1. introduction to prm
TRANSCRIPT
7/28/2019 1. Introduction to PRM
http://slidepdf.com/reader/full/1-introduction-to-prm 1/19
Introduction to Project Management
7/28/2019 1. Introduction to PRM
http://slidepdf.com/reader/full/1-introduction-to-prm 2/19
2
Project
• Project is any work that has: A well defined objective / goal
Sequence of the multitudinous activities
A specific start and end
• Project Characteristics The start is known as source and end is known as sink
A project can have multiple sources (start) but will have a
single sink (end)
• Examples: Building of a dam, Bandra-Worli sea link,
Chandrayaan, Repair of a machine etc.
7/28/2019 1. Introduction to PRM
http://slidepdf.com/reader/full/1-introduction-to-prm 3/19
3
Project Feasibility Analysis
1. Generation of project ideaso Constrains to be considered are physical, human and
financial resources
2. Screening of generated ideaso On the basis of priority and later on available resources
3. Detailed evaluation of the screened projecto Analysis of technical feasibility
o Measurement of cost
o Measurement of benefits
o Comparison of benefits & cost
• Project Management is the scientific way of planning,
implementing, monitoring & controlling various aspects of
a project such as time, money, materials, manpower and
other resources
7/28/2019 1. Introduction to PRM
http://slidepdf.com/reader/full/1-introduction-to-prm 4/19
4
Project Planning & Control
• Tools for project planning and control Network Techniques
o Critical Path Method (CPM)
o Programme Evaluation & Review Technique (PERT)
Bar charts e.g Gantt Chart
• Comparison of Bar charts & Network techniques Bar charts does not show relationship between jobs
Charts are static
Networks shows relationship in jobs and required resources
7/28/2019 1. Introduction to PRM
http://slidepdf.com/reader/full/1-introduction-to-prm 5/19
5
Gantt Chart
Date
Activities
1 2 3 4 5 6 7 8
A
B
C
D
E
F
7/28/2019 1. Introduction to PRM
http://slidepdf.com/reader/full/1-introduction-to-prm 6/19
6
Network Diagram / Arrow Diagram / Node diagram
1
2
3
4
5
6
7
8
Source /
Start
Sink /
End
Nodes
3A
3G
7B
5C
9D
6E
7F 3
I
2H
7/28/2019 1. Introduction to PRM
http://slidepdf.com/reader/full/1-introduction-to-prm 7/19
Problem 1
For a project consisting of several activities, the duration and required resources
to carry out each of the activities and their availabilities are given below:-
Activity Duration Men required
•Draw the Gantt chart & Resource Graph
•Resource availability = No of men = 50
7/28/2019 1. Introduction to PRM
http://slidepdf.com/reader/full/1-introduction-to-prm 8/19
Problem 1 – contd . .
Days
Activities
1 - 2
1 - 6
2 - 3
2 - 4
3 – 5
4 - 5
5 - 7
6 - 7
7 - 8
30
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
20
30
20
30
20
30
20
20
Resources 50 70
50
30 20
7/28/2019 1. Introduction to PRM
http://slidepdf.com/reader/full/1-introduction-to-prm 9/19
Problem 1 – contd . .
Class Intervals No of men
7/28/2019 1. Introduction to PRM
http://slidepdf.com/reader/full/1-introduction-to-prm 10/19
Problem 1 – contd . .
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
80
70
60
50
40
30
20
10
Men
Days
7/28/2019 1. Introduction to PRM
http://slidepdf.com/reader/full/1-introduction-to-prm 11/19
Problem - 2
The following table gives for each activity of a project its duration and
corresponding resource requirements and total availability of each resource
Resource required
Activity
1 - 2
• Draw Gantt chart
• Comment on demand of men and machines for entire project
7/28/2019 1. Introduction to PRM
http://slidepdf.com/reader/full/1-introduction-to-prm 12/19
Problem 3
A project consist of 7 activities for which the relevant data are given below:
Activity Preceding Activity Duration
•Draw the Gantt chart
7/28/2019 1. Introduction to PRM
http://slidepdf.com/reader/full/1-introduction-to-prm 13/19
Problem 3 – contd . .
DaysActivities
A
B
C
D
E
F
G
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
7/28/2019 1. Introduction to PRM
http://slidepdf.com/reader/full/1-introduction-to-prm 14/19
Problem 4 (Practice)
Draw the Gantt Chart and Resource Graph for the project schedule based on
the table below
Duration Workers
Activity Preceding Act
G C , D 5 5
H E 6 4
I F 6 5
• Calculate total time for completion
• Find days of over allocation of workers if maximum available are 20
7/28/2019 1. Introduction to PRM
http://slidepdf.com/reader/full/1-introduction-to-prm 15/19
Problem 5
Activity Start End Cost
Duration (months)
G 3 Nov 01 Jan 02 75000
H 7 July 01 Jan 02 70000
I 10 Feb 02 Nov 02 150000
• Assume that activity start in beginning of month and finish at end of month
•Draw Gantt chart and work out monthly aid and cumulative cash flows
•Draw S curve for cash flows
7/28/2019 1. Introduction to PRM
http://slidepdf.com/reader/full/1-introduction-to-prm 16/19
Problem 5 . . contd
Activity Cost Cost / month
Duration (months)
G 3 75000 25000
H 7 70000 10000
I 10 150000 15000
7/28/2019 1. Introduction to PRM
http://slidepdf.com/reader/full/1-introduction-to-prm 17/19
Problem 5 – contd . .
DaysActivities
A
B
C
D
E
F
G
H
I
J
20
M a y 0
1
J u n 0 1
J u l 0 1
A u g 0
1
S e p 0
1
O c t 0 1
N o v 0
1
D e c 0
1
J a n 0 2
F e b 0
2
M a r 0
2
A p r 0 2
M a y 0
2
J u n 0 2
J u l 0 2
A u g 0
2
S e p 0
2
O c t 0 2
N o v 0
2
D e c 0
2
30
15
5
25
20
25
10
15
40
cost 4 5 4 5 5 0 5 0 7 5 7 5 7 0 5 0 5 0 3 0 2 0 2 0 2 0 2 0 2 0 2 0 2 0 2 0 2 0 4 0
7/28/2019 1. Introduction to PRM
http://slidepdf.com/reader/full/1-introduction-to-prm 18/19
Problem 5 – contd . .
M a y 0 1
J u n
0 1
J u l
0 1
A u g
0 1
S e p
0 1
O c t
0 1
N o v
0 1
D e c
0 1
J a n
0 2
F e b
0 2
M a r 0 2
A p r
0 2
M a y 0 2
J u n
0 2
J u l
0 2
A u g
0 2
S e p
0 2
O c t
0 2
N o v
0 2
D e c
0 2
Time
50
100
150
200250
300
350
400
450
500
550600
650
700
750
800
850
850
900
950
1000
C u m u l a t
i v e C o s t (750)