INALA TECHNOLOGIESINSTALLATION TRAINING: ECS (EQUIPMENT COMMUNICATIONS SYSTEM) ECS (ETH/E1) COMMISSIONING
VERSION 1.0
2 |
ECS (ETH/E1) COMMISSIONINGCOMMISSIONING: ECS (ETH/E1) PROCEDURE
3 | SAM Training
ECS (ETH / E1) - COMMISSIONING
Setting up of the unit:• Power unit on• Connect using the ITMS ECT• Set-up the communication ports for the devices you are connecting to it• Set-up the Sever IP address • Click on set after making a change to save the configuration to the unit.• Call to commission site with representative.
Port Settings• SAM1.5 = Physical port 8 – Virtual Port 310, Baud rate 19200.• L&G = Physical port 10 – Virtual Port 309, Baud rate 19200• SAM2 & Access Control = Physical port RS485 – Virtual Port 301, Baud
rate 9600
ECS (E1/Eth) Communication Cable:• A “Straight RS232” cable must be used between the ECS-L and the computer.
(DB9 to IDC 10Way)• Once Connected open the “ITMS-C ECT” software.• Input User Name and Password, select “Serial Communication) and Click on
Login
*Note – Check following slide for detail information of above procedure
4 | SAM Training
ECS (ETH / E1) – PHYSICAL PORT NUMBERS
SP6 pluggable moduleEquipment Communications Controller (ECS)
RS485 Port
Port 1 – RS232
Port 10 – RS485
Port 9 – RS485 Port 8 – RS232
Port 7 – RS232
Port 6 – RS232 Port 5 – RS232
Port 4 – RS232
Port 3 – RS232
* The physical port that is connected to the SAM or Access Control must be selected as the
“UDP PORT”
Earth48vdc G
ND
5 | SAM Training
SOFTWARE FOR FULL ECS(ETH/E1) (EQUIPMENT COMMUNICATION CONTROLLER)
Communication Controller Software (ECT):ECT Version is viewed on the top left corner as indicated with the yellow circleEG: “ITMS-C Ver 2.12”
Firmware Version is viewed on the button left corner as indicated with the Red circleEG: “S/W: 4.0.1.4”
Set IP addresses as received from operator as indicated in the blue circle. After IP addresses has been completed, click on set to save them to the communications controller
6 | SAM Training
SOFTWARE FOR FULL ECS(ETH/E1) (EQUIPMENT COMMUNICATION CONTROLLER) – PORT SETUP
Port Set UP:The ports should be set-up as per the screen shot for a standard Vodacom BTS site.PORT - This is the physical port on the unitPort No. - This is the virtual port number allocated to a specific devicePort Name – You are able to label the port with the device you have connected to it.Baud rate – Select the appropriate baud rate for the deviceFlow Control – select the appropriate flow control for the deviceProtocol – Select the appropriate protocol for the device
Physical Port Type of PortRS485 Port RS485Port 1 RS232Port 3 RS232Port 4 RS232Port 5 RS232Port 6 RS232Port 7 RS232Port 8 RS232Port 9 RS485Port 10 RS485
7 | SAM Training
EQUIPMENT COMMUNICATION CONTROLLER – PORT & SERVER ALLOCATIONS
Virtual Port Allocations
301 SAM2 or SAM3 and Access Control
302 Rectifier A
303 Rectifier B
304 Generator
305 AVR
306 BMON
307 Fuel Cell 1308 Fuel Cell 2
309 Energy Meter / Fire System310 SAM 1.5 REC
Vodacom Server Name Vodacom UDP Server IP UDP Server Port
ZABLV06101 - CEN 10.121.5.165 299
ZABLV06102 - EAS 10.121.5.153 299
ZABLV06103 - LIM 10.121.5.154 299
ZABLV06104 - MPU 10.121.5.155 299
ZABLV06105 - SGC 10.121.5.156 299
ZABLV06106 - SGS 10.121.5.157 299
ZABLV06107 - WES 10.121.5.158 299
NGA Existing Server 10.102.242.202 299
Telkom Server Name Telkom UDP Server IP UDP Server Port
10.149.104.56 2999
Neotel Server Name Neotel UDP Server IP UDP Server Port
172.24.146.4 299
Operator Name APN Name
Vodacom Vodameter
Neotel internet
8 | SAM Training
EQUIPMENT COMMUNICATION CONTROLLER – COMS WIRINGCommunication Cable Consumables
ECS (Eth/E1), ECS-L
1. 10 way Ribbon Cable2. 10 way IDC connector for 10 way ribbon cable3. DB9 IDC, male and female for 10 way ribbon cable
ECS (Eth/GPRS), ECS (Eth/E1) & ECS-L
1. DB9, male and female, solder type2. Milar cable used with point 1 above (Same as SAM2 Coms cross over cable)
ECS (Eth/GPRS), ECS (Eth/E1) & ECS-L
1. RJ9 – small 4 way2. RJ11 – large 4 way3. RJ12 - 6 way4. RJ45 – 8way5. Cable for each above6. CAT5 cable
Possible Communication Cables needed
1. SAM1.52. SAM2, SAM3 & Access Control3. Energy Meter (Landis & Gyrr) Rectifier4. Rectifier (Battery Tech, Grintek, ASM, etc)5. Generator (Lovato, Deep Sea, Intellilite, etc)6. Fuel Cell (Idatech, Gencore, etc)
9 | SAM Training
ECS (ETH/E1) COMMUNICATION WIRINGSAM2 & ACCESS CONTROL
10 | SAM Training
ECS (ETH/E1) COMMUNICATION WIRINGSAM1.5
11 | SAM Training
ECS (ETH/E1) COMMUNICATION WIRINGLANDIS & GYRR
12 | SAM Training
ECS (ETH/E1) COMMUNICATION WIRINGBATTERY TECH SM50
13 | SAM Training
ECS (ETH/E1) COMMUNICATION WIRINGBATTERY TECH SM65
14 | SAM Training
ECS (ETH/E1) COMMUNICATION WIRINGGRINTEK GT500
15 | SAM Training
ECS (ETH/E1) COMMUNICATION WIRINGDEEP SEA
16 | SAM Training
ECS (ETH/E1) COMMUNICATION WIRING LOVATO
17 |
CLICK TO EDIT MASTER TITLE STYLE