TCTA Mandate
PSP Role
Consultations with mines
Western Basin
Central Basin
Eastern Basin
Programme
Key Challenges
Ministerial directive – 6 April 2011Emergency works in Witwatersrand Gold
Fields comprising:Installation of pumpsConstruction of water treatment plantsRelease treated water into river system
Obtain environmental and regulatory approvals
Funding via National Treasury (R225 million)Advise and assist DWA with O&M modelRight to expropriate landMinister may direct to do more
Issue tender on 8 April 2011PSP : BKS in association with GolderAward PSP contract (Part 1)on 9 May 2011Main tasks:
Due diligence review – report due 7 JulyTender design and documentationDetail design and construction supervisionProject closeout
Western and Central basins Eastern Basin?Explore institutional options (legal frameworks)Access to landAvailability and status of existing infrastructureCo-funding options
CapexOpex
Water off-takesO&M options
Agreed ECL level is 1550 amsl or 160 m below collar of 8 Shaft.
Current decant 17.7 ML/day into the Tweelopies Spruit.
Peak flows of 50 – 60 Ml/day have been measured in summer
Immediate solutions identified to reduce decant in Western BasinUpgrade of Rand Uranium plant to treat 30 Ml/day
(preferred)Upgrade Mogale Gold treatment plant 24 Ml/dayUpgrade Rand uranium and Mogale Gold
Cost of immediate solution (Capex R25 M) (Opex R52 M per year)
Short term solution - being identified
7
10
Agreed ECL level is 1467 amsl or 173 m below collar of SWV Shaft.
Gold Reef City requires level below 1480 amsl
CRG requires level to be 400m below SWV
Short term solution - being identified
Pumps have been ordered by CRG to pump to 400 m
Current Design ECL set at 1280 amsl or 290 m below Grootvlei collar
Role players to be identified
Final ECL to be determined based on mining requirements
Short term solution - being identified
11
ACTIVITY DATE
Receive directive 6 April 2011
Appoint PSP 9 May 2011
Complete due diligence 7 July 2011
Issue tenders 11 October 2011
Commission immediate solution (Western B) November 2011
Start construction January 2012
Project commissioning September 2012
Project closeout December 2012
12
Emergency status of project – accelerated processes
Unclear project scope definitionSeverely limited timeframesTimely regulatory and env approvalsPoor state of existing infrastructureHigh public profile and interestComplex institutional arrangementsLimited cost recoveryPossible budget limitationsTiming of long-term solution