1. introduction to prm

19
Introduction to Project Management

Upload: amitrao1983

Post on 03-Apr-2018

215 views

Category:

Documents


0 download

TRANSCRIPT

7/28/2019 1. Introduction to PRM

http://slidepdf.com/reader/full/1-introduction-to-prm 1/19

Introduction to Project Management

7/28/2019 1. Introduction to PRM

http://slidepdf.com/reader/full/1-introduction-to-prm 2/19

2

Project

• Project is any work that has:  A well defined objective / goal

Sequence of the multitudinous activities

 A specific start and end

• Project Characteristics The start is known as source and end is known as sink

 A project can have multiple sources (start) but will have a

single sink (end)

• Examples: Building of a dam, Bandra-Worli sea link,

Chandrayaan, Repair of a machine etc.

7/28/2019 1. Introduction to PRM

http://slidepdf.com/reader/full/1-introduction-to-prm 3/19

3

Project Feasibility Analysis

1. Generation of project ideaso Constrains to be considered are physical, human and

financial resources

2. Screening of generated ideaso On the basis of priority and later on available resources

3. Detailed evaluation of the screened projecto  Analysis of technical feasibility

o Measurement of cost

o Measurement of benefits

o Comparison of benefits & cost

• Project Management is the scientific way of planning,

implementing, monitoring & controlling various aspects of 

a project such as time, money, materials, manpower and

other resources

7/28/2019 1. Introduction to PRM

http://slidepdf.com/reader/full/1-introduction-to-prm 4/19

4

Project Planning & Control

• Tools for project planning and control Network Techniques

o Critical Path Method (CPM)

o Programme Evaluation & Review Technique (PERT)

Bar charts e.g Gantt Chart

• Comparison of Bar charts & Network techniques Bar charts does not show relationship between jobs

Charts are static

Networks shows relationship in jobs and required resources

7/28/2019 1. Introduction to PRM

http://slidepdf.com/reader/full/1-introduction-to-prm 5/19

5

Gantt Chart

Date

Activities

1 2 3 4 5 6 7 8

A

B

C

D

E

F

7/28/2019 1. Introduction to PRM

http://slidepdf.com/reader/full/1-introduction-to-prm 6/19

6

Network Diagram / Arrow Diagram / Node diagram

1

2

3

4

5

6

7

8

Source /

Start

Sink /

End

 Nodes

3A

3G

7B

5C

9D

6E

7F 3

I

2H

7/28/2019 1. Introduction to PRM

http://slidepdf.com/reader/full/1-introduction-to-prm 7/19

Problem 1

For a project consisting of several activities, the duration and required resources

to carry out each of the activities and their availabilities are given below:-

Activity Duration Men required

•Draw the Gantt chart & Resource Graph

•Resource availability = No of men = 50

7/28/2019 1. Introduction to PRM

http://slidepdf.com/reader/full/1-introduction-to-prm 8/19

Problem 1 – contd . .

Days

Activities

1 - 2

1 - 6

2 - 3

2 - 4

3 – 5

4 - 5

5 - 7

6 - 7

7 - 8

30

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32

20

30

20

30

20

30

20

20

Resources 50 70

50

30 20

7/28/2019 1. Introduction to PRM

http://slidepdf.com/reader/full/1-introduction-to-prm 9/19

Problem 1 – contd . .

Class Intervals No of men

7/28/2019 1. Introduction to PRM

http://slidepdf.com/reader/full/1-introduction-to-prm 10/19

Problem 1 – contd . .

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32

80

70

60

50

40

30

20

10

Men

Days

7/28/2019 1. Introduction to PRM

http://slidepdf.com/reader/full/1-introduction-to-prm 11/19

Problem - 2

The following table gives for each activity of a project its duration and

corresponding resource requirements and total availability of each resource

Resource required

Activity

1 - 2

• Draw Gantt chart

• Comment on demand of men and machines for entire project

7/28/2019 1. Introduction to PRM

http://slidepdf.com/reader/full/1-introduction-to-prm 12/19

Problem 3

 A project consist of 7 activities for which the relevant data are given below:

Activity Preceding Activity Duration

•Draw the Gantt chart

7/28/2019 1. Introduction to PRM

http://slidepdf.com/reader/full/1-introduction-to-prm 13/19

Problem 3 – contd . .

DaysActivities

A

B

C

D

E

F

G

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32

7/28/2019 1. Introduction to PRM

http://slidepdf.com/reader/full/1-introduction-to-prm 14/19

Problem 4 (Practice)

Draw the Gantt Chart and Resource Graph for the project schedule based on

the table below

Duration Workers

Activity Preceding Act

G C , D 5 5

H E 6 4

I F 6 5

• Calculate total time for completion

• Find days of over allocation of workers if maximum available are 20

7/28/2019 1. Introduction to PRM

http://slidepdf.com/reader/full/1-introduction-to-prm 15/19

Problem 5

Activity Start End Cost

Duration (months)

G 3 Nov 01 Jan 02 75000

H 7 July 01 Jan 02 70000

I 10 Feb 02 Nov 02 150000

• Assume that activity start in beginning of month and finish at end of month

•Draw Gantt chart and work out monthly aid and cumulative cash flows

•Draw S curve for cash flows

7/28/2019 1. Introduction to PRM

http://slidepdf.com/reader/full/1-introduction-to-prm 16/19

Problem 5 . . contd

Activity Cost Cost / month

Duration (months)

G 3 75000 25000

H 7 70000 10000

I 10 150000 15000

7/28/2019 1. Introduction to PRM

http://slidepdf.com/reader/full/1-introduction-to-prm 17/19

Problem 5 – contd . .

DaysActivities

A

B

C

D

E

F

G

H

I

J

20

   M  a  y   0

   1

   J  u  n   0   1

   J  u   l   0   1

   A  u  g   0

   1

   S  e  p   0

   1

   O  c   t   0   1

   N  o  v   0

   1

   D  e  c   0

   1

   J  a  n   0   2

   F  e   b   0

   2

   M  a  r   0

   2

   A  p  r   0   2

   M  a  y   0

   2

   J  u  n   0   2

   J  u   l   0   2

   A  u  g   0

   2

   S  e  p   0

   2

   O  c   t   0   2

   N  o  v   0

   2

   D  e  c   0

   2

30

15

5

25

20

25

10

15

40

cost    4   5    4   5    5   0    5   0    7   5    7   5    7   0    5   0    5   0    3   0    2   0    2   0    2   0    2   0    2   0    2   0    2   0    2   0    2   0    4   0

7/28/2019 1. Introduction to PRM

http://slidepdf.com/reader/full/1-introduction-to-prm 18/19

Problem 5 – contd . .

   M  a  y   0   1

   J  u  n

   0   1

   J  u   l

   0   1

   A  u  g

   0   1

   S  e  p

   0   1

   O  c   t

   0   1

   N  o  v

   0   1

   D  e  c

   0   1

   J  a  n

   0   2

   F  e   b

   0   2

   M  a  r   0   2

   A  p  r

   0   2

   M  a  y   0   2

   J  u  n

   0   2

   J  u   l

   0   2

   A  u  g

   0   2

   S  e  p

   0   2

   O  c   t

   0   2

   N  o  v

   0   2

   D  e  c

   0   2

Time

50

100

150

200250

300

350

400

450

500

550600

650

700

750

800

850

850

900

950

1000

   C  u  m  u   l  a   t

   i  v  e   C  o  s   t (750)

7/28/2019 1. Introduction to PRM

http://slidepdf.com/reader/full/1-introduction-to-prm 19/19

Problem 6 (Practice)

Activity Cost / month

Duration (months)

4-5 2 60000

5-6 3 20000

•Draw Gantt chart and work out monthly aid and cumulative cash flows

•Draw S curve for cash flows