1ISE 491 - Ch. 8
The Resource Problem
Resources and Priorities Project network times are not a schedule until
resources have been assigned. The implicit assumption is that resources will be available in
the required amounts when needed. Adding new projects requires making realistic judgments of
resource availability and project durations.
Resource-Constrained Scheduling Resource leveling (or smoothing) involves attempting
to even out demands on resources by using slack (delaying noncritical activities) to manage resource utilization.
![Page 2: 1 ISE 491 - Ch. 8 The Resource Problem Resources and Priorities Project network times are not a schedule until resources have been assigned. The implicit](https://reader036.vdocuments.us/reader036/viewer/2022070400/56649f0e5503460f94c2323a/html5/thumbnails/2.jpg)
2ISE 491 - Ch. 8
Types of Project Constraints Technical or Logic Constraints
Constraints related to the networked sequence in which project activities must occur
Resource Constraints The absence, shortage, or unique interrelationship
and interaction characteristics of resources that require a particular sequencing of project activities
![Page 3: 1 ISE 491 - Ch. 8 The Resource Problem Resources and Priorities Project network times are not a schedule until resources have been assigned. The implicit](https://reader036.vdocuments.us/reader036/viewer/2022070400/56649f0e5503460f94c2323a/html5/thumbnails/3.jpg)
3ISE 491 - Ch. 8
Constraint Examples
FIGURE 8.2
![Page 4: 1 ISE 491 - Ch. 8 The Resource Problem Resources and Priorities Project network times are not a schedule until resources have been assigned. The implicit](https://reader036.vdocuments.us/reader036/viewer/2022070400/56649f0e5503460f94c2323a/html5/thumbnails/4.jpg)
4ISE 491 - Ch. 8
A third constraint: Physical
![Page 5: 1 ISE 491 - Ch. 8 The Resource Problem Resources and Priorities Project network times are not a schedule until resources have been assigned. The implicit](https://reader036.vdocuments.us/reader036/viewer/2022070400/56649f0e5503460f94c2323a/html5/thumbnails/5.jpg)
5ISE 491 - Ch. 8
Kinds of resource constraints
People
skills, availability, priorities
Materials
availability, delivery schedule
Equipment
capability, availability, scheduling
Working Capital
availability, reliability, timing
![Page 6: 1 ISE 491 - Ch. 8 The Resource Problem Resources and Priorities Project network times are not a schedule until resources have been assigned. The implicit](https://reader036.vdocuments.us/reader036/viewer/2022070400/56649f0e5503460f94c2323a/html5/thumbnails/6.jpg)
6ISE 491 - Ch. 8
Classification of a scheduling problem
Classification of Problem Using a priority matrix will help determine if the project is
time or resource constrained
Time Constrained Project A project that must be completed by an imposed date
Time is fixed, resources are flexible: additional resources are required to ensure project meets schedule.
Resource Constrained Project A project in which the level of resources available cannot
be exceeded Resources are fixed, time is flexible: inadequate resources will
delay the project.
![Page 7: 1 ISE 491 - Ch. 8 The Resource Problem Resources and Priorities Project network times are not a schedule until resources have been assigned. The implicit](https://reader036.vdocuments.us/reader036/viewer/2022070400/56649f0e5503460f94c2323a/html5/thumbnails/7.jpg)
7ISE 491 - Ch. 8
Resource allocation methods
Limiting Assumptions Splitting activities is not allowed—once an activity is
start, it is carried to completion. Level of resource used for an activity cannot be
changed. Activities with the most slack pose the least risk. Reduction of flexibility does not increase risk. The nature of an activity (easy, complex) doesn’t
increase risk.
![Page 8: 1 ISE 491 - Ch. 8 The Resource Problem Resources and Priorities Project network times are not a schedule until resources have been assigned. The implicit](https://reader036.vdocuments.us/reader036/viewer/2022070400/56649f0e5503460f94c2323a/html5/thumbnails/8.jpg)
8ISE 491 - Ch. 8
Resource allocation methods (cont’d)
Time-Constrained Projects
Projects that must be completed by an imposed date
Require the use of leveling techniques that focus on balancing or smoothing resource demands by using positive slack (delaying noncritical activities) to manage resource utilization over the duration of the project
Peak resource demands are reduced.
Resources over the life of the project are reduced.
Fluctuation in resource demand is minimized.
![Page 9: 1 ISE 491 - Ch. 8 The Resource Problem Resources and Priorities Project network times are not a schedule until resources have been assigned. The implicit](https://reader036.vdocuments.us/reader036/viewer/2022070400/56649f0e5503460f94c2323a/html5/thumbnails/9.jpg)
9ISE 491 - Ch. 8
Example: Botanical Garden project
Resource: backhoe costs associated with use competition for the resource
FIGURE 8.3
![Page 10: 1 ISE 491 - Ch. 8 The Resource Problem Resources and Priorities Project network times are not a schedule until resources have been assigned. The implicit](https://reader036.vdocuments.us/reader036/viewer/2022070400/56649f0e5503460f94c2323a/html5/thumbnails/10.jpg)
10ISE 491 - Ch. 8
Botanical Garden (cont’d)
FIGURE 8.3 (cont’d)
![Page 11: 1 ISE 491 - Ch. 8 The Resource Problem Resources and Priorities Project network times are not a schedule until resources have been assigned. The implicit](https://reader036.vdocuments.us/reader036/viewer/2022070400/56649f0e5503460f94c2323a/html5/thumbnails/11.jpg)
11ISE 491 - Ch. 8
Resource allocation methods (cont’d)
Resource demand leveling techniques for time-constrained projects
Advantages Peak resource demands are reduced.
Resources over the life of the project are reduced.
Fluctuation in resource demand is minimized.
Disadvantages Loss of flexibility that occurs from reducing slack
Increases in the criticality of all activities
![Page 12: 1 ISE 491 - Ch. 8 The Resource Problem Resources and Priorities Project network times are not a schedule until resources have been assigned. The implicit](https://reader036.vdocuments.us/reader036/viewer/2022070400/56649f0e5503460f94c2323a/html5/thumbnails/12.jpg)
12ISE 491 - Ch. 8
Resource allocation methods (cont’d)
Resource-constrained projects Projects that involve resources that are limited in
quantity or by their availability Scheduling of activities requires the use of heuristics
(rules-of-thumb) that focus on:1. Minimum slack
2. Smallest (least) duration
3. Lowest activity identification number
The parallel method is used to apply heuristics. An iterative process that starts at the first time period of the
project and schedules period-by-period any activities scheduled to start using the three priority rules
![Page 13: 1 ISE 491 - Ch. 8 The Resource Problem Resources and Priorities Project network times are not a schedule until resources have been assigned. The implicit](https://reader036.vdocuments.us/reader036/viewer/2022070400/56649f0e5503460f94c2323a/html5/thumbnails/13.jpg)
13ISE 491 - Ch. 8
Example: Resource-constrained schedule Resource constraint: 3 programmers
FIGURE 8.4
![Page 14: 1 ISE 491 - Ch. 8 The Resource Problem Resources and Priorities Project network times are not a schedule until resources have been assigned. The implicit](https://reader036.vdocuments.us/reader036/viewer/2022070400/56649f0e5503460f94c2323a/html5/thumbnails/14.jpg)
14ISE 491 - Ch. 8
Resource-constrained schedule Resource load chart (no constraints showing)
FIGURE 8.4 (cont’d)
ES resource load chartES resource load chartES resource load chartES resource load chart
![Page 15: 1 ISE 491 - Ch. 8 The Resource Problem Resources and Priorities Project network times are not a schedule until resources have been assigned. The implicit](https://reader036.vdocuments.us/reader036/viewer/2022070400/56649f0e5503460f94c2323a/html5/thumbnails/15.jpg)
15ISE 491 - Ch. 8
Resource-constrained schedule (cont.)
Going from period to period, schedule activities according to the rules (see pg. 241)
FIGURE 8.4 (cont’d)
Resource-constrained schedule through period 2–3Resource-constrained schedule through period 2–3Resource-constrained schedule through period 2–3Resource-constrained schedule through period 2–3
![Page 16: 1 ISE 491 - Ch. 8 The Resource Problem Resources and Priorities Project network times are not a schedule until resources have been assigned. The implicit](https://reader036.vdocuments.us/reader036/viewer/2022070400/56649f0e5503460f94c2323a/html5/thumbnails/16.jpg)
16ISE 491 - Ch. 8
Resource-constrained schedule (cont.)
FIGURE 8.5
Resource-constrained schedule through period 5–6Resource-constrained schedule through period 5–6Resource-constrained schedule through period 5–6Resource-constrained schedule through period 5–6
![Page 17: 1 ISE 491 - Ch. 8 The Resource Problem Resources and Priorities Project network times are not a schedule until resources have been assigned. The implicit](https://reader036.vdocuments.us/reader036/viewer/2022070400/56649f0e5503460f94c2323a/html5/thumbnails/17.jpg)
17ISE 491 - Ch. 8
Resource-constrained schedule (cont.)
Final schedule shows delay in project completion and loss of flexibility
FIGURE 8.5 (cont’d)
Final resource-constrained scheduleFinal resource-constrained scheduleFinal resource-constrained scheduleFinal resource-constrained schedule
![Page 18: 1 ISE 491 - Ch. 8 The Resource Problem Resources and Priorities Project network times are not a schedule until resources have been assigned. The implicit](https://reader036.vdocuments.us/reader036/viewer/2022070400/56649f0e5503460f94c2323a/html5/thumbnails/18.jpg)
18ISE 491 - Ch. 8
Resource-constrained schedule (cont.)
FIGURE 8.5 (cont’d)New, resource-constrained networkNew, resource-constrained networkNew, resource-constrained networkNew, resource-constrained network