1 details of parties...(d) contact details for network rail: duncan lovatt & richard hooper,...
TRANSCRIPT
1
1 DETAILS OF PARTIES
1.1 The names and addresses of the parties to the reference are as follows;
(a) DB Cargo (UK) Limited whose Registered Office is at Lakeside Business Park, Carolina Way,
Doncaster, South Yorkshire, DN4 5PN (“DBC”) (“The Claimant”); and
(b) Network Rail Infrastructure Limited whose Registered Office is at 1 Eversholt Street, London
NW1 2DN (“Network Rail”) (“The Respondent”).
(c) Contact details for DB Cargo: Graham White, Access Manager South, Lakeside Business
Park, Carolina Way, Doncaster, South Yorkshire, DN4 5PN.
(d) Contact details for Network Rail: Duncan Lovatt & Richard Hooper, Network Rail, Wales
Route.
2 DETAILS OF REFERENCE
2.1 This matter is referred to a Timetable Panel (“the Panel”) for determination in accordance with Condition
D5 of the Network Code
2.2 This Dispute arises from a decision of Network Rail in respect of Network Rail variations made pursuant
to Condition D3.5 of the Network Code
3 CONTENTS OF REFERENCE
This Sole Reference includes: -
(a) The subject matter of the dispute in Section 4;
(b) A detailed explanation of the issues in dispute in Section 5;
(c) In Section 6, the decision sought from the panel in respect of legal entitlement.
4 SUBJECT MATTER OF DISPUTE
4.1 This dispute arises from the Late Notice Restrictions of Use between Stoke Gifford No 2/ Caldicot and
Leckwith Loop North Jn from 0200 on Saturday 19th October to 0420 on Monday 21st October 2019.
Possession Reference P2019/2680990
4.2 Copied and annexed to this Reference are:
• Appendix A: DB Cargo (UK) Ltd response to 157-W30-WA19 (original) [Part]
• Appendix B: Re-Issued request 157-W30-WA19
2
• Appendix C: DB Cargo (UK) Ltd response to 157-W30-WA19 (subsequent re-issue) [Part]
• Appendix D: Decision document for Re-Issued request 157-WA30-WA19 [Part]
• Appendix E: Works planned within the restriction of use.
5 DETAILED EXPLANATION OF THE DISPUTE
5.1 Network Rail, on Thursday 29th August 2019 sent out a meeting invitation for the following day, Friday
30th August to discuss further access required to for Electrification on Wales route. It should be noted
that I was on leave on those 2 days and no other DB Cargo invitees were included on the distribution
list. An ‘out of office’ response would have been sent. A follow-up meeting was held on Wednesday 4th
September when I expressed DB Cargo’s dismay at the request of another request for disruptive access
on the South Wales Main Line. This should be viewed in the context of the original plan was that similar
all line Restrictions of use in weeks 18 (0100 Saturday 27th to 0515 Monday 29th July 2019
(P2019/2556319)) and 25 (0120 Saturday 14th to 0450 Monday 16th September (P2019/2560805) plus
14-hour blocks with similar limits in 7 additional weekends should have delivered an Electrified Railway
between London and Cardiff. That these restrictions of use did not deliver this outcome and the work
type changed to be for construction; and in the case of Week 25 the limits extended from the CPPP
(originally Gaer Jn to Leckwith Loop North Jn) gave us cause for concern with the likelihood of further
disruptive access being required. Subsequently another restriction of use was proposed for a blockade
in weeks 39 and 40 (2330 Tuesday 24th to 0400 Tuesday 31st December 2019 (P2019/2617006)
adjacent to, but not fully under cover of the Newport S&C blockade (P2019/2529959).
5.2 At that 4th September 2019 follow up meeting I stated DB Cargo’s requirement to have route throughout
the Restriction of use, except for the Sunday 14 hour all line restriction of use previously agreed;
between Leckwith Loop North Jn and Caldicot with access to both the East and West ends of Llanwern
steelworks. Our principal (but not only) customers TATA steel and Puma energy require a smooth
supply chain and the prospect of interrupting that supply chain causes them concern. In the case of
TATA Steel, they require a constant cycling of wagons at Margam (empties in and loaded out) as if this
supply dries up they have to cease Steel production at great cost.
3
PUMA Energy require to service their terminals at Westerleigh and Theale with product, mostly heating
oil that supplies domestic and business customers over a wide area. As the weather gets colder the
requirement for product is correspondingly greater and restrictions of use cause greater issues at the
end of October (week 30) as opposed to end of July (week 18) and the middle of September (week 25).
The week following this restriction of use requires the overnight Westerleigh service to divert via the
Vale of Glamorgan requiring trains to be downloaded (by 5 wagons) so placing further restrictions on the
ability to replenish stocks.
5.3 The proposal was received at 1306 on Thursday 5 th September with a 5 working day response period
and DB Cargo’s response was sent at 1045 on Friday 6 th September restating that we required a route
as shown in 5.2 above [see appendix A]. Network Rail issued the Decision document at 1046 on
Thursday 12th September and subsequently withdrew it at 1528 the same afternoon; I believe because
the original proposal did not comply with Condition D3.4.4 (a). The Proposal was re-issued at 1538 the
same afternoon again with a 5 working day response [See appendix B] and DB Cargo’s response
subsequently sent at 0901 on Friday13th September restating our requirement for a through route [See
Appendix C].
The final Decision was issued at 1203 on Friday 20 th September, 4 weeks prior to the restriction of use
being taken.
5.4 The Decision document itself gives the reasons for it being required as ‘to facilitate further work in
connection with the Great Western Electrification project’ which is exceptionally vague , especially as the
request states that the Restriction of use is specifically for the ’commissioning of OHE, the testing of
OLE to Newport and construction to Cardiff West Jn’ [See Appendix B]. Given that there had already
been 2 additional 50-hour restrictions of use for construction it might be expected that the decision
should show a bit more detail to enable operators to understand that need for this restriction of use .I
requested of Network Rail that they provide a list of the activities that were taking place within this
restriction of use and which was subsequently provided and shown in Appendix E. The long list of
activities gives concern that further restrictions of use may be required given that work specifically for
Electrification on this list should have been completed prior to week 18.
4
5.5 I have also sought from Network Rail an understanding of their use of the decision criteria and the
weighting given the considerations as shown in Condition D4.6.2; namely ‘(f) the commercial interest of
…/… any Timetable Participant that Network Rail is aware’ and (j) enabling operators of trains to use
their assets efficiently. Network Rail have not provided this information to date. It is noted that Condition
D4.6 doesn’t require Network Rail to publish its conclusion in circumstances such as this but I contend
that it is desirable; without this information it is impossible to understand what the overarching
imperative in issuing this Decision is? My contention is that Network Rail’s to desire to get the project
completed at any cost to meet an ‘internal’ deadline go against the requirement of DB Cargo’s
commercial interests given the financial and reputational damage this Decision serves on us and our
customers and that interest has not been given enough weight in the Decision Criteria. We do not feel
that is reasonable for DB Cargo and our customers to be affected so substantially to allow Network Rail
to recover the work they have previously failed to deliver.
5.6 Although Condition D5 does specifically allow Network Rail to propose Restrictions of Use at less than
12 weeks-notice and to prescribe the timescales for the elements within that process I would argue that
by issuing a Decision for a Restriction of use that has such a major impact on ourselves and our
customers goes beyond what should reasonably expected by operators. It should also be noted that the
Decision gives no guidance as to when operators should bid changes to train planning; I would expect
this to be stated to ensure that those changes required to be made to train paths to try and mitigate the
restriction of use can indeed be accommodated.
5.7 Although the period between the hearing and the Restriction of Use is extremely short which is, in part,
due to the lateness of the original request and the need to re-propose but also by the availability of
parties on both sides as well as committee to convene a hearing. DB Cargo does not, however feel the
short timescales should be a factor in the final decision. The Determination for TTP1521 states that ‘I
am mindful of the potential danger of creating a precedent incentivising Network Rail../.. to believe it can
safely fail to perform its contractual obligations simply by waiting until a sufficiently late stage in the
Timetabling process’.
5.8 It should be noted that we have received a request (165-W40-WA19) for 2 further 12 hour all line
restrictions of use for Week 40 (Gaer Jn to Leckwith Loop North Jn from 1800 to 0600
5
Tuesday/Wednesday 31st December 2019 / 1st January 2020 and Wednesday/Thursday 1st
January/2ndJanuary 2020). Neither of these new proposals take any account of the agreed access for
freight within the Newport S&C Restriction of use (P2019/2529959) which re-enforces my contention
that Network Rail overriding objective is to deliver Electrification without any thought to DB Cargo’s (and
others) commercial interests.
6 DECISION SOUGHT FROM THE PANEL
6.1 The Panel is asked to determine:
(a) That the disruption and cost to both DB Cargo and our customers has not been weighted
sufficiently by Network Rails application of the decision criteria as shown in 5.5 and Network
Rail has not considered the damage to our business; both financial and reputational in the
headlong rush to complete the Electrification works.
(b) That this Restriction of use be removed or amended to allow access between Leckwith Loop
North Jn and Caldicot with access to Llanwern and both East and West ends as specified in
the reasoning for declining the original proposal as shown in Appendices A and C.
Appendix A
6
Kellyann
As discussed on yesterday’s conference this request is declined by DB Cargo as we cannot accept any
additional all lines block on the SWML.
We require a route from Margam to Caldicot including Llanwern outside of the 14 hours already agreed.
Graham
Graham White
Access Manager South
DB Cargo (UK) Limited, Lakeside Business Park, Carolina Way, Doncaster, DN4 5PN
Email: [email protected]
Phone: 01302 575143
Mobile: 07799 336296
Web: www.uk.dbcargo.com
From: Jones Kellyann <[email protected]> On Behalf Of Engineering Access Planning - Wales
Route
Sent: 05 September 2019 13:06
To: Clark Tim <[email protected]>; Freight - MK <[email protected]>; James Rory
<[email protected]>; James Thomas (MK) <[email protected]>; Arrand Jamie
<[email protected]>; MK Seasonal <[email protected]>; MK Test Trains
<[email protected]>; MK-STP-WESTERN <[email protected]>;
Schedule4Compensation <[email protected]>; Special Trains Mailbox
<[email protected]>; Webb Briony <[email protected]>; Alison Rowsell
([email protected]) <[email protected]>; Chris Owen <[email protected]>;
EXTL: Kirk Rob <[email protected]>; Scott Turner ([email protected])
<[email protected]>; EXTL: Engineering Access Team
<[email protected]>; Josh Watkins
<[email protected]>; A Raisbeck <[email protected]>; A Sheldon
<[email protected]>; EXTL: Grainger Adam <[email protected]>; S Chandler
<[email protected]>; Amanda Stevens <[email protected]>; Graham White
<[email protected]>; DRS <[email protected]>; Stuart Dean ([email protected])
<[email protected]>; Andrew Bramman <[email protected]>; Chris Chadwick
<[email protected]>; David Smith <[email protected]>; John Sadler
<[email protected]>; EXTL: Lunham Mark <[email protected]>; EXTL:
[email protected] <[email protected]>; EXTL: Barrett s <[email protected]>;
Adam Barber <[email protected]>; Ben Godfrey-Day <[email protected]>; GWR Strategy
<[email protected]>; Justin Kerr-Peterson <[email protected]>; Paul Dixon
7
<[email protected]>; Peter Bridges <[email protected]>; [email protected]; Rob Holder
([email protected]) <[email protected]>; Tim Fowler <[email protected]>; Tordoff Natasha
<[email protected]>; EXTL: Planning Lsltoc <[email protected]>; Charles Ashbury
<[email protected]>; Stephen Wood <[email protected]>; Adam Terry
([email protected]) <[email protected]>; Chris Dellard ([email protected])
<[email protected]>; Dean Bolton ([email protected]) <[email protected]>; John
Piper <[email protected]>; Nathan Doe <[email protected]>; Phil Edwards
<[email protected]>; EXTL: Ryan Gerrish <[email protected]>; Vintage Trains
<[email protected]>; gareth Roberts <[email protected]>; Peter Mathers
Cc: Engineering Access Planning - Wales Route <[email protected]>;
Wales Route Short Term Planning South <[email protected]>; Pullen
Andy <[email protected]>; Sealey James <[email protected]>
Subject: New Request: 157-W30-WA19 Stoke Gifford Jn and Leckwith Loop North Jn
Hi All,
Network Rail would like to take the following access to the network in Week 30 between Stoke Gifford Jn and
Leckwith Loop North Jn.
This is to extend the current possession of 14 hours to 50 hours for commissioning of OLE, for the testing of OLE
to Newport and construction to Cardiff West Jn.
If agreed this new possession: P2680990 will supersede the previous possession: P2561298 (which will be
cancelled)
Appendix B
8
Apologies All,
Further to my previous email regarding the withdrawal of the Decision Document for the above this is
now the RE-ISSUED REQUEST
Network Rail would like to take the following access to the network in Week 30 between Stoke Gifford Jn and
Leckwith Loop North Jn.
This is to extend the current possession of 14 hours to 50 hours for commissioning of OLE, for the testing of OLE
to Newport and construction to Cardiff West Jn.
If agreed this new possession: P2680990 will supersede the previous possession: P2561298 (which will be
cancelled)
GW4501 GW450C STOKE GIFFORD JN TO BRISTOL BULK HANDLING TERMINAL
GW600 GW6 AP WOOTTON BASSETT JN TO PILNING
GW700 GW70 B GLOUCESTER, BARNWOOD JN TO SEVERN TUNNEL JN
GW770 GW77 B EBBW VALE TOWN TO GAER JN (WESTERN VALLEY LINE)
GW780 PARK JN TO EBBW JN
GW790 GW790C PENGAM JN TO 4M 54C (ABP CARDIFF DOCKS)
GW830 GW83 B MERTHYR TYDFIL TO BARRY ISLAND VIA CARDIFF QUEEN ST
GW839 GW839C QUEEN STREET SOUTH JN TO CARDIFF BAY
GW900 GW9 A PILNING TO FISHGUARD HARBOUR
SATURDAY 19 to MONDAY 21 OCTOBER
Ref. No. P2019/2680990 Possession Manager Route Business Wales (Electrification)
Item Stoke Gifford Jn No.2 All 0130 to 0420
and Possession SAT
MON
Severn Tunnel Junction Station
Filton West Jn No.2 Patchway Chord 0130 to 0420
and Possession SAT
MON
9
Patchway Jn No.1
Caldicot Down and Up Main 0130 to 0420
and Possession SAT
MON
Severn Tunnel Junction Station
Severn Tunnel Junction Station All Lines 0130 to 0420
and Possession SAT
MON
Newtown Jn
Cardiff East Jn Line A 0130 to 0420
and Possession SAT
MON
Leckwith Loop North Jn
Newtown Jn Line B 0130 to 0420
and Possession SAT
MON
Leckwith Loop North Jn
Line C 0130 to 0420
Possession SAT
MON
Line D 0130 to 0420
Possession SAT
MON
Line E 0130 to 0420
10
Possession SAT
MON
Cardiff Central Platform Loop 0130 to 0420
Possession SAT
MON
Park Jn (Wales) Down and Up Cardiff Curve 0130 to 0420
and Possession SAT
MON
Ebbw Jn
Rumney River Bridge Jn No 1, 2 & 3 Rec Lns 0130 to 0420
and Possession SAT
MON
Pengam Jn
Llanwern Works East
Connection
Down & Up Service Lines 0130 to 0420
and Possession SAT
MON
Llanwern Works West
Connection
East Usk Jn Headshunt (East) 0130 to 0420
Possession SAT
MON
Headshunt (West) 0130 to 0420
Possession SAT
MON
East Usk Jn No. 1 Reception Road 0130 to 0420
11
and Possession SAT
MON
Maindee West Jn
East Usk Jn Single 0130 to 0420
and Possession SAT
MON
Network Rail
Boundary/Uskmouth
Maindee North Jn Single 0130 to 0420
and Possession SAT
MON
Maindee East Jn
Park Jn (Wales) Single 0130 to 0420
and Possession SAT
MON
Gaer Jn
Alexandra Dock Jn Up/Down Goods Loop 0130 to 0420
Possession SAT
MON
Filton Jn No.2 Down and Up Bristol 0130 to 0420
and Possession SAT
MON
Patchway
Cardiff West Brickyard Siding 0130 to 0420
Sidings Possession SAT
MON
12
Wentloog Freight Terminal East
Jn
Wentloog Freight Terminal Sidings 0130 to 0420
and Sidings Possession SAT
MON
Wentloog Freight Terminal
West Jn
Severn Tunnel Junction Station Cripple Sidings 0130 to 0420
Sidings Possession SAT
MON
Gator Garage Sidings 0130 to 0420
Sidings Possession SAT
MON
East Usk Jn No.2 Reception Road 0130 to 0420
and Sidings Possession SAT
MON
Maindee West Jn
Alexandra Dock Jn AD West Sidings 0130 to 0420
Sidings Possession SAT
MON
New Yard Sidings 0130 to 0420
Sidings Possession SAT
MON
Courtybella Single 0130 to 0420
Sidings Possession SAT
MON
13
Cardiff West Brickyard Siding 0130 to 0420
Sidings Possession SAT
MON
Queen St South Jn (Cardiff) Up Llandaff 0001 to 0115
and Possession SUN
SUN
Cardiff Central
Cardiff East Jn Up Barry Relief 0001 to 0115
and Possession SUN
SUN
Cardiff West Jn
Queen Street North Jn (inc.) All Lines 0115 to 0555
and Possession SUN
SUN
Cardiff East Jn
Queen St South Jn (Cardiff) Single 0115 to 0555
and Possession SUN
SUN
Cardiff Bay
Cardiff East Jn Down & Up Barry 0115 to 0555
and Possession SUN
SUN
Cardiff West Jn
Down Barry Loop 0115 to 0555
Possession SUN
SUN
14
Up Barry Relief 0115 to 0555
Possession SUN
SUN
Cardiff West Jn Down & Up Barry Relief 0115 to 0555
Possession SUN
SUN
Down & Up E&C 0115 to 0555
Possession SUN
SUN
Queen St South Jn (Cardiff) Up Llandaff 0555 to 0420
and Possession SUN
MON
Cardiff Central
Cardiff East Jn Up Barry Relief 0555 to 0420
and Possession SUN
MON
Cardiff West Jn
PROTECTION LIMITS
Until 0001 Sunday:
Down Tunnel: Beyond BL1533#
Up Tunnel: Approach BL1526#
Down Bristol: Approach BL1567#
Up Bristol: Beyond BL1566#
Patchway Chord: Approach BL2047#
Down Main: Beyond NT1457# to Approach CF9084pts#
Up Main: Beyond CF9085Bpts# to Approach NT1456#
15
Down Tidal: Approach CF7027#
Up Tidal: Beyond CF7026#
Down Hereford: Beyond NT8519A Pts#
Up Hereford: Approach NT1564#
Single Maindee Loop: Beyond NT1387#
Single Uskmouth: Staff
Gaer Single: Beyond PJ31 pts#
Down Cardiff Curve: Beyond PJ54 pts#
Up Cardiff Curve: Approach PJ78#
Single Courtybella/Up and Down Goods Loop: Single Courtybella/Up and Down Goods Loop to HeadShunt
From 0001 to 0115 Sunday
Down Tunnel: Beyond BL1533#
Up Tunnel: Approach BL1526#
Down Bristol: Approach BL1567#
Up Bristol: Beyond BL1566#
Patchway Chord: Approach BL2047#
Down Main: Beyond NT1457# to Approach CF9084pts#
Up Main: Beyond CF9085Bpts# to Approach NT1456#
Up Barry Relief/Platform 4: Beyond CF9065Apts#
Up Barry/Platform 6/Up Llandaff: Beyond CF9204Bpts# to Approach CF2896#
Down Tidal: Approach CF7027#
Up Tidal: Beyond CF7026#
Down Hereford: Beyond NT8519A Pts#
Up Hereford: Approach NT1564#
Single Maindee Loop: Beyond NT1387#
Single Uskmouth: Staff
Gaer Single: Beyond PJ31 pts#
Down Cardiff Curve: Beyond PJ54 pts#
Up Cardiff Curve: Approach PJ78#
Single Courtybella/Up and Down Goods Loop: Single Courtybella/Up and Down Goods Loop to HeadShunt
From 0115 to 0555 Sunday
Down Tunnel: Beyond BL1533#
Up Tunnel: Approach BL1526#
Down Bristol: Approach BL1567#
Up Bristol: Beyond BL1566#
Patchway Chord: Approach BL2047#
Down Main: Beyond NT1457# to Approach CF9084pts#
Up Main: Beyond CF9085Bpts# to Approach NT1456#
Down Tidal: Approach CF7027#
Up Tidal: Beyond CF7026#
Down Hereford: Beyond NT8519A Pts#
Up Hereford: Approach NT1564#
Single Maindee Loop: Beyond NT1387#
Single Uskmouth: Staff
Gaer Single: Beyond PJ31 pts#
Down Cardiff Curve: Beyond PJ54 pts#
16
Up Cardiff Curve: Approach PJ78#
Down Rhymney: Beyond CF2867#
Up Rhymney: Approach CF2866#
Down Llandaff: Beyond CF2891#
Up Llandaff: Approach CF2890#
Down Barry: Approach CF2951#
Up Barry: Beyond CF2950#
Down Barry Relief: Approach CF2569#
Up Barry Relief: Beyond CF2568#
Single Cardiff Bay: Stop Block
Down E&C: Approach CWM2#
Up E&C: Beyond CF2324#
Single Courtybella/Up and Down Goods Loop: Single Courtybella/Up and Down Goods Loop to HeadShunt
From 0555 Sunday
Down Tunnel: Beyond BL1533#
Up Tunnel: Approach BL1526#
Down Bristol: Approach BL1567#
Up Bristol: Beyond BL1566#
Patchway Chord: Approach BL2047#
Down Main: Beyond NT1457# to Approach CF9084pts#
Up Main: Beyond CF9085Bpts# to Approach NT1456#
Up Barry Relief/Platform 4: Beyond CF9065Apts#
Up Barry/Platform 6/Up Llandaff: Beyond CF9204Bpts# to Approach CF2896#
Down Tidal: Approach CF7027#
Up Tidal: Beyond CF7026#
Down Hereford: Beyond NT8519A Pts#
Up Hereford: Approach NT1564#
Single Maindee Loop: Beyond NT1387#
Single Uskmouth: Staff
Gaer Single: Beyond PJ31 pts#
Down Cardiff Curve: Beyond PJ54 pts#
Up Cardiff Curve: Approach PJ78#
Single Courtybella/Up and Down Goods Loop: Single Courtybella/Up and Down Goods Loop to HeadShunt
TRAFFIC REMARKS
TIME CRITICAL POSSESSION.
UNTIL 0001 SUNDAY:
NO TRAINS TO RUN BETWEEN FILTON ABBEY WOOD, BRISTOL PARKWAY, CHEPSTOW, CWMBRAN, EBBW VALE AND
CARDIFF CENTRAL STATION.
NO ACCESS TO PLATFORMS 0,1,2, AND 3 AT CARDIFF CENTRAL.
NO ACCESS TO PLATFORM 4 FROM LINE E.
TO/FROM BRIDGEND VIA PLATFORMS 4, 6, 7 & 8 VIA LECKWITH LOOP OR THE VOG ONLY.
ACCESS AVAILABLE TO CARDIFF CANTON FROM PLATFORMS 4, 6, 7 AND 8 VIA CARRIAGE WASHER LINES.
ACCESS TO CANTON AVAILABLE VIA LECKWITH LOOP AND NINIAN PARK.
NO OUTSTABLING AVAILABLE AT NEWPORT.
17
NO ACCESS TO CANTON VIA LECKWITH G.F.
NO ACCESS TO WESTERN VALLEY LINES (EBBW VALE)
NO ACCESS TO LLANWERN.
NO ACCESS TO EAST USK.
NO ACCESS TO ALEXANDRA DOCK.
NO ACCESS TO WENTLOOG TERMINAL.
NO ACCESS TO PENGAM. NO TRAINS TO STABLE AT PENGAM.
NO ACCESS TO PULLMANS DEPOT.
CROSS COUNTRY TO START/TERMINATE AT CHEPSTOW DOWN PLATFORM.
TfW TO TERMINATE AT CWMBRAN AND SHUNT TO THE UP LINE VIA MAINDEE LOOP.
FROM 0001 SUNDAY:
NO TRAINS TO RUN BETWEEN FILTON ABBEY WOOD, BRISTOL PARKWAY, CHEPSTOW, CWMBRAN, EBBW VALE AND
CARDIFF CENTRAL STATION.
NO ACCESS TO PLATFORMS 0,1,2,3,4 AND 6 AT CARDIFF CENTRAL.
ACCESS AVAILABLE TO CARDIFF CANTON FROM PLATFORMS 7 AND 8 VIA CARRIAGE WASHER LINES.
ACCESS TO CANTON AVAILABLE VIA LECKWITH LOOP AND NINIAN PARK.
TO/FROM BRIDGEND VIA PLATFORMS 7 & 8 VIA LECKWITH LOOP OR THE VOG ONLY.
NO OUTSTABLING AVAILABLE AT NEWPORT.
NO ACCESS TO CANTON VIA LECKWITH G.F.
NO ACCESS TO WESTERN VALLEY LINES (EBBW VALE)
NO ACCESS TO LLANWERN.
NO ACCESS TO EAST USK.
NO ACCESS TO ALEXANDRA DOCK.
NO ACCESS TO WENTLOOG TERMINAL.
NO ACCESS TO PENGAM. NO TRAINS TO STABLE AT PENGAM.
NO ACCESS TO PULLMANS DEPOT.
NO ACCESS BETWEEN CARDIFF QUEEN STREET AND CARDIFF CENTRAL VIA UP LLANDAFF/BARRY.
CROSS COUNTRY TO START/TERMINATE AT CHEPSTOW DOWN PLATFORM.
TfW TO TERMINATE AT CWMBRAN AND SHUNT TO THE UP LINE VIA MAINDEE LOOP.
I look forward to receiving your formal responses to the above request by Thursday 19th September 2019
This email is in accordance with Access Condition D3.5.2 and relates to Section 3.1 of the Timetable Planning
Rules being the Procedure for Altering the Engineering Access Statement or Timetable Planning other than
through the Twice-Yearly Process Having Effect from a Passenger Change Date.
Many Thanks
K. Jones
Kellyann Jones
18
Access Planner, Wales Route,
Floor 2, St. Patricks House,
Penarth Road. Cardiff
CF10 5ZE
Mobile: 07809378108
Email: [email protected]
****************************************************************************************************************************************************************
The content of this email (and any attachment) is confidential. It may also be legally privileged or otherwise protected from disclosure. This email should not be used by anyone who is not an original intended recipient, nor may it be copied or disclosed to anyone who is not an original intended recipient.
If you have received this email by mistake please notify us by emailing the sender, and then delete the email and any copies from your system.
Liability cannot be accepted for statements made which are clearly the sender's own and not made on behalf of Network Rail. Network Rail Infrastructure Limited registered in England and Wales No. 2904587, registered office Network Rail, 2nd Floor, One Eversholt Street, London, NW1 2DN
********************************************************************************************************************************
********************************
Appendix C Kellyann
As per the original request this is declined by DB Cargo as we cannot accept any additional all lines
blocks on the SWML.
19
We still require a route from Margam to Caldicot including Llanwern outside of the 14 hours already
agreed.
Thanks
Graham
Graham White
Access Manager South
DB Cargo (UK) Limited, Lakeside Business Park, Carolina Way, Doncaster, DN4 5PN
Email: [email protected]
Phone: 01302 575143
Mobile: 07799 336296
Web: www.uk.dbcargo.com
Appendix D Dear all,
20
Network Rail will be taking the below access to the network in weekend 30. This is to facilitate
further work in connection with the Great Western Electrification Project. This is in response to the
request made on 12 September 2019.
SATURDAY 19 to MONDAY 21 OCTOBER
Ref. No. P2019/2680990 Possession Manager Route Business Wales (Electrification)
Appendix E Stations
21
Newport Station
a) Permanent Canopy Reinstatements (Platform 1, 2 & 3) b) Permanent Platform Reinstatements (Platform 1, 2 & 3) c) Removal of Platform Hoarding (Platform 2&3)
1. Cardiff Station a) Platform reinstatements (Platform 1 &2) b) Installation of platform fencing around Mast/Struts (Platform 3&4) c) CCTV Diversions (Platform 3&4) d) Adjustment of a lighting column (Platform 4)
2. CEJ Screen Installation a) Landing of pre-cast units b) Vertical coring of the pre-cast units c) Installation of screen post and fixings d) Horizontal coring (from SWM2, Line E) e) Removal/replacement of existing handrail
3. Cardiff West Remedial works to damaged arch (234/004
E&B
1) Line side Bonding Saturday Day 0700 – 1700 2 Teams installing line side bonds (15 bonds)
Sunday Day 0700 – 1700 2 Teams installing Line side bonds (15 bonds)
2) Traction Bonding Saturday Day 0700 – 1700 2 Teams installing Traction bonds (20 Bonds)
Sunday Day 0700 – 1700 2 Teams installing Traction Bonds (20 Bonds)
3) Spider Plates Saturday Day 0700 – 1700 1 team installing spider plates (5)
4) Cardiff Station Saturday Night 2200 – 0800 Installation of CBC and Bonds Tails
Sunday Night 2200 – 0800 Installation of CBC and Bonds Tails
Tunnels:
1. Patchway Old, Short & Gap tunnels a. Heights and Staggers check 50 locations b. Cloud point survey c. London portal survey
22
d. Patchway Gap Drainage repair
2. Patchway New tunnel a. Heights and Staggers check 50 locations b. Cloud point survey c. London portal survey d. Cess drainage survey outside London portal e. Insulator cleaning
3. Ableton Lane tunnel a. Installation of aerial AFT lashing rods 4 no. cables
4. Severn tunnel a. Secondary E&B b. E&B of ATF 18 no. locations c. Replacement of continuity jumpers 228 no. d. Installation of aerial AFT lashing rods 2 no. cables Welsh Portal e. Insulator cleaning and Insulator Resistance testing f. Water management approx 25 locations g. Mid-point anchor remedial works approx 28 locations h. Cloud point survey
5. Newport New tunnel a. Installation of aerial AFT lashing rods 2 no. b. Cloud point survey
6. Newport Old tunnel a. Installation of aerial AFT lashing rods 2 no. b. Cloud point survey
In addition to the above work for the electrification project, the following work will be
taking place for Track Renewals. This is work at the Llandevenny site which has been lost as
a result of an earlier electrification possession for commissioning.
Place and erect vortex fencing to enable safe system of work in ALO sections
Pre site for rail drop including protecting track furniture and cables (week 32)
Run out geo textile
Run out additional materials
Set up lighting
23
Install temporary RRV access point
Kind regards
Richard Hooper
Access Planning Manager
Wales Route
Tel. 07740 223585