT/PPP- and comments thereon 1(2)
• Interest rates and equity returns more expensive than government bonds
- But different risk distribution gives lower overall cost
• Only large contractors are big enough to compete for these projects
- Very often these deals attract international contractors using local companies as subcontractors
• Costly and complex transaction- But with enough size and right structure good value for money
• Gives wrong priority of projects- It is the politicians not the private sector who decide priorities,
irrespective of traditional or BOT/PPP procurement
• Commit our children- But is it wrong to spread the project cost over the economic life time
of the facility being normally 20-40 years ?
Obstacles
18
July 2004
Opponent opinions on BOT/PPP – and comments thereon 2(2)
• Our country cannot afford a new project- Casualties go down on motorways - political responsibility?- Pollution in congestions higher than traffic flow- Operational costs lower in modern buildings than old- Transport infrastructure stimulate regional development- Infrastructure development drives economic growth
• Testing new concepts will improve effectiveness of public as well as private sectors- Is it political responsibility to do nothing or not to try
changes?
Obstacles
19
July 2004
Value for Money (VfM) Assessment
Value/“price”
Conventional Procurement
PSC
PFIProcurement
Whole life cost of procuring services
Cost of finance
Risks retained by Public Sector
VfM
20
July 2004
To conclude.... - BOT/PPP is like a marriage
• You flirt, fall in love and enter into contract
• Hopefully a long duration
• Quality of service depends on maintenance
• Objectivity and rational not always ruling
• There are good and bad times
• Recourse to lawyers in case of dispute
21
July 2004
Walsgrave Hospital, UK
Nelostie Motorway Project, Finland North-South Highway, Chile
Kings College Hospital, UK
Skanska BOT investments
Maputo Port, Mozambique
Derby Hospital, UK
Ponte de Pedra Hydro, Brazil
Bridgend Prison, UK
Breitener Energy Plant, Brazil
St Petersburg Waste water,
Russia
Orkdalsvegen, Norway Bexley Schools, UK